SCDOT contract 0965790 bid tabulation
Safety Improvement - US 21/ SC 172/ SC 6 (Calhoun Co). Let by South Carolina DOT on September 9, 2026, Calhoun, District 7. 8 bids received; low bid $2,584,739 by Palmetto Sitework Services, LLC.
- Owner
- South Carolina DOT
- Letting
- 09 SEP 2026
- Pay items
- 92
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Palmetto Sitework Services, LLC | $2,584,739 | Low |
| 2 | Coogler Construction, Inc. | $2,651,398 | +3.0% |
| 3 | Eagle Construction Company | $2,737,040 | +6.0% |
| 4 | Site-Prep, Inc. of NC | $2,898,472 | +12% |
| 5 | Palmetto Corp. of Conway | $3,170,611 | +23% |
| 6 | L & L Contractors, Inc. | $3,209,844 | +24% |
| 7 | Aos Specialty Contractors, Inc. | $3,347,239 | +30% |
| 8 | Reeves Construction Company | $3,390,321 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Palmetto Sitework Services, LLC | 2. Coogler Construction, Inc. | 3. Eagle Construction Company | 4. Site-Prep, Inc. of NC | 5. Palmetto Corp. of Conway | 6. L & L Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $132,500 | $175,920 | $135,000 | $160,000 | $155,000 | $160,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $52,000 | $29,415 | $51,000 | $68,900 | $62,000 | $64,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $78,900 | $38,000 | $50,500 | $30,690 | $44,000 | $131,560 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $34,200 | $20,000 | $3,500.00 | $8,855.00 | $6,500.00 | $16,700 |
| 0050 | Clearing & grubbing within right of way (2011000) | LS | 1 | $67,500 | $10,000 | $66,000 | $44,000 | $300,000 | $251,000 |
| 0060 | Removal & disposal of existing asphalt pavement (2025000) | SY | 3,731 | $12.00 | $18.00 | $10.00 | $17.14 | $17.15 | $16.15 |
| 0070 | Unclassified excavation (2031000) | CY | 2,563 | $39.50 | $26.00 | $40.50 | $47.75 | $50.00 | $58.20 |
| 0080 | Borrow excavation (2033000) | CY | 3,612 | $34.00 | $29.00 | $40.00 | $50.25 | $40.70 | $35.00 |
| 0090 | Fine grading (2081001) | SY | 2,750 | $6.00 | $7.50 | $3.00 | $9.75 | $7.85 | $8.00 |
| 0100 | Flowable fill (2103000) | CY | 10 | $230.00 | $350.00 | $750.00 | $220.00 | $570.00 | $300.00 |
| 0110 | Maintenance stone (3059900) | TON | 100 | $65.00 | $100.00 | $61.00 | $106.50 | $165.00 | $65.00 |
| 0120 | Liquid asphalt binder PG64-22 (4011004) | TON | 238 | $775.00 | $840.00 | $810.00 | $258.23 | $870.00 | $875.00 |
| 0130 | Milling existing asphalt pavement (variable) (4013990) | SY | 1,193 | $8.00 | $12.00 | $12.00 | $10.85 | $9.25 | $9.75 |
| 0140 | Asphalt base course - type A (4020310) | TON | 1,203 | $104.00 | $130.00 | $128.00 | $130.20 | $135.10 | $153.00 |
| 0150 | Asphalt intermediate course type B (4030320) | TON | 210 | $104.00 | $130.00 | $135.00 | $130.20 | $191.95 | $215.70 |
| 0160 | Asphalt surface course type B (4040320) | TON | 809 | $109.00 | $130.00 | $114.00 | $119.35 | $145.35 | $148.40 |
| 0170 | Asphalt surface course type C (4040340) | TON | 894 | $104.00 | $130.00 | $132.00 | $135.63 | $132.25 | $138.00 |
| 0180 | Asphalt surface course type E (4040360) | TON | 894 | $104.00 | $130.00 | $132.00 | $135.63 | $133.25 | $138.00 |
