TxDOT contract A00063821 bid tabulation
Bridge Replacement, IH 20 (.955 MI W OF SABINE RIVER to .842 MI E OF SABINE RIVER). Let by Texas DOT on September 5, 2025, Gregg, Tyler District. 10 bids received; low bid $36,971,035 by Longview Bridge and Road, LTD., -8.1% against the engineer's estimate of $40,248,856.
- Owner
- Texas DOT
- Letting
- 05 SEP 2025
- Pay items
- 139
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Longview Bridge and Road, LTD. | $36,971,035 | Low | -8.0% |
| 2 | East Texas Bridge, Inc. | $37,531,651 | +2.0% | -7.0% |
| 3 | True Roads Construction, LLC | $38,685,254 | +5.0% | -4.0% |
| 4 | Indus Road & Bridge, Inc. | $39,770,109 | +8.0% | -1.0% |
| 5 | Highway 19 Construction LLC | $41,535,504 | +12% | +3.0% |
| 6 | Pulice Construction, Inc. | $43,513,669 | +18% | +8.0% |
| 7 | Harper Brothers Construction LLC | $44,068,021 | +19% | +9.0% |
| 8 | James Construction Group, LLC | $44,523,477 | +20% | +11% |
| 9 | Altus Construction LLC | $47,554,431 | +29% | +18% |
| 10 | Copasa Inc | $48,556,554 | +31% | +21% |
Engineer's estimate: $40,248,856.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Longview Bridge and Road, LTD. | 2. East Texas Bridge, Inc. | 3. True Roads Construction, LLC | 4. Indus Road & Bridge, Inc. | 5. Highway 19 Construction LLC | 6. Pulice Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 70 | $5,000.00 | $15,000 | $18,000 | $14,500 | $10,109 | $10,450 | $62,162 |
| 2 | Removing concrete (pavement) (104-7002) | CY | 3,260 | $30.00 | $36.00 | $30.00 | $40.00 | $65.00 | $50.00 | $75.75 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 974 | $40.00 | $34.00 | $15.00 | $10.00 | $12.00 | $25.00 | $1,223.65 |
| 4 | Removing concrete (rail) (104-7036) | LF | 1,180 | $48.26 | $22.00 | $15.00 | $20.00 | $23.00 | $55.00 | $358.75 |
| 5 | Remove (11"-15") TRT/untrt base & asphalt pavement (105-7011) | SY | 4,333 | $18.00 | $14.00 | $13.50 | $7.00 | $12.00 | $10.00 | $14.18 |
| 6 | Remove (16"-20") TRT/untrt base & asphalt pavement (105-7016) | SY | 2,433 | $33.00 | $16.00 | $17.50 | $9.00 | $13.00 | $15.00 | $17.96 |
| 7 | Remove (5"-11") TRT/untrt base & asphalt pavement (105-7056) | SY | 5,963 | $15.00 | $10.00 | $11.00 | $6.00 | $11.00 | $10.00 | $10.65 |
| 8 | Excavation (roadway) (110-7001) | CY | 104,314 | $8.00 | $8.00 | $13.00 | $7.50 | $15.00 | $10.00 | $2.80 |
| 9 | Excavation (special) (110-7003) | CY | 100 | $20.00 | $45.00 | $40.00 | $50.00 | $100.00 | $100.00 | $126.02 |
| 10 | Embankment (final)(DC)(type C) (132-7006) | CY | 135,817 | $11.00 | $11.00 | $15.75 | $16.50 | $15.00 | $16.00 | $7.09 |
| 11 | Furn & place topsoil (4") (160-7002) | SY | 203,380 | $6.92 | $2.50 | $2.00 | $1.85 | $1.20 | $1.50 | $1.99 |
| 12 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 101,690 | $0.16 | $0.26 | $0.14 | $0.14 | $0.15 | $0.14 | $0.16 |
