TxDOT contract A00128458 bid tabulation
Construct New Road, SL 335 (NORTH OF FM 2186 to NORTH OF ARDEN ROAD). Let by Texas DOT on August 5, 2026, Randall, Amarillo District. 5 bids received; low bid $42,220,204 by J. Lee Milligan, Inc., -16% against the engineer's estimate of $50,287,232.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 225
- Data through
- 19 NOV 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J. Lee Milligan, Inc. | $42,220,204 | Low | -16% |
| 2 | L A Fuller & Sons Construction, LTD. | $44,477,635 | +5.0% | -12% |
| 3 | Ragle Construction, Inc. | $48,810,035 | +16% | -3.0% |
| 4 | Gilvin-Terrill, LTD. | $51,748,003 | +23% | +3.0% |
Engineer's estimate: $50,287,232.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. J. Lee Milligan, Inc. | 2. L A Fuller & Sons Construction, LTD. | 3. Ragle Construction, Inc. | 4. Gilvin-Terrill, LTD. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7003) | SY | 57 | $25.00 | $25.00 | $23.55 | $20.00 | $20.00 |
| 2 | Removing concrete (medians) (104-7008) | SY | 588 | $45.00 | $20.00 | $33.35 | $13.00 | $20.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 211 | $20.00 | $28.00 | $36.65 | $20.00 | $20.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 824 | $25.00 | $17.00 | $45.15 | $15.00 | $20.00 |
| 5 | Removing concrete (curb & gutter) (104-7017) | LF | 3,681 | $15.00 | $4.00 | $14.25 | $7.50 | $10.00 |
| 6 | Remove (8") TRT/untrt base & asphalt pavement (105-7028) | SY | 326 | $10.00 | $14.00 | $26.60 | $8.50 | $25.00 |
| 7 | Remove (19") TRT/untrt base & asphalt pavement (105-7039) | SY | 1,811 | $19.00 | $16.00 | $21.75 | $12.00 | $25.00 |
| 8 | Excavation (roadway) (110-7001) | CY | 3,888 | $30.00 | $8.00 | $15.70 | $65.00 | $47.00 |
| 9 | Embankment (final)(DC)(type B) (132-7004) | CY | 230,572 | $12.00 | $25.00 | $25.00 | $15.00 | $47.00 |
| 10 | Embankment (final)(DC)(type C1) (132-7008) | CY | 3,940 | $40.00 | $14.00 | $25.15 | $17.50 | $47.00 |
| 11 | Drill seed (temporary_warm_cool) (164-7047) | ACRE | 13.81 | $1,000.00 | $650.00 | $922.90 | $800.00 | $750.00 |
| 12 | Hydro mulch seed (permanent_rural_clay) (164-7050) | ACRE | 13.81 | $2,600.00 | $2,850.00 | $2,588.25 | $2,800.00 | $3,000.00 |
| 13 | Vegetative watering (168-7001) | TGL | 1,128 | $55.00 | $18.00 | $36.55 | $35.00 | $30.00 |
| 14 | FL BS(compacted in place)(type A,B or D GR4)(12") (247-7134) | SY | 3,482 | $41.00 | $41.00 | $40.30 | $35.00 | $30.00 |
| 15 | Cement (275-7001) | TON | 589 | $310.00 | $255.00 | $279.85 | $220.00 | $250.00 |
| 16 | Cement TRT (existing material)(8") (275-7003) | SY | 54,520 | $5.50 | $3.65 | $3.65 | $3.75 | $10.00 |
| 17 | Prime coat (multi option) (310-7015) | GAL | 833 | $6.00 | $5.45 | $8.40 | $7.50 | $6.00 |
| 18 | D-GR HMA type-B PG64-22 (341-7001) | TON | 393 | $140.00 | $150.00 | $278.90 | $210.00 | $160.00 |
| 19 | D-GR HMA type-B PG64-28 (341-7005) | TON | 0 | $110.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 20 | SP mixes SP-D sac-A PG70-28 (344-7057) | TON | 7,241 | $170.00 | $145.00 | $185.00 | $190.00 | $200.00 |
| 21 | Plane & text asphalt concrete pavement(2") (354-7019) | SY | 61,087 | $3.00 | $3.65 | $2.25 | $1.90 | $3.00 |
| 22 | Planing asphalt concrete pavement(4") (354-7053) | SY | 107 | $6.00 | $30.00 | $24.45 | $12.25 | $15.50 |
| 23 | Concrete pavement (CRCP) (13") (360-7007) | SY | 0 | $173.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 24 | Concrete pavement(transition slab) (13") (360-7036) | SY | 0 | $300.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 25 | Cut & restoring pavement (400-7006) | SY | 31 | $200.00 | $115.00 | $233.10 | $175.00 | $135.00 |
| 26 | Cem stabil BKFL (400-7010) | CY | 600 | $175.00 | $180.00 | $216.25 | $150.00 | $200.00 |
| 27 | Flowable backfill (401-7001) | CY | 76 | $280.00 | $215.00 | $210.55 | $290.00 | $200.00 |
| 28 | Trench excavation protection (402-7001) | LF | 4,552 | $20.00 | $25.00 | $2.50 | $2.50 | $6.00 |
| 29 | Drilled shaft (18 in) (416-7002) | LF | 360 | $150.00 | $100.00 | $100.70 | $60.00 | $80.00 |
| 30 | Drilled shaft (36 in) (416-7006) | LF | 1,488 | $375.00 | $176.00 | $253.85 | $175.00 | $195.00 |
| 31 | Drilled shaft (48 in) (416-7008) | LF | 908 | $440.00 | $375.00 | $435.35 | $300.00 | $320.00 |
| 32 | Drilled shaft (sign mounts) (48 in) (416-7032) | LF | 82 | $300.00 | $680.00 | $575.00 | $500.00 | $500.00 |
| 33 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 840 | $1,000.00 | $850.00 | $690.00 | $600.00 | $600.00 |
| 34 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 20 | $330.00 | $325.00 | $258.75 | $225.00 | $225.00 |
| 35 | Drilled shaft (traffic signal pole) (24 in) (416-7042) | LF | 60 | $250.00 | $260.00 | $184.00 | $160.00 | $160.00 |
| 36 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 30 | $500.00 | $460.00 | $299.00 | $260.00 | $260.00 |
| 37 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 88 | $750.00 | $625.00 | $575.00 | $500.00 | $500.00 |
| 38 | Class C concrete (abutment) (420-7012) | CY | 142.80 | $1,550.00 | $1,800.00 | $1,857.75 | $1,200.00 | $1,500.00 |
| 39 | Class C concrete (cap) (420-7022) | CY | 122.80 | $1,900.00 | $1,425.00 | $2,014.00 | $1,150.00 | $1,500.00 |
| 40 | Class C concrete (column) (420-7038) | CY | 129.40 | $1,900.00 | $1,150.00 | $1,759.85 | $1,250.00 | $1,500.00 |
| 41 | Class C concrete (rail foundation) (420-7052) | CY | 33 | $800.00 | $650.00 | $1,087.10 | $505.00 | $650.00 |
| 42 | Reinforced concrete slab (422-7001) | SF | 41,796 | $42.50 | $25.50 | $30.00 | $26.00 | $30.00 |
| 43 | Approach slab (422-7013) | CY | 170 | $925.00 | $860.00 | $972.80 | $700.00 | $1,500.00 |
| 44 | Retaining wall (MSE) (423-7001) | SF | 96,735 | $112.00 | $52.00 | $58.75 | $120.00 | $60.00 |
| 45 | Prestressed concrete girder (TX54) (425-7005) | LF | 3,486 | $335.00 | $310.00 | $400.00 | $270.00 | $290.00 |
| 46 | Prestressed concrete girder (TX62) (425-7006) | LF | 1,911 | $350.00 | $340.00 | $425.00 | $305.00 | $310.00 |
| 47 | Riprap (concrete)(4 in) (432-7001) | CY | 175.20 | $750.00 | $710.00 | $730.65 | $600.00 | $600.00 |
| 48 | Riprap (concrete)(5 in) (432-7002) | CY | 495 | $800.00 | $600.00 | $508.15 | $540.00 | $550.00 |
| 49 | Riprap (concrete)(CL A) (432-7004) | CY | 0 | $780.99 | $0.00 | $0.00 | $0.00 | $0.00 |
| 50 | Riprap (concrete)(flume) (432-7012) | CY | 40 | $750.00 | $950.00 | $678.30 | $580.00 | $800.00 |
| 51 | Riprap (mow strip)(5 in) (432-7014) | CY | 227 | $750.00 | $710.00 | $537.60 | $540.00 | $600.00 |
| 52 | Rail (type SSTR) (450-7024) | LF | 7,969 | $103.00 | $105.00 | $75.00 | $65.00 | $100.00 |
| 53 | Rail (handrail)(type F) (450-7063) | LF | 453 | $150.00 | $170.00 | $147.10 | $145.00 | $150.00 |
| 54 | Sealed expansion joint (5 in) (SEJ - M) (454-7005) | LF | 212 | $280.00 | $350.00 | $407.90 | $220.00 | $235.00 |
| 55 | RC pipe (CL III)(18 in) (464-7003) | LF | 593 | $130.00 | $145.00 | $78.10 | $80.00 | $220.00 |
| 56 | RC pipe (CL III)(24 in) (464-7005) | LF | 7,379 | $170.00 | $175.00 | $97.15 | $100.00 | $150.00 |
| 57 | RC pipe (CL III)(30 in) (464-7007) | LF | 62 | $400.00 | $395.00 | $159.85 | $140.00 | $190.00 |
| 58 | RC pipe (CL V)(24 in) (464-7034) | LF | 314 | $270.00 | $260.00 | $320.55 | $190.00 | $175.00 |
| 59 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 38 | $8,000.00 | $4,250.00 | $7,928.85 | $4,350.00 | $6,000.00 |
| 60 | Inlet (complete)(PSL)(RC)(3FTX3FT) (465-7070) | EACH | 20 | $9,000.00 | $5,450.00 | $9,577.90 | $4,575.00 | $7,000.00 |
| 61 | Inlet (complete)(PSL)(RC)(4FTX4FT) (465-7071) | EACH | 3 | $12,000 | $7,950.00 | $11,530 | $6,175.00 | $8,500.00 |
| 62 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 25 | $10,000 | $6,525.00 | $10,737 | $5,400.00 | $8,000.00 |
| 63 | Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128) | EACH | 2 | $12,000 | $6,800.00 | $11,299 | $6,000.00 | $8,000.00 |
| 64 | Inlet(complete)(PSL)(SFG)(4FTX4FT-4FTX4FT) (465-7147) | EACH | 5 | $12,000 | $8,300.00 | $11,909 | $6,500.00 | $9,000.00 |
| 65 | Inlet(complete)(PSL)(SFG)(3FTX5FT-3FTX5FT) (465-7148) | EACH | 3 | $12,000 | $8,600.00 | $11,421 | $6,125.00 | $8,500.00 |
| 66 | Inlet (complete) (rwi) (type II) (465-7349) | EACH | 34 | $7,500.00 | $15,250 | $10,056 | $8,500.00 | $8,500.00 |
| 67 | Inlet (complete)(rwi)(type I) (465-7353) | EACH | 2 | $7,000.00 | $14,000 | $9,219.05 | $8,500.00 | $7,500.00 |
| 68 | Adjusting inlets (479-7002) | EACH | 9 | $5,000.00 | $3,800.00 | $20,388 | $1,150.00 | $12,000 |
| 69 | Removing structure (inlet) (496-7002) | EACH | 4 | $1,100.00 | $2,750.00 | $3,012.55 | $625.00 | $3,200.00 |
| 70 | Removing structure (set) (496-7004) | EACH | 1 | $1,100.00 | $1,430.00 | $1,617.85 | $625.00 | $3,200.00 |
