Rail (type SSTR), TxDOT 450-7024

Low bidders on TxDOT contracts carried a median of $85.00 per LF for this item, over the 24 months to 19 NOV 2026, across 95 low bids. Half of all 605 bids fell between $70.00 and $145.00.

Owner
Texas DOT
Item
450-7024
Unit
LF
Data through
19 NOV 2026

TxDOT prints this item as “RAIL (TY SSTR)”.

TxDOT has bid this work under more than one code: 4506023 on lettings from 10 JAN 2020 to 02 JUN 2022 (412 bids); 4506023001 on lettings from 04 FEB 2022 to 02 AUG 2024 (442 bids); 450-7024 on lettings from 06 NOV 2024 to 04 NOV 2026 (626 bids); 450-6023 on lettings from 07 NOV 2024 to 07 FEB 2025 (11 bids). They are combined here into one trend.

$85.00Low bidder's median, per LF
$95.00Median of all bids, per LF
95Contracts in the window
$86.25Engineer's estimate, median per LF

By year of letting

Rail (type SSTR), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20204039$56.50186$58.48
20213939$48.00205$52.58
20223838$70.50164$75.00
20234141$112.22139$98.61
20245353$97.00213$103.00
20254545$80.95262$107.41
20264747$85.00321$90.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Yoakum District11$118.5289$141.25
Houston District11$78.0088$80.00
Dallas District10$85.0057$75.00
Tyler District5$82.0042$100.00
San Antonio District8$71.0041$73.00
Austin District6$89.1038$93.10
Amarillo District7$110.0034$127.08
Fort Worth District4$87.5029$79.00
Laredo District4$96.5724$76.50
Pharr District5$45.0024$57.76
Waco District3$80.9523$125.00
Bryan District3$120.0021$100.00
Rail (type SSTR), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
54 to 45823$138.45
464 to 2,607.4824$97.50
2,629 to 7,96924$80.20
8,050 to 99,345.5024$63.00
Rail (type SSTR), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Rail (type SSTR), TxDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00124162Bryan District2,830$43.50$90.00$85.0012Fluor Enterprises, Inc.TxDOT
04 NOV 2026A00212892Dallas District21,467.20$82.00$63.74$60.006Indus Road & Bridge, Inc.TxDOT
03 NOV 2026A00184974Austin District46,652.90$63.20$72.69$115.006Austin Bridge & Road Services, LPTxDOT
03 SEP 2026A00184830Amarillo District828$110.00$110.00$120.007Gilvin-Terrill, LTD.TxDOT
03 SEP 2026A00207389Childress District1,056$117.00$135.00$75.837Coppell Construction Co., Inc.TxDOT
02 SEP 2026A00121174Pharr District13,645.20$45.00$57.67$65.007Ioc Company LLCTxDOT
02 SEP 2026A00206056Wichita Falls District106$250.00$220.00$240.007Tight Line Construction, LLCTxDOT
06 AUG 2026A00191470Houston District5,312.30$56.51$61.44$85.009James Construction Group, LLCTxDOT
06 AUG 2026A00062075Fort Worth District5,828$76.00$66.00$85.007Indus Road & Bridge, Inc.TxDOT
06 AUG 2026A00193006Amarillo District1,075$128.25$128.25n/a3J. Lee Milligan, Inc.TxDOT
06 AUG 2026A00136986San Antonio District708$67.00$105.75$70.008Hunter Industries, LTD.TxDOT
05 AUG 2026A00128458Amarillo District7,969$105.00$87.50$103.004J. Lee Milligan, Inc.TxDOT
05 AUG 2026A00191471Houston District5,679$60.40$69.50$75.008James Construction Group, LLCTxDOT
05 AUG 2026A00007222Fort Worth District2,652$85.00$79.00n/a11Indus Road & Bridge, Inc.TxDOT
05 AUG 2026A00068611Houston District335$59.00$132.00$55.007Ser Construction Partners, LLCTxDOT
Latest TxDOT contracts carrying Rail (type SSTR)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy