SCDOT contract 2670190 bid tabulation
Forestbrook Road (S-137) Advanced Clearing. Let by South Carolina DOT on December 9, 2025, Horry, District 5. 3 bids received; low bid $5,698,497 by Seed Slingers LLC.
- Owner
- South Carolina DOT
- Letting
- 09 DEC 2025
- Pay items
- 144
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Seed Slingers LLC | $5,698,497 | Low |
| 2 | NJR Group, Inc | $7,032,407 | +23% |
| 3 | B M C O Construction, Inc. | $10,037,770 | +76% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Seed Slingers LLC | 2. NJR Group, Inc | 3. B M C O Construction, Inc. |
|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $204,599 | $351,000 | $478,000 |
| 0020 | Mobilization - subcontractor (1031100) | LS | 1 | $173,526 | $17,000 | $250,000 |
| 0030 | Bonds and insurance (1032010) | LS | 1 | $165,582 | $84,278 | $153,000 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 1 | $87,612 | $130,000 | $550,000 |
| 0050 | Utility staking (1052001) | LS | 1 | $58,766 | $75,000 | $30,000 |
| 0060 | CPM progress schedule (1080300) | LS | 1 | $17,577 | $20,000 | $40,000 |
| 0070 | Clearing & grubbing within right of way (2011000) | LS | 1 | $818,707 | $2,595,000 | $1,500,000 |
| 0080 | Removal & disposal item no. 01 (2022000) | LS | 1 | $1,244.00 | $900.00 | $1,500.00 |
| 0090 | Removal & disposal item no. 02 (2022000) | LS | 1 | $1,244.00 | $950.00 | $1,000.00 |
| 0100 | Removal & disposal item no. 03 (2022000) | LS | 1 | $1,244.00 | $900.00 | $1,000.00 |
| 0110 | Removal & disposal item no. 04 (2022000) | LS | 1 | $1,244.00 | $1,200.00 | $1,200.00 |
| 0120 | Removal & disposal item no. 05 (2022000) | LS | 1 | $1,244.00 | $880.00 | $1,000.00 |
| 0130 | Removal & disposal item no. 06 (2022000) | LS | 1 | $1,244.00 | $1,500.00 | $1,200.00 |
| 0140 | Removal & disposal item no. 07 (2022000) | LS | 1 | $1,244.00 | $1,400.00 | $1,000.00 |
| 0150 | Removal & disposal item no. 08 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,000.00 |
| 0160 | Removal & disposal item no. 09 (2022000) | LS | 1 | $1,244.00 | $1,500.00 | $1,000.00 |
| 0170 | Removal & disposal item no. 10 (2022000) | LS | 1 | $13,926 | $26,000 | $8,000.00 |
| 0180 | Removal & disposal item no. 11 (2022000) | LS | 1 | $1.00 | $1,000.00 | $1,000.00 |
| 0190 | Removal & disposal item no. 12 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,000.00 |
| 0200 | Removal & disposal item no. 13 (2022000) | LS | 1 | $1,244.00 | $1,500.00 | $1,000.00 |
| 0210 | Removal & disposal item no. 14 (2022000) | LS | 1 | $13,926 | $450.00 | $10,000 |
| 0220 | Removal & disposal item no. 15 (2022000) | LS | 1 | $1,933.90 | $2,200.00 | $1,500.00 |
| 0230 | Removal & disposal item no. 16 (2022000) | LS | 1 | $1,244.00 | $1,120.00 | $1,100.00 |
| 0240 | Removal & disposal item no. 17 (2022000) | LS | 1 | $1,244.00 | $880.00 | $1,100.00 |
| 0250 | Removal & disposal item no. 18 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,100.00 |
| 0260 | Removal & disposal item no. 19 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,100.00 |
| 0270 | Removal & disposal item no. 20 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,100.00 |
| 0280 | Removal & disposal item no. 21 (2022000) | LS | 1 | $2,602.87 | $1,200.00 | $2,000.00 |
| 0290 | Removal & disposal item no. 22 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,100.00 |
| 0300 | Removal & disposal item no. 23 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,100.00 |
| 0310 | Removal & disposal item no. 24 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,100.00 |
| 0320 | Removal & disposal item no. 25 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,100.00 |
| 0330 | Removal & disposal item no. 26 (2022000) | LS | 1 | $1,244.00 | $1,400.00 | $1,100.00 |
| 0340 | Removal & disposal item no. 27 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,500.00 |
| 0350 | Removal & disposal item no. 28 (2022000) | LS | 1 | $1,244.00 | $800.00 | $1,500.00 |
| 0360 | Removal & disposal item no. 29 (2022000) | LS | 1 | $1,244.00 | $400.00 | $1,000.00 |
| 0370 | Removal & disposal item no. 30 (2022000) | LS | 1 | $4,503.40 | $2,000.00 | $2,000.00 |
| 0380 | Removal & disposal item no. 31 (2022000) | LS | 1 | $1,244.00 | $50.00 | $500.00 |
| 0390 | Removal & disposal item no. 32 (2022000) | LS | 1 | $1,244.00 | $500.00 | $500.00 |
| 0400 | Removal & disposal item no. 33 (2022000) | LS | 1 | $1,244.00 | $880.00 | $1,000.00 |
| 0410 | Removal & disposal item no. 34 (2022000) | LS | 1 | $1,244.00 | $880.00 | $1,500.00 |
| 0420 | Removal & disposal item no. 35 (2022000) | LS | 1 | $3,135.60 | $1,200.00 | $2,500.00 |
| 0430 | Removal & disposal item no. 36 (2022000) | LS | 1 | $3,135.60 | $1,200.00 | $2,500.00 |
| 0440 | Removal & disposal item no. 37 (2022000) | LS | 1 | $1,244.00 | $1,000.00 | $1,500.00 |
| 0450 | Removal & disposal item no. 38 (2022000) | LS | 1 | $1,244.00 | $1,250.00 | $2,500.00 |
| 0460 | Removal & disposal item no. 39 (2022000) | LS | 1 | $1,244.00 | $1,200.00 | $1,500.00 |
| 0470 | Removal & disposal item no. 40 (2022000) | LS | 1 | $1,928.79 | $2,500.00 | $2,000.00 |
| 0480 | Removal & disposal item no. 41 (2022000) | LS | 1 | $1,244.00 | $500.00 | $1,000.00 |
| 0490 | Removal & disposal item no. 42 (2022000) | LS | 1 | $1,244.00 | $500.00 | $1,000.00 |
| 0500 | Removal & disposal item no. 43 (2022000) | LS | 1 | $1.00 | $105,000 | $30,000 |
| 0510 | Removal & disposal item no. 44 (2022000) | LS | 1 | $1,244.00 | $550.00 | $2,000.00 |
| 0520 | Removal & disposal item no. 45 (2022000) | LS | 1 | $1,244.00 | $1,500.00 | $1,500.00 |
| 0530 | Removal & disposal item no. 46 (2022000) | LS | 1 | $1,244.00 | $525.00 | $1,500.00 |
| 0540 | Removal & disposal item no. 47 (2022000) | LS | 1 | $1,244.00 | $525.00 | $1,500.00 |
| 0550 | Removal & disposal item no. 48 (2022000) | LS | 1 | $14,357 | $11,000 | $8,000.00 |
| 0560 | Removal & disposal item no. 49 (2022000) | LS | 1 | $2,459.23 | $1,500.00 | $5,000.00 |
| 0570 | Removal & disposal item no. 50 (2022000) | LS | 1 | $2,514.70 | $1,500.00 | $1,500.00 |
| 0580 | Removal & disposal item no. 51 (2022000) | LS | 1 | $4,955.43 | $1,500.00 | $10,000 |
| 0590 | Removal & disposal item no. 52 (2022000) | LS | 1 | $4,955.43 | $2,000.00 | $2,000.00 |
| 0600 | Removal & disposal item no. 53 (2022000) | LS | 1 | $6,271.19 | $2,500.00 | $2,000.00 |
| 0610 | Removal & disposal item no. 54 (2022000) | LS | 1 | $6,252.76 | $2,500.00 | $2,000.00 |
| 0620 | Removal & disposal item no. 55 (2022000) | LS | 1 | $6,258.36 | $1,500.00 | $2,500.00 |
| 0630 | Removal & disposal item no. 56 (2022000) | LS | 1 | $3,345.27 | $14,000 | $5,000.00 |
| 0640 | Removal & disposal item no. 57 (2022000) | LS | 1 | $1,235.07 | $880.00 | $1,000.00 |
| 0650 | Removal & disposal item no. 58 (2022000) | LS | 1 | $4,029.17 | $1,500.00 | $2,500.00 |
| 0660 | Removal & disposal item no. 59 (2022000) | LS | 1 | $1,232.54 | $880.00 | $1,500.00 |
| 0670 | Removal & disposal item no. 60 (2022000) | LS | 1 | $1,909.14 | $1,250.00 | $1,500.00 |
| 0680 | Removal & disposal item no. 61 (2022000) | LS | 1 | $1,232.54 | $1,000.00 | $1,500.00 |
| 0690 | Removal & disposal item no. 62 (2022000) | LS | 1 | $2,779.35 | $1,250.00 | $2,000.00 |
| 0700 | Removal & disposal item no. 63 (2022000) | LS | 1 | $1,235.07 | $5,000.00 | $8,000.00 |
| 0710 | Removal & disposal item no. 64 (2022000) | LS | 1 | $807.07 | $1,500.00 | $1,000.00 |
| 0720 | Removal & disposal item no. 65 (2022000) | LS | 1 | $1,577.02 | $1,250.00 | $1,500.00 |
| 0730 | Removal & disposal item no. 66 (2022000) | LS | 1 | $1,235.07 | $1,250.00 | $2,500.00 |
| 0740 | Removal & disposal item no. 67 (2022000) | LS | 1 | $1,235.07 | $1,000.00 | $2,000.00 |
| 0750 | Removal & disposal item no. 68 (2022000) | LS | 1 | $1,235.07 | $1,000.00 | $1,000.00 |
| 0760 | Removal & disposal item no. 69 (2022000) | LS | 1 | $1,235.07 | $500.00 | $2,500.00 |
| 0770 | Removal & disposal item no. 70 (2022000) | LS | 1 | $12,277 | $12,000 | $4,500.00 |
| 0780 | Removal & disposal item no. 71 (2022000) | LS | 1 | $1,235.07 | $6,000.00 | $10,000 |
| 0790 | Removal & disposal item no. 72 (2022000) | LS | 1 | $13,926 | $12,000 | $20,000 |
| 0800 | Removal & disposal item no. 73 (2022000) | LS | 1 | $1,235.07 | $1,000.00 | $1,500.00 |
| 0810 | Removal & disposal item no. 74 (2022000) | LS | 1 | $1,918.97 | $2,250.00 | $5,000.00 |
| 0820 | Removal & disposal item no. 75 (2022000) | LS | 1 | $1,235.07 | $1,250.00 | $1,000.00 |
| 0830 | Removal & disposal item no. 76 (2022000) | LS | 1 | $1,235.07 | $1,100.00 | $1,000.00 |
| 0840 | Removal & disposal item no. 77 (2022000) | LS | 1 | $2,451.70 | $950.00 | $1,500.00 |
| 0850 | Removal & disposal item no. 78 (2022000) | LS | 1 | $1,918.97 | $1,750.00 | $2,500.00 |
| 0860 | Removal & disposal item no. 79 (2022000) | LS | 1 | $1,235.07 | $975.00 | $1,000.00 |
| 0870 | Removal & disposal item no. 80 (2022000) | LS | 1 | $1,918.97 | $1,250.00 | $2,500.00 |
| 0880 | Removal & disposal item no. 81 (2022000) | LS | 1 | $1,918.97 | $1,850.00 | $3,000.00 |
| 0890 | Removal & disposal item no. 82 (2022000) | LS | 1 | $1,235.07 | $800.00 | $1,000.00 |
| 0900 | Removal & disposal item no. 83 (2022000) | LS | 1 | $7,484.13 | $7,200.00 | $3,000.00 |
| 0910 | Removal & disposal item no. 84 (2022000) | LS | 1 | $3,896.85 | $1,750.00 | $4,000.00 |
| 0920 | Removal & disposal item no. 85 (2022000) | LS | 1 | $3,202.45 | $2,500.00 | $4,000.00 |
| 0930 | Removal & disposal item no. 86 (2022000) | LS | 1 | $3,202.45 | $1,750.00 | $2,000.00 |
| 0940 | Removal & disposal item no. 87 (2022000) | LS | 1 | $1,235.07 | $2,100.00 | $1,500.00 |
| 0950 | Removal & disposal item no. 88 (2022000) | LS | 1 | $1,235.07 | $1,250.00 | $1,500.00 |
| 0960 | Removal & disposal item no. 89 (2022000) | LS | 1 | $1,577.02 | $950.00 | $3,000.00 |
| 0970 | Removal & disposal item no. 90 (2022000) | LS | 1 | $1,918.97 | $1,000.00 | $3,000.00 |
| 0980 | Removal & disposal item no. 91 (2022000) | LS | 1 | $6,377.38 | $1,500.00 | $2,500.00 |
| 0990 | Removal & disposal item no. 92 (2022000) | LS | 1 | $2,508.05 | $1,200.00 | $3,000.00 |
| 1000 | Removal & disposal item no. 93 (2022000) | LS | 1 | $2,489.34 | $1,080.00 | $2,000.00 |
| 1010 | Removal & disposal item no. 94 (2022000) | LS | 1 | $2,489.34 | $800.00 | $1,000.00 |
| 1020 | Traffic control (6011000) | LS | 1 | $470,061 | $705,000 | $750,000 |
| 1030 | Permanent construction signs (ground mounted) (6051120) | SF | 1,752 | $9.68 | $15.00 | $10.00 |
| 1040 | Temporary barrier fence (orange) (8068301) | LF | 21,425 | $3.08 | $4.00 | $4.00 |
| 1050 | Moving item no. 01 (8081000) | LS | 1 | $2,664.24 | $5,000.00 | $8,000.00 |
| 1060 | Moving item no. 02 (8081000) | LS | 1 | $1,473.42 | $2,500.00 | $8,000.00 |
| 1070 | Moving item no. 03 (8081000) | LS | 1 | $2,664.24 | $5,000.00 | $12,000 |
| 1080 | Moving item no. 04 (8081000) | LS | 1 | $2,664.24 | $1,500.00 | $6,000.00 |
| 1090 | Moving item no. 05 (8081000) | LS | 1 | $20,638 | $4,500.00 | $8,000.00 |
| 1100 | Moving item no. 06 (8081000) | LS | 1 | $1,528.17 | $750.00 | $3,000.00 |
| 1110 | Moving item no. 07 (8081000) | LS | 1 | $9,455.47 | $5,000.00 | $7,000.00 |
| 1120 | Moving item no. 08 (8081000) | LS | 1 | $5,207.64 | $5,000.00 | $7,000.00 |
| 1130 | Moving item no. 09 (8081000) | LS | 1 | $7,109.38 | $1,000.00 | $5,000.00 |
| 1140 | Moving item no. 10 (8081000) | LS | 1 | $7,144.92 | $3,000.00 | $4,000.00 |
| 1150 | Moving item no. 11 (8081000) | LS | 1 | $7,144.92 | $3,000.00 | $4,000.00 |
| 1160 | Moving item no. 12 (8081000) | LS | 1 | $4,763.28 | $1,500.00 | $3,000.00 |
| 1170 | Moving item no. 13 (8081000) | LS | 1 | $4,763.28 | $1,500.00 | $3,000.00 |
| 1180 | Moving item no. 14 (8081000) | LS | 1 | $4,763.28 | $1,500.00 | $3,000.00 |
| 1190 | Moving item no. 15 (8081000) | LS | 1 | $4,763.28 | $1,500.00 | $3,000.00 |
| 1200 | Right of way marker(rebar and cap) (8091010) | EACH | 941 | $275.00 | $75.00 | $350.00 |
| 1210 | Right of way plat (8091050) | LS | 1 | $16,535 | $11,000 | $80,000 |
| 1220 | Permanent cover (8100100) | ACRE | 69 | $1,950.00 | $1,750.00 | $2,100.00 |
| 1230 | Temporary cover (8100200) | ACRE | 35 | $965.00 | $1,300.00 | $1,350.00 |
| 1240 | Compost (8101105) | CY | 18,600 | $2.00 | $20.00 | $75.00 |
| 1250 | Fertilizer (nitrogen) (8104005) | LB | 6,900 | $1.94 | $4.00 | $2.50 |
| 1260 | Fertilizer (phosphoric acid) (8104010) | LB | 6,900 | $1.94 | $4.00 | $2.50 |
| 1270 | Fertilizer (potash) (8104015) | LB | 6,900 | $1.94 | $4.00 | $2.50 |
| 1280 | Agricultural granular lime (8105005) | LB | 138,000 | $2.94 | $0.13 | $1.05 |
| 1290 | Selective watering (8109050) | GAL | 271,500 | $0.01 | $0.12 | $0.25 |
| 1300 | Mowing (8109901) | ACRE | 208 | $600.00 | $299.00 | $600.00 |
| 1310 | Enhanced stacked ditch checks (8151050) | LF | 9,560 | $49.50 | $21.00 | $62.00 |
| 1320 | Turf reinforcement matting (TRM) type 1 (8151151) | SY | 1,771 | $4.93 | $10.00 | $80.00 |
| 1330 | Inlet structure filter - type F (weighted) (8152004) | LF | 490 | $10.00 | $16.00 | $15.00 |
| 1340 | Sediment tubes for ditch checks (8152007) | LF | 18,200 | $12.00 | $14.50 | $16.00 |
| 1350 | Silt fence (8153000) | LF | 190,890 | $4.25 | $3.75 | $4.65 |
| 1360 | Replace/repair silt fence (8153090) | LF | 19,089 | $3.64 | $3.75 | $4.00 |
| 1370 | Floating turbidity barrier- medium duty(5'depth) (8153205) | LF | 260 | $47.50 | $95.00 | $40.00 |
| 1380 | Cleaning silt basins (8154010) | CY | 90 | $100.00 | $8.50 | $30.00 |
| 1390 | Removal of silt retained by silt fence (8154050) | LF | 47,723 | $2.60 | $5.00 | $10.00 |
| 1400 | Inlet filter cleaning (8154155) | EACH | 1,176 | $166.88 | $20.00 | $400.00 |
| 1410 | Inlet structure filter - type B (8156210) | EACH | 714 | $246.08 | $199.00 | $400.00 |
| 1420 | Inlet structure filter - type D2 (8156215) | EACH | 47 | $790.70 | $500.00 | $1,250.00 |
| 1430 | Filter material for inlet structure filter - type D2 (8156217) | EACH | 47 | $423.00 | $320.00 | $650.00 |
| 1440 | Stabilized construction entrance (8156490) | SY | 2,750 | $26.50 | $15.00 | $45.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of December 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.