SCDOT contract 2973031 bid tabulation
Intersection Improvement - SC 5 at S-358 (Steel Hill Road). Let by South Carolina DOT on October 13, 2026, Lancaster, District 4. 9 bids received; low bid $1,484,396 by Truerock Construction, LLC.
- Owner
- South Carolina DOT
- Letting
- 13 OCT 2026
- Pay items
- 74
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Truerock Construction, LLC | $1,484,396 | Low |
| 2 | Eagle Construction Company | $1,625,018 | +9.0% |
| 3 | King Asphalt, Inc. | $1,648,219 | +11% |
| 4 | Blythe Development, LLC | $1,764,187 | +19% |
| 5 | Kershaw Builders, Inc. | $1,790,185 | +21% |
| 6 | Lci-Lineberger Construction, Inc. | $1,944,884 | +31% |
| 7 | Universal Civil Construction, LLC | $2,317,599 | +56% |
| 8 | Coogler Construction, Inc. | $2,677,260 | +80% |
| 9 | Aos Specialty Contractors, Inc. | $2,697,170 | +82% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Truerock Construction, LLC | 2. Eagle Construction Company | 3. King Asphalt, Inc. | 4. Blythe Development, LLC | 5. Kershaw Builders, Inc. | 6. Lci-Lineberger Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $68,113 | $70,000 | $81,800 | $87,000 | $75,000 | $64,500 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $5,200.00 | $10,000 | $48,800 | $10,077 | $35,102 | $33,500 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $15,000 | $29,000 | $18,750 | $30,000 | $35,000 | $36,850 |
| 0040 | Utility staking (1052001) | LS | 1 | $7,500.00 | $2,500.00 | $7,000.00 | $25,000 | $15,000 | $6,500.00 |
| 0050 | Clearing & grubbing within right of way (2011000) | LS | 1 | $118,010 | $63,500 | $70,000 | $306,981 | $25,000 | $65,000 |
| 0060 | Removal & disposal of existing pavement (2023000) | SY | 245 | $25.00 | $10.00 | $23.00 | $15.00 | $12.00 | $15.00 |
| 0070 | Removal of exist. guardrail (2027801) | LF | 275 | $1.00 | $3.00 | $1.00 | $1.00 | $10.00 | $5.71 |
| 0080 | Unclassified excavation (2031000) | CY | 13,384 | $12.95 | $13.50 | $23.00 | $11.00 | $6.50 | $28.95 |
| 0090 | Borrow excavation (2033000) | CY | 100 | $100.00 | $25.00 | $45.00 | $27.00 | $28.50 | $40.00 |
| 0100 | Fine grading (2081001) | SY | 2,973 | $6.35 | $1.50 | $12.00 | $5.00 | $10.00 | $7.50 |
| 0110 | Maintenance stone (3059900) | TON | 20 | $98.00 | $56.50 | $60.00 | $53.00 | $75.00 | $140.00 |
| 0120 | Liquid asphalt binder PG64-22 (4011004) | TON | 243 | $665.00 | $895.00 | $889.00 | $815.00 | $825.00 | $870.00 |
| 0130 | Full depth asph. pav. patching 15"unif (4012150) | SY | 100 | $245.00 | $300.00 | $291.00 | $200.00 | $325.00 | $325.00 |
| 0140 | Milling existing asphalt pavement 1.75" (4013117) | SY | 14,500 | $3.55 | $4.35 | $4.00 | $3.40 | $3.69 | $2.86 |
| 0150 | Milling existing asphalt pavement (variable) (4013990) | SY | 1,373 | $9.05 | $10.00 | $9.00 | $3.40 | $6.44 | $11.00 |
| 0160 | Asphalt base course - type A (4020310) | TON | 1,874 | $81.00 | $89.50 | $86.00 | $94.00 | $135.08 | $102.00 |
| 0170 | Asphalt base course - type B (4020320) | TON | 62 | $160.00 | $165.00 | $156.00 | $94.00 | $165.00 | $210.00 |
| 0180 | Asphalt intermediate course type B (4030320) | TON | 627 | $90.00 | $101.00 | $98.00 | $97.00 | $144.00 | $125.00 |
| 0190 | Asphalt surface course type B (4040320) | TON | 1,908 | $81.00 | $84.25 | $81.00 | $82.50 | $121.00 | $98.00 |
| 0200 | Asphalt surface course type C (4040340) | TON | 20 | $208.00 | $400.00 | $375.00 | $100.00 | $165.00 | $260.00 |
| 0210 | Asphalt surface course type E (4040360) | TON | 194 | $85.00 | $117.00 | $112.00 | $100.00 | $165.00 | $150.00 |
| 0220 | Driveway paving-surface type C (4047220) | TON | 104 | $158.00 | $235.00 | $220.00 | $150.00 | $357.50 | $150.00 |
| 0230 | Traffic control (6011000) | LS | 1 | $130,000 | $217,000 | $50,000 | $150,000 | $150,000 | $190,000 |
| 0240 | Permanent construction signs (ground mounted) (6051120) | SF | 276 | $6.85 | $10.00 | $5.80 | $8.64 | $11.00 | $8.08 |
| 0250 | Pavement markings(temp- paint) 4" white broken lines (609105A) | LF | 310 | $0.15 | $0.18 | $0.15 | $0.15 | $0.20 | $0.14 |
| 0260 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 51,780 | $0.15 | $0.18 | $0.15 | $0.15 | $0.20 | $0.14 |
| 0270 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 51,780 | $0.15 | $0.18 | $0.15 | $0.15 | $0.20 | $0.14 |
| 0280 | Pavement markings(temporary-paint)- 24"white solid lines (609135A) | LF | 200 | $1.50 | $1.70 | $1.50 | $1.50 | $1.25 | $1.15 |
| 0290 | Temporary yellow pavement markers BI-dir.- 4"X4" (6092155) | EACH | 300 | $8.50 | $9.75 | $8.50 | $8.50 | $10.50 | $11.54 |
| 0300 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 540 | $0.75 | $0.85 | $0.75 | $0.75 | $0.95 | $0.58 |
| 0310 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 9,900 | $0.50 | $0.60 | $0.50 | $0.50 | $0.95 | $0.58 |
| 0320 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 86 | $15.00 | $17.00 | $15.00 | $15.00 | $14.00 | $11.54 |
| 0330 | White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030) | EACH | 2 | $150.00 | $170.00 | $150.00 | $150.00 | $125.00 | $86.53 |
| 0340 | White word message "only" - thermoplastic - 125 mil. (6271035) | EACH | 2 | $150.00 | $170.00 | $150.00 | $150.00 | $125.00 | $86.53 |
| 0350 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 14,600 | $0.50 | $0.60 | $0.50 | $0.50 | $0.95 | $0.58 |
| 0360 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 5 | $8.50 | $9.75 | $8.50 | $8.50 | $9.50 | $6.92 |
| 0370 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 150 | $8.50 | $9.75 | $8.50 | $8.50 | $9.50 | $6.92 |
| 0380 | Milled-in rumble strip (6321000) | MI | 2 | $3,700.00 | $2,800.00 | $3,292.00 | $3,000.00 | $4,500.00 | $2,768.99 |
| 0390 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 110 | $14.94 | $29.50 | $13.00 | $15.12 | $42.50 | $28.84 |
| 0400 | Flat sheet, type III, size determined by MSG (6510106) | SF | 55 | $12.64 | $37.00 | $11.00 | $15.12 | $42.50 | $28.84 |
| 0410 | U-section post for sign supports - 3P (6531210) | LF | 359 | $10.34 | $21.00 | $9.00 | $9.19 | $10.90 | $17.31 |
| 0420 | U-section post for sign bracing - 2P (6531215) | LF | 28 | $9.19 | $21.00 | $8.00 | $8.64 | $10.50 | $17.31 |
| 0430 | 18" smooth wall pipe (7143618) | LF | 224 | $298.00 | $78.00 | $196.89 | $180.00 | $84.50 | $265.00 |
| 0440 | Drop inlet type 112 (7192040) | EACH | 1 | $6,229.70 | $12,000 | $6,856.00 | $11,000 | $7,250.00 | $10,150 |
| 0450 | Concrete collar for UP to 24" pipe (7197052) | EACH | 1 | $3,458.50 | $6,500.00 | $5,693.00 | $1,600.00 | $4,400.00 | $5,800.00 |
| 0460 | Beveling of pipe end (7199100) | EACH | 4 | $1,660.00 | $700.00 | $784.00 | $1,600.00 | $450.00 | $2,200.00 |
| 0470 | Concrete flume (7207001) | LF | 35 | $118.00 | $425.00 | $240.00 | $55.00 | $300.00 | $70.00 |
| 0480 | Bituminous curb (7211000) | LF | 275 | $59.55 | $45.00 | $39.00 | $73.00 | $64.00 | $48.58 |
| 0490 | Rip-rap (class A) (8041010) | TON | 51 | $111.65 | $75.50 | $146.00 | $87.00 | $132.50 | $175.00 |
| 0500 | Rip-rap (class B) (8041020) | TON | 52 | $107.90 | $75.50 | $139.00 | $93.00 | $115.50 | $175.00 |
| 0510 | Geotextile for erosion control under riprap(class 2)type B (8048205) | SY | 201 | $8.00 | $4.50 | $5.00 | $4.00 | $3.75 | $10.00 |
| 0520 | Premash reset W-beam strong post system (8051900) | LF | 12.50 | $25.00 | $26.00 | $25.00 | $18.00 | $35.00 | $28.84 |
| 0530 | Premash W-beam compressed SHLDR 9' post (8053001) | LF | 225 | $36.00 | $46.00 | $36.00 | $36.00 | $59.00 | $56.53 |
| 0540 | Premash type T TL3 leading 50' (8057100) | EACH | 1 | $3,200.00 | $4,000.00 | $3,200.00 | $3,200.00 | $5,250.00 | $5,191.85 |
| 0550 | Right of way marker(rebar and cap) (8091010) | EACH | 5 | $80.00 | $350.00 | $700.00 | $288.00 | $1,500.00 | $331.24 |
| 0560 | Right of way plat (8091050) | LS | 1 | $2,250.00 | $2,500.00 | $4,000.00 | $1,500.00 | $5,000.00 | $1,730.62 |
| 0570 | Permanent cover (8100100) | ACRE | 2.90 | $1,325.00 | $1,525.00 | $1,995.00 | $1,800.00 | $2,750.00 | $2,134.42 |
| 0580 | Temporary cover (8100200) | ACRE | 1.45 | $1,100.00 | $1,275.00 | $1,075.00 | $1,800.00 | $2,750.00 | $1,442.10 |
| 0590 | Compost (8101105) | CY | 780 | $26.00 | $30.00 | $10.00 | $45.00 | $78.50 | $20.00 |
| 0600 | Fertilizer (nitrogen) (8104005) | LB | 290 | $3.25 | $3.75 | $2.25 | $2.00 | $7.50 | $2.60 |
| 0610 | Fertilizer (phosphoric acid) (8104010) | LB | 290 | $3.25 | $3.75 | $2.25 | $2.00 | $7.50 | $2.60 |
| 0620 | Fertilizer (potash) (8104015) | LB | 290 | $3.25 | $3.75 | $2.25 | $2.00 | $7.50 | $2.60 |
| 0630 | Agricultural granular lime (8105005) | LB | 5,800 | $0.35 | $0.50 | $0.35 | $0.90 | $5.00 | $0.81 |
| 0640 | Selective watering (8109050) | GAL | 54,300 | $0.07 | $0.08 | $0.25 | $0.15 | $0.15 | $0.10 |
| 0650 | Mowing (8109901) | ACRE | 8.70 | $450.00 | $500.00 | $450.00 | $600.00 | $750.00 | $340.35 |
| 0660 | Temporary erosion control blanket (ecb) (8151110) | MSY | 4.58 | $1,600.00 | $1,850.00 | $1,648.00 | $1,655.00 | $3,600.00 | $1,619.24 |
| 0670 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 8.70 | $2,850.00 | $3,275.00 | $3,350.00 | $3,200.00 | $3,500.00 | $4,384.23 |
| 0680 | Silt fence (8153000) | LF | 500 | $4.00 | $4.50 | $3.00 | $5.25 | $4.25 | $7.00 |
| 0690 | Cleaning silt basins (8154010) | CY | 150 | $16.50 | $20.00 | $53.00 | $26.00 | $50.00 | $50.00 |
| 0700 | Cleaning inlet structure filters (8156200) | EACH | 2 | $247.00 | $175.00 | $900.00 | $150.00 | $1,250.00 | $525.00 |
| 0710 | Inlet structure filter - type D2 (8156215) | EACH | 1 | $650.00 | $650.00 | $400.00 | $260.00 | $1,250.00 | $675.00 |
| 0720 | Filter material for inlet structure filter - type D2 (8156217) | EACH | 1 | $450.00 | $400.00 | $650.00 | $30.00 | $1,250.00 | $675.00 |
| 0730 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 13 | $78.00 | $70.00 | $100.00 | $69.00 | $78.50 | $125.00 |
| 0740 | Stabilized construction entrance (8156490) | SY | 550 | $22.00 | $26.00 | $25.00 | $27.00 | $18.50 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of October 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.