SCDOT contract 0965790 bid tabulation

Safety Improvement - US 21/ SC 172/ SC 6 (Calhoun Co). Let by South Carolina DOT on September 9, 2026, Calhoun, District 7. 8 bids received; low bid $2,584,739 by Palmetto Sitework Services, LLC.

Owner
South Carolina DOT
Letting
09 SEP 2026
Pay items
92
Data through
13 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Palmetto Sitework Services, LLC$2,584,739Low
2Coogler Construction, Inc.$2,651,398+3.0%
3Eagle Construction Company$2,737,040+6.0%
4Site-Prep, Inc. of NC$2,898,472+12%
5Palmetto Corp. of Conway$3,170,611+23%
6L & L Contractors, Inc.$3,209,844+24%
7Aos Specialty Contractors, Inc.$3,347,239+30%
8Reeves Construction Company$3,390,321+31%
SCDOT contract 0965790: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Palmetto Sitework Services, LLC2. Coogler Construction, Inc.3. Eagle Construction Company4. Site-Prep, Inc. of NC5. Palmetto Corp. of Conway6. L & L Contractors, Inc.
0010Mobilization (1031000)LS1$132,500$175,920$135,000$160,000$155,000$160,000
0020Bonds and insurance (1032010)LS1$52,000$29,415$51,000$68,900$62,000$64,000
0030Construction stakes, lines & grades (1050800)EACH1$78,900$38,000$50,500$30,690$44,000$131,560
0040CPM progress schedule (1080300)LS1$34,200$20,000$3,500.00$8,855.00$6,500.00$16,700
0050Clearing & grubbing within right of way (2011000)LS1$67,500$10,000$66,000$44,000$300,000$251,000
0060Removal & disposal of existing asphalt pavement (2025000)SY3,731$12.00$18.00$10.00$17.14$17.15$16.15
0070Unclassified excavation (2031000)CY2,563$39.50$26.00$40.50$47.75$50.00$58.20
0080Borrow excavation (2033000)CY3,612$34.00$29.00$40.00$50.25$40.70$35.00
0090Fine grading (2081001)SY2,750$6.00$7.50$3.00$9.75$7.85$8.00
0100Flowable fill (2103000)CY10$230.00$350.00$750.00$220.00$570.00$300.00
0110Maintenance stone (3059900)TON100$65.00$100.00$61.00$106.50$165.00$65.00
0120Liquid asphalt binder PG64-22 (4011004)TON238$775.00$840.00$810.00$258.23$870.00$875.00
0130Milling existing asphalt pavement (variable) (4013990)SY1,193$8.00$12.00$12.00$10.85$9.25$9.75
0140Asphalt base course - type A (4020310)TON1,203$104.00$130.00$128.00$130.20$135.10$153.00
0150Asphalt intermediate course type B (4030320)TON210$104.00$130.00$135.00$130.20$191.95$215.70
0160Asphalt surface course type B (4040320)TON809$109.00$130.00$114.00$119.35$145.35$148.40
0170Asphalt surface course type C (4040340)TON894$104.00$130.00$132.00$135.63$132.25$138.00
0180Asphalt surface course type E (4040360)TON894$104.00$130.00$132.00$135.63$133.25$138.00
0190Driveway paving-surface type C (4047220)TON19$165.00$200.00$750.00$685.72$360.00$375.00
0200Stained concrete pavement (8" uniform) (5019010)SY492$195.00$190.00$250.00$200.00$158.15$220.00
0210Traffic control (6011000)LS1$285,500$126,700$251,000$340,700$302,780$197,780
0220Permanent construction signs (ground mounted) (6051120)SF368$7.80$8.70$11.00$7.03$6.00$7.75
0230Pavement markings(temporary-paint)-4" white solid lines (609115A)LF5,700$0.11$0.18$0.15$0.16$0.15$0.10
0240Pavement markings(temporary-paint)-4" yellow solid lines (609115B)LF12,500$0.11$0.18$0.15$0.16$0.15$0.10
0250Pavement markings(temporary-paint)-8" white solid lines (609125A)LF250$0.11$0.24$0.25$0.22$0.20$0.10
