TxDOT contract A00065546 bid tabulation
Rehabilitate Existing Roadway, US 190 (US 87 to WEST MAIN STREET). Let by Texas DOT on January 7, 2026, McCulloch, Brownwood District. 4 bids received; low bid $1,459,866 by STX Civil, -5.3% against the engineer's estimate of $1,541,997.
- Owner
- Texas DOT
- Letting
- 07 JAN 2026
- Pay items
- 58
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | STX Civil | $1,459,866 | Low | -5.0% |
| 2 | O. Trevino Construction, LLC | $1,549,739 | +6.0% | +1.0% |
| 3 | Grey Sky Construction LLC | $1,642,024 | +12% | +6.0% |
| 4 | Prater Dirt Work LLC | $1,694,743 | +16% | +10% |
Engineer's estimate: $1,541,997.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. STX Civil | 2. O. Trevino Construction, LLC | 3. Grey Sky Construction LLC | 4. Prater Dirt Work LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pavement) (104-7001) | SY | 4,715 | $32.00 | $20.00 | $17.00 | $20.00 | $40.00 |
| 2 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 67 | $400.00 | $10.00 | $95.00 | $50.00 | $43.00 |
| 3 | Removing concrete (curb) (104-7016) | LF | 18 | $100.00 | $1.00 | $25.00 | $20.00 | $16.00 |
| 4 | Removing concrete (curb & gutter) (104-7017) | LF | 252 | $75.00 | $8.00 | $25.00 | $50.00 | $32.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 917 | $50.00 | $20.00 | $85.00 | $20.00 | $132.50 |
| 6 | Cement (275-7001) | TON | 13 | $500.00 | $450.00 | $660.00 | $350.00 | $550.00 |
| 7 | Cement TRT (subgrade)(6") (275-7022) | SY | 1,180 | $10.00 | $5.00 | $45.00 | $12.00 | $35.00 |
| 8 | D-GR HMA type-B sac-B PG64-22 (341-7002) | TON | 1,085 | $125.00 | $250.00 | $215.00 | $165.00 | $158.00 |
| 9 | Concrete pavement (CRCP) (12") (360-7006) | SY | 4,715 | $158.00 | $160.00 | $160.00 | $200.00 | $168.00 |
| 10 | Adjusting inlets (479-7002) | EACH | 1 | $6,500.00 | $5,000.00 | $9,500.00 | $1,500.00 | $8,500.00 |
| 11 | Mobilization (500-7001) | LS | 1 | $139,662 | $160,000 | $150,000 | $150,000 | $145,000 |
| 12 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $25,000 | $2,800.00 | $6,150.00 | $12,500 | $12,500 |
| 13 | Portable changeable message sign (503-7001) | DAY | 63 | $100.00 | $100.00 | $145.00 | $150.00 | $400.00 |
| 14 | TMA (stationary) (505-7001) | DAY | 20 | $300.00 | $185.00 | $180.00 | $250.00 | $400.00 |
| 15 | Concrete curb (type II) (529-7002) | LF | 18 | $400.00 | $50.00 | $50.00 | $65.00 | $55.00 |
| 16 | Concrete curb (mono) (type II) (529-7007) | LF | 252 | $200.00 | $45.00 | $50.00 | $65.00 | $22.00 |
| 17 | Driveways (concrete) (530-7006) | SY | 54 | $150.00 | $145.00 | $150.00 | $105.00 | $165.00 |
| 18 | Concrete sidewalks (5") (531-7002) | SY | 67 | $250.00 | $100.00 | $105.00 | $85.00 | $160.00 |
| 19 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 2 | $800.00 | $950.00 | $1,100.00 | $1,500.00 | $970.00 |
| 20 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 4 | $800.00 | $575.00 | $750.00 | $1,500.00 | $700.00 |
| 21 | Relocate SM RD SN sup&AM type TWT (644-7068) | EACH | 7 | $600.00 | $440.00 | $700.00 | $1,100.00 | $650.00 |
| 22 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 7 | $15.00 | $50.00 | $800.00 | $100.00 | $100.00 |
| 23 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 480 | $2.00 | $10.00 | $9.50 | $5.00 | $9.80 |
| 24 | Work zone pavement marking removing (W)18"(solid) (662-7076) | LF | 15 | $10.00 | $24.00 | $24.00 | $12.00 | $25.30 |
| 25 | Work zone pavement marking removing (Y)6"(DOT) (662-7099) | LF | 87 | $5.00 | $11.00 | $11.00 | $5.00 | $11.00 |
| 26 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 2,214 | $2.00 | $8.25 | $8.50 | $5.00 | $8.50 |
| 27 | Reflectorized pavement marking type I (W)18"(solid)(100MIL) (666-7033) | LF | 216 | $6.50 | $13.00 | $13.50 | $12.00 | $14.00 |
| 28 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 282 | $9.35 | $13.50 | $14.00 | $20.00 | $14.50 |
| 29 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 10 | $250.00 | $190.00 | $185.00 | $250.00 | $193.00 |
| 30 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 1 | $275.00 | $200.00 | $195.00 | $500.00 | $204.00 |
| 31 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 7 | $250.00 | $200.00 | $200.00 | $250.00 | $209.00 |
| 32 | Reflectorized pavement marking type I (W)(symbol)(100MIL) (666-7084) | EACH | 4 | $480.00 | $280.00 | $275.00 | $250.00 | $292.00 |
| 33 | Ref pavement marking type I(W)18"(yld tri)(100MIL) (666-7087) | EACH | 40 | $47.00 | $50.00 | $43.00 | $150.00 | $44.00 |
| 34 | Pavement sler 6" (666-7347) | LF | 5,066 | $1.35 | $2.00 | $1.75 | $2.00 | $1.77 |
| 35 | Pavement sler 18" (666-7351) | LF | 200 | $1.40 | $3.50 | $3.50 | $12.00 | $3.75 |
| 36 | Pavement sler 24" (666-7352) | LF | 138 | $1.50 | $6.50 | $7.50 | $20.00 | $7.15 |
| 37 | Pavement sler (arrow) (666-7353) | EACH | 4 | $26.00 | $100.00 | $106.00 | $250.00 | $104.50 |
| 38 | Pavement sler (word) (666-7354) | EACH | 1 | $35.00 | $120.00 | $123.00 | $250.00 | $121.00 |
| 39 | Pavement sler (double arrow) (666-7356) | EACH | 1 | $48.00 | $120.00 | $123.00 | $500.00 | $121.00 |
| 40 | Pavement sler (symbol) (666-7363) | EACH | 4 | $74.00 | $120.00 | $123.00 | $250.00 | $121.00 |
| 41 | Pavement sler (yld tri) (666-7365) | EACH | 40 | $20.00 | $40.00 | $39.00 | $150.00 | $38.50 |
| 42 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 4,392 | $1.20 | $3.33 | $3.50 | $2.00 | $3.63 |
| 43 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 3,050 | $1.75 | $2.25 | $2.50 | $2.00 | $2.42 |
| 44 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 22 | $15.85 | $10.00 | $11.00 | $6.00 | $10.65 |
| 45 | Eliminating existing PM & markers (4") (677-7001) | LF | 1,847 | $1.00 | $1.75 | $2.00 | $1.00 | $1.90 |
| 46 | Eliminating existing PM & markers (8") (677-7004) | LF | 495 | $1.00 | $4.00 | $4.00 | $6.00 | $3.80 |
| 47 | Eliminating existing PM & markers (12") (677-7006) | LF | 45 | $1.85 | $5.50 | $6.00 | $12.00 | $5.72 |
| 48 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 6 | $72.00 | $100.00 | $95.00 | $250.00 | $93.50 |
| 49 | Eliminating existing PM & markers (word) (677-7015) | EACH | 6 | $80.00 | $100.00 | $105.00 | $250.00 | $104.50 |
| 50 | Eliminating existing PM & markers (18")(yld tri) (677-7023) | EACH | 12 | $16.00 | $40.00 | $38.00 | $150.00 | $38.50 |
| 51 | Pavement surface preparation for marking (6") (678-7002) | LF | 5,066 | $0.87 | $0.65 | $0.75 | $2.00 | $0.70 |
| 52 | Pavement surface preparation for marking (18") (678-7007) | LF | 200 | $0.90 | $1.25 | $1.25 | $12.00 | $1.32 |
| 53 | Pavement surface preparation for marking (24") (678-7008) | LF | 138 | $2.50 | $2.50 | $2.50 | $20.00 | $2.53 |
| 54 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 10 | $52.50 | $50.00 | $39.00 | $250.00 | $38.50 |
| 55 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 1 | $64.00 | $45.00 | $44.00 | $250.00 | $44.00 |
| 56 | Pavement surface preparation for marking (word) (678-7016) | EACH | 7 | $60.00 | $45.00 | $44.00 | $250.00 | $44.00 |
| 57 | Pavement surface preparation for marking (symbol) (678-7021) | EACH | 4 | $70.00 | $45.00 | $44.00 | $250.00 | $44.00 |
| 58 | Pavement surface preparation for marking (18")(yld tri) (678-7022) | EACH | 40 | $30.00 | $17.00 | $17.50 | $150.00 | $18.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way