TxDOT contract A00062075 bid tabulation

Construct Ramps, IH 20 (FM 1884 to SH 171). Let by Texas DOT on August 6, 2026, Parker, Fort Worth District. 7 bids received; low bid $15,697,165 by Indus Road & Bridge, Inc., -14% against the engineer's estimate of $18,156,437.

Owner
Texas DOT
Letting
06 AUG 2026
Pay items
167
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Indus Road & Bridge, Inc.$15,697,165Low-14%
2Prater Dirt Work LLC$15,958,879+2.0%-12%
3Reyes TX, Inc.$16,000,000+2.0%-12%
4Urban Infraconstruction LLC$16,839,039+7.0%-7.0%
5Ed Bell Construction Company$18,154,876+16%0.0%
6Jay Mills Contracting, Incorporated$20,088,567+28%+11%
7Rebcon, Inc.$21,300,102+36%+17%
TxDOT contract A00062075: bids by rank

Engineer's estimate: $18,156,437.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Indus Road & Bridge, Inc.2. Prater Dirt Work LLC3. Reyes TX, Inc.4. Urban Infraconstruction LLC5. Ed Bell Construction Company6. Jay Mills Contracting, Incorporated
1Preparing row (100-7002)STA61.20$3,000.00$17,519$5,000.00$9,874.91$7,000.00$5,575.00$10,000
2Removing concrete (pavement) (104-7001)SY3,973$20.00$11.00$12.75$16.00$12.00$20.00$15.00
3Removing concrete (mowstrip) (104-7003)SY2,254$17.00$10.00$20.00$2.50$7.00$15.00$17.00
4Removing concrete (riprap) (104-7006)SY2,745$28.00$7.00$15.00$23.00$8.00$15.00$17.00
5Removing concrete (curb & gutter) (104-7017)LF1,251$12.00$7.00$10.00$12.00$3.00$10.00$14.00
6Removing concrete (flume) (104-7041)SY1,366$35.00$8.00$17.00$4.80$8.50$20.00$17.00
7Remove (4") TRT/untrt base & asphalt pavement (105-7024)SY4,559$14.00$6.00$3.50$11.00$7.15$6.50$9.00
8Excavation (roadway) (110-7001)CY7,727$23.00$28.00$15.00$25.00$25.00$20.00$19.00
9Embankment (final)(DC)(type B) (132-7004)CY8,293$35.00$7.00$15.00$25.00$5.00$20.00$28.00
10Embankment (final)(DC)(type D) (132-7012)CY7,727$15.00$9.00$20.00$9.50$5.00$10.00$6.50
11Backfill (type A or B) (134-7004)STA98.20$260.00$268.00$200.00$510.00$155.00$175.00$550.00
12Compost manuf topsoil (4") (161-7002)SY13,335$3.75$1.90$2.10$4.40$3.00$12.00$8.00
13Block sodding (162-7002)SY13,335$6.00$5.00$5.00$4.10$4.65$6.00$4.50
14Hydro mulch seed (permanent_urban_clay) (164-7020)SY15,426$3.00$0.50$0.53$0.45$0.48$1.00$0.80
15Hydro mulch seed (temporary_warm) (164-7021)SY9,659$1.00$0.50$0.42$0.40$0.45$0.82$0.85
16Hydro mulch seed (temporary_cool) (164-7022)SY9,659$1.00$0.50$0.42$0.40$0.46$0.82$0.90
17Vegetative watering (168-7001)TGL1,006$15.00$10.00$15.00$15.00$15.00$80.00$62.00
18Lime (com or QK)(slurry) (260-7005)TON140$350.00$360.00$325.00$386.00$325.00$337.00$375.00
19Lime TRT (existing material)(8") (260-7007)SY8,331$12.00$6.40$6.00$6.00$6.00$9.86$8.00
20Cement (275-7001)TON116$275.00$246.00$210.00$509.00$168.00$414.00$350.00
21Cement TRT (existing material)(8") (275-7003)SY8,331$9.00$5.30$5.00$5.50$4.00$4.56$8.00
22Salvage, haul & stockpile reclaimed asphalt PV (2"-6") (305-7035)SY3,973$4.25$7.00$7.00$2.20$7.43$7.50$9.00
