| 0010 | Mobilization (1031000) | LS | 1 | $391,000 | $350,000 | $180,421 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $234,500 | $48,000 | $82,103 |
| 0030 | Selected clearing & grubbing (2014000) | LS | 1 | $78,000 | $257,000 | $110,567 |
| 0040 | Removal & disposal of existing pavement (2023000) | SY | 1,375 | $47.00 | $27.00 | $11.85 |
| 0050 | Removal & disposal of existing curb (2024100) | LF | 822 | $17.00 | $37.00 | $23.83 |
| 0060 | Removal of exist. guardrail (2027801) | LF | 1,525 | $2.00 | $1.00 | $2.12 |
| 0070 | Unclassified excavation (2031000) | CY | 851 | $56.75 | $20.00 | $37.99 |
| 0080 | Borrow excavation (2033000) | CY | 810 | $39.55 | $74.00 | $91.08 |
| 0090 | Station grading (2035000) | STA | 19.91 | $2,285.00 | $1,500.00 | $1,333.67 |
| 0100 | Additional rock for full depth reclamation (3059001) | TON | 438 | $49.00 | $42.70 | $67.82 |
| 0110 | Maintenance stone (3059900) | TON | 183.17 | $76.00 | $75.00 | $124.64 |
| 0120 | Cement modified recycled base (8" unif)-curing method B (3063222) | SY | 4,253 | $10.60 | $11.00 | $8.24 |
| 0130 | Cement modified recycled base (10" unif)-curing method B (3063232) | SY | 52,886 | $7.90 | $8.40 | $6.06 |
| 0140 | Portland cement for cement modified recycled base course (3064000) | TON | 1,728.50 | $212.00 | $248.00 | $237.31 |
| 0150 | Liquid asphalt binder PG64-22 (4011004) | TON | 1,688.99 | $594.40 | $605.00 | $663.76 |
| 0160 | Full depth asph. pav. patching 8" unif (4012080) | SY | 3,235 | $78.50 | $64.00 | $88.56 |
| 0170 | Full depth asph. pav. patching 10"unif (4012100) | SY | 65 | $330.50 | $95.00 | $190.60 |
| 0180 | Full depth asph. pav. patching 12"unif (4012120) | SY | 3,477 | $115.90 | $95.00 | $124.78 |
| 0190 | Full depth asph. pav. patching 14"unif (4012140) | SY | 2,265 | $128.50 | $110.00 | $149.54 |
| 0200 | Milling existing asphalt pavement 1.75" (4013117) | SY | 50,890 | $3.30 | $3.20 | $3.14 |
| 0210 | Milling existing asphalt pavement 2.0" (4013120) | SY | 53,053 | $2.60 | $3.70 | $3.72 |
| 0220 | Milling existing asphalt pavement (variable) (4013990) | SY | 9,530 | $9.70 | $9.50 | $9.35 |
| 0230 | Asphalt intermediate course type B (4030320) | TON | 5,761.07 | $70.50 | $90.40 | $94.05 |
| 0240 | Asphalt intermediate course type C (4030330) | TON | 2,112 | $53.40 | $81.00 | $90.43 |
| 0250 | Asphalt surface course type B (4040320) | TON | 14,112.71 | $73.70 | $81.00 | $94.91 |
| 0260 | Asphalt surface course type C (4040340) | TON | 6,144.33 | $70.00 | $88.00 | $94.81 |
| 0270 | Asphalt surface course type E (4040360) | TON | 657.07 | $73.00 | $99.00 | $95.21 |
| 0280 | Driveway paving-surface type C (4047220) | TON | 1,018.75 | $187.50 | $175.00 | $196.58 |
| 0290 | Asphalt surface treat (single treatment) (4060010) | SY | 57,139 | $2.70 | $2.50 | $2.03 |
| 0300 | Traffic control (6011000) | LS | 1 | $475,400 | $287,000 | $385,749 |
| 0310 | Permanent construction signs (ground mounted) (6051120) | SF | 2,652 | $5.65 | $5.65 | $6.26 |
| 0320 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 20,868 | $0.14 | $0.14 | $0.06 |
| 0330 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 206,673 | $0.14 | $0.14 | $0.13 |
| 0340 | 8"white solid lines (crosswalk& channelization)fast dry paint (6240015) | LF | 8,062 | $0.05 | $0.05 | $0.13 |
| 0350 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 4,994 | $1.00 | $1.00 | $0.56 |
| 0360 | White single arrow (left, straight, right)-fast dry paint (6240030) | EACH | 147 | $5.00 | $5.00 | $11.18 |
| 0370 | White word message "only"- fast dry paint (6240035) | EACH | 109 | $5.00 | $5.00 | $11.18 |
| 0380 | White combination arrow(STR.& RT.or STR.& LT.)fast dry paint (6240040) | EACH | 35 | $5.00 | $5.00 | $11.18 |
| 0390 | 4" yellow broken lines(gaps exc) - fast dry paint (6240105) | LF | 5,940 | $0.14 | $0.14 | $0.13 |
| 0400 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 225,660 | $0.14 | $0.14 | $0.13 |
| 0410 | 6" yellow solid line on curb/median - fast dry paint (6240112) | LF | 3,092 | $1.00 | $1.00 | $0.56 |
| 0420 | 4" white solid lines (PVT. edge lines) epoxy paint slow cure (6261010) | LF | 850 | $3.50 | $3.50 | $5.59 |
| 0430 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint slow cure (6261110) | LF | 850 | $3.50 | $3.50 | $5.59 |
| 0440 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 11,812 | $0.75 | $0.75 | $0.50 |
| 0450 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 76,724 | $0.45 | $0.45 | $0.50 |
| 0460 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 4,096 | $2.75 | $2.75 | $3.35 |
| 0470 | 24IN X 36IN white triang. yield bar (gaps exc)thermo-125MIL (6271024) | LF | 10 | $15.00 | $15.00 | $5.59 |
| 0480 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 3,044 | $8.25 | $8.25 | $8.94 |
| 0490 | White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030) | EACH | 76 | $65.00 | $65.00 | $67.08 |
| 0500 | White word message "only" - thermoplastic - 125 mil. (6271035) | EACH | 54 | $75.00 | $75.00 | $67.08 |
| 0510 | White combination arrows(STR&RT.or STR& LT)thermo-125MIL (6271040) | EACH | 18 | $100.00 | $100.00 | $83.85 |
| 0520 | 4" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064) | LF | 3,700 | $0.45 | $0.45 | $0.50 |
| 0530 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 87,697 | $0.45 | $0.45 | $0.50 |
| 0540 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 685 | $6.50 | $6.50 | $6.71 |
| 0550 | Permanent yellow pavement markers mono-dir.- 4"X 4" perm. yel. (6301005) | EACH | 387 | $6.50 | $6.50 | $6.71 |
| 0560 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 1,154 | $6.50 | $6.50 | $5.59 |
| 0570 | Milled-in rumble strip (6321000) | MI | 7.90 | $1,240.00 | $1,185.00 | $558.98 |
| 0580 | Furnish & install 1.0" schedule 80 PVC conduit (6750275) | LF | 440 | $18.00 | $17.50 | $22.36 |
| 0590 | Furnish & instl no. 14 copper wire,1-conductor for loop wire (6770413) | LF | 14,884 | $1.20 | $1.15 | $2.79 |
| 0600 | Sawcut for loop detector (6780495) | LF | 4,810 | $9.90 | $9.70 | $13.97 |
| 0610 | F&I-12"X12"X12"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (6800508) | EACH | 22 | $615.00 | $600.00 | $894.37 |
| 0620 | Temporary adjustment of traffic signal equipment (6885993) | EACH | 8 | $10,825 | $10,500 | $35,775 |
| 0630 | 15" smooth wall pipe (7143615) | LF | 120 | $133.50 | $150.00 | $298.21 |
| 0640 | 18" smooth wall pipe (7143618) | LF | 16 | $361.50 | $150.00 | $369.75 |
| 0650 | Cleaning existing pipe (7149999) | LF | 112 | $41.60 | $50.00 | $35.79 |
| 0660 | Concrete collar for UP to 24" pipe (7197052) | EACH | 2 | $4,860.00 | $2,500.00 | $2,395.52 |
| 0670 | Adjust catch basin (7197110) | EACH | 1 | $2,365.00 | $2,200.00 | $3,012.18 |
| 0680 | Concrete curb and gutter(1'-6") vertical face (7203110) | LF | 474 | $37.11 | $35.00 | $26.08 |
| 0690 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 348 | $40.20 | $41.00 | $47.18 |
| 0700 | Concrete sidewalk(4" uniform) (7204100) | SY | 120 | $97.93 | $70.00 | $89.86 |
| 0710 | Detectable warning material (7204900) | SF | 600 | $77.32 | $40.00 | $8.94 |
| 0720 | Pedestrian ramp construction (7209000) | SY | 1,200 | $149.48 | $120.00 | $106.77 |
| 0730 | Reseal deck expansion joint (7261127) | LF | 190 | $52.63 | $55.00 | $58.84 |
| 0740 | MT3 leading end treatment TL3 (8051151) | EACH | 8 | $3,100.00 | $3,150.00 | $3,465.69 |
| 0750 | MB trailing end treatment (8051710) | EACH | 2 | $1,650.00 | $1,600.00 | $1,844.64 |
| 0760 | MGS3 GR standard shoulder (8052100) | LF | 1,037.50 | $23.50 | $23.50 | $26.27 |
| 0770 | Reset fence (8071000) | LF | 450 | $20.00 | $21.50 | $22.36 |
| 0780 | Permanent grassing for non-permitted resurfacing projects (8100102) | ACRE | 5 | $4,255.00 | $4,300.00 | $3,912.88 |