SCDOT contract 2378290 bid tabulation
S-978 Tugaloo Road Bridge Replacement in Greenville. Let by South Carolina DOT on October 13, 2026, Greenville, District 3. 8 bids received; low bid $1,298,681 by Reeves Construction Company.
- Owner
- South Carolina DOT
- Letting
- 13 OCT 2026
- Pay items
- 83
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Reeves Construction Company | $1,298,681 | Low |
| 2 | Eagle Construction Company | $1,318,986 | +2.0% |
| 3 | Rakes Building and Maintenance | $1,406,907 | +8.0% |
| 4 | Dane Construction, LLC | $1,545,209 | +19% |
| 5 | Palmetto Infrastructure, Inc. | $1,564,997 | +21% |
| 6 | Coogler Construction, Inc. | $1,761,259 | +36% |
| 7 | Freyssinet, Inc. | $1,903,634 | +47% |
| 8 | Griffin Grading & Concrete, LLC | $1,923,628 | +48% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Reeves Construction Company | 2. Eagle Construction Company | 3. Rakes Building and Maintenance | 4. Dane Construction, LLC | 5. Palmetto Infrastructure, Inc. | 6. Coogler Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $65,000 | $65,000 | $40,000 | $77,200 | $75,000 | $151,200 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $40,000 | $13,500 | $26,000 | $30,900 | $26,000 | $20,903 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $18,000 | $28,500 | $14,000 | $25,800 | $40,000 | $51,200 |
| 0040 | Utility staking (1052001) | LS | 1 | $5,000.00 | $3,500.00 | $5,000.00 | $3,500.00 | $200.00 | $10,000 |
| 0050 | CPM progress schedule (1080300) | LS | 1 | $2,500.00 | $1,000.00 | $6,000.00 | $7,500.00 | $7,500.00 | $20,000 |
| 0060 | Clearing & grubbing within right of way (2011000) | LS | 1 | $100,000 | $52,400 | $9,500.00 | $70,000 | $72,400 | $85,000 |
| 0070 | Removal & disposal item no. remove and dispose of 298 LF of fence within R/W (2022000) | LS | 1 | $5,000.00 | $2,000.00 | $5,324.00 | $350.00 | $2,900.00 | $1,500.00 |
| 0080 | Removal & disposal of existing asphalt pavement (2025000) | SY | 1,343 | $17.00 | $10.00 | $42.00 | $10.00 | $12.00 | $15.00 |
| 0090 | Removal & disposal of existing bridge (2028100) | LS | 1 | $70,000 | $40,000 | $58,000 | $121,377 | $200,000 | $114,571 |
| 0100 | Unclassified excavation (2031000) | CY | 102 | $75.00 | $65.00 | $45.00 | $25.00 | $55.00 | $100.00 |
| 0110 | Borrow excavation (2033000) | CY | 1,743 | $47.00 | $49.00 | $52.00 | $35.00 | $50.00 | $40.00 |
| 0120 | Fine grading (2081001) | SY | 980 | $21.00 | $1.00 | $6.00 | $3.50 | $12.00 | $10.00 |
| 0130 | Maintenance stone (3059900) | TON | 100 | $72.00 | $49.00 | $127.50 | $54.50 | $85.00 | $100.00 |
| 0140 | Liquid asphalt binder PG64-22 (4011004) | TON | 35 | $775.00 | $1,200.00 | $704.00 | $950.09 | $1,000.00 | $1,000.00 |
| 0150 | Full depth asph. pav. patching 8" unif (4012080) | SY | 150 | $200.00 | $180.00 | $95.00 | $100.87 | $160.00 | $30.00 |
| 0160 | Asphalt base course - type B (4020320) | TON | 337 | $180.00 | $178.00 | $315.00 | $164.23 | $170.00 | $170.00 |
| 0170 | Asphalt intermediate course type C (4030330) | TON | 148 | $181.00 | $290.00 | $315.00 | $197.18 | $268.50 | $268.00 |
| 0180 | Asphalt surface course type B (4040320) | TON | 220 | $184.00 | $190.00 | $315.00 | $190.99 | $177.40 | $177.00 |
| 0190 | Traffic control (6011000) | LS | 1 | $4,000.00 | $24,000 | $15,000 | $5,000.00 | $3,400.00 | $20,000 |
| 0200 | Barricade - type III (6041200) | LF | 168 | $21.00 | $30.00 | $29.50 | $22.43 | $13.00 | $46.00 |
| 0210 | Permanent construction signs (ground mounted) (6051120) | SF | 256 | $7.40 | $10.00 | $9.44 | $7.85 | $7.50 | $39.00 |
| 0220 | Permanent construction signs (barricade mounted) (6051125) | SF | 164 | $7.40 | $10.00 | $10.00 | $7.85 | $7.50 | $38.50 |
| 0230 | Type B - flashing light (608100B) | EACH | 32 | $125.00 | $175.00 | $51.00 | $150.00 | $110.00 | $210.00 |