23Prime coat(MC-30 or AE-P) (310-7013)GAL3,194$6.00$3.40$7.50$7.00$6.50$6.50$6.00
24D-GR HMA type-B PG64-22 (341-7001)TON3,428$115.00$119.00$150.00$129.00$120.00$110.00$112.00
25D-GR HMA type D sac-A PG70-28 (341-7053)TON427.20$148.00$203.00$240.00$215.00$308.00$200.00$200.00
26Tack coat (341-7082)GAL4,060.40$4.00$1.20$7.50$5.50$0.50$0.01$0.01
27Plane & text asphalt concrete pavement(0" to 3") (354-7003)SY3,706$2.00$6.00$6.00$4.40$7.06$7.50$6.00
28Concrete pavement (CRCP) (13") (360-7007)SY14,589$114.00$111.00$113.00$130.00$110.00$130.00$106.00
29Cut & restore asphalt paving (400-7008)SY40$450.00$525.00$150.00$201.00$678.65$400.00$500.00
30Cem stabil BKFL (400-7010)CY115.60$220.00$292.00$400.00$298.00$415.80$300.00$180.00
31Trench excavation protection (402-7001)LF854$9.00$9.00$5.25$19.00$3.74$25.00$6.00
32Temporary special shoring (403-7001)SF30,444$32.00$16.00$34.00$2.60$40.67$33.00$51.00
33Soil nail anchors (410-7001)LF17,153$35.00$38.00$28.35$26.00$33.96$27.50$35.50
34Drilled shaft (36 in) (416-7006)LF676$323.00$355.00$320.00$260.00$280.72$425.00$388.00
35Drilled shaft (sign mounts) (24 in) (416-7028)LF38$325.00$195.00$715.00$219.00$194.00$240.00$265.00
36Drilled shaft (sign mounts) (36 in) (416-7030)LF62.50$600.00$325.00$490.00$364.00$324.00$360.00$525.00
37Drilled shaft (sign mounts) (42 in) (416-7031)LF16$500.00$491.00$620.00$416.00$490.00$540.00$675.00
38Drilled shaft (sign mounts) (48 in) (416-7032)LF16$732.00$554.00$840.00$460.00$553.00$600.00$900.00
39Drilled shaft (sign mounts) (54 in) (416-7033)LF17$900.00$598.00$950.00$526.00$597.00$720.00$1,050.00
40Class B concrete (flume) (420-7010)CY328.80$800.00$626.00$640.50$611.00$400.00$1,000.00$750.00
41Class C concrete (abutment)(HPC)(extend) (420-7017)CY34.60$3,770.00$1,250.00$3,100.00$2,010.00$2,000.00$3,000.00$1,885.00
42Class C concrete (cap)(HPC) (420-7023)CY20$1,500.00$1,625.00$3,200.00$2,720.00$3,500.00$2,000.00$2,330.00
43Class C concrete (column)(HPC) (420-7039)CY39.50$1,850.00$1,262.00$2,500.00$2,110.00$1,500.00$1,500.00$2,800.00
44Class C concrete (collar) (420-7061)EACH2$1,250.00$1,320.00$1,517.50$2,200.00$1,500.00$2,000.00$1,470.00
45Reinforced concrete slab (HPC) (422-7002)SF4,854$30.00$31.00$38.75$64.00$46.00$50.00$49.00
46Approach slab (extend) (HPC) (422-7015)CY22$1,080.00$975.00$1,800.00$1,240.00$1,300.00$1,500.00$1,330.00
47Retaining wall (MSE) (423-7001)SF49,918$100.00$72.00$68.67$90.00$94.29$85.50$110.00
48Retaining wall (soil nail) (fascia) (423-7023)SF10,397$69.00$60.00$73.50$52.00$89.14$85.50$68.00
49Prestressed concrete girder (TX28) (425-7001)LF653.90$350.00$256.00$320.00$327.00$220.00$300.00$325.00
50Opaque sealer finish (427-7003)SF1,490$1.10$0.55$3.00$5.50$0.54$3.15$12.25
51Riprap (concrete) (CL B) (4 in) (432-7007)CY165.50$750.00$500.00$630.00$659.00$500.00$1,000.00$650.00
52Riprap (concrete)(flume) (432-7012)CY159$750.00$530.00$661.50$566.00$450.00$1,000.00$750.00
53Riprap (mow strip)(4 in) (432-7013)CY195.90$620.00$467.00$500.00$592.00$550.00$1,000.00$850.00
54Riprap (stone common)(dry)(12 in) (432-7031)CY2.40$175.00$750.00$400.00$1,560.00$525.00$1,000.00$500.00
55Rail (type SSTR) (450-7024)LF5,828$85.00$76.00$68.25$62.00$56.00$60.00$66.00
56Rail (type SSTR)(HPC) (450-7025)LF378$170.00$96.00$78.75$2.80$107.37$75.00$170.00
57Retrofit rail (type SSTR) (451-7024)LF378$210.00$190.00$115.50$259.00$467.78$150.00$395.00
58Armor joint (454-7002)LF58.80$150.00$122.00$180.00$341.00$224.50$150.00$222.00
59Sealed expansion JNT(4 in)(SEJ-S (O)) (454-7007)LF58.80$202.00$272.00$275.00$341.00$224.50$50.00$216.01
60RC pipe (CL III)(18 in) (464-7003)LF521$85.00$60.00$68.00$185.00$115.00$125.00$90.00
61RC pipe (CL III)(24 in) (464-7005)LF240$120.00$100.00$84.00$164.00$120.00$130.00$115.00
62RC pipe (CL III)(30 in) (464-7007)LF8$130.00$440.00$210.00$894.00$450.00$750.00$155.00
63RC pipe (CL III)(42 in) (464-7010)LF10$225.00$455.00$241.50$1,240.00$800.00$850.00$240.00
64RC pipe (CL IV)(42 in) (464-7025)LF8$340.00$545.00$288.75$937.00$900.00$875.00$300.00
65RC pipe (CL V)(18 in) (464-7032)LF203$110.00$116.00$78.75$100.00$200.00$130.00$115.00
66Inlet (complete)(AD)(3FT X 3FT)(FTW) (465-7234)EACH5$10,500$6,300.00$9,240.00$7,870.00$6,000.00$12,000$3,150.00
67Inlet (complete)(RWF)(FTW) (465-7257)EACH5$10,500$10,000$12,941$10,360$12,000$17,000$3,200.00
68Manh (complete)(type SD)(4'X 3'-3'X 3')(FTW) (465-7260)EACH2$10,800$3,500.00$5,916.75$12,050$6,000.00$10,000$4,500.00
69Junct box (complete)(JB)(5FT X 3FT)(FTW) (465-7284)EACH1$1,400.00$8,800.00$14,438$8,800.00$8,000.00$12,000$10,000
70Headwall (CH - FW - 0) (diameter= 18 in) (466-7003)EACH1$10,075$8,200.00$3,780.00$5,620.00$4,000.00$9,000.00$13,000
71Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH1$1,500.00$2,700.00$2,520.00$875.00$3,000.00$1,800.00$1,600.00
72Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH1$1,975.00$3,000.00$2,940.00$1,170.00$3,000.00$2,400.00$1,900.00
73Removing structure (inlet) (496-7002)EACH1$1,700.00$2,000.00$1,050.00$1,980.00$2,000.00$2,000.00$1,600.00
74Removing structure (set) (496-7004)EACH1$275.00$1,200.00$315.00$377.00$2,500.00$1,000.00$600.00
75Removing structure (pipe) (496-7007)LF45$25.00$45.00$21.00$95.00$95.00$75.00$25.00
76Mobilization (500-7001)LS1$1,650,585$1,500,000$1,500,000$1,456,177$1,306,570$1,635,000$2,000,000
77Barricades, signs and traffic handling (502-7001)MO21$15,000$8,000.00$19,000$8,100.00$7,500.00$52,500$20,000
78Portable changeable message sign (503-7002)EACH8$10,000$20,000$8,000.00$7,140.00$10,000$4,000.00$17,000
79TMA (stationary) (505-7001)DAY805$225.00$280.00$165.00$227.00$194.00$25.00$100.00
80TMA (mobile operation) (505-7003)DAY64$225.00$750.00$300.00$929.00$803.00$200.00$350.00
81Rock filter dams (install) (type 2) (506-7002)LF270$45.00$40.00$44.00$33.00$37.75$70.00$45.00
82Rock filter dams (install) (type 3) (506-7003)LF70$90.00$95.00$85.00$78.00$89.00$80.00$105.00
83Rock filter dams (remove) (506-7011)LF340$14.50$12.00$11.00$11.00$12.00$50.00$16.00
84Construction exits (install) (type 1) (506-7020)SY777$32.00$40.00$41.00$31.00$34.50$31.50$48.00
85Construction exits (remove) (506-7024)SY777$12.00$10.00$13.65$9.00$10.00$15.75$14.00
86Temporary sediment control fence (install) (506-7039)LF2,328$4.00$4.00$4.50$3.20$3.60$4.00$4.00
87Temporary sediment control fence (remove) (506-7041)LF2,328$1.25$1.10$1.10$0.95$1.10$2.00$1.00
88Biodegradable erosion control logs (install) (12") (506-7044)LF500$7.00$6.00$8.00$5.50$5.85$6.00$6.00
89Biodegradable erosion control logs (remove) (506-7046)LF500$1.25$1.30$1.75$1.10$1.25$3.00$1.00
90Constructing detours (508-7001)SY4,218$79.00$90.00$115.00$89.00$117.40$105.00$100.00
91Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF6,150$80.00$56.00$50.40$46.00$45.00$17.50$85.00
92Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF2,960$53.00$80.00$44.00$51.00$41.34$14.50$79.00
93Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF80$65.00$83.00$31.50$84.00$48.81$43.50$78.00
94Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF5,160$15.00$10.00$15.00$9.00$14.25$8.75$20.00
95Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF2,940$15.00$9.00$12.00$4.80$13.82$8.75$17.50
96Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF60$17.50$7.00$12.00$35.00$23.34$26.25$17.50
97Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF6,150$17.50$12.00$22.00$11.00$7.00$13.50$18.00
98Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF2,960$17.50$12.00$16.00$13.00$17.26$12.50$17.50
99Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF80$17.50$15.00$16.00$25.00$21.13$37.50$17.50
100Concrete curb (mono) (type II) (529-7007)LF411$14.00$2.80$8.40$11.00$3.02$10.00$20.00
101Concrete curb & gutter (type II) (529-7009)LF10$55.00$53.00$52.50$81.00$71.10$200.00$200.00
102Mill rumble strips (asphalt) (shoulder) (533-7001)LF6,671$0.25$2.10$1.00$0.85$1.45$2.00$2.25
103Fill milled asphalt rumble strips (shoulder) (533-7005)LF6,671$2.25$14.50$14.00$9.50$1.00$15.00$19.00
104Metal W-beam guard fence (timber post) (540-7001)LF1,500$24.00$24.00$24.15$20.00$23.00$25.00$25.50
105Metal beam guard fence trans (thrie-beam) (540-7005)EACH9$2,200.00$1,900.00$1,890.00$1,580.00$1,800.00$3,000.00$2,000.00
106Downstream anchor terminal section (540-7015)EACH4$1,200.00$1,300.00$1,260.00$1,050.00$1,200.00$1,500.00$1,350.00
107Remove metal beam guard fence (542-7001)LF2,866$3.00$2.70$2.63$2.20$2.50$5.00$3.00
108Remove downstream anchor terminal (542-7003)EACH3$260.00$160.00$200.00$131.00$150.00$200.00$170.00
109RM metal beam guard fence trans (thrie-beam) (542-7004)EACH8$400.00$210.00$200.00$175.00$200.00$250.00$225.00
110Cable barrier system (install)(TL-3) (543-7001)LF2,688$18.00$22.00$25.00$19.00$21.75$33.00$24.25
111Cable barrier terminal sec (install)(TL-3) (543-7017)EACH2$4,500.00$4,100.00$4,250.00$3,540.00$4,040.00$5,500.00$4,500.00
112Cable barrier (remove) (543-7037)LF2,620$3.00$3.10$3.15$2.60$3.00$8.00$3.50
113Cable barrier terminal section (remove) (543-7038)EACH2$1,200.00$310.00$500.00$263.00$300.00$2,750.00$350.00
114Guardrail end treatment (install) (544-7001)EACH4$3,200.00$3,100.00$3,150.00$2,630.00$3,000.00$3,300.00$3,325.00
115Guardrail end treatment (remove) (544-7003)EACH2$275.00$260.00$275.00$219.00$250.00$275.00$280.00
116Crash cushion attenuator (remove) (545-7004)EACH6$1,200.00$820.00$2,500.00$1,880.00$2,752.07$750.00$3,425.00
117Crash cushion attenuator (install)(R)(N)(TL3) (545-7010)EACH1$27,000$28,000$25,500$26,610$21,350$30,000$7,000.00
118Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH6$10,500$8,500.00$10,000$9,570.00$8,232.90$9,000.00$7,000.00
119Pipe underdrains (type 6) (6") (556-7006)LF5,548$40.00$23.00$20.00$37.00$47.14$33.00$30.00
120Aluminum signs (type A) (636-7001)SF9$36.00$30.00$45.50$31.00$29.35$80.00$51.00
121Aluminum signs (type G) (636-7002)SF341$32.25$30.00$40.75$31.00$29.00$45.00$43.00
122Aluminum signs (type O) (636-7003)SF1,080.25$45.00$30.00$40.00$30.00$29.00$40.00$43.00
123Replace existing aluminum signs(type O) (636-7006)SF170$36.50$40.00$44.32$31.00$39.35$42.00$47.00
124Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH7$750.00$720.00$950.00$626.00$798.00$800.00$1,050.00
125Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH12$850.00$850.00$1,150.00$736.00$903.00$925.00$1,225.00
126Install small roadside sign support and assembly TYS80(2)SA(P) (644-7048)EACH3$1,800.00$2,200.00$2,000.00$1,880.00$2,340.00$2,100.00$2,150.00
127In bridge MNT clearance sign assembly(type N) (644-7061)EACH2$2,500.00$3,200.00$3,000.00$2,190.00$3,170.00$2,750.00$3,250.00
128Remove SM RD SN sup&AM (644-7073)EACH9$105.00$160.00$140.00$131.00$179.00$250.00$155.00
129Install LRSS (struct steel) (647-7001)LB1,594.50$8.12$7.00$9.00$11.00$6.65$10.00$10.00
130Remove lrsa (647-7003)EACH4$675.00$720.00$1,100.00$1,750.00$714.00$1,000.00$1,200.00
131Remove lrsa (foundation only)(24 in) (647-7006)EACH1$850.00$1,400.00$1,300.00$1,310.00$1,500.00$1,000.00$1,400.00
132Install overhead sign support(25 FT cant) (650-7025)EACH1$48,800$36,000$33,000$29,350$35,647$40,000$35,000
133Install overhead sign support(30 FT cant) (650-7032)EACH1$50,500$36,000$34,137$29,350$34,380$42,500$36,500
134Install overhead sign support(40 FT cant) (650-7045)EACH1$55,000$49,000$40,900$36,790$48,865$50,000$43,500
135Install overhead sign support(80 FT BRDG) (650-7089)EACH1$100,000$69,000$64,000$59,570$68,837$85,000$67,500
136Remove overhd sign sup (650-7193)EACH1$10,000$4,700.00$6,800.00$13,140$4,635.00$11,000$7,500.00
137Remove overhd sign sup (sign only) (650-7194)EACH1$1,200.00$1,000.00$3,150.00$876.00$955.00$2,750.00$3,500.00
138Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003)EACH26$80.00$48.00$75.00$53.00$55.93$60.00$50.00
139Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH10$8.00$21.00$22.50$13.00$16.68$25.00$23.00
140Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015)EACH19$15.00$21.00$40.00$13.00$51.67$25.00$23.00
141Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031)EACH16$11.00$21.00$30.00$13.00$14.09$25.00$23.00
142Install delineator assembly (D-SY)SZ 1(BRF)GF1 (658-7034)EACH4$2.00$21.00$50.00$13.00$51.67$25.00$23.00
143Work zone pavement marking removing (W)6"(broken) (662-7065)LF3,334$1.20$1.00$1.31$0.95$1.25$1.33$1.50
144Work zone pavement marking removing (W)6"(solid) (662-7068)LF15,730$0.80$1.00$1.15$0.95$1.10$1.17$1.25
145Work zone pavement marking removing (W)8"(solid) (662-7072)LF2,244$2.00$1.70$2.10$1.70$2.00$2.13$2.25
146Work zone pavement marking removing (Y)6"(solid) (662-7100)LF15,130$0.80$0.90$1.15$0.90$1.10$1.17$1.25
147Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF3,443$1.25$1.00$1.15$0.90$1.10$1.17$1.25
148Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027)LF639$2.10$3.10$4.75$3.10$4.50$4.79$5.00
149Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF1,907$4.00$3.10$4.50$3.10$4.25$4.53$4.75
150Reflectorized pavement marking type I (W)(number)(100MIL) (666-7063)EACH6$150.00$230.00$100.00$226.00$96.00$102.24$110.00
151All-wther PM type I (W)6"(solid)(100MIL) (666-7309)LF8,995$0.85$0.60$1.00$0.55$0.95$1.01$1.05
152All-wther PM type I (W)6"(broken)(100MIL) (666-7310)LF1,974$1.50$0.60$1.05$0.55$1.00$1.07$1.15
153All-wther PM type I (Y)6"(solid)(100MIL) (666-7315)LF10,267$0.85$0.60$1.00$0.55$0.95$1.01$1.05
154Pavement sler 6" (666-7347)LF13,643$0.40$0.30$0.32$0.30$0.30$0.32$0.35
155Pavement sler 8" (666-7348)LF2,427$1.00$0.35$0.32$0.35$0.30$0.32$0.35
156Pavement sler 12" (666-7350)LF2,304$5.00$0.45$2.10$0.40$2.00$2.13$2.25
157Pavement sler (number) (666-7367)EACH3$25.00$26.00$42.00$25.00$40.00$42.60$45.00
158Reflectorized pavement marker type II-C-R (672-7006)EACH411$4.50$4.20$5.00$4.10$4.75$5.06$5.50
159Eliminating existing PM & markers (6") (677-7002)LF53,814$0.50$0.60$0.75$0.55$0.50$0.53$0.55
160Eliminating existing PM & markers (8") (677-7004)LF2,408$1.25$0.75$1.00$0.70$0.75$0.80$0.85
161Eliminating existing PM & markers (12") (677-7006)LF663$2.00$2.10$2.00$2.10$1.75$1.86$2.00
162Eliminating existing PM & markers (exit gore) (677-7017)EACH1$500.00$930.00$1,050.00$929.00$1,000.00$1,065.00$1,150.00
163Pavement surface preparation for marking (6") (678-7002)LF7,593$0.50$0.25$0.25$0.20$0.20$0.21$0.25
164Pavement surface preparation for marking (8") (678-7004)LF1,016$2.00$0.21$0.30$0.20$0.25$0.27$0.30
165Pavement surface preparation for marking (12") (678-7006)LF242$4.00$0.42$1.75$0.40$1.50$1.60$1.75
166Pavement surface preparation for marking (number) (678-7015)EACH3$35.00$10.50$32.00$11.00$30.00$31.95$34.00
167Pavement surface preparation for marking (RPM) (678-7033)EACH411$2.50$0.60$1.10$0.55$1.00$1.07$1.25
TxDOT contract A00062075: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy