TxDOT contract A00058517 bid tabulation

Highway Improvement, SH 204 (RUSK C/L AT REKLAW, SE to CHEROKEE C/L). Let by Texas DOT on February 5, 2026, Rusk, Tyler District. 8 bids received; low bid $10,286,588 by Pinto Construction Co., Inc., -19% against the engineer's estimate of $12,659,927.

Owner
Texas DOT
Letting
05 FEB 2026
Pay items
126
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Pinto Construction Co., Inc.$10,286,588Low-19%
2Big Creek Construction, LTD.$10,587,906+3.0%-16%
3A. L. Helmcamp, Inc.$10,980,138+7.0%-13%
4Madden Contracting Company, LLC.$11,248,405+9.0%-11%
5Reynolds & Kay, LTD.$11,965,671+16%-5.0%
6East Texas Bridge, Inc.$12,114,805+18%-4.0%
7Drewery Construction Company, Incorporated$12,279,155+19%-3.0%
8Longview Bridge and Road, LTD.$12,759,590+24%+1.0%
TxDOT contract A00058517: bids by rank

Engineer's estimate: $12,659,927.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Pinto Construction Co., Inc.2. Big Creek Construction, LTD.3. A. L. Helmcamp, Inc.4. Madden Contracting Company, LLC.5. Reynolds & Kay, LTD.6. East Texas Bridge, Inc.
1Preparing row (100-7001)ACRE61.99$15,000$6,876.60$5,000.00$5,000.00$5,000.00$4,000.00$6,000.00
2Excavation (roadway) (110-7001)CY5,314$9.00$15.00$27.00$14.00$11.00$10.00$18.00
3Embankment (final)(OC)(type A) (132-7001)CY15,897$15.00$18.00$30.00$23.00$11.00$25.00$20.00
4Furn & place topsoil (4") (160-7002)SY87,177$2.00$1.23$1.00$0.40$1.10$3.00$2.95
5Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076)SY87,177$0.58$0.53$0.60$0.53$0.50$0.55$0.55
6Bond fiber MTRX seed (temporary)(warm) (164-7077)SY43,589$0.57$0.53$0.60$0.53$0.50$0.55$0.55
7Bond fiber MTRX seed (temporary)(cool) (164-7078)SY43,589$0.59$0.53$0.60$0.53$0.50$0.55$0.55
8Vegetative watering (168-7001)TGL1,918$10.00$0.01$20.00$3.00$8.25$25.00$13.00
9Soil ret BLKT(SL_steep_sand_short) (169-7007)SY2,349$1.10$1.58$1.50$1.55$1.50$0.65$0.75
10Proof rolling (216-7001)HR40$200.00$240.00$140.00$200.00$65.00$85.00$100.00
11Lime (com or QK)(slurry) or QK(dry) (260-7001)TON514$350.00$168.00$275.00$330.00$275.00$338.00$380.00
12Lime TRT (existing material)(8") (260-7007)SY25,036$5.50$3.26$5.00$6.20$2.65$7.00$4.25
13Cement (275-7001)TON514$275.00$392.00$275.00$188.00$365.00$260.00$275.00
14Cement TRT (existing material)(8") (275-7003)SY25,036$4.50$7.50$5.00$4.00$8.68$5.75$3.25
15Prime coat (MC-30) (310-7004)GAL12,518$8.00$6.50$4.85$5.00$6.76$6.00$6.50
16Asphalt (AC-20XP, AC-10-2TR, or AC-20-5TR) (316-7068)GAL36,320$4.50$5.00$3.40$4.00$4.00$4.00$5.75
17Aggregate (type-PD or PL, GR-4) (316-7258)CY748$185.00$231.00$165.00$200.00$155.00$155.00$225.00
18PFC-C PG76-22 sac-A (342-7001)TON7,405$155.00$157.07$170.00$170.00$170.00$178.00$175.00
19SP mixes SP-B PG64-22 (344-7001)TON23,364$140.00$113.92$112.00$128.00$137.50$132.00$135.00
20SP mixes SP-D PG64-22 (level-UP) (344-7044)TON3,864$180.00$134.34$132.00$153.00$150.00$140.00$195.00
21SP mixes SP-D PG64-22 (exempt) (344-7074)TON33$396.92$160.00$200.00$400.00$275.00$200.00
22Tack coat (344-7077)GAL9,235$3.00$0.01$5.00$4.75$0.01$1.00$5.00
23Flexible pavement structure repair(6") (351-7005)SY8,800$55.00$51.30$52.00$72.00$60.00$59.00$68.00
24Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY994$11.48$6.00$7.90$14.00$11.00$9.00
25Plane & text asphalt concrete pavement(0" to 4") (354-7004)SY25,025$8.00$1.77$3.00$4.90$2.00$3.75$4.00
26Temporary special shoring (403-7001)SF7,837$50.00$40.43$31.00$36.75$26.00$62.50$58.00
27Class C concrete (collar) (420-7061)EACH10$1,400.00$1,365.00$1,400.00$2,100.00$1,000.00$1,200.00$1,200.00
28CL E concrete (seal slab)(non-reinforced) (420-7070)CY61$420.00$498.75$600.00$198.00$685.00$1,100.00$625.00
29Riprap (concrete)(5 in) (432-7002)CY121$750.00$636.30$720.00$945.00$762.00$950.00$700.00
30Riprap (mow strip)(4 in) (432-7013)CY72$700.00$903.00$675.00$945.00$775.00$950.00$675.00
31Riprap (stone protection)(18 in) (432-7043)CY279$220.00$262.50$165.00$289.00$191.00$220.00$200.00
32Rail (type T223) (450-7008)LF120$180.00$231.00$350.00$231.00$185.00$140.00$200.00
33Concrete box culvert (3 FT X 2 FT)(extend) (462-7056)LF21$651.00$850.00$735.00$910.00$810.00$800.00
34Concrete box culvert (3 FT X 3 FT)(extend) (462-7057)LF20$600.00$756.00$875.00$761.00$910.00$1,700.00$800.00
35Concrete box culvert (4 FT X 4 FT)(extend) (462-7060)LF30$700.00$761.25$950.00$788.00$1,160.00$1,200.00$1,000.00
36Concrete box culvert (5 FT X 3 FT)(extend) (462-7062)LF34$787.50$1,050.00$788.00$1,225.00$1,155.00$1,000.00
37Concrete box culvert (5 FT X 4 FT)(extend) (462-7063)LF4$1,051.05$1,200.00$892.50$1,700.00$2,200.00$1,500.00
38Concrete box culvert (6 FT X 6 FT)(extend) (462-7069)LF30$1,000.00$1,155.00$1,400.00$998.00$1,225.00$1,150.00$1,250.00
39Concrete box culvert (7 FT X 7 FT)(extend) (462-7074)LF31$1,260.00$1,500.00$1,260.00$1,485.00$1,100.00$1,400.00
40Concrete box culvert (10 FT X 10 FT)(extend) (462-7093)LF52$2,000.00$1,575.00$1,700.00$2,625.00$1,710.00$2,000.00$2,000.00
41RC pipe (CL III)(18 in) (464-7003)LF938$65.00$68.25$73.00$63.00$58.00$62.00$60.00
42RC pipe (CL III)(24 in) (464-7005)LF118$103.95$103.00$136.00$110.00$98.00$80.00
43RC pipe (CL III)(30 in) (464-7007)LF26$120.00$157.50$130.00$315.00$210.00$113.00$120.00
44Headwall (CH - PW - 0) (diameter= 24 in) (466-7101)EACH1$9,135.00$8,500.00$4,725.00$7,210.00$12,000$4,500.00
45Wingwall (FW - 0) (HW=3 FT) (466-7145)EACH1$9,345.00$8,700.00$3,675.00$7,650.00$12,000$4,500.00
46Wingwall (FW - 0) (HW=4 FT) (466-7146)EACH1$10,477$9,100.00$5,250.00$8,890.00$12,300$6,000.00
47Wingwall (FW - 0) (HW=6 FT) (466-7148)EACH3$18,000$15,013$13,100$9,975.00$17,650$17,000$10,000
48Wingwall (FW - 0) (HW=7 FT) (466-7149)EACH1$20,000$21,525$18,250$13,650$24,875$19,000$13,000
49Wingwall (FW - 0) (HW=9 FT) (466-7151)EACH1$26,250$27,800$17,850$29,285$34,000$20,000
50Wingwall (FW - 0) (HW=10 FT) (466-7152)EACH1$37,275$24,000$36,750$32,265$28,000$16,000
51Wingwall (FW - 0) (HW=13 FT) (466-7155)EACH1$60,000$60,900$72,000$44,100$48,660$64,000$45,000
52Wingwall (FW - 0) (HW=14 FT) (466-7156)EACH1$70,000$68,250$81,500$47,250$57,725$67,000$46,000
53Wingwall (FW - S) (HW=4 FT) (466-7160)EACH2$10,827$9,300.00$6,300.00$6,800.00$13,000$10,000
54Wingwall (PW - 2) (HW=7 FT) (466-7191)EACH2$22,680$23,400$19,950$32,415$21,500$18,000
55Wingwall (PW - 2) (HW=9 FT) (466-7193)EACH2$34,276$31,100$24,150$41,250$34,000$22,000
56Wingwall (PW - 2) (HW=12 FT) (466-7196)EACH2$84,000$58,800$62,800$48,300$72,210$47,000$42,000
57Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH66$1,000.00$997.50$1,040.00$998.00$710.00$1,300.00$975.00
58Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325)EACH1$1,260.00$1,325.00$2,100.00$990.00$2,000.00$1,100.00
59Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH4$1,260.00$1,550.00$2,310.00$990.00$2,000.00$1,200.00
60Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327)EACH2$1,575.00$1,570.00$2,625.00$1,220.00$2,100.00$1,500.00
61Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346)EACH2$1,800.00$1,837.50$2,075.00$3,150.00$2,110.00$2,400.00$2,000.00
62Set (type II) (18") (RCP) (4:1) (P) (467-7474)EACH2$1,800.00$892.50$920.00$945.00$850.00$1,200.00$900.00
63Clean existing culverts (480-7001)EACH15$2,500.00$1,995.00$2,650.00$1,575.00$1,000.00$1,850.00$3,000.00
64Removing structure (pipe) (496-7037)EACH25$600.00$320.25$430.00$1,050.00$300.00$500.00$800.00
65Mobilization (500-7001)LS1$1,260,546$500,000$1,000,000$825,000$1,100,000$1,000,000$900,000
66Barricades, signs and traffic handling (502-7001)MO28$6,000.00$9,150.00$3,000.00$6,000.00$10,000$5,400.00$8,000.00
67Portable changeable message sign (503-7001)DAY42$100.00$500.00$150.00$135.00$100.00$95.00$250.00
68TMA (stationary) (505-7001)DAY110$140.00$300.00$350.00$200.00$300.00$300.00$275.00
69TMA (mobile operation) (505-7003)DAY20$140.00$50.00$750.00$580.00$0.01$150.00$300.00
70Rock filter dams (install) (type 1) (506-7001)LF2,175$35.00$34.65$30.00$34.00$33.00$41.00$35.00
71Rock filter dams (install) (type 2) (506-7002)LF2,175$45.00$36.75$37.00$36.00$35.00$41.00$38.00
72Rock filter dams (remove) (506-7011)LF4,350$12.00$10.50$7.00$10.00$10.00$17.00$11.00
73Earthwork (erosion & sediment control, in vehicle) (506-7029)CY1,000$40.00$25.00$25.00$32.00$8.00$16.00$30.00
74Backhoe work (erosion & sediment control) (506-7030)HR200$70.00$167.00$90.00$110.00$75.00$64.00$85.00
75Temporary sediment control fence (install) (506-7039)LF8,902$4.50$4.20$3.50$4.10$3.99$4.00$4.35
76Temporary sediment control fence (remove) (506-7041)LF8,902$1.40$0.42$1.00$0.40$0.40$0.60$0.50
77Trackhoe work (erosion & sediment control) (506-7051)HR200$95.00$206.00$90.00$115.00$125.00$123.00$125.00
78Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005)LF810$50.00$105.00$88.00$33.00$54.00$120.00$75.00
79Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041)LF810$20.00$46.20$19.00$29.00$23.00$40.00$25.00
80Intersections (ACP) (530-7002)SY340$50.00$132.71$45.00$56.00$154.77$80.00$40.00
81Driveways (ACP) (530-7010)SY3,249$50.00$40.00$35.00$65.00$61.00$46.00$50.00
82Turnouts (ACP) (530-7018)SY48$60.00$150.00$40.00$101.00$135.00$175.00$75.00
83Mill rumble strips (asphalt) (shoulder) (533-7001)LF35,060$0.30$0.35$0.28$0.17$0.46$0.20$0.30
84Mill rumble strips (asphalt) (centerline) (533-7002)LF17,232$0.30$0.35$0.28$0.17$0.46$0.20$0.30
85Metal W-beam guard fence (steel post) (540-7002)LF800$30.00$25.57$35.00$26.00$25.00$28.00$27.50
86Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$2,400.00$2,150.00$2,500.00$1,863.00$1,875.00$2,100.00$2,300.00
87Guardrail end treatment (install) (544-7001)EACH6$3,100.00$2,987.25$3,500.00$2,987.00$1,850.00$2,100.00$2,100.00
88Crash cushion attenuator (remove) (545-7004)EACH4$1,000.00$1,219.05$1,500.00$1,066.00$800.00$900.00$1,000.00
89Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH4$9,400.00$29,400$10,000$26,579$26,750$30,000$29,500
90Chain link fence (install) (6') (550-7001)LF51$42.00$31.62$60.00$75.00$73.00$52.00$70.00
91Chain link fence (remove) (550-7007)LF44$6.00$10.00$15.00$50.00$17.00$12.00$10.00
92Wire fence (type D) (552-7004)LF226$20.00$35.00$40.00$18.00$17.00$32.00$35.00
93Wire fence (remove) (552-7011)LF287$1.50$3.00$15.00$12.00$6.00$12.00$10.00
94Mailbox install-S (TWG-post) type 2 (560-7002)EACH14$300.00$363.23$300.00$262.00$346.00$325.00$380.00
95Mailbox install-D (TWG-post) type 2 (560-7003)EACH2$411.68$350.00$288.00$392.00$400.00$435.00
96Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH41$700.00$703.08$750.00$735.00$669.00$550.00$740.00
97Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH1$800.00$922.78$800.00$861.00$879.00$750.00$975.00
98Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH2$1,000.00$930.07$1,000.00$945.00$886.00$850.00$975.00
99Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH5$1,100.00$1,152.44$1,200.00$1,050.00$1,098.00$900.00$1,200.00
100Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035)EACH2$1,300.00$1,432.69$1,400.00$1,365.00$1,364.00$1,200.00$1,500.00
101Relocate SM RD SN sup&AM type S80 (644-7067)EACH1$700.00$720.73$800.00$1,260.00$686.00$600.00$755.00
102Remove SM RD SN sup&AM (644-7073)EACH35$110.00$106.49$150.00$105.00$101.00$100.00$115.00
103Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH1$40.00$32.55$30.00$32.00$18.00$20.00$20.00
104Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH15$30.00$44.10$45.00$44.00$25.00$28.00$30.00
105Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH30$75.00$76.07$70.00$86.00$72.00$80.00$80.00
106Install OM SM RD sign (1-OM-con)Y (658-7079)EACH10$91.40$50.00$24.00$87.00$75.00$100.00
107Install OM SM RD sign (1-OM-con)R (658-7080)EACH5$280.00$105.74$50.00$24.00$100.00$75.00$115.00
108Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF72,771$0.30$0.25$0.35$0.21$0.30$0.23$0.22
109Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF72,771$0.30$0.25$0.35$0.21$0.30$0.23$0.22
110Work zone pavement marking removing (W)6"(solid) (662-7068)LF72,771$1.60$0.01$0.40$0.20$0.01$1.50$1.75
111Work zone pavement marking removing (Y)6"(solid) (662-7100)LF72,771$1.60$0.01$0.40$0.17$0.01$1.50$1.75
112Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH3,639$2.00$2.00$1.50$1.08$1.15$1.15$2.50
113Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF339$1.30$1.05$1.50$2.10$2.00$2.25$2.20
114Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF213$1.30$1.26$2.00$1.60$1.50$1.55$1.65
115Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF110$6.00$7.61$10.00$8.40$8.00$9.00$8.80
116Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090)EACH5$100.00$57.75$65.00$105.00$100.00$112.00$110.00
117Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF2,405$0.70$0.60$0.70$0.84$0.80$0.92$0.88
118Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF38,480$0.70$0.55$0.65$0.60$0.70$0.65$0.62
119Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF546$0.80$0.60$0.70$0.84$0.80$0.92$0.88
120Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF36,622$0.70$0.55$0.65$0.60$0.70$0.65$0.62
121Prefabricated PM type C (W)(LN reduct arrow) (668-7100)EACH2$400.00$441.00$500.00$367.00$350.00$400.00$385.00
122Reflectorized pavement marker type I-A (672-7001)EACH66$5.00$5.50$6.00$6.30$6.00$6.50$6.60
123Reflectorized pavement marker type I-C (672-7002)EACH131$4.50$5.50$6.00$6.30$6.00$6.50$6.60
124Reflectorized pavement marker type II-A-A (672-7004)EACH485$5.00$5.50$6.00$5.25$5.00$5.50$5.50
125Full - width mowing (730-7019)CYC4$5,500.00$6,000.00$6,000.00$6,000.00$3,750.00$3,000.00$8,000.00
126Litter removal (734-7002)CYC4$4,500.00$3,000.00$3,000.00$5,400.00$1,875.00$1,000.00$5,000.00
TxDOT contract A00058517: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy