Backhoe work (erosion & sediment control), TxDOT 506-7030
Low bidders on TxDOT contracts carried a median of $92.50 per HR for this item, over the 24 months to 19 NOV 2026, across 28 low bids. Half of all 177 bids fell between $74.05 and $150.00.
- Owner
- Texas DOT
- Item
- 506-7030
- Unit
- HR
- Data through
- 19 NOV 2026
TxDOT prints this item as “BACKHOE WORK (EROSION & SEDMT CONT)”.
TxDOT has bid this work under more than one code: 5066030004 on lettings from 10 JAN 2020 to 06 AUG 2020 (48 bids); 5066030002 on lettings from 06 FEB 2020 to 05 JUN 2024 (199 bids); 5066030005 on lettings from 07 JAN 2021 to 10 JUL 2024 (280 bids); 506-7030 on lettings from 07 JAN 2025 to 07 OCT 2026 (179 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 18 | 17 | $85.00 | 101 | $80.00 |
| 2021 | 27 | 26 | $75.00 | 154 | $82.28 |
| 2022 | 22 | 22 | $80.00 | 100 | $85.00 |
| 2023 | 24 | 24 | $100.00 | 98 | $120.00 |
| 2024 | 12 | 12 | $122.50 | 59 | $120.00 |
| 2025 | 15 | 15 | $120.00 | 96 | $122.50 |
| 2026 | 13 | 13 | $80.00 | 81 | $90.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Tyler District | 17 | $75.00 | 117 | $99.00 |
| Laredo District | 8 | $137.50 | 41 | $100.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (HR) | Low bids | Low-bid median |
|---|---|---|
| 4 to 20 | 7 | $150.00 |
| 22 to 60 | 7 | $75.00 |
| 68 to 198 | 7 | $100.00 |
| 200 to 600 | 7 | $50.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Reynolds & Kay, LTD. | 34 | 24 (71%) |
| Highway 19 Construction LLC | 27 | 18 (67%) |
| East Texas Bridge, Inc. | 68 | 12 (18%) |
| A. L. Helmcamp, Inc. | 30 | 9 (30%) |
| CK Newberry, LLC | 21 | 5 (24%) |
| Relmco, Inc. | 10 | 5 (50%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07 OCT 2026 | A00209154 | Laredo District | 20 | $135.00 | $95.52 | $140.00 | 5 | Presidio Contracting, LLC | TxDOT |
| 06 AUG 2026 | A00189724 | Laredo District | 35 | $140.00 | $85.00 | $122.50 | 3 | Anderson Columbia Co., Inc. | TxDOT |
| 06 AUG 2026 | A00049653 | Tyler District | 300 | $45.00 | $55.00 | $85.00 | 5 | Longview Bridge and Road, LTD. | TxDOT |
| 05 AUG 2026 | A00136503 | Laredo District | 120 | $80.00 | $82.55 | $100.00 | 10 | Relmco, Inc. | TxDOT |
| 01 JUL 2026 | A00206448 | Tyler District | 5 | $60.00 | $100.00 | n/a | 3 | Reynolds & Kay, LTD. | TxDOT |
| 01 JUL 2026 | A00058522 | Tyler District | 300 | $50.00 | $100.00 | $55.88 | 7 | Drake Companies LLC | TxDOT |
| 06 MAY 2026 | A00014162 | Dallas District | 22 | $66.00 | $269.66 | $80.00 | 9 | Webber, LLC | TxDOT |
| 08 APR 2026 | A00212486 | Tyler District | 198 | $45.00 | $50.00 | $80.00 | 8 | Drake Companies LLC | TxDOT |
| 07 APR 2026 | A00186521 | Laredo District | 40 | $40.00 | $100.00 | $75.00 | 5 | Acee Construction LLC. | TxDOT |
| 07 APR 2026 | A00060559 | Tyler District | 300 | $85.00 | $80.00 | $107.00 | 8 | Drake Companies LLC | TxDOT |
| 04 MAR 2026 | A00127306 | Laredo District | 20 | $150.00 | $125.00 | $150.00 | 5 | Hunter Industries, LTD. | TxDOT |
| 05 FEB 2026 | A00058517 | Tyler District | 200 | $167.00 | $91.00 | $70.00 | 8 | Pinto Construction Co., Inc. | TxDOT |
| 07 JAN 2026 | A00196226 | Tyler District | 25 | $147.00 | $105.00 | $65.00 | 5 | Baker & Company Construction, LLC | TxDOT |
| 06 NOV 2025 | A00059355 | Tyler District | 150 | $100.00 | $110.00 | $55.00 | 8 | Big Creek Construction, LTD. | TxDOT |
| 05 SEP 2025 | A00193132 | Brownwood District | 68 | $156.61 | $153.31 | $182.00 | 4 | Allen Keller Company | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.