Blythe Development, LLC submitted 18 bids on South Carolina DOT contracts in the data, from 08 MAR 2022 to 13 OCT 2026, and was the low bidder on 2 of them (11%). When it was not low, its total sat a median +18% above the low bid.
- Owner
- South Carolina DOT
- Low bid volume
- $14,297,716
- Latest bid
- 13 OCT 2026
- Data through
- 13 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 3 | 1 | 33% |
| 2023 | 2 | 0 | 0% |
| 2024 | 2 | 1 | 50% |
| 2025 | 5 | 0 | 0% |
| 2026 | 6 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 4 | 12 | 2 | 17% |
| District 6 | 3 | 0 | 0% |
| District 1 | 3 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Aggregate no.5 or 57 for erosion control | 8156410 | TON | 14 | 8 (57%) | $69.50 | $91.62 |
| Unclassified excavation | 2031000 | CY | 18 | 7 (39%) | $20.00 | $42.80 |
| Selective watering | 8109050 | GAL | 16 | 7 (44%) | $0.08 | $0.07 |
| On-the-job trainee (roadway) | 9001000 | HR | 5 | 5 (100%) | $0.80 | $0.80 |
| Stabilized construction entrance | 8156490 | SY | 18 | 4 (22%) | $23.00 | $23.00 |
| Borrow excavation | 2033000 | CY | 17 | 4 (24%) | $33.00 | $49.70 |
| Agricultural granular lime | 8105005 | LB | 17 | 4 (24%) | $0.60 | $0.60 |
| Milling existing asphalt pavement (variable) | 4013990 | SY | 16 | 4 (25%) | $16.45 | $11.30 |
| Rip-rap (class B) | 8041020 | TON | 15 | 4 (27%) | $99.00 | $118.00 |
| Rip-rap (class A) | 8041010 | TON | 14 | 4 (29%) | $99.00 | $106.71 |
| Removal of silt retained by silt fence | 8154050 | LF | 13 | 4 (31%) | $3.30 | $4.75 |
| Maintenance stone | 3059900 | TON | 10 | 4 (40%) | $61.50 | $92.63 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Dane Construction, LLC | 9 | 2 of 9 |
| Eagle Construction Company | 8 | 4 of 8 |
| Coogler Construction, Inc. | 6 | 4 of 6 |
| Reeves Construction Company | 5 | 3 of 5 |
| Aos Specialty Contractors, Inc. | 5 | 2 of 5 |
| United Infrastructure Group, Inc. | 4 | 3 of 4 |
| Boggs Contracting, Inc. | 3 | 1 of 3 |
| McClam & Associates, Inc. | 3 | 3 of 3 |
| Palmetto Sitework Services, LLC | 3 | 2 of 3 |
| Lee Construction Company of the | 2 | 2 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 13 OCT 2026 | 1075380 | District 6 | US 17 at Buck Hall Landing Road (Right Turn Lane) | 5 of 7 | $627,601 | +72% |
| 13 OCT 2026 | 2973031 | District 4 | Intersection Improvement - SC 5 at S-358 (Steel Hill Road) | 4 of 9 | $1,764,187 | +19% |
| 13 OCT 2026 | 4673600 | District 4 | Br Replacement S-46-832 over Branch of Catawba River | 5 of 8 | $2,474,417 | +19% |
| 11 AUG 2026 | 2970980 | District 4 | S-55 (Van Wyck Rd) bridge Replacement over Twelve Mile Creek | 2 of 7 | $9,391,026 | +9.0% |
| 14 APR 2026 | 3270840 | District 1 | Improvements to S-48 (Columbia Ave) in Chapin | 5 of 5 | $68,302,028 | +26% |
| 13 JAN 2026 | 2971000 | District 4 | S-294(Uriah Rd) Bridge Replacement over Camp Branch Rd | 3 of 6 | $2,017,269 | +30% |
| 09 DEC 2025 | 2974910 | District 4 | SC 9 Bridge Replacement Over Wildcat Creek | 2 of 4 | $13,212,144 | +12% |
| 09 DEC 2025 | 3265530 | District 1 | Roundabout at SC 6 and S-65 | 8 of 8 | $3,948,152 | +48% |
| 12 NOV 2025 | 4674600 | District 4 | S-884 over Fishing Creek Bridge Replacement in York County | 4 of 6 | $3,239,740 | +22% |
| 14 OCT 2025 | 1274610 | District 4 | SC 72 BRO South Fork Creek - Asset ID 330 | 2 of 6 | $11,985,955 | +1.0% |
| 13 MAY 2025 | 1170740 | District 4 | S-59 Bridge Replacement Over Thicketty Creek | 4 of 6 | $1,999,942 | +17% |
| 11 JUN 2024 | 2968580 | District 4 | S-195 (New Cut Church Rd) Bridge Replacement over Camp Creek | 6 of 7 | $2,416,466 | +16% |
| 09 JAN 2024 | 2958320 | District 4 | Intersection Improvement - US 521/S-54 | 1 of 3 | $7,132,772 | Low, 15% under the second |
| 11 APR 2023 | 0857131 | District 6 | Intersection Improvements - US 176 (Berkeley Co) | 4 of 4 | $3,598,300 | +79% |
| 28 MAR 2023 | 3265121 | District 1 | Reconfigure existing I-26 @ US 21 interchange | 4 of 4 | $52,661,073 | +11% |
| 11 OCT 2022 | 4646751 | District 4 | Intersection Improvement - SC 161/S-30 (York Co) | 1 of 3 | $7,164,944 | Low, 8.0% under the second |
| 13 SEP 2022 | 0847050 | District 6 | Widening - I-26 (187-194) | 2 of 3 | $191,563,738 | +6.0% |
| 08 MAR 2022 | 1252450 | District 4 | Bridge Replacement - SC 901 (Rocky Creek) | 6 of 7 | $4,361,597 | +11% |
How this record was read
SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; SCDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.