0260Pavement markings(temporary-paint)- 24"white solid lines (609135A)LF330$1.05$1.20$1.25$1.09$1.00$1.00
0270Pavement markings (temporary paint) 24"X36" white triangle yield bar (609138A)LF350$5.30$6.00$6.00$5.43$5.00$5.00
0280Temporary yellow pavement markers BI-dir.- 4"X4" (6092155)EACH110$7.90$12.00$9.00$10.85$10.00$7.50
02906" yellow solid line on curb/median - fast dry paint (6240112)LF1,300$1.60$1.20$2.00$1.09$1.00$1.50
03008" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271008)LF125$2.90$3.60$3.50$3.26$3.00$2.75
03104" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010)LF1,900$0.80$1.20$0.90$1.09$1.00$0.75
03208" white solid lines thermoplastic - 125 mil. (6271015)LF250$2.90$3.60$3.50$3.26$3.00$2.75
033024IN X 36IN white triang. yield bar (gaps exc)thermo-125MIL (6271024)LF75$15.80$12.00$20.00$10.85$10.00$15.00
03404" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074)LF4,100$0.80$1.20$0.90$1.09$1.00$0.75
0350Permanent yellow pavement markers BI-dir.- 4"X4" (6301100)EACH110$8.25$8.40$9.00$7.60$7.00$7.50
0360Flat sheet, type III, fixed SZ. & MSG. sign (6510105)SF326.64$29.70$30.00$32.00$15.23$13.00$27.00
0370Flat sheet, type III, size determined by MSG (6510106)SF44$32.08$30.00$40.00$10.55$9.00$25.00
0380U-section post for sign supports - 3P (6531210)LF553$17.82$18.00$21.00$10.55$9.00$15.50
0390Reflective sign post panels (6531500)LF80$14.26$15.60$25.00$14.06$12.00$11.00
0400Design & installation of rdwy. lighting electrical system 01 (6581000)EACH1$40,000$78,600$65,000$86,800$65,500$25,800
0410SGL.light STD.35'HT.AL.pole- incl top tenon MT. (6581145)EACH9$13,200$16,200$17,500$15,733$13,500$12,000
042018" smooth wall pipe (7143618)LF208$120.00$95.00$78.00$189.50$140.85$166.00
043024" smooth wall pipe (7143624)LF173$185.00$135.00$106.00$235.00$168.70$215.00
044030" smooth wall pipe (7143630)LF56$170.00$178.00$132.00$277.00$242.15$296.00
045036" smooth wall pipe (7143636)LF243$360.00$225.00$153.00$346.50$284.00$387.00
046042" smooth wall pipe (7143642)LF224$375.00$360.00$208.00$352.32$355.45$426.00
0470Catch basin - type 1 special (7191050)EACH2$8,460.00$10,000$5,600.00$7,778.00$6,135.00$7,200.00
0480Catch basin -type 9 (7191205)EACH2$6,510.00$5,000.00$5,600.00$8,567.00$5,460.00$6,300.00
0490Catch basin -type 9 with standard 3' X 5' box (7191207)EACH2$7,890.00$7,500.00$12,500$8,567.00$7,245.00$7,500.00
0500Catch basin -type 16 (7191605)EACH2$9,400.00$8,000.00$9,100.00$9,236.00$9,240.00$9,500.00
0510Catch basin -type 17 (7191625)EACH5$11,400$10,000$11,300$13,095$10,535$11,000
0520Manhole (7192105)EACH1$5,157.00$10,000$6,300.00$8,570.00$5,400.00$7,900.00
0530Beveling of pipe end (7199100)EACH20$400.00$300.00$700.00$457.00$600.00$850.00
0540Concrete curb (9" X 15") (7201000)LF290$44.50$40.00$90.00$45.85$58.00$49.00
0550Concrete curb and gutter(2'-0") vertical face (7203210)LF1,430$33.70$32.00$46.00$34.68$46.05$46.00
0560Concrete median (7206000)SY412$107.00$120.00$135.00$110.15$129.25$135.00
0580Rip-rap (class A) (8041010)TON240$100.00$106.00$94.50$168.53$181.00$200.00
0590Rip-rap (class B) (8041020)TON120$95.00$114.00$94.50$191.00$181.00$200.00
0600Rip-rap (class C) (8041030)TON500$93.00$95.00$110.00$167.16$168.00$200.00
