Backhoe work (erosion & sediment control), TxDOT 506-7030

Low bidders on TxDOT contracts carried a median of $92.50 per HR for this item, over the 24 months to 19 NOV 2026, across 28 low bids. Half of all 177 bids fell between $74.05 and $150.00.

Owner
Texas DOT
Item
506-7030
Unit
HR
Data through
19 NOV 2026

TxDOT prints this item as “BACKHOE WORK (EROSION & SEDMT CONT)”.

TxDOT has bid this work under more than one code: 5066030004 on lettings from 10 JAN 2020 to 06 AUG 2020 (48 bids); 5066030002 on lettings from 06 FEB 2020 to 05 JUN 2024 (199 bids); 5066030005 on lettings from 07 JAN 2021 to 10 JUL 2024 (280 bids); 506-7030 on lettings from 07 JAN 2025 to 07 OCT 2026 (179 bids). They are combined here into one trend.

$92.50Low bidder's median, per HR
$100.00Median of all bids, per HR
28Contracts in the window
$122.50Engineer's estimate, median per HR

By year of letting

Backhoe work (erosion & sediment control), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201817$85.00101$80.00
20212726$75.00154$82.28
20222222$80.00100$85.00
20232424$100.0098$120.00
20241212$122.5059$120.00
20251515$120.0096$122.50
20261313$80.0081$90.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Tyler District17$75.00117$99.00
Laredo District8$137.5041$100.00
Backhoe work (erosion & sediment control), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (HR)Low bidsLow-bid median
4 to 207$150.00
22 to 607$75.00
68 to 1987$100.00
200 to 6007$50.00
Backhoe work (erosion & sediment control), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Reynolds & Kay, LTD.3424 (71%)
Highway 19 Construction LLC2718 (67%)
East Texas Bridge, Inc.6812 (18%)
A. L. Helmcamp, Inc.309 (30%)
CK Newberry, LLC215 (24%)
Relmco, Inc.105 (50%)
Backhoe work (erosion & sediment control), TxDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
07 OCT 2026A00209154Laredo District20$135.00$95.52$140.005Presidio Contracting, LLCTxDOT
06 AUG 2026A00189724Laredo District35$140.00$85.00$122.503Anderson Columbia Co., Inc.TxDOT
06 AUG 2026A00049653Tyler District300$45.00$55.00$85.005Longview Bridge and Road, LTD.TxDOT
05 AUG 2026A00136503Laredo District120$80.00$82.55$100.0010Relmco, Inc.TxDOT
01 JUL 2026A00206448Tyler District5$60.00$100.00n/a3Reynolds & Kay, LTD.TxDOT
01 JUL 2026A00058522Tyler District300$50.00$100.00$55.887Drake Companies LLCTxDOT
06 MAY 2026A00014162Dallas District22$66.00$269.66$80.009Webber, LLCTxDOT
08 APR 2026A00212486Tyler District198$45.00$50.00$80.008Drake Companies LLCTxDOT
07 APR 2026A00186521Laredo District40$40.00$100.00$75.005Acee Construction LLC.TxDOT
07 APR 2026A00060559Tyler District300$85.00$80.00$107.008Drake Companies LLCTxDOT
04 MAR 2026A00127306Laredo District20$150.00$125.00$150.005Hunter Industries, LTD.TxDOT
05 FEB 2026A00058517Tyler District200$167.00$91.00$70.008Pinto Construction Co., Inc.TxDOT
07 JAN 2026A00196226Tyler District25$147.00$105.00$65.005Baker & Company Construction, LLCTxDOT
06 NOV 2025A00059355Tyler District150$100.00$110.00$55.008Big Creek Construction, LTD.TxDOT
05 SEP 2025A00193132Brownwood District68$156.61$153.31$182.004Allen Keller CompanyTxDOT
Latest TxDOT contracts carrying Backhoe work (erosion & sediment control)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy