Trackhoe work (erosion & sediment control), TxDOT 506-7051
Low bidders on TxDOT contracts carried a median of $110.00 per HR for this item, over the 24 months to 19 NOV 2026, across 14 low bids. Half of all 98 bids fell between $100.00 and $196.88.
- Owner
- Texas DOT
- Item
- 506-7051
- Unit
- HR
- Data through
- 19 NOV 2026
TxDOT prints this item as “TRACKHOE WORK (EROSION & SEDMT CONT)”.
TxDOT has bid this work under more than one code: 5066046002 on lettings from 07 FEB 2020 to 05 JUN 2024 (132 bids); 5066046004 on lettings from 08 APR 2020 to 05 AUG 2020 (12 bids); 5066046005 on lettings from 07 JAN 2021 to 05 MAR 2024 (129 bids); 506-7051 on lettings from 07 JAN 2025 to 06 AUG 2026 (98 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 6 | 6 | $107.50 | 30 | $100.00 |
| 2021 | 10 | 10 | $92.62 | 62 | $100.00 |
| 2022 | 13 | 13 | $100.00 | 69 | $100.00 |
| 2023 | 18 | 18 | $150.00 | 71 | $150.00 |
| 2024 | 6 | 6 | $162.50 | 31 | $150.00 |
| 2025 | 10 | 10 | $100.00 | 73 | $130.00 |
| 2026 | 4 | 4 | $125.00 | 25 | $123.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (HR) | Low bids | Low-bid median |
|---|---|---|
| 10 to 20 | 3 | $200.00 |
| 25 to 150 | 4 | $115.00 |
| 190 to 300 | 3 | $89.00 |
| 300 to 600 | 4 | $97.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Highway 19 Construction LLC | 22 | 16 (73%) |
| East Texas Bridge, Inc. | 56 | 14 (25%) |
| Reynolds & Kay, LTD. | 28 | 12 (43%) |
| Big Creek Construction, LTD. | 15 | 8 (53%) |
| A. L. Helmcamp, Inc. | 24 | 6 (25%) |
| True Roads Construction, LLC | 12 | 5 (42%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 AUG 2026 | A00049653 | Tyler District | 300 | $89.00 | $100.00 | $145.00 | 5 | Longview Bridge and Road, LTD. | TxDOT |
| 01 JUL 2026 | A00058522 | Tyler District | 300 | $120.00 | $125.00 | $98.00 | 7 | Drake Companies LLC | TxDOT |
| 05 FEB 2026 | A00058517 | Tyler District | 200 | $206.00 | $125.00 | $95.00 | 8 | Pinto Construction Co., Inc. | TxDOT |
| 07 JAN 2026 | A00196226 | Tyler District | 25 | $130.00 | $105.00 | $100.00 | 5 | Baker & Company Construction, LLC | TxDOT |
| 06 NOV 2025 | A00059355 | Tyler District | 150 | $100.00 | $127.50 | $55.00 | 8 | Big Creek Construction, LTD. | TxDOT |
| 05 SEP 2025 | A00063821 | Tyler District | 375 | $95.00 | $115.00 | $175.00 | 10 | Longview Bridge and Road, LTD. | TxDOT |
| 08 AUG 2025 | A00196862 | Tyler District | 60 | $50.00 | $120.00 | $125.00 | 13 | 3LW Civil LLC | TxDOT |
| 07 AUG 2025 | A00049652 | Tyler District | 300 | $95.00 | $90.00 | $110.00 | 4 | Longview Bridge and Road, LTD. | TxDOT |
| 07 AUG 2025 | A00184659 | Tyler District | 190 | $75.00 | $135.00 | $250.00 | 4 | True Roads Construction, LLC | TxDOT |
| 02 JUL 2025 | A00058519 | Tyler District | 600 | $100.00 | $116.16 | $151.63 | 6 | Highway 19 Construction LLC | TxDOT |
| 01 JUL 2025 | A00193092 | Tyler District | 20 | $200.00 | $148.50 | $200.00 | 10 | THK Construction LLC | TxDOT |
| 07 FEB 2025 | A00064408 | Tyler District | 20 | $175.00 | $150.00 | $176.43 | 7 | Madden Contracting Company, LLC. | TxDOT |
| 08 JAN 2025 | A00196216 | Tyler District | 10 | $250.00 | $250.00 | $150.00 | 3 | East Texas Bridge, Inc. | TxDOT |
| 07 JAN 2025 | A00178624 | Tyler District | 60 | $200.00 | $193.50 | $90.00 | 8 | Big Creek Construction, LTD. | TxDOT |
| 05 JUN 2024 | 06243041 | Tyler District | 5 | $200.00 | $150.00 | $125.00 | 5 | Garret Shields Infrastructure | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way