| 13 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076) | SY | 203,380 | $0.58 | $0.60 | $0.63 | $0.58 | $0.60 | $0.58 | $0.72 |
| 14 | Bond fiber MTRX seed (temporary)(warm) (164-7077) | SY | 101,690 | $0.54 | $0.57 | $0.60 | $0.56 | $0.60 | $0.58 | $0.69 |
| 15 | Bond fiber MTRX seed (temporary)(cool) (164-7078) | SY | 101,690 | $0.54 | $0.59 | $0.60 | $0.56 | $0.60 | $0.58 | $0.69 |
| 16 | Vegetative watering (168-7001) | TGL | 6,712 | $22.40 | $14.50 | $5.00 | $14.00 | $2.00 | $10.00 | $30.45 |
| 17 | Wildflower seeding (180-7001) | ACRE | 5.82 | $1,050.00 | $705.00 | $1,425.00 | $1,365.00 | $1,350.00 | $1,100.00 | $1,638.25 |
| 18 | FL BS (compacted in place)(type A GR 1-2) (10") (247-7090) | SY | 22,057 | $30.00 | $38.00 | $38.00 | $40.00 | $45.00 | $31.00 | $18.64 |
| 19 | Cement (275-7001) | TON | 1,029 | $275.00 | $275.00 | $275.00 | $304.00 | $262.00 | $300.00 | $315.15 |
| 20 | Cement TRT (existing material)(12") (275-7005) | SY | 22,385 | $3.50 | $3.00 | $3.00 | $3.50 | $7.00 | $7.00 | $4.32 |
| 21 | Cement TRT (subgrade)(6") (275-7022) | SY | 31,404 | $3.50 | $2.50 | $2.35 | $4.40 | $5.00 | $5.00 | $2.77 |
| 22 | Prime coat & blotter (MC-30) (310-7010) | GAL | 5,274 | $8.00 | $5.70 | $6.25 | $7.00 | $8.40 | $7.00 | $8.82 |
| 23 | Asphalt (AC-20XP, AC-10-2TR, or AC-20-5TR) (316-7068) | GAL | 28,032 | $5.00 | $4.50 | $5.00 | $5.50 | $7.00 | $6.00 | $6.93 |
| 24 | Aggregate (type-PD or PL, GR-4) (316-7258) | CY | 649 | $180.00 | $185.00 | $235.00 | $310.00 | $400.00 | $200.00 | $270.94 |
| 25 | SP mixes SP-B PG64-22 (344-7001) | TON | 16,302 | $170.00 | $170.00 | $178.00 | $168.00 | $234.00 | $192.00 | $229.36 |
| 26 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 3,579 | $180.00 | $188.00 | $186.00 | $180.00 | $241.00 | $210.00 | $252.04 |
| 27 | Tack coat (344-7077) | GAL | 11,714 | $3.00 | $4.00 | $4.50 | $4.00 | $6.00 | $2.00 | $5.67 |
| 28 | SP mixes SP-C PG70-22 (level-UP) (344-7078) | TON | 143 | $125.00 | $210.00 | $185.00 | $250.00 | $266.00 | $210.00 | $296.15 |
| 29 | Concrete pavement (CRCP) (14") (360-7008) | SY | 30,369 | $104.00 | $155.00 | $140.00 | $156.00 | $143.00 | $178.00 | $171.95 |
| 30 | Cem stabil BKFL (400-7010) | CY | 775.20 | $230.00 | $228.00 | $185.00 | $265.00 | $250.00 | $250.00 | $250.15 |
| 31 | Flowable backfill (401-7001) | CY | 4 | $450.00 | $500.00 | $400.00 | $290.00 | $370.00 | $350.00 | $630.08 |
| 32 | Trench excavation protection (402-7001) | LF | 42 | $22.00 | $25.00 | $25.00 | $20.00 | $300.00 | $10.00 | $25.20 |
| 33 | Temporary special shoring (403-7001) | SF | 420 | $55.25 | $60.00 | $50.00 | $85.00 | $50.00 | $55.00 | $63.01 |
| 34 | Foundaton loadtest(D4945)(drilld shaft) (405-7003) | EACH | 3 | $41,860 | $22,000 | $22,000 | $21,000 | $26,000 | $22,500 | $28,001 |
| 35 | Drilled shaft (18 in) (416-7002) | LF | 170 | $208.67 | $140.00 | $84.00 | $85.00 | $140.00 | $144.00 | $103.75 |
| 36 | Drilled shaft (36 in) (416-7006) | LF | 1,565 | $344.00 | $292.00 | $280.00 | $275.00 | $355.00 | $218.00 | $347.69 |
| 37 | Drilled shaft (48 in) (416-7008) | LF | 1,440 | $475.00 | $445.00 | $480.00 | $480.00 | $450.00 | $343.00 | $594.45 |
| 38 | Drilled shaft (60 in) (416-7010) | LF | 1,600 | $600.00 | $880.00 | $900.00 | $800.00 | $970.00 | $591.00 | $1,008.09 |
| 39 | Drilled shaft (sign mounts) (12 in) (416-7027) | LF | 14 | $165.00 | $160.00 | $160.00 | $150.00 | $200.00 | $145.00 | $107.12 |
| 40 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 14 | $215.00 | $250.00 | $245.00 | $235.00 | $265.00 | $225.00 | $228.09 |
| 41 | Class C concrete (abutment) (420-7012) | CY | 155.40 | $1,200.00 | $1,250.00 | $1,100.00 | $1,350.00 | $975.00 | $1,266.00 | $1,539.63 |
| 42 | Class C concrete (cap) (420-7022) | CY | 223.80 | $1,200.00 | $1,000.00 | $1,100.00 | $1,325.00 | $1,200.00 | $1,600.00 | $1,469.50 |
| 43 | Class C concrete (cap)(mass) (420-7024) | CY | 374.30 | $1,370.11 | $1,100.00 | $1,050.00 | $1,465.00 | $1,100.00 | $1,650.00 | $1,716.03 |
| 44 | Class C concrete (column) (420-7038) | CY | 517.90 | $1,750.00 | $1,000.00 | $1,075.00 | $1,675.00 | $1,250.00 | $1,000.00 | $1,546.84 |
| 45 | Class C concrete (rail foundation) (420-7052) | CY | 97 | $938.25 | $750.00 | $1,500.00 | $850.00 | $620.00 | $780.00 | $722.28 |
| 46 | Class C concrete (collar) (420-7061) | EACH | 3 | $1,650.00 | $1,200.00 | $1,100.00 | $2,300.00 | $3,200.00 | $1,500.00 | $3,163.04 |
| 47 | CL E concrete (seal slab)(non-reinforced) (420-7070) | CY | 2 | $717.50 | $1,500.00 | $800.00 | $1,690.00 | $1,900.00 | $1,000.00 | $5,790.00 |
| 48 | Reinforced concrete slab (422-7001) | SF | 89,900 | $28.00 | $27.00 | $25.00 | $24.00 | $21.00 | $25.14 | $23.99 |
| 49 | Approach slab (422-7013) | CY | 314.80 | $914.19 | $800.00 | $850.00 | $730.00 | $950.00 | $750.00 | $947.83 |
| 50 | Prestressed concrete girder (TX54) (425-7005) | LF | 8,878.15 | $245.00 | $235.00 | $237.00 | $245.00 | $220.00 | $270.00 | $244.58 |
| 51 | Prestressed concrete girder (TX62) (425-7006) | LF | 1,942.20 | $260.00 | $240.00 | $237.00 | $245.00 | $230.00 | $262.00 | $244.62 |
| 52 | Riprap (concrete)(4 in) (432-7001) | CY | 1,128 | $700.00 | $550.00 | $640.00 | $570.00 | $650.00 | $700.00 | $637.62 |
| 53 | Riprap (mow strip)(4 in) (432-7013) | CY | 234 | $722.50 | $705.00 | $600.00 | $750.00 | $725.00 | $500.00 | $782.88 |
| 54 | Riprap (stone protection)(12 in) (432-7041) | CY | 79 | $222.16 | $230.00 | $210.00 | $190.00 | $220.00 | $180.00 | $317.58 |
| 55 | Riprap (stone protection)(24 in) (432-7045) | CY | 1,664 | $247.50 | $190.00 | $210.00 | $190.00 | $190.00 | $180.00 | $284.79 |
| 56 | Clean and seal existing JTS (strip seal) (438-7014) | LF | 82 | $70.00 | $90.00 | $150.00 | $125.00 | $125.00 | $100.00 | $170.13 |
| 57 | Rail (type SSTR) (450-7024) | LF | 9,500 | $110.00 | $65.00 | $75.00 | $118.00 | $85.00 | $180.00 | $113.12 |
| 58 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 503 | $244.06 | $220.00 | $200.00 | $200.00 | $200.00 | $250.00 | $245.49 |
| 59 | RC pipe (CL III)(24 in) (464-7005) | LF | 180 | $155.00 | $75.00 | $82.00 | $78.00 | $145.00 | $82.00 | $203.65 |
| 60 | RC pipe (CL III)(42 in) (464-7010) | LF | 238 | $250.00 | $170.00 | $195.00 | $185.00 | $260.00 | $212.00 | $312.99 |
| 61 | RC pipe (CL III)(66 in) (464-7014) | LF | 56 | $478.40 | $650.00 | $545.00 | $560.00 | $560.00 | $450.00 | $1,019.89 |
| 62 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 1 | $8,500.00 | $6,600.00 | $6,500.00 | $6,500.00 | $7,200.00 | $7,500.00 | $6,931.01 |
| 63 | Headwall (CH - FW - 15) (diameter= 66 in) (466-7029) | EACH | 2 | $23,000 | $16,500 | $13,500 | $15,000 | $17,500 | $18,500 | $22,683 |
| 64 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 2 | $1,979.51 | $1,500.00 | $1,100.00 | $1,000.00 | $2,500.00 | $1,200.00 | $2,520.37 |
| 65 | Set (type II) (42 in) (RCP) (4: 1) (C) (467-7378) | EACH | 3 | $6,328.27 | $6,000.00 | $6,200.00 | $5,000.00 | $7,500.00 | $9,000.00 | $9,451.44 |
| 66 | Removing structure (wingwall) (496-7005) | EACH | 5 | $1,875.00 | $1,500.00 | $500.00 | $1,250.00 | $6,500.00 | $1,000.00 | $2,579.61 |
| 67 | Removing structure (bridge 500 - 999 FT length) (496-7011) | EACH | 1 | $500,000 | $150,000 | $200,000 | $300,000 | $200,000 | $300,000 | $470,346 |
| 68 | Mobilization (500-7001) | LS | 1 | $3,000,000 | $3,500,000 | $2,700,000 | $3,650,000 | $3,970,000 | $4,000,000 | $4,319,963 |
| 69 | Barricades, signs and traffic handling (502-7001) | MO | 33 | $5,000.00 | $7,500.00 | $5,000.00 | $5,000.00 | $20,000 | $5,000.00 | $9,501.62 |
| 70 | Portable changeable message sign (503-7001) | DAY | 1,228 | $151.43 | $110.00 | $100.00 | $65.00 | $82.00 | $100.00 | $55.22 |
| 71 | TMA (stationary) (505-7001) | DAY | 54 | $306.67 | $225.00 | $200.00 | $100.00 | $200.00 | $1,000.00 | $1,747.90 |
| 72 | TMA (mobile operation) (505-7003) | DAY | 54 | $350.33 | $275.00 | $200.00 | $100.00 | $560.00 | $1,000.00 | $856.29 |
| 73 | Rock filter dams (install) (type 2) (506-7002) | LF | 690 | $55.46 | $45.00 | $43.00 | $38.85 | $44.00 | $56.00 | $49.15 |
| 74 | Rock filter dams (install) (type 3) (506-7003) | LF | 300 | $85.83 | $65.00 | $65.00 | $52.50 | $65.00 | $140.00 | $75.61 |
| 75 | Rock filter dams (remove) (506-7011) | LF | 990 | $12.07 | $11.00 | $11.00 | $10.50 | $11.00 | $10.00 | $12.60 |
| 76 | Construction exits (install) (type 1) (506-7020) | SY | 500 | $43.00 | $39.00 | $36.00 | $34.65 | $35.00 | $35.00 | $41.59 |
| 77 | Construction exits (remove) (506-7024) | SY | 500 | $12.84 | $11.00 | $11.00 | $10.50 | $11.00 | $10.00 | $12.60 |
| 78 | Earthwork (erosion & sediment control, in vehicle) (506-7029) | CY | 750 | $35.00 | $25.00 | $30.00 | $20.70 | $44.00 | $50.00 | $73.15 |
| 79 | Backhoe work (erosion & sediment control) (506-7030) | HR | 375 | $160.00 | $70.00 | $70.00 | $100.00 | $195.00 | $50.00 | $296.44 |
| 80 | Temporary sediment control fence (install) (506-7039) | LF | 19,362 | $4.33 | $4.50 | $4.25 | $3.94 | $4.00 | $4.00 | $4.85 |
| 81 | Temporary sediment control fence (remove) (506-7041) | LF | 19,362 | $1.50 | $1.50 | $0.55 | $0.52 | $0.60 | $1.00 | $0.63 |
| 82 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 24 | $7.00 | $11.00 | $9.00 | $8.40 | $9.00 | $20.00 | $10.08 |
| 83 | Biodegradable erosion control logs (remove) (506-7046) | LF | 24 | $1.10 | $2.50 | $2.20 | $2.10 | $2.00 | $1.00 | $2.52 |
| 84 | Trackhoe work (erosion & sediment control) (506-7051) | HR | 375 | $175.00 | $95.00 | $100.00 | $100.00 | $230.00 | $50.00 | $340.54 |
| 85 | Constructing detours (508-7001) | SY | 18,111 | $400.00 | $208.00 | $245.00 | $215.00 | $210.00 | $248.00 | $53.56 |
| 86 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 14,940 | $55.00 | $87.00 | $75.00 | $88.00 | $54.00 | $87.00 | $71.30 |
| 87 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 19,180 | $17.71 | $8.00 | $7.50 | $12.00 | $10.00 | $19.00 | $5.91 |
| 88 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 12,400 | $28.08 | $12.00 | $10.00 | $9.00 | $13.00 | $23.00 | $10.41 |
| 89 | PCTB (fur&inst)(F-shape or SNGL SLP)type 1 (512-7089) | LF | 2,525 | $47.50 | $85.00 | $72.00 | $88.00 | $72.00 | $70.00 | $96.51 |
| 90 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 725 | $98.75 | $90.00 | $100.00 | $115.00 | $110.00 | $90.00 | $152.42 |
| 91 | Permanent CTB (single slope) (type 1) (48 ) (514-7005) | LF | 4,107 | $110.00 | $105.00 | $110.00 | $115.00 | $122.00 | $180.00 | $184.39 |
| 92 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 11,110 | $0.30 | $0.90 | $0.50 | $0.33 | $0.60 | $0.16 | $0.57 |
| 93 | Mill rumble strips (concrete) (shoulder) (533-7003) | LF | 9,720 | $2.42 | $1.10 | $0.90 | $0.23 | $0.40 | $0.16 | $0.39 |
| 94 | Metal W-beam guard fence (steel post) (540-7002) | LF | 1,312 | $32.00 | $30.00 | $30.00 | $28.00 | $28.00 | $29.00 | $43.89 |
| 95 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $2,400.00 | $2,200.00 | $2,150.00 | $2,020.00 | $2,400.00 | $2,200.00 | $3,256.45 |
| 96 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,753.00 | $1,450.00 | $1,450.00 | $1,365.00 | $1,650.00 | $1,200.00 | $1,541.12 |
| 97 | Remove metal beam guard fence (542-7001) | LF | 692 | $3.00 | $2.75 | $2.75 | $2.60 | $3.00 | $3.00 | $4.02 |
| 98 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 3 | $272.00 | $165.00 | $165.00 | $157.00 | $285.00 | $250.00 | $348.43 |
| 99 | Guardrail end treatment (install) (544-7001) | EACH | 3 | $3,360.00 | $3,350.00 | $3,300.00 | $3,175.00 | $3,300.00 | $2,950.00 | $4,415.67 |
| 100 | Guardrail end treatment (remove) (544-7003) | EACH | 3 | $300.00 | $225.00 | $220.00 | $210.00 | $285.00 | $250.00 | $442.22 |
| 101 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 9 | $3,075.00 | $4,600.00 | $4,550.00 | $4,350.00 | $3,250.00 | $7,300.00 | $4,020.35 |
| 102 | Crash cushion attenuator (remove) (545-7004) | EACH | 5 | $1,454.70 | $1,100.00 | $1,100.00 | $1,050.00 | $1,290.00 | $2,000.00 | $1,581.32 |
| 103 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 7 | $34,980 | $26,750 | $28,000 | $25,500 | $34,000 | $29,900 | $35,848 |
| 104 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 3,206 | $25.00 | $5.85 | $5.75 | $5.50 | $6.00 | $6.00 | $22.38 |
| 105 | Aluminum signs (type A) (636-7001) | SF | 33 | $65.56 | $55.00 | $40.00 | $52.50 | $36.00 | $37.00 | $35.29 |
| 106 | Aluminum signs (type G) (636-7002) | SF | 190 | $38.00 | $40.00 | $40.00 | $38.00 | $48.00 | $37.00 | $41.59 |
| 107 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 2 | $800.00 | $900.00 | $900.00 | $700.00 | $710.00 | $850.00 | $825.43 |
| 108 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 4 | $870.00 | $1,200.00 | $1,200.00 | $835.00 | $840.00 | $1,100.00 | $1,216.09 |
| 109 | Remove SM RD SN sup&AM (644-7073) | EACH | 3 | $118.33 | $180.00 | $100.00 | $105.00 | $105.00 | $100.00 | $138.61 |
| 110 | Install LRSS (struct steel) (647-7001) | LB | 820 | $10.00 | $9.00 | $8.50 | $8.00 | $10.00 | $7.75 | $9.07 |
| 111 | Remove lrsa (647-7003) | EACH | 2 | $1,500.00 | $910.00 | $900.00 | $865.00 | $950.00 | $825.00 | $932.51 |
| 112 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 5 | $81.92 | $180.00 | $180.00 | $57.00 | $57.00 | $163.00 | $88.20 |
| 113 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 118 | $26.23 | $27.50 | $30.00 | $15.75 | $16.00 | $20.00 | $30.24 |
| 114 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 18 | $32.96 | $27.50 | $30.00 | $26.25 | $26.00 | $35.00 | $37.81 |
| 115 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 20 | $24.00 | $27.50 | $30.00 | $15.75 | $16.00 | $20.00 | $30.24 |
| 116 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 62 | $24.00 | $27.50 | $30.00 | $15.75 | $16.00 | $20.00 | $30.24 |
| 117 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 8 | $68.00 | $40.00 | $175.00 | $57.75 | $58.00 | $158.00 | $90.73 |
| 118 | Install object marker assembly (OM-3L)(WFLX)SRF (658-7064) | EACH | 2 | $327.55 | $375.00 | $375.00 | $255.00 | $260.00 | $342.00 | $327.63 |
| 119 | Install object marker assembly (OM-3R)(WFLX)SRF (658-7067) | EACH | 1 | $433.60 | $375.00 | $375.00 | $255.00 | $260.00 | $342.00 | $327.62 |
| 120 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 5,463 | $8.17 | $3.30 | $3.25 | $3.15 | $3.00 | $3.00 | $3.78 |
| 121 | Work zone pavement marking removing (traffic BTN) type Y (662-7059) | EACH | 2,749 | $6.50 | $3.30 | $3.25 | $3.15 | $3.00 | $3.00 | $3.78 |
| 122 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 3,785 | $2.33 | $1.70 | $1.65 | $1.57 | $1.60 | $1.50 | $1.89 |
| 123 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 15,300 | $1.44 | $1.65 | $1.65 | $1.57 | $1.60 | $1.50 | $1.89 |
| 124 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 15,180 | $1.44 | $1.65 | $1.65 | $1.57 | $1.60 | $1.50 | $1.89 |
| 125 | RE PV marking type I(black)6"(shadow)(100MIL) (666-7138) | LF | 2,580 | $1.83 | $2.20 | $2.20 | $2.10 | $2.10 | $2.00 | $2.52 |
| 126 | RE prof PM (W)6"(solid) raisd prof only (666-7279) | LF | 1,564 | $0.50 | $5.50 | $5.50 | $5.25 | $5.10 | $5.00 | $6.30 |
| 127 | RE prof PM (Y)6"(solid) raisd prof only (666-7280) | LF | 1,564 | $0.36 | $5.50 | $5.50 | $5.25 | $5.10 | $5.00 | $6.30 |
| 128 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 3,960 | $2.17 | $1.10 | $1.10 | $1.05 | $1.10 | $1.00 | $1.26 |
| 129 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 14,050 | $2.02 | $0.85 | $0.82 | $0.79 | $0.80 | $0.75 | $0.95 |
| 130 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 13,875 | $1.93 | $0.85 | $0.82 | $0.79 | $0.80 | $0.75 | $0.95 |
| 131 | Pavement sler 6" (666-7347) | LF | 17,951 | $0.50 | $0.30 | $0.27 | $0.26 | $0.30 | $0.25 | $0.32 |
| 132 | Reflectorized pavement marker type I-C (672-7002) | EACH | 4,596 | $6.00 | $4.20 | $4.15 | $3.99 | $4.00 | $3.80 | $4.79 |
| 133 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 550 | $7.77 | $6.60 | $6.50 | $6.30 | $6.50 | $6.00 | $7.56 |
| 134 | Pavement surface preparation for marking (6") (678-7002) | LF | 17,951 | $0.20 | $1.10 | $0.27 | $0.26 | $0.28 | $0.25 | $0.32 |
| 135 | Full - width mowing (730-7019) | CYC | 6 | $2,860.00 | $6,000.00 | $5,000.00 | $135.00 | $4,000.00 | $5,000.00 | $10,097 |
| 136 | Litter removal (734-7002) | CYC | 6 | $2,275.00 | $5,500.00 | $3,000.00 | $1,000.00 | $2,500.00 | $5,000.00 | $29,508 |
| 137 | Tip testing(drilled shaft) (4003-7001) | EACH | 8 | $8,000.00 | $5,500.00 | $5,500.00 | $5,200.00 | $4,100.00 | $5,000.00 | $6,847.72 |
| 138 | Amphibian/reptile exclusion fence inst (5003-7001) | LF | 4,800 | $4.33 | $7.00 | $4.35 | $4.20 | $4.50 | $3.49 | $5.04 |
| 139 | Amphibian/reptile exclusion fence rem (5003-7002) | LF | 4,800 | $1.50 | $1.50 | $1.00 | $1.05 | $1.20 | $1.07 | $1.26 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.