TxDOT contract A00209154 bid tabulation
Bridge Replacement, BROWN RD (BROWN RD to .). Let by Texas DOT on October 7, 2026, La Salle, Laredo District. 6 bids received; low bid $485,016 by Presidio Contracting, LLC, -27% against the engineer's estimate of $668,834.
- Owner
- Texas DOT
- Letting
- 07 OCT 2026
- Pay items
- 40
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Presidio Contracting, LLC | $485,016 | Low | -27% |
| 2 | Lucania Contractors LLC | $594,689 | +23% | -11% |
| 3 | STX Civil | $608,304 | +25% | -9.0% |
| 4 | Salinas Construction Technologies, LTD. | $616,739 | +27% | -8.0% |
| 5 | J. Carroll Weaver, Inc. | $639,345 | +32% | -4.0% |
| 6 | E-Z Bel Construction, LLC | $653,352 | +35% | -2.0% |
Engineer's estimate: $668,834.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Presidio Contracting, LLC | 2. Lucania Contractors LLC | 3. STX Civil | 4. Salinas Construction Technologies, LTD. | 5. J. Carroll Weaver, Inc. | 6. E-Z Bel Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3 | $3,500.00 | $2,100.00 | $1,200.00 | $1,690.00 | $1,601.64 | $2,164.10 | $8,000.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 55 | $75.00 | $76.00 | $25.00 | $88.00 | $50.09 | $102.68 | $90.00 |
| 3 | Excavation (channel) (110-7002) | CY | 39 | $50.00 | $76.00 | $30.00 | $62.00 | $68.76 | $50.57 | $95.00 |
| 4 | Embankment (final)(DC)(type A) (132-7002) | CY | 241 | $80.00 | $35.00 | $40.00 | $60.00 | $68.44 | $30.11 | $60.00 |
| 5 | Blading (150-7002) | HR | 8 | $100.00 | $50.00 | $1.00 | $121.00 | $158.12 | $135.11 | $191.00 |
| 6 | Drill seed (permanent_rural_clay) (164-7042) | ACRE | 0.25 | $4,000.00 | $6,825.00 | $27,000 | $7,440.00 | $4,252.82 | $25,200 | $6,600.00 |
| 7 | Drill seed (temporary_warm) (164-7045) | ACRE | 0.25 | $4,000.00 | $6,825.00 | $22,200 | $7,440.00 | $4,252.82 | $20,720 | $6,600.00 |
| 8 | Proof rolling (216-7001) | HR | 16 | $150.00 | $50.00 | $1.00 | $90.50 | $83.15 | $89.45 | $130.00 |
| 9 | FL BS (compacted in place)(type A GR 1-2) (247-7001) | TON | 205 | $100.00 | $74.25 | $75.00 | $107.00 | $121.41 | $133.77 | $130.00 |
| 10 | Prime coat (MC-30) (310-7004) | GAL | 200 | $25.00 | $25.00 | $10.00 | $11.00 | $12.53 | $8.73 | $11.00 |
| 11 | Lra pavement type-II GR-CS (330-7010) | TON | 96 | $235.00 | $286.15 | $200.00 | $206.00 | $234.47 | $213.73 | $306.00 |
| 12 | Cem stabil BKFL (400-7010) | CY | 28 | $300.00 | $263.00 | $160.00 | $260.00 | $172.15 | $177.98 | $400.00 |
| 13 | Flowable backfill (401-7001) | CY | 25 | $350.00 | $226.00 | $160.00 | $226.00 | $272.87 | $265.14 | $300.00 |
| 14 | Drilled shaft (24 in) (416-7004) | LF | 240 | $320.00 | $227.50 | $370.00 | $375.00 | $274.19 | $207.79 | $376.00 |
| 15 | Class C concrete (abutment) (420-7012) | CY | 17.60 | $1,600.00 | $1,190.00 | $1,900.00 | $2,830.00 | $1,642.96 | $1,578.88 | $2,000.00 |
| 16 | Reinforced concrete slab (slab beam) (422-7007) | SF | 1,040 | $35.00 | $36.30 | $50.00 | $42.50 | $40.79 | $34.45 | $36.00 |
| 17 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 197.50 | $370.00 | $312.10 | $450.00 | $366.00 | $322.63 | $387.63 | $420.00 |
| 18 | Riprap (mow strip)(4 in) (432-7013) | CY | 30 | $700.00 | $588.00 | $450.00 | $552.00 | $754.12 | $776.46 | $550.00 |
| 19 | Riprap (stone protection)(12 in) (432-7041) | CY | 48 | $350.00 | $250.00 | $300.00 | $330.00 | $293.83 | $310.25 | $450.00 |
| 20 | Rail (type T631) (450-7020) | LF | 104 | $125.00 | $120.00 | $150.00 | $157.00 | $124.07 | $132.16 | $117.15 |
| 21 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $25,000 | $23,000 | $25,000 | $15,310 | $18,580 | $18,513 | $25,000 |
| 22 | Mobilization (500-7001) | LS | 1 | $49,543 | $48,320 | $37,000 | $53,175 | $109,254 | $154,248 | $49,500 |
| 23 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $9,000.00 | $1,650.00 | $2,000.00 | $3,040.00 | $5,485.88 | $2,800.00 | $1,250.00 |
| 24 | Portable changeable message sign (503-7002) | EACH | 2 | $8,500.00 | $7,830.00 | $7,000.00 | $7,440.00 | $5,952.26 | $2,022.23 | $6,250.00 |
| 25 | Rock filter dams (install) (type 4) (506-7004) | LF | 120 | $75.00 | $69.00 | $50.00 | $96.50 | $37.67 | $30.63 | $85.80 |
| 26 | Rock filter dams (remove) (506-7011) | LF | 120 | $17.00 | $14.35 | $20.00 | $11.00 | $8.79 | $16.44 | $9.90 |
| 27 | Construction exits (install) (type 1) (506-7020) | SY | 77 | $45.00 | $35.00 | $50.00 | $52.50 | $27.68 | $46.17 | $46.40 |
| 28 | Construction exits (remove) (506-7024) | SY | 77 | $18.00 | $13.45 | $10.00 | $11.50 | $9.31 | $10.25 | $10.00 |
| 29 | Backhoe work (erosion & sediment control) (506-7030) | HR | 20 | $140.00 | $135.00 | $1.00 | $165.00 | $95.52 | $74.05 | $81.00 |
| 30 | Temporary sediment control fence (install) (506-7039) | LF | 400 | $8.00 | $3.80 | $5.00 | $9.43 | $3.95 | $6.73 | $8.36 |
| 31 | Temporary sediment control fence (remove) (506-7041) | LF | 400 | $3.00 | $1.90 | $2.00 | $2.25 | $1.06 | $2.28 | $2.00 |
| 32 | Constructing detours (type 1) (508-7003) | SY | 945 | $100.00 | $29.55 | $70.00 | $51.00 | $60.36 | $60.65 | $75.00 |
| 33 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 160 | $100.00 | $40.00 | $90.00 | $39.50 | $46.56 | $38.31 | $40.00 |
| 34 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 80 | $80.00 | $44.00 | $100.00 | $78.50 | $34.04 | $38.03 | $35.00 |
| 35 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 160 | $45.00 | $34.00 | $24.00 | $17.00 | $36.11 | $24.52 | $40.00 |
| 36 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 80 | $30.00 | $34.00 | $26.00 | $33.50 | $25.82 | $29.70 | $35.00 |
| 37 | Metal W-beam guard fence (timber post) (540-7001) | LF | 100 | $40.00 | $40.30 | $30.00 | $46.50 | $42.00 | $43.68 | $38.95 |
| 38 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $4,400.00 | $3,800.00 | $5,090.00 | $4,497.69 | $4,768.96 | $4,257.25 |
| 39 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 2 | $100.00 | $118.00 | $200.00 | $124.00 | $89.78 | $140.00 | $750.00 |
| 40 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 20 | $100.00 | $30.00 | $100.00 | $37.00 | $89.78 | $56.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 7, 2026. Compiled by Mirage Metrics.