Lci-Lineberger Construction, Inc.: SCDOT bid record
Lci-Lineberger Construction, Inc. submitted 19 bids on South Carolina DOT contracts in the data, from 12 APR 2022 to 13 OCT 2026, and was the low bidder on 5 of them (26%). When it was not low, its total sat a median +15% above the low bid.
- Owner
- South Carolina DOT
- Low bid volume
- $30,840,527
- Latest bid
- 13 OCT 2026
- Data through
- 13 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 1 | 1 | 100% |
| 2024 | 4 | 3 | 75% |
| 2025 | 7 | 0 | 0% |
| 2026 | 7 | 1 | 14% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 4 | 18 | 5 | 28% |
| District 1 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Station grading | 2035000 | STA | 14 | 11 (79%) | $1,049.73 | $1,630.00 |
| Detectable warning material | 7204900 | SF | 11 | 10 (91%) | $19.87 | $50.00 |
| Milling existing asphalt pavement (variable) | 4013990 | SY | 18 | 7 (39%) | $5.61 | $11.30 |
| Removal & disposal of existing pavement | 2023000 | SY | 13 | 7 (54%) | $24.41 | $35.00 |
| Full depth asph. pav. patching 8" unif | 4012080 | SY | 12 | 5 (42%) | $95.00 | $84.00 |
| Cement modified recycled base (10" unif)-curing method B | 3063232 | SY | 12 | 5 (42%) | $7.00 | $8.00 |
| Concrete collar for UP to 24" pipe | 7197052 | EACH | 10 | 5 (50%) | $2,111.03 | $3,500.00 |
| Unclassified excavation | 2031000 | CY | 18 | 4 (22%) | $42.12 | $42.80 |
| 4" white broken lines(gaps excl.)thermoplastic- 90 mil. | 6271005 | LF | 18 | 4 (22%) | $0.82 | $0.60 |
| Driveway paving-surface type C | 4047220 | TON | 13 | 4 (31%) | $192.99 | $225.00 |
| Pedestrian ramp construction | 7209000 | SY | 10 | 4 (40%) | $130.00 | $150.00 |
| Concrete sidewalk(4" uniform) | 7204100 | SY | 9 | 4 (44%) | $83.85 | $78.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Truerock Construction, LLC | 12 | 9 of 12 |
| C.R. Jackson, Inc. | 10 | 6 of 10 |
| King Asphalt, Inc. | 9 | 4 of 9 |
| Palmetto Corp. of Conway | 8 | 3 of 8 |
| Blythe Brothers Asphalt Co., LLC | 4 | 3 of 4 |
| Eagle Construction Company | 3 | 2 of 3 |
| Universal Civil Construction, LLC | 2 | 0 of 2 |
| Aos Specialty Contractors, Inc. | 2 | 0 of 2 |
| C. Ray Miles Construction Company, Inc. | 1 | 0 of 1 |
| Cherokee, Inc. | 1 | 0 of 1 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 13 OCT 2026 | 2973031 | District 4 | Intersection Improvement - SC 5 at S-358 (Steel Hill Road) | 6 of 9 | $1,944,884 | +31% |
| 09 SEP 2026 | 1377860 | District 4 | 2027 Chesterfield Pavement Improvement | 3 of 3 | $10,532,886 | +29% |
| 09 SEP 2026 | 2977880 | District 4 | 2027 Lancaster Pavement Improvement | 3 of 4 | $8,723,694 | +9.0% |
| 10 MAR 2026 | 1374080 | District 4 | 2026 Chesterfield Pavement Improvement | 3 of 3 | $6,372,063 | +13% |
| 10 MAR 2026 | 2974520 | District 4 | 2026 District 4 Pavement Improvement | 1 of 4 | $7,991,202 | Low, 6.0% under the second |
| 13 JAN 2026 | 2875500 | District 1 | 2026 Kershaw Pavement Improvement | 4 of 4 | $9,344,277 | +15% |
| 13 JAN 2026 | 4673510 | District 4 | 2026 York Pavement Improvement | 3 of 3 | $8,424,163 | +8.0% |
| 12 NOV 2025 | 5474530 | District 4 | 2026 District 4 Pavement Improvement | 3 of 3 | $6,655,268 | +14% |
| 14 OCT 2025 | 1272231 | District 4 | SYSTEM UPGRADE: SC 901 (Edgeland Road) | 2 of 7 | $4,515,662 | +3.0% |
| 09 SEP 2025 | 1273410 | District 4 | 2026 Chester Rehab/Reconstruction | 4 of 4 | $9,380,719 | +16% |
| 09 SEP 2025 | 2073350 | District 4 | 2026 Fairfield Recon-Rehab | 2 of 3 | $7,625,106 | +9.0% |
| 10 JUN 2025 | 8872880 | District 4 | SC 903 RRSP Project Lancaster County | 2 of 3 | $2,977,616 | +4.0% |
| 11 MAR 2025 | 1369610 | District 4 | 2025 Chesterfield Recon/Rehab | 3 of 3 | $7,831,186 | +16% |
| 11 MAR 2025 | 4669320 | District 4 | 2025 York Rehabilitation | 3 of 3 | $6,589,412 | +23% |
| 10 DEC 2024 | 2969801 | District 4 | Resurfacing - S-28 Shiloh Unity Road (S-36 Potters Rd to SC 522) | 2 of 5 | $3,221,153 | +17% |
| 13 NOV 2024 | 2969570 | District 4 | 2025 NHS Primary Pavement Improvement Program | 1 of 4 | $7,996,865 | Low, 1.0% under the second |
| 12 MAR 2024 | 2965500 | District 4 | 2024 Lancaster Pavement Improvement Program | 1 of 3 | $5,869,831 | Low, 0.0% under the second |
| 13 FEB 2024 | 5465960 | District 4 | CMRB, STA Grade, HMA | 1 of 3 | $7,995,581 | Low, 8.0% under the second |
| 12 APR 2022 | 2959560 | District 4 | Corridor Improvements - S-83 (Lancaster Co) | 1 of 3 | $987,048 | Low, 37% under the second |
How this record was read
SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; SCDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.