Excavation (roadway), TxDOT 110-7001

Low bidders on TxDOT contracts carried a median of $18.71 per CY for this item, over the 24 months to 19 NOV 2026, across 552 low bids. Half of all 3,502 bids fell between $15.00 and $35.62.

Owner
Texas DOT
Item
110-7001
Unit
CY
Data through
19 NOV 2026

TxDOT prints this item as “EXCAV (ROADWAY)”.

TxDOT has bid this work under more than one code: 1106001 on lettings from 09 JAN 2020 to 02 AUG 2024 (5,811 bids); 110-7001 on lettings from 06 NOV 2024 to 04 NOV 2026 (3,605 bids); 110-6001 on lettings from 06 NOV 2024 to 07 FEB 2025 (29 bids). They are combined here into one trend.

$18.71Low bidder's median, per CY
$22.05Median of all bids, per CY
554Contracts in the window
$20.00Engineer's estimate, median per CY

By year of letting

Excavation (roadway), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
2020228227$13.001,331$15.00
2021289289$12.181,580$15.00
2022216215$15.00953$18.30
2023281280$22.001,067$25.00
2024225225$20.001,036$25.00
2025300300$20.001,773$24.95
2026248246$17.001,684$20.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District76$22.00496$24.43
Yoakum District47$18.00338$24.00
Austin District39$17.00271$22.00
Fort Worth District34$25.00212$30.00
Bryan District28$19.30211$25.00
San Antonio District31$20.00199$21.23
Houston District26$21.50194$22.00
Corpus Christi District25$14.73186$18.00
Paris District25$20.00167$20.00
Pharr District27$7.00147$12.12
Tyler District19$12.85127$15.00
Waco District18$16.50123$22.00
Excavation (roadway), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (CY)Low bidsLow-bid median
2 to 462138$30.00
464 to 2,401138$21.50
2,402 to 14,205138$17.00
14,567 to 1,046,879138$12.12
Excavation (roadway), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Ed Bell Construction Company19755 (28%)
Webber, LLC16948 (28%)
Texas Materials Group, Inc.30047 (16%)
James Construction Group, LLC17242 (24%)
A. L. Helmcamp, Inc.23341 (18%)
FNH Construction, LLC13941 (29%)
Excavation (roadway), TxDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00193521Corpus Christi District8,898$8.00$9.02$9.005J E Construction Services, LLCTxDOT
04 NOV 2026A00124162Bryan District33,904$6.50$11.25$10.0012Fluor Enterprises, Inc.TxDOT
04 NOV 2026A00206631Bryan District21,027$15.00$16.00$12.007Big Creek Construction, LTD.TxDOT
04 NOV 2026A00212892Dallas District130,961$15.00$13.82$11.006Indus Road & Bridge, Inc.TxDOT
04 NOV 2026A00209149Laredo District350$20.80$20.80$11.007STX CivilTxDOT
04 NOV 2026A00196925Paris District22,931$7.45$15.00$18.009Highway 19 Construction LLCTxDOT
04 NOV 2026A00129572Dallas District42,020$20.00$16.00$16.004Mario Sinacola & Sons Excavating, Inc.TxDOT
04 NOV 2026A00222905Fort Worth District455$30.00$40.00$31.007Xit Paving and Construction Inc.TxDOT
03 NOV 2026A00184974Austin District186,501$30.00$26.76$12.706Austin Bridge & Road Services, LPTxDOT
03 NOV 2026A00188510Fort Worth District182$26.00$37.00$60.008Jay Mills Contracting, IncorporatedTxDOT
03 NOV 2026A00204003Bryan District104$25.00$30.00$30.0015C & W Southern LLCTxDOT
03 NOV 2026A00215726Corpus Christi District31$20.00$146.39$15.007LCR Total Transport LLCTxDOT
07 OCT 2026A00209154Laredo District55$76.00$82.00$75.006Presidio Contracting, LLCTxDOT
07 OCT 2026A00135746Dallas District25$40.00$74.00$150.009Garret Shields InfrastructureTxDOT
07 OCT 2026A00132124Lufkin District18,824$7.00$10.38$10.007Longview Bridge and Road, LTD.TxDOT
Latest TxDOT contracts carrying Excavation (roadway)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy