SCDOT contract 5671010 bid tabulation
US 17 replacement bridges in Colleton County (MP 17.2) and C. Let by South Carolina DOT on February 10, 2026, Charleston, Colleton, District 6. 4 bids received; low bid $46,467,501 by United Infrastructure Group, Inc..
- Owner
- South Carolina DOT
- Letting
- 10 FEB 2026
- Pay items
- 137
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | United Infrastructure Group, Inc. | $46,467,501 | Low |
| 2 | Zachry Construction Corporation | $48,971,160 | +5.0% |
| 3 | Crowder Construction Company | $50,286,866 | +8.0% |
| 4 | Mastec Civil, LLC | $61,590,906 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. United Infrastructure Group, Inc. | 2. Zachry Construction Corporation | 3. Crowder Construction Company | 4. Mastec Civil, LLC |
|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $2,323,375 | $2,448,558 | $2,514,359 | $3,070,000 |
| 0020 | Mobilization - subcontractor (1031100) | LS | 1 | $2,323,375 | $2,448,558 | $2,514,359 | $3,070,000 |
| 0030 | Bridge construction access (1031200) | LS | 1 | $929,350 | $2,448,558 | $4,000,000 | $7,500,000 |
| 0040 | Bonds and insurance (1032010) | LS | 1 | $1,394,025 | $979,423 | $1,005,744 | $1,840,000 |
| 0050 | Construction stakes, lines & grades (1050800) | EACH | 2 | $250,000 | $300,000 | $172,429 | $450,000 |
| 0060 | Utility staking (1052001) | LS | 1 | $35,000 | $300,000 | $53,055 | $100,000 |
| 0070 | CPM progress schedule (1080300) | LS | 1 | $25,000 | $50,000 | $59,472 | $18,000 |
| 0080 | Clearing & grubbing within roadway (2012000) | LS | 1 | $1,500,000 | $4,400,000 | $213,347 | $3,035,253 |
| 0090 | Removal & disposal of existing asphalt pavement (2025000) | SY | 8,235 | $5.97 | $22.50 | $15.00 | $16.00 |
| 0100 | Removal of exist. guardrail (2027801) | LF | 7,256 | $2.73 | $1.20 | $2.69 | $1.50 |
| 0110 | Removal & disposal of existing bridge (2028101) | LS | 1 | $400,000 | $201,471 | $596,009 | $3,917,000 |
| 0120 | Removal & disposal of existing bridge (2028102) | LS | 1 | $2,341,200 | $2,282,240 | $2,684,192 | $1,000,000 |
| 0130 | Unclassified excavation (2031000) | CY | 8,539 | $26.87 | $15.00 | $51.02 | $17.00 |
| 0140 | Borrow excavation (2033000) | CY | 83,657 | $40.30 | $24.00 | $29.59 | $34.00 |
| 0150 | Borrow pit set-UP (2033100) | LS | 1 | $1.00 | $0.01 | $10,204 | $40,000 |
| 0160 | Muck excavation (2034000) | CY | 3,755 | $18.91 | $8.98 | $35.71 | $38.00 |
| 0170 | 18" diameter pipe additional foundation work (2034518) | LF | 746 | $19.90 | $39.23 | $51.02 | $18.00 |
| 0180 | Geotextile, separation (2036020) | SY | 29,200 | $1.99 | $2.95 | $7.14 | $1.50 |
| 0190 | Monitoring device - settlement plate (2038110) | EACH | 4 | $1,592.02 | $1,899.44 | $7,105.03 | $2,500.00 |
| 0200 | Temporary shoring system (2047000) | LF | 595 | $527.34 | $285.24 | $1,171.99 | $545.00 |
| 0210 | No. 57 stone for backfill (2052000) | TON | 2,055 | $97.51 | $90.11 | $91.84 | $107.00 |
| 0220 | Stone bridge lift material (2052010) | TON | 16,275 | $92.54 | $94.93 | $91.84 | $135.00 |
| 0230 | Granular bridge lift material (2052020) | CY | 1,000 | $61.69 | $178.69 | $51.02 | $52.00 |
| 0240 | Fine grading (2081001) | SY | 20,000 | $4.28 | $6.00 | $10.20 | $7.00 |
| 0250 | Flowable fill (2103000) | CY | 106 | $274.44 | $300.19 | $1,183.54 | $240.00 |
| 0260 | Maintenance stone (3059900) | TON | 200 | $179.10 | $89.40 | $124.88 | $95.00 |
| 0270 | Liquid asphalt binder PG64-22 (4011004) | TON | 1,317 | $567.45 | $847.78 | $710.00 | $796.00 |
| 0280 | Milling existing asphalt pavement (variable) (4013990) | SY | 2,115 | $10.95 | $26.67 | $18.50 | $21.00 |
| 0290 | Asphalt base course - type A (4020310) | TON | 12,230 | $120.46 | $164.19 | $137.50 | $154.00 |
| 0300 | Asphalt intermediate course type B (4030320) | TON | 7,290 | $134.40 | $173.13 | $145.00 | $162.00 |
| 0310 | Asphalt surface course type B (4040320) | TON | 2,860 | $119.46 | $169.56 | $142.00 | $160.00 |
| 0320 | Traffic control (6011000) | LS | 1 | $1,000,000 | $110,555 | $443,355 | $1,943,000 |
| 0330 | Permanent construction signs (ground mounted) (6051120) | SF | 644 | $7.53 | $9.04 | $10.07 | $12.00 |
| 0340 | Portable terminal impact attenuator-test level 3-60 MPH (6052122) | EACH | 4 | $14,129 | $9,566.06 | $14,457 | $13,500 |
| 0350 | Anchor kit - port. attenuator(test level 3) 60MPH (605212B) | EACH | 3 | $3,339.52 | $1,768.87 | $3,417.05 | $4,500.00 |
| 0360 | Temporary concrete barrier - unanchored (6053110) | LF | 1,456 | $58.27 | $43.89 | $64.83 | $82.00 |
| 0370 | Temp conc barrier with anchorage for bridge decks (6053112) | LF | 792 | $77.84 | $25.43 | $79.64 | $98.00 |
| 0380 | Construction zone electric changeable message sign (trailer (6062000) | EACH | 2 | $18,500 | $12,050 | $13,607 | $12,000 |
| 0390 | Removable paint 4" white broken lines (609105K) | LF | 8,320 | $0.26 | $4.42 | $0.28 | $0.28 |
| 0400 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 62,410 | $0.26 | $0.18 | $0.28 | $0.28 |
| 0410 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 83,825 | $0.26 | $0.18 | $0.28 | $0.28 |
| 0420 | Temporary clear pavement markers mono-dir.- 4"X4" (6092100) | EACH | 1,940 | $5.70 | $4.84 | $5.84 | $6.20 |
| 0430 | Temporary yellow pavement markers BI-dir.- 4"X4" (6092155) | EACH | 2,330 | $5.70 | $4.84 | $5.84 | $6.20 |
| 0440 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 1,775 | $1.04 | $0.63 | $1.11 | $1.12 |
| 0450 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 7,095 | $0.67 | $0.60 | $0.72 | $0.73 |
| 0460 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 8,590 | $0.67 | $0.60 | $0.72 | $0.73 |
| 0470 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 450 | $5.70 | $6.06 | $6.10 | $6.16 |
| 0480 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 230 | $5.70 | $6.06 | $6.10 | $6.16 |
| 0490 | Removal of pavement markings (6319505) | LF | 65,495 | $0.52 | $0.18 | $0.55 | $0.50 |
| 0500 | Milled-in rumble strip (6321000) | MI | 1.35 | $2,500.00 | $3,021.34 | $5,561.98 | $2,850.00 |
| 0510 | Pref.flex.retro.PVMT.mark(T- 1)perm.60MIL4"WH.broken (6351100) | LF | 455 | $5.18 | $6.06 | $5.55 | $5.60 |
| 0520 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"WH.solid (6351150) | LF | 1,805 | $5.18 | $6.06 | $5.55 | $5.60 |
| 0530 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"yel.sol. (6351450) | LF | 1,805 | $5.18 | $6.06 | $5.55 | $5.60 |
| 0540 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 60.19 | $33.58 | $18.07 | $35.66 | $37.00 |
| 0550 | Flat sheet, type III, size determined by MSG (6510106) | SF | 48.75 | $33.58 | $19.28 | $35.66 | $37.00 |
| 0560 | U-section post for sign supports - 3P (6531210) | LF | 240 | $18.32 | $11.45 | $14.67 | $15.00 |
| 0570 | Permanent terminal impact attenuator (6700000) | EACH | 2 | $52,000 | $5,935.76 | $4,848.30 | $15,400 |
| 0580 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 3,612 | $7.00 | $26.25 | $30.89 | $19.00 |
| 0590 | Conc. for structures - class 4000 (7011400) | CY | 4,480.80 | $1,725.00 | $1,125.79 | $1,445.75 | $1,550.00 |
| 0600 | Straight headwall for 18" circular pipe-1 line (7016125) | EACH | 8 | $4,477.56 | $2,281.65 | $12,653 | $3,900.00 |
| 0610 | Grooved surface finish (7023200) | SY | 7,654 | $10.00 | $3.59 | $21.46 | $8.00 |
| 0620 | Reinf. steel for structures (bridge) (7031200) | LB | 1,476,749 | $1.50 | $1.54 | $2.11 | $1.70 |
| 0630 | Hoop reinforcing steel for structures (bridge) (7031220) | LB | 118,886 | $2.75 | $2.69 | $3.22 | $2.70 |
| 0640 | Prestressed concrete florida I-beam(54") (7045454) | LF | 1,203.40 | $425.00 | $447.93 | $400.00 | $525.00 |
| 0650 | Prestressed concrete florida I-beam(72") (7045472) | LF | 6,950 | $475.00 | $426.76 | $400.00 | $510.00 |
| 0660 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 1,802 | $100.00 | $111.40 | $99.69 | $120.00 |
| 0670 | 56" concrete median barrier (TL-5)-bridge 01 (7051070) | LF | 901 | $150.00 | $205.86 | $178.88 | $215.00 |
| 0680 | Dynamic pile analyzer test set-UP dynamic pile analyzer test setup (7110001) | EACH | 4 | $2,100.00 | $2,891.37 | $3,656.89 | $4,000.00 |
| 0690 | Pile driving set-UP (7110010) | EACH | 64 | $3,000.00 | $2,195.94 | $3,596.44 | $7,000.00 |
| 0700 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 1,993 | $60.00 | $106.65 | $65.34 | $79.00 |
| 0710 | Steel H bearing index piling (HP 14 X 73) (7112222) | LF | 188 | $130.00 | $107.34 | $65.34 | $76.00 |
| 0720 | Steel H bearing piling (HP14 X 89) (7112230) | LF | 2,725 | $72.00 | $123.56 | $78.86 | $66.00 |
| 0730 | Steel H bearing index piling (HP14 X 89) (7112232) | LF | 149 | $250.00 | $118.05 | $78.86 | $79.00 |
| 0740 | Permanent sheet pile for ground modfification (7118000) | LF | 4,046 | $70.00 | $110.00 | $110.34 | $67.00 |
| 0750 | Drilled shaft set-UP (7120006) | EACH | 24 | $80,000 | $73,986 | $92,308 | $44,180 |
| 0760 | Crosshole sonic logging setup (7120010) | EACH | 24 | $6,000.00 | $50,134 | $9,885.00 | $3,400.00 |
| 0770 | Drilled shaft with wet & dry excavation - 72" diameter (7120201) | LF | 1,080 | $856.76 | $1,156.06 | $870.63 | $1,032.00 |
| 0780 | Drilled shaft with wet & dry excavation - 78" diameter (7120211) | LF | 960 | $856.76 | $1,171.04 | $870.63 | $1,042.00 |
| 0790 | Construction casing - 78" diameter (7120215) | LF | 1,272 | $796.20 | $898.38 | $816.21 | $945.00 |
| 0800 | Construction casing - 102" diameter . (7120255) | LF | 216 | $1,592.41 | $1,796.78 | $1,632.43 | $2,075.00 |
| 0810 | 18" smooth wall pipe (7143618) | LF | 2,556 | $106.47 | $115.77 | $255.10 | $110.00 |
| 0820 | 24" smooth wall pipe (7143624) | LF | 80 | $186.07 | $164.96 | $306.20 | $158.00 |
| 0830 | Cleaning existing pipe (7149999) | LF | 168 | $8.96 | $11.87 | $102.04 | $37.00 |
| 0840 | Catch basin -type 1 CB - type 1 (7191005) | EACH | 2 | $8,039.72 | $7,925.53 | $10,204 | $12,000 |
| 0850 | Catch basin type 25 - single 4' X 6' box (7191515) | EACH | 15 | $11,443 | $12,393 | $10,204 | $12,000 |
| 0860 | Drop inlet (24" X 36") (7192020) | EACH | 6 | $6,169.09 | $6,477.34 | $10,204 | $7,000.00 |
| 0870 | Manhole (7192105) | EACH | 2 | $6,169.09 | $6,445.95 | $10,204 | $8,500.00 |
| 0880 | Extra depth of box (7196000) | LF | 47 | $582.08 | $759.08 | $663.27 | $580.00 |
| 0890 | Beveling of pipe end (7199100) | EACH | 2 | $547.26 | $1,346.08 | $2,040.82 | $771.00 |
| 0900 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 72 | $211.53 | $389.91 | $325.62 | $420.00 |
| 0910 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 269 | $60.44 | $137.39 | $54.46 | $162.00 |
| 0920 | Elastomeric bearing (7243100) | EACH | 120 | $1,500.00 | $2,118.89 | $3,980.35 | $2,100.00 |
| 0930 | Waterproofing (7282000) | SY | 110.60 | $150.00 | $148.56 | $145.11 | $85.00 |
| 0940 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 898 | $140.00 | $102.98 | $137.16 | $143.00 |
| 0950 | Rip-rap (class B) (8041020) | TON | 2,185 | $157.21 | $127.05 | $204.08 | $153.00 |
| 0960 | Geotextile for erosion control under riprap(class 2)type D (8048215) | SY | 2,675 | $2.24 | $3.78 | $7.14 | $7.50 |
| 0970 | Premash W-beam strong post system WSP3 (8051050) | LF | 4,350 | $25.10 | $27.58 | $25.14 | $26.00 |
| 0980 | MT3 leading end treatment TL3 (8051151) | EACH | 1 | $3,273.44 | $3,836.87 | $3,279.00 | $3,620.00 |
| 0990 | MB trailing end treatment (8051710) | EACH | 1 | $1,964.06 | $1,918.43 | $1,967.40 | $1,800.00 |
| 1000 | MGS3 GR standard shoulder (8052100) | LF | 1,862.50 | $26.19 | $29.38 | $26.23 | $26.00 |
| 1010 | Premash W-beam compressed SHLDR 9' post (8053001) | LF | 405 | $31.64 | $35.97 | $31.70 | $33.00 |
| 1020 | Premash thriebeam bridge conn TBBC3 (8053250) | EACH | 2 | $3,382.55 | $3,117.46 | $3,388.30 | $2,940.00 |
| 1030 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 6 | $3,819.01 | $3,237.37 | $3,825.50 | $3,050.00 |
| 1040 | Flume inlet at guardrail (handwork) (8053257) | EACH | 2 | $6,043.70 | $4,238.12 | $4,798.37 | $5,050.00 |
| 1050 | Non-mow strip under guardrail (8055250) | SY | 100 | $151.09 | $124.71 | $116.69 | $120.00 |
| 1060 | Premash type T TL3 leading 50' (8057100) | EACH | 2 | $3,273.44 | $2,697.80 | $3,279.00 | $2,540.00 |
| 1070 | 2' crash cushion 3B (8057355) | EACH | 2 | $39,250 | $41,259 | $32,790 | $36,000 |
| 1080 | 56SS reinforced barrier wall (8058055) | LF | 2,305 | $225.94 | $207.07 | $179.90 | $210.00 |
| 1090 | Temporary barrier fence (orange) (8068301) | LF | 8,883 | $3.06 | $2.87 | $2.76 | $3.50 |
| 1100 | Right of way marker(rebar and cap) (8091010) | EACH | 22 | $150.00 | $59.36 | $522.70 | $280.00 |
| 1110 | Right of way plat (8091050) | LS | 1 | $7,500.00 | $2,967.86 | $2,613.50 | $6,700.00 |
| 1120 | Permanent cover (8100100) | ACRE | 5.14 | $1,350.98 | $1,693.01 | $1,624.00 | $2,015.00 |
| 1130 | Temporary cover (8100200) | ACRE | 10.28 | $1,019.60 | $1,068.77 | $1,218.00 | $1,792.00 |
| 1140 | Fertilizer (nitrogen) (8104005) | LB | 514 | $3.06 | $2.35 | $3.81 | $2.24 |
| 1150 | Fertilizer (phosphoric acid) (8104010) | LB | 514 | $3.06 | $2.35 | $3.81 | $2.24 |
| 1160 | Fertilizer (potash) (8104015) | LB | 514 | $3.06 | $2.35 | $3.81 | $2.24 |
| 1170 | Agricultural granular lime (8105005) | LB | 10,280 | $0.41 | $1.14 | $0.11 | $0.67 |
| 1180 | Selective watering (8109050) | GAL | 135,750 | $0.09 | $0.01 | $0.11 | $0.03 |
| 1190 | Mowing (8109901) | ACRE | 30.84 | $458.82 | $497.49 | $253.75 | $84.00 |
| 1200 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 1 | $3,466.66 | $5,000.25 | $4,060.00 | $4,820.00 |
| 1210 | Temporary erosion control blanket (ecb) (8151110) | MSY | 61.59 | $1,631.37 | $1,824.82 | $1,624.00 | $3,900.00 |
| 1220 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 7.66 | $1,427.45 | $1,702.71 | $1,725.50 | $3,135.00 |
| 1230 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 7.92 | $2,936.46 | $4,128.52 | $3,248.00 | $5,365.00 |
| 1240 | Hydraulic erosion control product (hecp) - type 4 (8151204) | ACRE | 0.12 | $5,505.87 | $6,896.41 | $8,120.00 | $10,640 |
| 1250 | Inlet structure filter - type F (weighted) (8152004) | LF | 460 | $14.53 | $12.11 | $12.69 | $16.00 |
| 1260 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 3,200 | $13.25 | $12.11 | $10.15 | $11.00 |
| 1270 | Sediment tubes for ditch checks (8152007) | LF | 840 | $13.76 | $12.90 | $10.15 | $10.00 |
| 1280 | Silt fence (8153000) | LF | 43,120 | $3.77 | $3.57 | $2.89 | $3.36 |
| 1290 | Replace/repair silt fence (8153090) | LF | 8,624 | $4.59 | $4.39 | $2.89 | $3.36 |
| 1300 | Floating turbidity barrier- heavy duty(5'depth) (8153305) | LF | 835 | $28.55 | $42.01 | $65.98 | $44.00 |
| 1310 | Cleaning silt basins (8154010) | CY | 89 | $46.83 | $14.81 | $52.83 | $95.00 |
| 1320 | Removal of silt retained by silt fence (8154050) | LF | 10,780 | $9.47 | $1.87 | $43.34 | $4.50 |
| 1330 | Inlet structure filter - type A (8156219) | LF | 616 | $18.24 | $13.21 | $7.11 | $36.00 |
| 1340 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 40 | $131.11 | $89.24 | $195.48 | $108.00 |
| 1350 | Stabilized construction entrance (8156490) | SY | 1,100 | $41.52 | $44.75 | $85.74 | $30.00 |
| 1360 | Molded rubber segmental expansion joint (8990043) | LF | 92 | $2,400.00 | $2,708.33 | $5,761.44 | $2,500.00 |
| 1370 | On-the-job trainee (bridge) (9002000) | HR | 5,200 | $0.80 | $0.80 | $0.80 | $0.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of February 10, 2026. Compiled by Mirage Metrics.