PRI of East Tennessee Inc.: TDOT bid record

PRI of East Tennessee Inc. submitted 42 bids on Tennessee DOT contracts in the data, from 08 DEC 2023 to 02 OCT 2026, and was the low bidder on 12 of them (29%). When it was not low, its total sat a median +14% above the low bid.

Owner
Tennessee DOT
Low bid volume
$25,127,811
Latest bid
02 OCT 2026
Data through
02 OCT 2026
42Bids
12Low bids
29Win rate, percent
+14%Median gap to the low bid when not low, 30 bids

By year

YearBidsLow bidsWin rate
2023100%
20241119%
202513431%
202617741%
PRI of East Tennessee Inc., TDOT: bids and low bids by year of letting

By county

CountyBidsLow bidsWin rate
Knox County13215%
Blount County5120%
Grainger County4250%
Jefferson County3133%
Anderson County300%
Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington3267%
Union County2150%
Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington200%
Monroe County100%
Hamblen County100%
Loudon And Monroe Counties100%
Sevier County11100%
PRI of East Tennessee Inc., TDOT: bids and low bids by county

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Signs (construction)712-06SF3816 (42%)$9.00$8.00
Flexible drums (channelizing)712-04.01EACH2814 (50%)$38.50$34.50
Arrow board (type C)712-08.03EACH2714 (52%)$1,130.00$1,170.00
Brooming & degrassing shoulders208-01.05LM3513 (37%)$1,025.00$1,500.00
Painted pavement marking (6" line)716-05.20LM3411 (32%)$1,022.50$1,400.00
Snowplowable raised pavement markers (BI-dir) (1 color)716-01.21EACH2911 (38%)$43.00$40.48
Plastic pavement marking(channelization striping)716-02.04SY2711 (41%)$24.00$29.75
Plastic pavement marking (stop line)716-02.05LF3110 (32%)$13.00$17.30
Spray thermo PVMT MRKNG (60 mil) (6IN line)716-13.02LM309 (30%)$3,800.00$3,650.00
Snowplowable raised pavment markers (mono-dir)(1 color)716-01.22EACH219 (43%)$40.00$40.00
Saw slot730-14.02LF219 (43%)$7.25$5.50
Cold planing bituminous pavement415-01.02SY199 (47%)$20.00$14.00
PRI of East Tennessee Inc., TDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
APAC-Atlantic, Inc.3222 of 32
Rogers Group, Inc.2214 of 22
Duracap Asphalt Paving Co., Inc.128 of 12
Pave Grade & Aggregate, Inc33 of 3
Vulcan Construction Materials, LLC33 of 3
Bluegrass Contracting Corporation22 of 2
Charles Blalock & Sons, Inc.21 of 2
Sessions Paving Company20 of 2
Summers-Taylor, Inc.10 of 1
Newport Paving Company, Inc.10 of 1
PRI of East Tennessee Inc., TDOT: the firms on the same contracts most often

Latest bids

LetContractCountyProjectRankIts bidAgainst the low bid
02 OCT 2026CN261066Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And WashingtonThe random on-call asphalt pothole patching on various interstate and state routes1 of 1$1,223,250Low
02 OCT 2026CN263062Counties Bedford, Cheatham, Davidson, Dickson, Giles, Hickman, Houston, Humphreys, Lawrence, Lewis, Lincoln, Macon, Marshall, Maury, Montgomery, Moore, Perry, Robertson, Rutherford, Smith, Stewart, Sumner, Trousdale, Wayne, Williamson, And WilsonThe random on-call asphalt pothole patching on various interstate and state routes1 of 2$852,000Low, 5.0% under the second
02 OCT 2026CN262063Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And WhiteR2bvar-m3-070 the random on-call asphalt pothole patching on various interstate and state routes1 of 2$918,350Low, 16% under the second
26 JUN 2026CN261056Knox CountyThe resurfacing on u.s. 441 (s.r. 33) from near s.r. 71 (l.m. 5.72) to near central street (l.m. 8.26)3 of 3$2,573,488+55%
08 MAY 2026CN261031Blount CountyThe resurfacing on s.r. 33 from near s.r. 35 (l.m. 12.35) to near clarks grove road (l.m. 16.08)2 of 3$2,392,980+42%
08 MAY 2026CN261035Grainger CountyThe resurfacing on s.r. 375 from s.r. 92 (l.m. 0.00) to near white oak lane (l.m. 5.08)2 of 2$880,5300.0%
08 MAY 2026CN261045Grainger CountyThe resurfacing on u.s. 11w (s.r. 1) from near helton road (l.m. 22.02) to near u.s. 25e (s.r. 32) (l.m. 27.18), including thin epoxy overla2 of 3$1,478,522+4.0%
08 MAY 2026CN261038Jefferson CountyThe resurfacing on s.r. 139 from the sevier county line (l.m. 0.00) to s.r. 92 (l.m. 7.97)2 of 2$1,638,567+31%
08 MAY 2026CN261041Knox CountyThe resurfacing on u.s. 11e (u.s. 25w, s.r. 9) from s.r. 168 (l.m. 8.09) to near strawberry plains road (l.m. 13.98)3 of 3$3,586,249+12%
08 MAY 2026CN261042Knox CountyThe resurfacing on s.r. 331 from s.r. 131 (l.m. 8.31) to s.r. 61 (l.m. 16.02)3 of 3$1,849,528+29%
08 MAY 2026CN261052Loudon County005,53s002-f8-005 the resurfacing on u.s. 11 (s.r. 2) from near natalie boulevard (l.m. 8.40) to near u.s. 321 (s.r. 73) (l.m. 13.42)3 of 3$2,903,145+24%
20 MAR 2026CN261014Anderson CountyThe resurfacing on u.s. 25w (s.r. 9) from i-75 (l.m. 0.00) to near industrial park road (l.m. 7.75)3 of 3$1,676,418+26%
20 MAR 2026CN261016Grainger CountyThe resurfacing on s.r. 92 from near the jefferson county line (l.m. 0.05) to u.s. 11w (s.r. 1) (l.m. 9.24) and on u.s. 11w (s.r. 1) from ne1 of 2$4,010,040Low, 0.0% under the second
20 MAR 2026CN261019Knox CountyThe resurfacing on s.r. 62 from near west emory road (l.m. 2.04) to near beaver ridge road (l.m. 8.91)2 of 3$2,823,871+7.0%
20 MAR 2026CN261018Knox CountyThe resurfacing on u.s. 11w (s.r. 1) from near historic preservation drive (l.m. 20.41) to s.r. 168 (l.m. 24.21)1 of 3$2,413,630Low, 1.0% under the second
20 MAR 2026CN261023Knox CountyThe resurfacing on s.r. 169 from near cedar bluff road (l.m. 1.86) to near weisgarber road (l.m. 6.65)1 of 3$3,536,214Low, 10% under the second
20 MAR 2026CN261024Sevier CountyThe resurfacing on s.r. 449 from near center view road (l.m. 3.35) to u.s. 411 (s.r. 35) (l.m. 6.20), including bridge repair work1 of 2$3,366,703Low, 1.0% under the second
05 DEC 2025CNZ332Anderson CountyThe resurfacing on s.r. 95 from the roane county line (l.m. 0.00) to near west vanderbilt drive (l.m. 2.56), including bridge repair work ov3 of 3$2,100,950+27%
05 DEC 2025CNZ310Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And WashingtonThe random on-call concrete pavement repair on various interstate and state routes4 of 4$2,441,350+28%
05 DEC 2025CNZ299Knox CountyThe resurfacing on i-275 from near i-40 (l.m. 0.00) to near i-640 (l.m. 2.98)2 of 3$9,185,627+14%
05 DEC 2025CNZ298Knox CountyThe resurfacing on i-75 from north of s.r. 131 (l.m. 8.69) to the anderson county line (l.m. 13.67)2 of 3$6,602,401+2.0%
05 DEC 2025CNZ300Knox CountyThe resurfacing on u.s. 25w (s.r. 9) from near schaad road (l.m. 3.50) to near i-640 (l.m. 6.80)3 of 3$3,070,343+14%
07 NOV 2025CNZ280Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And WashingtonThe random on-call asphalt pothole patching on various interstate and state routes1 of 1$1,247,000Low
25 JUL 2025CNZ228Blount CountyThe resurfacing on s.r. 336 from near u.s. 411 (s.r. 33) (l.m. 0.00) to near reagan mill road (l.m. 5.04)3 of 3$1,052,694+26%
27 JUN 2025CNZ175Jefferson CountyThe resurfacing on s.r. 363 from s.r. 92 (l.m. 0.00) to u.s. 25w (u.s. 70, s.r. 9) (l.m. 6.02)1 of 2$1,554,327Low, 3.0% under the second
PRI of East Tennessee Inc.: latest TDOT bids in the data

How this record was read

TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

  • Every bid counted here matched its published total to within one dollar; TDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.