SCDOT contract 4674600 bid tabulation
S-884 over Fishing Creek Bridge Replacement in York County. Let by South Carolina DOT on November 12, 2025, York, District 4. 6 bids received; low bid $2,645,880 by Kemp Sigmon Construction Co., Inc..
- Owner
- South Carolina DOT
- Letting
- 12 NOV 2025
- Pay items
- 83
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Kemp Sigmon Construction Co., Inc. | $2,645,880 | Low |
| 2 | Aos Specialty Contractors, Inc. | $3,102,583 | +17% |
| 3 | United Infrastructure Group, Inc. | $3,227,346 | +22% |
| 4 | Blythe Development, LLC | $3,239,740 | +22% |
| 5 | Dane Construction, LLC | $3,426,154 | +29% |
| 6 | Eagle Construction Company | $3,587,246 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kemp Sigmon Construction Co., Inc. | 2. Aos Specialty Contractors, Inc. | 3. United Infrastructure Group, Inc. | 4. Blythe Development, LLC | 5. Dane Construction, LLC | 6. Eagle Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $130,000 | $131,377 | $161,367 | $160,000 | $171,305 | $175,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $52,000 | $73,367 | $96,820 | $45,000 | $102,780 | $69,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $20,000 | $69,752 | $70,000 | $30,000 | $38,920 | $126,000 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $20,000 | $29,228 | $10,000 | $10,000 | $25,000 | $5,000.00 |
| 0050 | Clearing & grubbing within right of way (2011000) | LS | 1 | $170,000 | $48,289 | $275,000 | $120,000 | $55,000 | $105,000 |
| 0060 | Removal & disposal of existing asphalt pavement (2025000) | SY | 2,075 | $10.00 | $5.50 | $17.00 | $12.00 | $25.00 | $11.00 |
| 0070 | Removal & disposal of existing bridge (2028100) | LS | 1 | $200,000 | $136,292 | $150,000 | $113,000 | $177,040 | $168,000 |
| 0080 | Unclassified excavation (2031000) | CY | 996 | $25.00 | $44.00 | $26.00 | $32.00 | $25.00 | $56.92 |
| 0090 | Borrow excavation (2033000) | CY | 12,406 | $18.00 | $34.00 | $38.00 | $40.00 | $40.00 | $47.00 |
| 0100 | Fine grading (2081001) | SY | 2,505 | $12.00 | $17.00 | $25.00 | $35.00 | $8.00 | $3.00 |
| 0110 | Maintenance stone (3059900) | TON | 110 | $40.00 | $93.00 | $110.00 | $60.00 | $60.00 | $57.50 |
| 0120 | Liquid asphalt binder PG64-22 (4011004) | TON | 98 | $670.00 | $719.00 | $686.59 | $760.00 | $670.00 | $790.00 |
| 0130 | Full depth asph. pav. patching 6" unif. (4012060) | SY | 3,700 | $55.00 | $59.00 | $56.36 | $63.00 | $55.00 | $65.00 |
| 0140 | Full depth asph. pav. patching 8" unif (4012080) | SY | 900 | $73.00 | $78.00 | $74.81 | $83.00 | $73.00 | $85.00 |
| 0150 | Milling existing asphalt pavement (variable) (4013990) | SY | 540 | $18.00 | $19.00 | $18.45 | $20.00 | $18.00 | $22.00 |
| 0160 | Asphalt base course - type B (4020320) | TON | 884 | $95.00 | $102.00 | $97.35 | $110.00 | $95.00 | $110.00 |
| 0170 | Asphalt intermediate course type C (4030330) | TON | 494 | $95.00 | $102.00 | $97.35 | $110.00 | $95.00 | $110.00 |
| 0180 | Asphalt surface course type C (4040340) | TON | 460 | $96.00 | $103.00 | $98.38 | $110.00 | $96.00 | $115.00 |
| 0190 | Asphalt surface course type E (4040360) | TON | 106 | $105.00 | $113.00 | $107.60 | $120.00 | $105.00 | $125.00 |
| 0200 | Traffic control (6011000) | LS | 1 | $50,000 | $17,169 | $53,415 | $12,000 | $17,000 | $195,000 |
| 0210 | Barricade - type III (6041200) | LF | 120 | $25.00 | $23.00 | $25.00 | $30.00 | $21.00 | $65.00 |
| 0220 | Permanent construction signs (ground mounted) (6051120) | SF | 200 | $8.00 | $9.00 | $6.95 | $8.00 | $7.40 | $13.00 |
| 0230 | Permanent construction signs (barricade mounted) (6051125) | SF | 107 | $8.00 | $9.00 | $8.95 | $10.00 | $7.40 | $15.00 |