| 0190 | Driveway paving-surface type C (4047220) | TON | 19 | $165.00 | $200.00 | $750.00 | $685.72 | $360.00 | $375.00 |
| 0200 | Stained concrete pavement (8" uniform) (5019010) | SY | 492 | $195.00 | $190.00 | $250.00 | $200.00 | $158.15 | $220.00 |
| 0210 | Traffic control (6011000) | LS | 1 | $285,500 | $126,700 | $251,000 | $340,700 | $302,780 | $197,780 |
| 0220 | Permanent construction signs (ground mounted) (6051120) | SF | 368 | $7.80 | $8.70 | $11.00 | $7.03 | $6.00 | $7.75 |
| 0230 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 5,700 | $0.11 | $0.18 | $0.15 | $0.16 | $0.15 | $0.10 |
| 0240 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 12,500 | $0.11 | $0.18 | $0.15 | $0.16 | $0.15 | $0.10 |
| 0250 | Pavement markings(temporary-paint)-8" white solid lines (609125A) | LF | 250 | $0.11 | $0.24 | $0.25 | $0.22 | $0.20 | $0.10 |
| 0260 | Pavement markings(temporary-paint)- 24"white solid lines (609135A) | LF | 330 | $1.05 | $1.20 | $1.25 | $1.09 | $1.00 | $1.00 |
| 0270 | Pavement markings (temporary paint) 24"X36" white triangle yield bar (609138A) | LF | 350 | $5.30 | $6.00 | $6.00 | $5.43 | $5.00 | $5.00 |
| 0280 | Temporary yellow pavement markers BI-dir.- 4"X4" (6092155) | EACH | 110 | $7.90 | $12.00 | $9.00 | $10.85 | $10.00 | $7.50 |
| 0290 | 6" yellow solid line on curb/median - fast dry paint (6240112) | LF | 1,300 | $1.60 | $1.20 | $2.00 | $1.09 | $1.00 | $1.50 |
| 0300 | 8" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271008) | LF | 125 | $2.90 | $3.60 | $3.50 | $3.26 | $3.00 | $2.75 |
| 0310 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 1,900 | $0.80 | $1.20 | $0.90 | $1.09 | $1.00 | $0.75 |
| 0320 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 250 | $2.90 | $3.60 | $3.50 | $3.26 | $3.00 | $2.75 |
| 0330 | 24IN X 36IN white triang. yield bar (gaps exc)thermo-125MIL (6271024) | LF | 75 | $15.80 | $12.00 | $20.00 | $10.85 | $10.00 | $15.00 |
| 0340 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 4,100 | $0.80 | $1.20 | $0.90 | $1.09 | $1.00 | $0.75 |
| 0350 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 110 | $8.25 | $8.40 | $9.00 | $7.60 | $7.00 | $7.50 |
| 0360 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 326.64 | $29.70 | $30.00 | $32.00 | $15.23 | $13.00 | $27.00 |
| 0370 | Flat sheet, type III, size determined by MSG (6510106) | SF | 44 | $32.08 | $30.00 | $40.00 | $10.55 | $9.00 | $25.00 |
| 0380 | U-section post for sign supports - 3P (6531210) | LF | 553 | $17.82 | $18.00 | $21.00 | $10.55 | $9.00 | $15.50 |
| 0390 | Reflective sign post panels (6531500) | LF | 80 | $14.26 | $15.60 | $25.00 | $14.06 | $12.00 | $11.00 |
| 0400 | Design & installation of rdwy. lighting electrical system 01 (6581000) | EACH | 1 | $40,000 | $78,600 | $65,000 | $86,800 | $65,500 | $25,800 |
| 0410 | SGL.light STD.35'HT.AL.pole- incl top tenon MT. (6581145) | EACH | 9 | $13,200 | $16,200 | $17,500 | $15,733 | $13,500 | $12,000 |
| 0420 | 18" smooth wall pipe (7143618) | LF | 208 | $120.00 | $95.00 | $78.00 | $189.50 | $140.85 | $166.00 |
