SCDOT contract 2971000 bid tabulation
S-294(Uriah Rd) Bridge Replacement over Camp Branch Rd. Let by South Carolina DOT on January 13, 2026, Lancaster, District 4. 6 bids received; low bid $1,556,668 by Coogler Construction, Inc..
- Owner
- South Carolina DOT
- Letting
- 13 JAN 2026
- Pay items
- 47
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Coogler Construction, Inc. | $1,556,668 | Low |
| 2 | Mountain Creek Contractors, Inc. | $1,996,561 | +28% |
| 3 | Blythe Development, LLC | $2,017,269 | +30% |
| 4 | Dane Construction, LLC | $2,474,101 | +59% |
| 5 | Eagle Construction Company | $3,422,556 | +120% |
| 6 | Cekra, Inc. | $3,782,539 | +143% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Coogler Construction, Inc. | 2. Mountain Creek Contractors, Inc. | 3. Blythe Development, LLC | 4. Dane Construction, LLC | 5. Eagle Construction Company | 6. Cekra, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $170,000 | $90,131 | $100,000 | $123,705 | $170,000 | $185,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $18,878 | $90,131 | $21,000 | $49,480 | $22,500 | $74,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $9,000.00 | $25,000 | $17,000 | $12,000 | $32,000 | $80,000 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $20,000 | $13,756 | $10,000 | $25,000 | $5,000.00 | $54,000 |
| 0050 | Clearing & grubbing within right of way (2011000) | LS | 1 | $47,500 | $62,742 | $108,000 | $115,000 | $94,500 | $125,000 |
| 0060 | Removal & disposal of existing pavement (2023000) | SY | 524 | $22.50 | $16.82 | $10.00 | $15.00 | $12.00 | $40.00 |
| 0070 | Removal & disposal of existing culvert(__)'X(__) 30' X 13' (2028500) | EACH | 1 | $18,500 | $100,000 | $180,000 | $150,000 | $150,000 | $450,000 |
| 0080 | Unclassified excavation (2031000) | CY | 82 | $200.00 | $78.13 | $90.00 | $40.00 | $150.00 | $30.00 |
| 0090 | Borrow excavation (2033000) | CY | 3,843 | $25.00 | $30.00 | $30.00 | $42.00 | $95.00 | $30.00 |
| 0100 | Fine grading (2081001) | SY | 900 | $7.50 | $14.33 | $7.00 | $10.00 | $4.00 | $6.00 |
| 0110 | Liquid asphalt binder PG64-22 (4011004) | TON | 14.50 | $740.00 | $714.51 | $900.00 | $797.12 | $750.00 | $850.00 |
| 0120 | Asphalt base course - type B (4020320) | TON | 240 | $160.00 | $138.00 | $210.00 | $148.17 | $225.00 | $400.00 |
| 0130 | Asphalt surface course type C (4040340) | TON | 58 | $94.00 | $215.50 | $245.00 | $214.01 | $575.00 | $650.00 |
| 0140 | Traffic control (6011000) | LS | 1 | $10,500 | $1,000.00 | $7,000.00 | $6,500.00 | $55,000 | $185,000 |
| 0150 | Barricade - type III (6041200) | LF | 84 | $45.60 | $25.00 | $54.00 | $25.00 | $60.00 | $40.00 |
| 0160 | Permanent construction signs (ground mounted) (6051120) | SF | 184 | $39.19 | $6.95 | $9.00 | $6.95 | $15.00 | $16.00 |
| 0170 | Construction zone electric changeable message sign (trailer (6062000) | EACH | 2 | $26,000 | $5,200.00 | $6,400.00 | $5,200.00 | $18,000 | $12,000 |
| 0180 | Type B - flashing light (608100B) | EACH | 16 | $155.00 | $165.00 | $200.00 | $190.00 | $225.00 | $110.00 |
| 0190 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 1,188 | $1.15 | $0.25 | $0.30 | $0.25 | $0.35 | $2.00 |
| 0200 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 1,188 | $1.15 | $0.25 | $0.30 | $0.25 | $0.35 | $2.00 |
| 0210 | Temporary yellow pavement markers BI-dir.- 4"X4" (6092155) | EACH | 8 | $11.00 | $7.50 | $10.00 | $7.50 | $10.00 | $14.00 |
| 0220 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 594 | $2.96 | $2.50 | $3.00 | $2.50 | $3.25 | $2.00 |
| 0230 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 594 | $2.96 | $2.50 | $3.00 | $2.50 | $3.25 | $2.00 |
| 0240 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 4 | $11.00 | $7.50 | $9.00 | $7.50 | $10.00 | $2.00 |
| 0250 | Design, detail and construct PC floorless culvert no. 1 (7225001) | EACH | 1 | $944,500 | $1,350,000 | $1,297,000 | $1,699,760 | $2,300,000 | $2,200,000 |
| 0260 | Rip-rap (class A) (8041010) | TON | 15 | $115.00 | $216.29 | $100.00 | $125.00 | $90.00 | $300.00 |
| 0270 | Geotextile fabric for erosion control under riprap (class 2) (8042800) | SY | 30 | $4.50 | $20.03 | $4.00 | $10.00 | $40.00 | $6.00 |
| 0275 | Temporary barrier fence (orange) (8068301) | LF | 300 | $5.25 | $5.00 | $6.00 | $3.75 | $6.00 | $6.00 |
| 0280 | Right of way marker(rebar and cap) (8091010) | EACH | 14 | $250.00 | $200.00 | $250.00 | $150.00 | $240.00 | $180.00 |
| 0290 | Right of way plat (8091050) | LS | 1 | $5,500.00 | $5,000.00 | $2,000.00 | $3,000.00 | $3,200.00 | $8,000.00 |
| 0300 | Permanent cover (8100100) | ACRE | 0.65 | $3,500.00 | $1,485.37 | $2,000.00 | $1,485.37 | $3,000.00 | $2,000.00 |
| 0310 | Temporary cover (8100200) | ACRE | 0.33 | $3,500.00 | $923.26 | $1,200.00 | $937.68 | $5,300.00 | $2,000.00 |
| 0320 | Compost (8101105) | CY | 17 | $85.50 | $24.21 | $30.00 | $24.21 | $100.00 | $14.00 |
| 0330 | Fertilizer (nitrogen) (8104005) | LB | 65 | $24.00 | $1.74 | $2.00 | $1.74 | $5.00 | $4.00 |
| 0340 | Fertilizer (phosphoric acid) (8104010) | LB | 65 | $24.00 | $1.74 | $2.00 | $1.74 | $5.00 | $4.00 |
| 0350 | Fertilizer (potash) (8104015) | LB | 65 | $24.00 | $1.74 | $2.00 | $1.74 | $5.00 | $4.00 |
| 0360 | Agricultural granular lime (8105005) | LB | 1,300 | $1.50 | $1.74 | $2.00 | $1.74 | $1.00 | $1.00 |
| 0370 | Selective watering (8109050) | GAL | 54,300 | $0.25 | $0.01 | $0.01 | $0.01 | $0.06 | $1.00 |
| 0380 | Mowing (8109901) | ACRE | 1.95 | $1,500.00 | $851.14 | $550.00 | $436.48 | $850.00 | $400.00 |
| 0390 | Temporary erosion control blanket (ecb) (8151110) | MSY | 0.50 | $3,000.00 | $2,456.44 | $3,100.00 | $2,491.53 | $2,500.00 | $1,900.00 |
| 0400 | Sediment tubes for ditch checks (8152007) | LF | 110 | $20.00 | $11.31 | $14.00 | $15.00 | $20.00 | $12.00 |
| 0410 | Silt fence (8153000) | LF | 600 | $4.75 | $3.81 | $6.50 | $3.85 | $5.00 | $4.00 |
| 0420 | Replace/repair silt fence (8153090) | LF | 60 | $4.75 | $3.86 | $5.00 | $3.86 | $8.00 | $5.00 |
| 0430 | Cleaning silt basins (8154010) | CY | 22 | $30.00 | $37.81 | $93.00 | $50.00 | $200.00 | $25.00 |
| 0440 | Removal of silt retained by silt fence (8154050) | LF | 156 | $4.00 | $23.46 | $2.00 | $8.00 | $12.50 | $5.00 |
| 0450 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 10 | $75.00 | $116.59 | $80.00 | $100.00 | $150.00 | $95.00 |
| 0451 | Stabilized construction entrance (8156490) | SY | 550 | $20.00 | $25.59 | $23.00 | $15.00 | $32.00 | $30.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of January 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.