| 0240 | Pavement markings(temp- paint) 4" yellow broken lines (609105B) | LF | 375 | $0.20 | $0.23 | $1.86 | $0.20 | $0.20 | $1.93 |
| 0250 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 4,400 | $0.20 | $0.23 | $1.86 | $0.20 | $0.20 | $1.10 |
| 0260 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 3,000 | $0.20 | $0.23 | $1.86 | $0.20 | $0.20 | $1.10 |
| 0270 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 1,200 | $2.00 | $2.25 | $5.50 | $2.00 | $2.00 | $12.12 |
| 0280 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 1,200 | $2.00 | $2.25 | $5.50 | $2.00 | $2.00 | $2.92 |
| 0290 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 20 | $10.00 | $12.00 | $60.00 | $10.00 | $10.00 | $35.20 |
| 0300 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"WH.solid (6351150) | LF | 200 | $6.00 | $6.75 | $6.00 | $6.00 | $6.00 | $19.25 |
| 0310 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"yel.sol. (6351450) | LF | 200 | $6.00 | $6.75 | $6.00 | $6.00 | $6.00 | $19.25 |
| 0320 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 12 | $24.30 | $35.00 | $42.00 | $30.00 | $27.00 | $40.00 |
| 0330 | Flat sheet, type III, size determined by MSG (6510106) | SF | 10.50 | $33.10 | $45.00 | $42.00 | $30.00 | $30.00 | $40.00 |
| 0340 | U-section post for sign supports - 2P (6531205) | LF | 40 | $12.00 | $17.00 | $18.00 | $11.00 | $8.00 | $11.00 |
| 0350 | U-section post for sign supports - 3P (6531210) | LF | 40 | $12.00 | $17.00 | $18.00 | $12.00 | $13.00 | $11.00 |
| 0360 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 404 | $30.00 | $32.50 | $8.50 | $16.00 | $25.00 | $24.42 |
| 0370 | Conc. for structures - class 4000 (7011400) | CY | 81 | $1,200.00 | $1,090.00 | $1,100.00 | $2,500.00 | $2,750.00 | $2,441.40 |
| 0380 | Reinf. steel for structures (bridge) (7031200) | LB | 27,330 | $2.00 | $3.04 | $3.00 | $5.00 | $1.75 | $2.51 |
| 0390 | 3'-0" X 2'-0" cored slabs (7046020) | LF | 598.80 | $350.00 | $418.00 | $292.00 | $509.40 | $400.00 | $340.45 |
| 0400 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 200 | $195.00 | $168.00 | $306.00 | $170.00 | $155.00 | $234.36 |
| 0410 | Pile driving set-UP (7110010) | EACH | 10 | $1,730.00 | $4,400.00 | $1,200.00 | $3,500.00 | $3,500.00 | $13,851 |
| 0420 | Reinf. pile tips (HP14 X 73) (7111560) | EACH | 10 | $245.00 | $310.00 | $250.00 | $500.00 | $300.00 | $152.00 |
| 0430 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 226 | $90.00 | $115.00 | $200.00 | $83.00 | $100.00 | $145.00 |
| 0440 | 18" smooth wall pipe (7143618) | LF | 48 | $220.00 | $82.00 | $140.00 | $65.45 | $165.00 | $140.00 |
| 0450 | Beveling of pipe end (7199100) | EACH | 4 | $665.00 | $500.00 | $2,600.00 | $250.00 | $300.00 | $300.00 |
| 0460 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 14 | $300.00 | $425.00 | $118.00 | $273.00 | $350.00 | $320.00 |
| 0470 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 77 | $75.00 | $125.00 | $112.00 | $68.00 | $100.00 | $65.00 |
| 0480 | Elastomeric bearing (7243100) | EACH | 20 | $350.00 | $450.00 | $370.00 | $500.00 | $200.00 | $603.00 |
| 0490 | Liquid membrane waterproofing (bridge deck) (7283100) | SY | 185.60 | $160.00 | $115.00 | $192.00 | $135.00 | $85.00 | $150.00 |
| 0500 | 12" temporary pipe slope drain (8034120) | LF | 120 | $18.00 | $45.00 | $30.00 | $40.80 | $24.00 | $75.00 |
| 0510 | Rip-rap (class A) (8041010) | TON | 7 | $120.00 | $79.50 | $130.00 | $94.00 | $100.00 | $95.00 |
| 0520 | Rip-rap (class B) (8041020) | TON | 382 | $94.00 | $78.50 | $130.00 | $99.00 | $90.00 | $95.00 |
| 0530 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 500 | $7.00 | $4.00 | $9.00 | $5.00 | $12.00 | $9.00 |
| 0540 | MT2 leading end treatment TL2 (8051155) | EACH | 2 | $3,110.00 | $3,800.00 | $5,500.00 | $3,110.00 | $3,100.00 | $3,495.95 |
| 0550 | MB trailing end treatment (8051710) | EACH | 2 | $1,700.00 | $2,700.00 | $1,860.00 | $1,700.00 | $2,100.00 | $2,253.13 |
| 0560 | MTBBC2 MASH thrie-beam barrier connector TL2 (8053255) | EACH | 4 | $1,650.00 | $2,600.00 | $3,500.00 | $1,650.00 | $2,250.00 | $2,015.63 |
| 0570 | Flume inlet at guardrail (handwork) (8053257) | EACH | 1 | $4,200.00 | $3,500.00 | $885.00 | $4,500.00 | $3,000.00 | $2,300.00 |
| 0580 | Non-mow strip under guardrail (8055250) | SY | 80 | $150.00 | $135.00 | $106.00 | $92.00 | $110.00 | $80.00 |
| 0590 | Barbed wire fence - 3 strands (8062300) | LF | 355 | $15.00 | $40.00 | $10.00 | $5.50 | $12.00 | $15.00 |
| 0600 | Temporary barrier fence (orange) (8068301) | LF | 676 | $3.00 | $4.50 | $10.00 | $3.50 | $4.00 | $5.25 |
| 0610 | Moving item no. reset steel gate 1 FT off R/W (8081000) | LS | 1 | $1,900.00 | $1,500.00 | $3,200.00 | $550.00 | $1,650.00 | $850.00 |
| 0620 | Moving item no. reset steel gate and wood posts 1 FT off R/W (8081000) | LS | 1 | $1,900.00 | $1,500.00 | $3,200.00 | $600.00 | $1,600.00 | $850.00 |
| 0630 | Right of way marker(rebar and cap) (8091010) | EACH | 12 | $340.00 | $175.00 | $120.00 | $252.00 | $250.00 | $150.00 |
| 0640 | Right of way plat (8091050) | LS | 1 | $4,000.00 | $2,000.00 | $5,000.00 | $1,500.00 | $3,500.00 | $5,500.00 |
| 0650 | Permanent cover (8100100) | ACRE | 0.51 | $2,515.00 | $2,900.00 | $7,000.00 | $1,972.39 | $1,418.52 | $10,000 |
| 0660 | Temporary cover (8100200) | ACRE | 0.25 | $3,838.00 | $4,300.00 | $6,500.00 | $1,574.80 | $934.09 | $10,000 |
| 0670 | Fertilizer (nitrogen) (8104005) | LB | 51 | $3.00 | $3.50 | $7.50 | $5.00 | $1.76 | $24.00 |
| 0680 | Fertilizer (phosphoric acid) (8104010) | LB | 51 | $3.00 | $3.50 | $7.50 | $5.00 | $1.76 | $24.00 |
| 0690 | Fertilizer (potash) (8104015) | LB | 51 | $3.00 | $3.50 | $10.00 | $5.00 | $1.76 | $24.00 |
| 0700 | Agricultural granular lime (8105005) | LB | 2,025 | $0.35 | $0.50 | $6.00 | $0.50 | $0.96 | $2.00 |
| 0710 | Selective watering (8109050) | GAL | 54,300 | $0.07 | $0.08 | $0.60 | $0.20 | $0.13 | $0.25 |
| 0720 | Mowing (8109901) | ACRE | 1.52 | $527.76 | $600.00 | $800.00 | $399.47 | $452.85 | $1,500.00 |
| 0730 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 0.35 | $3,540.00 | $4,000.00 | $10,500 | $4,421.97 | $5,279.10 | $3,865.00 |
| 0740 | Turf reinforcement matting (TRM) type 2 (8151102) | MSY | 0.16 | $3,824.00 | $4,400.00 | $12,000 | $4,245.28 | $5,279.10 | $3,865.00 |
| 0750 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 0.51 | $3,571.00 | $4,100.00 | $9,230.00 | $3,944.77 | $3,001.16 | $3,500.00 |
| 0760 | Sediment tubes for ditch checks (8152007) | LF | 300 | $11.00 | $15.00 | $12.00 | $5.00 | $11.28 | $25.00 |
| 0770 | Silt fence (8153000) | LF | 1,582 | $2.85 | $3.30 | $7.00 | $3.50 | $4.72 | $4.75 |
| 0780 | Cleaning silt basins (8154010) | CY | 14 | $79.37 | $30.00 | $175.00 | $75.00 | $90.00 | $100.00 |
| 0790 | Removal of silt retained by silt fence (8154050) | LF | 60 | $9.97 | $6.00 | $4.00 | $12.00 | $28.00 | $4.75 |
| 0800 | Cleaning inlet structure filters (8156200) | EACH | 15 | $175.00 | $100.00 | $250.00 | $250.00 | $283.94 | $225.00 |
| 0810 | Inlet structure filter - type B (8156210) | EACH | 7 | $400.00 | $425.00 | $210.00 | $365.00 | $199.19 | $450.00 |
| 0820 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 1 | $195.00 | $400.00 | $127.50 | $84.00 | $650.00 | $1,000.00 |
| 0830 | Stabilized construction entrance (8156490) | SY | 550 | $17.00 | $26.50 | $12.00 | $19.50 | $25.00 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of October 13, 2026. Compiled by Mirage Metrics.