| 0430 | 24" smooth wall pipe (7143624) | LF | 173 | $185.00 | $135.00 | $106.00 | $235.00 | $168.70 | $215.00 |
| 0440 | 30" smooth wall pipe (7143630) | LF | 56 | $170.00 | $178.00 | $132.00 | $277.00 | $242.15 | $296.00 |
| 0450 | 36" smooth wall pipe (7143636) | LF | 243 | $360.00 | $225.00 | $153.00 | $346.50 | $284.00 | $387.00 |
| 0460 | 42" smooth wall pipe (7143642) | LF | 224 | $375.00 | $360.00 | $208.00 | $352.32 | $355.45 | $426.00 |
| 0470 | Catch basin - type 1 special (7191050) | EACH | 2 | $8,460.00 | $10,000 | $5,600.00 | $7,778.00 | $6,135.00 | $7,200.00 |
| 0480 | Catch basin -type 9 (7191205) | EACH | 2 | $6,510.00 | $5,000.00 | $5,600.00 | $8,567.00 | $5,460.00 | $6,300.00 |
| 0490 | Catch basin -type 9 with standard 3' X 5' box (7191207) | EACH | 2 | $7,890.00 | $7,500.00 | $12,500 | $8,567.00 | $7,245.00 | $7,500.00 |
| 0500 | Catch basin -type 16 (7191605) | EACH | 2 | $9,400.00 | $8,000.00 | $9,100.00 | $9,236.00 | $9,240.00 | $9,500.00 |
| 0510 | Catch basin -type 17 (7191625) | EACH | 5 | $11,400 | $10,000 | $11,300 | $13,095 | $10,535 | $11,000 |
| 0520 | Manhole (7192105) | EACH | 1 | $5,157.00 | $10,000 | $6,300.00 | $8,570.00 | $5,400.00 | $7,900.00 |
| 0530 | Beveling of pipe end (7199100) | EACH | 20 | $400.00 | $300.00 | $700.00 | $457.00 | $600.00 | $850.00 |
| 0540 | Concrete curb (9" X 15") (7201000) | LF | 290 | $44.50 | $40.00 | $90.00 | $45.85 | $58.00 | $49.00 |
| 0550 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 1,430 | $33.70 | $32.00 | $46.00 | $34.68 | $46.05 | $46.00 |
| 0560 | Concrete median (7206000) | SY | 412 | $107.00 | $120.00 | $135.00 | $110.15 | $129.25 | $135.00 |
| 0580 | Rip-rap (class A) (8041010) | TON | 240 | $100.00 | $106.00 | $94.50 | $168.53 | $181.00 | $200.00 |
| 0590 | Rip-rap (class B) (8041020) | TON | 120 | $95.00 | $114.00 | $94.50 | $191.00 | $181.00 | $200.00 |
| 0600 | Rip-rap (class C) (8041030) | TON | 500 | $93.00 | $95.00 | $110.00 | $167.16 | $168.00 | $200.00 |
| 0610 | Geotextile fabric for erosion control under riprap (class 2) (8042800) | SY | 960 | $2.40 | $6.00 | $5.00 | $1.51 | $3.25 | $5.00 |
| 0620 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 444 | $2.40 | $9.00 | $5.00 | $1.65 | $5.25 | $5.00 |
| 0630 | MT3 leading end treatment TL3 (8051151) | EACH | 2 | $3,500.00 | $3,649.68 | $3,900.00 | $3,375.00 | $3,110.00 | $3,630.00 |
| 0640 | MGS3 GR standard shoulder (8052100) | LF | 325 | $28.50 | $44.88 | $45.00 | $28.21 | $26.00 | $29.70 |
| 0643 | Moving item no. 001 (8081000) | LS | 1 | $500.00 | $10,000 | $10,500 | $2,200.00 | $2,500.00 | $5,000.00 |
| 0646 | Moving item no. 002 (8081000) | LS | 1 | $500.00 | $2,000.00 | $1,500.00 | $2,750.00 | $2,000.00 | $5,000.00 |
| 0650 | Right of way marker(rebar and cap) (8091010) | EACH | 17 | $174.00 | $150.00 | $250.00 | $220.00 | $117.80 | $181.50 |
| 0660 | Right of way plat (8091050) | LS | 1 | $2,900.00 | $5,500.00 | $6,800.00 | $2,200.00 | $4,500.00 | $3,025.00 |
| 0670 | Permanent cover (8100100) | ACRE | 4.25 | $1,650.00 | $4,000.00 | $1,650.00 | $1,827.14 | $1,684.00 | $1,370.00 |
| 0680 | Temporary cover (8100200) | ACRE | 8.50 | $1,370.00 | $3,000.00 | $1,450.00 | $1,182.00 | $1,089.00 | $1,200.00 |
| 0690 | Seeding - eragrostis curvula - weeping lovegrass (8102520) | MSY | 0.72 | $870.00 | $5,000.00 | $1,300.00 | $1,064.00 | $980.00 | $1,100.00 |
| 0700 | Fertilizer (nitrogen) (8104005) | LB | 425 | $2.90 | $24.00 | $5.00 | $2.10 | $1.94 | $4.00 |
| 0710 | Fertilizer (phosphoric acid) (8104010) | LB | 425 | $2.90 | $24.00 | $5.00 | $2.10 | $1.94 | $4.00 |
| 0720 | Fertilizer (potash) (8104015) | LB | 425 | $2.90 | $24.00 | $5.00 | $2.10 | $1.94 | $4.00 |
| 0730 | Agricultural granular lime (8105005) | LB | 8,494 | $0.40 | $2.00 | $0.60 | $1.09 | $1.00 | $0.40 |
| 0740 | Selective watering (8109050) | GAL | 54,300 | $0.01 | $0.25 | $0.11 | $0.06 | $0.05 | $0.09 |
| 0750 | Mowing (8109901) | ACRE | 8.50 | $200.00 | $1,500.00 | $500.00 | $542.50 | $500.00 | $400.00 |
| 0760 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 1.20 | $4,450.00 | $3,800.00 | $4,300.00 | $4,657.00 | $4,921.30 | $3,600.00 |
| 0770 | Turf reinforcement matting (TRM) type 3 (8151103) | MSY | 0.13 | $5,800.00 | $3,800.00 | $13,000 | $14,870 | $13,702 | $11,000 |
| 0780 | Temporary erosion control blanket (ecb) (8151110) | MSY | 5.89 | $1,750.00 | $2,800.00 | $1,900.00 | $2,136.00 | $1,968.80 | $1,600.00 |
| 0790 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 12.75 | $3,800.00 | $6,200.00 | $3,450.00 | $3,695.00 | $3,405.25 | $2,900.00 |
| 0800 | Inlet structure filter - type F (weighted) (8152004) | LF | 146 | $17.00 | $14.25 | $16.00 | $13.02 | $12.00 | $11.50 |
| 0810 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 146 | $7.00 | $12.25 | $15.00 | $13.02 | $12.00 | $10.25 |
| 0820 | Sediment tubes for ditch checks (8152007) | LF | 1,004 | $10.50 | $20.00 | $16.00 | $13.02 | $12.00 | $13.00 |
| 0830 | Silt fence (8153000) | LF | 1,515 | $2.90 | $4.75 | $3.80 | $3.50 | $3.22 | $3.00 |
| 0840 | Replace/repair silt fence (8153090) | LF | 700 | $1.00 | $4.75 | $7.00 | $4.34 | $4.00 | $4.25 |
| 0850 | Cleaning silt basins (8154010) | CY | 320 | $3.00 | $100.00 | $20.00 | $13.50 | $40.00 | $15.00 |
| 0860 | Removal of silt retained by silt fence (8154050) | LF | 1,515 | $2.00 | $4.75 | $6.00 | $3.40 | $1.90 | $3.25 |
| 0870 | Cleaning inlet structure filters (8156200) | EACH | 26 | $20.00 | $100.00 | $325.00 | $135.00 | $200.00 | $275.00 |
| 0880 | Inlet structure filter - type B (8156210) | EACH | 13 | $660.00 | $16.50 | $450.00 | $248.50 | $229.00 | $365.00 |
| 0890 | Inlet structure filter - type A (8156219) | LF | 258 | $4.75 | $10.00 | $15.00 | $14.53 | $13.39 | $8.00 |
| 0900 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 60 | $120.25 | $95.00 | $78.50 | $114.52 | $168.00 | $65.00 |
| 0910 | Stabilized construction entrance (8156490) | SY | 550 | $12.00 | $20.00 | $30.00 | $29.73 | $35.90 | $30.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of September 9, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.