| 0240 | Type B - flashing light (608100B) | EACH | 16 | $100.00 | $134.00 | $165.00 | $195.00 | $150.00 | $200.00 |
| 0250 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 50 | $0.15 | $0.16 | $0.15 | $0.20 | $0.15 | $0.20 |
| 0260 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 3,230 | $0.15 | $0.16 | $0.15 | $0.20 | $0.15 | $0.20 |
| 0270 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 16 | $1.50 | $1.60 | $1.50 | $1.80 | $1.50 | $3.00 |
| 0280 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 3,180 | $0.15 | $0.16 | $0.15 | $0.20 | $0.15 | $0.20 |
| 0290 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 50 | $1.00 | $1.10 | $1.00 | $1.20 | $1.00 | $2.00 |
| 0300 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 3,230 | $1.00 | $1.10 | $1.00 | $1.20 | $1.00 | $1.50 |
| 0310 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 16 | $10.00 | $11.00 | $10.00 | $12.00 | $10.00 | $15.00 |
| 0320 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 3,180 | $1.00 | $1.10 | $1.00 | $1.20 | $1.00 | $1.50 |
| 0330 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 20 | $10.00 | $11.00 | $10.00 | $12.00 | $10.00 | $25.00 |
| 0340 | Milled-in rumble strip (6321000) | MI | 0.53 | $20,000 | $3,756.00 | $3,500.00 | $3,500.00 | $3,500.00 | $14,000 |
| 0350 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 44 | $20.00 | $29.00 | $18.00 | $31.00 | $27.00 | $60.00 |
| 0360 | U-section post for sign supports - 3P (6531210) | LF | 120 | $15.00 | $16.50 | $14.00 | $10.00 | $14.75 | $35.00 |
| 0370 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 588 | $16.00 | $17.00 | $10.00 | $20.00 | $35.80 | $12.00 |
| 0380 | Conc. for structures - class 4000 (7011400) | CY | 261.49 | $1,250.00 | $1,513.00 | $1,650.00 | $1,800.00 | $2,000.00 | $1,850.00 |
| 0390 | Grooved surface finish (7023200) | SY | 376.89 | $18.00 | $17.00 | $15.00 | $18.00 | $9.35 | $17.00 |
| 0400 | Reinf. steel for structures (bridge) (7031200) | LB | 62,219 | $1.75 | $1.88 | $1.25 | $2.00 | $2.50 | $1.50 |
| 0410 | Prestressed conc. beam (type IV) (7044000) | LF | 526.51 | $450.00 | $571.00 | $325.00 | $500.00 | $765.00 | $365.00 |
| 0420 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 292 | $115.00 | $168.00 | $100.00 | $140.00 | $128.13 | $115.00 |
| 0430 | Pile driving set-UP (7110010) | EACH | 10 | $2,000.00 | $6,550.00 | $4,000.00 | $2,000.00 | $3,575.00 | $4,500.00 |
| 0440 | Reinf. pile tips (HP14 X 73) (7111560) | EACH | 10 | $200.00 | $378.00 | $175.00 | $420.00 | $800.00 | $200.00 |
| 0450 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 472.16 | $65.00 | $60.00 | $46.00 | $86.00 | $60.00 | $52.00 |
| 0460 | 15" smooth wall pipe (7143615) | LF | 80 | $125.00 | $161.00 | $140.00 | $144.00 | $75.00 | $93.00 |
| 0470 | 18" smooth wall pipe (7143618) | LF | 160 | $140.00 | $152.00 | $145.00 | $150.00 | $90.00 | $96.00 |
| 0480 | Beveling of pipe end (7199100) | EACH | 18 | $1,500.00 | $414.00 | $1,000.00 | $600.00 | $1,500.00 | $850.00 |
| 0490 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 65 | $168.00 | $237.00 | $306.90 | $200.00 | $168.00 | $325.00 |
| 0500 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 72 | $50.00 | $95.00 | $71.50 | $70.00 | $50.00 | $75.00 |
| 0510 | Concrete driveway(6" uniform) (7205000) | SY | 74 | $100.00 | $168.00 | $107.80 | $116.00 | $100.00 | $145.00 |
| 0520 | Elastomeric bearing (7243100) | EACH | 10 | $250.00 | $390.00 | $800.00 | $300.00 | $725.00 | $900.00 |
| 0530 | Waterproofing (7282000) | SY | 25.06 | $50.00 | $97.00 | $100.00 | $120.00 | $100.00 | $125.00 |
