TDOT contract CN262063 bid tabulation
R2bvar-m3-070 the random on-call asphalt pothole patching on various interstate and state routes. Let by Tennessee DOT on October 2, 2026, Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White. 2 bids received; low bid $918,350 by PRI of East Tennessee Inc..
- Owner
- Tennessee DOT
- Letting
- 02 OCT 2026
- Pay items
- 10
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | PRI of East Tennessee Inc. | $918,350 | Low |
| 2 | Sessions Paving Company | $1,066,100 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. PRI of East Tennessee Inc. | 2. Sessions Paving Company |
|---|---|---|---|---|---|
| 1 | Pothole temporary repair (asphalt) (411-51.01) | TON | 40 | $120.00 | $165.00 |
| 2 | Pothole permanent repair (asphalt) (411-51.02) | TON | 500 | $160.00 | $200.00 |
| 3 | Infrared pothole repair (asphalt) (411-51.10) | SF | 300 | $3.50 | $50.00 |
| 4 | Lane closure (interstate and controlled access) (712-01.08) | EACH | 5 | $1,800.00 | $3,000.00 |
| 5 | Lane closure (state routes) (712-01.09) | EACH | 95 | $1,800.00 | $2,100.00 |
| 6 | Queue protection truck (712-08.12) | DAY | 5 | $1,200.00 | $1,400.00 |
| 7 | Truck mounted attenuator W/mssage board (712-08.20) | DAY | 5 | $1,000.00 | $1,200.00 |
| 8 | Mobilization (interstate and controlled access) (717-01.20) | EACH | 5 | $10,500 | $13,250 |
| 9 | Mobilization (state routes) (717-01.21) | EACH | 45 | $10,200 | $10,950 |
| 10 | Mobilization (infrared repairs ) (717-01.22) | EACH | 40 | $3,250.00 | $3,950.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.