0610Geotextile fabric for erosion control under riprap (class 2) (8042800)SY960$2.40$6.00$5.00$1.51$3.25$5.00
0620Geotextile for erosion control under riprap(class 2)type C (8048210)SY444$2.40$9.00$5.00$1.65$5.25$5.00
0630MT3 leading end treatment TL3 (8051151)EACH2$3,500.00$3,649.68$3,900.00$3,375.00$3,110.00$3,630.00
0640MGS3 GR standard shoulder (8052100)LF325$28.50$44.88$45.00$28.21$26.00$29.70
0643Moving item no. 001 (8081000)LS1$500.00$10,000$10,500$2,200.00$2,500.00$5,000.00
0646Moving item no. 002 (8081000)LS1$500.00$2,000.00$1,500.00$2,750.00$2,000.00$5,000.00
0650Right of way marker(rebar and cap) (8091010)EACH17$174.00$150.00$250.00$220.00$117.80$181.50
0660Right of way plat (8091050)LS1$2,900.00$5,500.00$6,800.00$2,200.00$4,500.00$3,025.00
0670Permanent cover (8100100)ACRE4.25$1,650.00$4,000.00$1,650.00$1,827.14$1,684.00$1,370.00
0680Temporary cover (8100200)ACRE8.50$1,370.00$3,000.00$1,450.00$1,182.00$1,089.00$1,200.00
0690Seeding - eragrostis curvula - weeping lovegrass (8102520)MSY0.72$870.00$5,000.00$1,300.00$1,064.00$980.00$1,100.00
0700Fertilizer (nitrogen) (8104005)LB425$2.90$24.00$5.00$2.10$1.94$4.00
0710Fertilizer (phosphoric acid) (8104010)LB425$2.90$24.00$5.00$2.10$1.94$4.00
0720Fertilizer (potash) (8104015)LB425$2.90$24.00$5.00$2.10$1.94$4.00
0730Agricultural granular lime (8105005)LB8,494$0.40$2.00$0.60$1.09$1.00$0.40
0740Selective watering (8109050)GAL54,300$0.01$0.25$0.11$0.06$0.05$0.09
0750Mowing (8109901)ACRE8.50$200.00$1,500.00$500.00$542.50$500.00$400.00
0760Turf reinforcement matting (TRM) type 1 (8151101)MSY1.20$4,450.00$3,800.00$4,300.00$4,657.00$4,921.30$3,600.00
0770Turf reinforcement matting (TRM) type 3 (8151103)MSY0.13$5,800.00$3,800.00$13,000$14,870$13,702$11,000
0780Temporary erosion control blanket (ecb) (8151110)MSY5.89$1,750.00$2,800.00$1,900.00$2,136.00$1,968.80$1,600.00
0790Hydraulic erosion control product (hecp) - type 3 (8151203)ACRE12.75$3,800.00$6,200.00$3,450.00$3,695.00$3,405.25$2,900.00
0800Inlet structure filter - type F (weighted) (8152004)LF146$17.00$14.25$16.00$13.02$12.00$11.50
0810Inlet structure filter- type F (non-weighted) (8152006)LF146$7.00$12.25$15.00$13.02$12.00$10.25
0820Sediment tubes for ditch checks (8152007)LF1,004$10.50$20.00$16.00$13.02$12.00$13.00
0830Silt fence (8153000)LF1,515$2.90$4.75$3.80$3.50$3.22$3.00
0840Replace/repair silt fence (8153090)LF700$1.00$4.75$7.00$4.34$4.00$4.25
0850Cleaning silt basins (8154010)CY320$3.00$100.00$20.00$13.50$40.00$15.00
0860Removal of silt retained by silt fence (8154050)LF1,515$2.00$4.75$6.00$3.40$1.90$3.25
0870Cleaning inlet structure filters (8156200)EACH26$20.00$100.00$325.00$135.00$200.00$275.00
0880Inlet structure filter - type B (8156210)EACH13$660.00$16.50$450.00$248.50$229.00$365.00
0890Inlet structure filter - type A (8156219)LF258$4.75$10.00$15.00$14.53$13.39$8.00
0900Aggregate no.5 or 57 for erosion control (8156410)TON60$120.25$95.00$78.50$114.52$168.00$65.00
0910Stabilized construction entrance (8156490)SY550$12.00$20.00$30.00$29.73$35.90$30.00
SCDOT contract 0965790: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.

Every contract let that day: SCDOT letting of September 9, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy