TDOT contract CNZ218 bid tabulation
The ada curb ramp upgrades on various state routes. Let by Tennessee DOT on August 15, 2025, Counties Fayette, Shelby, And Tipton. 2 bids received; low bid $391,750 by Bluff City Construction Company, LLC.
- Owner
- Tennessee DOT
- Letting
- 15 AUG 2025
- Pay items
- 13
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bluff City Construction Company, LLC | $391,750 | Low |
| 2 | GCM, Inc. | $453,918 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bluff City Construction Company, LLC | 2. GCM, Inc. |
|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $18,000 | $2,000.00 |
| 2 | Removal of trash and debris (202-01.03) | LS | 1 | $8,000.00 | $5,000.00 |
| 3 | Removal of rigid pavement, sidewalk, etc. (202-03) | SY | 295 | $50.00 | $55.00 |
| 4 | Removal of curb and gutter (description) (202-08.15) | LF | 1,362 | $15.50 | $27.00 |
| 5 | Furnishing & spreading topsoil (203-07) | CY | 74 | $157.00 | $90.00 |
| 6 | Concrete sidewalk (4 ") (701-01.01) | SF | 2,654 | $10.00 | $16.00 |
| 7 | Concrete curb ramp (retrofit) (701-02.01) | SF | 5,858 | $25.50 | $35.00 |
| 8 | Detectable warning surface (rehabilitation) (701-02.06) | SF | 487 | $69.00 | $95.00 |
| 9 | Concrete curb (702-01) | CY | 17 | $700.00 | $875.00 |
| 10 | Concrete combined curb & gutter (702-03) | CY | 49 | $685.00 | $725.00 |
| 11 | Traffic control (712-01) | LS | 1 | $27,000 | $20,000 |
| 12 | Mobilization (717-01) | LS | 1 | $34,500 | $22,500 |
| 13 | Seeding (with mulch) (801-01) | UNIT | 8 | $223.00 | $75.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.