SCDOT contract 4274690 bid tabulation
2026 Spartanburg Pavement Improvement. Let by South Carolina DOT on January 13, 2026, Spartanburg, District 3. 4 bids received; low bid $12,826,785 by King Asphalt, Inc..
- Owner
- South Carolina DOT
- Letting
- 13 JAN 2026
- Pay items
- 42
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | King Asphalt, Inc. | $12,826,785 | Low |
| 2 | Rogers Group, Inc. | $13,272,595 | +3.0% |
| 3 | Reeves Construction Company | $13,735,967 | +7.0% |
| 4 | Palmetto Corp. of Conway | $16,102,687 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. King Asphalt, Inc. | 2. Rogers Group, Inc. | 3. Reeves Construction Company | 4. Palmetto Corp. of Conway |
|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $395,000 | $663,550 | $320,000 | $805,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $51,500 | $395,000 | $125,535 | $320,000 |
| 0030 | Removal & disposal of existing pavement (2023000) | SY | 163 | $47.40 | $100.00 | $140.00 | $90.00 |
| 0040 | Removal of exist. guardrail (2027801) | LF | 1,000 | $2.20 | $2.15 | $2.50 | $2.10 |
| 0050 | Borrow excavation (2033000) | CY | 3,603.80 | $84.00 | $130.00 | $100.00 | $75.70 |
| 0060 | Maintenance stone (3059900) | TON | 403.60 | $91.00 | $155.00 | $133.00 | $165.00 |
| 0070 | Cement modified recycled base (10" unif)-curing method B (3063232) | SY | 69,396 | $10.00 | $11.20 | $8.95 | $11.30 |
| 0080 | Cement modified recycled base (12" unif)-curing method B (3063242) | SY | 201,719 | $11.00 | $11.79 | $9.65 | $11.35 |
| 0090 | Portland cement for cement modified recycled base course (3064000) | TON | 10,192 | $250.00 | $210.00 | $272.00 | $275.00 |
| 0100 | Liquid asphalt binder PG64-22 (4011004) | TON | 2,114.54 | $655.00 | $625.00 | $660.00 | $700.00 |
| 0110 | Full depth asph. pav. patching 8" unif (4012080) | SY | 360 | $220.00 | $200.00 | $194.00 | $160.00 |
| 0120 | Milling existing asphalt pavement (variable) (4013990) | SY | 2,281 | $10.00 | $21.00 | $35.00 | $13.25 |
| 0130 | Asphalt intermediate course type C (4030330) | TON | 3,449.60 | $87.00 | $83.60 | $99.00 | $115.25 |
| 0140 | Asphalt surface course type C (4040340) | TON | 28,336.58 | $90.00 | $94.45 | $107.00 | $123.95 |
| 0150 | Driveway paving-surface type C (4047220) | TON | 2,435 | $205.00 | $219.60 | $270.00 | $255.00 |
| 0160 | Traffic control (6011000) | LS | 1 | $1,085,000 | $805,000 | $1,250,000 | $2,060,000 |
| 0170 | Permanent construction signs (ground mounted) (6051120) | SF | 4,508 | $6.70 | $6.35 | $7.50 | $5.60 |
| 0180 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 2,600 | $0.15 | $0.13 | $0.15 | $0.14 |
| 0190 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 406,470 | $0.15 | $0.13 | $0.15 | $0.12 |
| 0200 | 8"white solid lines (crosswalk& channelization)fast dry paint (6240015) | LF | 104 | $0.01 | $0.14 | $0.15 | $0.01 |
| 0210 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 1,103 | $1.60 | $1.00 | $1.15 | $1.50 |
| 0220 | White single arrow (left, straight, right)-fast dry paint (6240030) | EACH | 10 | $0.01 | $10.05 | $11.75 | $0.01 |
| 0230 | 4" yellow broken lines(gaps exc) - fast dry paint (6240105) | LF | 5,520 | $0.15 | $0.13 | $0.15 | $0.14 |
| 0240 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 797,740 | $0.15 | $0.13 | $0.15 | $0.12 |
| 0250 | 4" white solid lines (PVT. edge lines) epoxy paint slow cure (6261010) | LF | 2,800 | $5.25 | $2.55 | $2.90 | $5.00 |
| 0260 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint slow cure (6261110) | LF | 2,800 | $5.25 | $2.55 | $2.90 | $5.00 |
| 0270 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 3,499 | $0.55 | $0.75 | $0.85 | $0.50 |
| 0280 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 187,819 | $0.50 | $0.50 | $0.55 | $0.48 |
| 0290 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 52 | $5.25 | $3.05 | $3.50 | $5.00 |
| 0300 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 544 | $10.55 | $9.05 | $10.00 | $10.00 |
| 0310 | White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030) | EACH | 5 | $200.00 | $100.50 | $115.00 | $185.00 |
| 0320 | 4" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064) | LF | 1,380 | $0.55 | $0.50 | $0.55 | $0.50 |
| 0330 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 186,448 | $0.50 | $0.50 | $0.55 | $0.48 |
| 0340 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 16 | $5.25 | $7.55 | $8.90 | $5.00 |
| 0350 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 1,264 | $5.25 | $7.55 | $8.90 | $5.00 |
| 0360 | Milled-in rumble strip (6321000) | MI | 13.96 | $525.00 | $2,000.00 | $590.00 | $500.00 |
| 0370 | Surface applied detectable warning (7209100) | SF | 10 | $63.15 | $105.00 | $295.00 | $100.00 |
| 0380 | Premash reset W-beam strong post system (8051900) | LF | 4,150 | $14.75 | $14.15 | $16.00 | $14.00 |
| 0390 | Premash reset trail W-beam type B 12.5' (8052400) | EACH | 1 | $630.00 | $606.25 | $700.00 | $600.00 |
| 0400 | Premash reset type T TL3 leading 50' (8052420) | EACH | 5 | $1,500.00 | $1,415.00 | $1,600.00 | $1,400.00 |
| 0410 | Premash type T TL3 leading 50' (8057100) | EACH | 20 | $3,160.00 | $3,035.00 | $3,500.00 | $3,000.00 |
| 0420 | Permanent grassing for non-permitted resurfacing projects (8100102) | ACRE | 17.47 | $3,500.00 | $3,390.00 | $3,900.00 | $3,255.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of January 13, 2026. Compiled by Mirage Metrics.