| 0540 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 124 | $100.00 | $126.00 | $100.00 | $180.00 | $95.00 | $125.00 |
| 0550 | Rip-rap (class A) (8041010) | TON | 529 | $85.00 | $113.00 | $75.00 | $100.00 | $90.00 | $74.00 |
| 0560 | Rip-rap (class B) (8041020) | TON | 703 | $85.00 | $111.00 | $85.00 | $100.00 | $90.00 | $77.00 |
| 0570 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 1,626 | $3.00 | $4.00 | $6.00 | $6.00 | $8.00 | $4.25 |
| 0580 | MT2 leading end treatment TL2 (8051155) | EACH | 4 | $3,100.00 | $2,897.00 | $3,100.00 | $3,700.00 | $3,100.00 | $4,500.00 |
| 0590 | MGS3 GR standard shoulder (8052100) | LF | 475 | $23.00 | $26.00 | $23.00 | $29.00 | $23.00 | $35.00 |
| 0600 | MTBBC2 MASH thrie-beam barrier connector TL2 (8053255) | EACH | 4 | $1,950.00 | $2,682.00 | $1,950.00 | $2,300.00 | $1,950.00 | $3,300.00 |
| 0610 | Flume inlet at guardrail (handwork) (8053257) | EACH | 2 | $4,900.00 | $3,323.00 | $4,950.00 | $6,000.00 | $7,900.00 | $9,000.00 |
| 0620 | Non-mow strip under guardrail (8055250) | SY | 490 | $40.00 | $103.00 | $150.92 | $140.00 | $120.00 | $165.00 |
| 0625 | Temporary barrier fence (orange) (8068301) | LF | 325 | $3.00 | $2.00 | $4.07 | $3.50 | $3.25 | $6.00 |
| 0630 | Right of way marker(rebar and cap) (8091010) | EACH | 35 | $275.00 | $161.00 | $150.00 | $160.00 | $125.00 | $185.00 |
| 0640 | Right of way plat (8091050) | LS | 1 | $3,700.00 | $8,048.00 | $7,500.00 | $5,600.00 | $1,500.00 | $3,000.00 |
| 0650 | Permanent cover (8100100) | ACRE | 2.60 | $1,400.00 | $2,253.00 | $1,731.52 | $2,000.00 | $1,400.00 | $3,900.00 |
| 0660 | Temporary cover (8100200) | ACRE | 1.30 | $1,295.00 | $1,985.00 | $1,425.96 | $1,500.00 | $1,295.00 | $2,975.00 |
| 0670 | Fertilizer (nitrogen) (8104005) | LB | 260 | $4.00 | $2.20 | $4.58 | $2.35 | $4.00 | $8.25 |
| 0680 | Fertilizer (phosphoric acid) (8104010) | LB | 260 | $4.00 | $2.20 | $4.58 | $2.35 | $4.00 | $8.25 |
| 0690 | Fertilizer (potash) (8104015) | LB | 260 | $4.00 | $2.20 | $4.58 | $2.35 | $4.00 | $8.25 |
| 0700 | Agricultural granular lime (8105005) | LB | 520 | $4.00 | $0.43 | $0.12 | $0.60 | $4.00 | $1.00 |
| 0710 | Selective watering (8109050) | GAL | 54,300 | $0.09 | $0.16 | $0.12 | $0.01 | $0.09 | $0.10 |
| 0720 | Mowing (8109901) | ACRE | 8 | $450.00 | $591.00 | $254.64 | $560.00 | $450.00 | $750.00 |
| 0730 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 1.73 | $3,800.00 | $3,914.00 | $4,074.17 | $4,600.00 | $3,800.00 | $5,400.00 |
| 0740 | Temporary erosion control blanket (ecb) (8151110) | MSY | 4.15 | $1,700.00 | $1,664.00 | $1,680.60 | $1,950.00 | $1,700.00 | $2,500.00 |
| 0750 | Hydraulic erosion control product (hecp) - type 2 (8151202) | ACRE | 5.85 | $2,720.00 | $3,863.00 | $2,444.50 | $3,400.00 | $2,720.00 | $3,400.00 |
| 0760 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 1.95 | $3,000.00 | $4,292.00 | $3,259.34 | $3,820.00 | $3,000.00 | $4,350.00 |
| 0770 | Silt fence (8153000) | LF | 3,130 | $3.25 | $4.00 | $2.95 | $3.50 | $3.25 | $4.00 |
| 0780 | Replace/repair silt fence (8153090) | LF | 313 | $5.50 | $6.00 | $2.95 | $3.50 | $3.25 | $9.00 |
| 0790 | Cleaning silt basins (8154010) | CY | 1,245 | $1.00 | $32.00 | $10.00 | $20.00 | $40.00 | $24.00 |
| 0800 | Removal of silt retained by silt fence (8154050) | LF | 782.50 | $3.00 | $8.50 | $7.00 | $10.00 | $15.00 | $6.00 |
| 0810 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 106 | $60.00 | $73.00 | $150.00 | $80.00 | $75.00 | $69.00 |
| 0820 | Stabilized construction entrance (8156490) | SY | 550 | $15.00 | $21.00 | $20.00 | $23.00 | $20.00 | $28.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of November 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.