| 71 | Removing structure (pipe) (496-7007) | LF | 42 | $50.00 | $70.00 | $77.05 | $25.00 | $20.00 |
| 72 | Mobilization (500-7001) | LS | 1 | $4,500,000 | $4,644,800 | $4,432,453 | $4,900,000 | $5,105,000 |
| 73 | Barricades, signs and traffic handling (502-7001) | MO | 26 | $41,500 | $35,000 | $7,897.25 | $113,615 | $100,000 |
| 74 | Portable changeable message sign (503-7002) | EACH | 4 | $14,000 | $25,000 | $25,000 | $60,000 | $18,500 |
| 75 | TMA (stationary) (505-7001) | DAY | 380 | $200.00 | $425.00 | $428.70 | $300.00 | $525.00 |
| 76 | TMA (mobile operation) (505-7002) | HR | 96 | $100.00 | $87.00 | $94.05 | $125.00 | $95.00 |
| 77 | Temporary sediment control fence (install) (506-7039) | LF | 1,000 | $5.00 | $10.00 | $9.40 | $5.00 | $5.00 |
| 78 | Temporary sediment control fence (remove) (506-7041) | LF | 1,000 | $2.00 | $5.00 | $2.85 | $1.25 | $1.00 |
| 79 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 3,592 | $5.50 | $7.00 | $11.80 | $6.00 | $6.00 |
| 80 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,592 | $2.00 | $3.00 | $1.60 | $1.50 | $2.00 |
| 81 | Constructing detours (508-7001) | SY | 678 | $200.00 | $76.00 | $155.15 | $135.00 | $60.00 |
| 82 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 3,805 | $145.00 | $128.25 | $135.00 | $200.00 | $70.00 |
| 83 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 680 | $110.00 | $55.00 | $130.60 | $150.00 | $110.00 |
| 84 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 20 | $110.00 | $55.00 | $141.15 | $150.00 | $110.00 |
| 85 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 1,360 | $13.00 | $27.00 | $20.85 | $7.50 | $15.00 |
| 86 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 40 | $13.00 | $27.00 | $20.65 | $12.50 | $15.00 |
| 87 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 680 | $25.00 | $30.00 | $21.25 | $18.00 | $15.00 |
| 88 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 20 | $25.00 | $30.00 | $34.40 | $60.00 | $15.00 |
| 89 | Permanent CTB (tran SSCB to SSTR) (mod) (514-7038) | LF | 50 | $700.00 | $220.00 | $291.50 | $240.00 | $200.00 |
| 90 | Colored textured concrete (5") (527-7002) | SY | 1,581 | $100.00 | $80.60 | $91.50 | $95.00 | $80.00 |
| 91 | Concrete curb (mono) (type I) (529-7006) | LF | 0 | $20.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 92 | Concrete curb & gutter (type I) (529-7008) | LF | 901 | $44.00 | $31.50 | $37.75 | $31.50 | $30.00 |
| 93 | Concrete curb & gutter (type II) (529-7009) | LF | 3,140 | $44.00 | $29.30 | $36.70 | $29.50 | $30.00 |
| 94 | Concrete curb (type C1) (529-7016) | LF | 710 | $125.00 | $63.00 | $19.45 | $70.00 | $60.00 |
| 95 | Concrete curb (type F1) (529-7017) | LF | 145 | $165.00 | $108.50 | $137.45 | $140.00 | $100.00 |
| 96 | Driveways (concrete) (530-7006) | SY | 220 | $150.00 | $216.50 | $191.40 | $110.00 | $130.00 |
| 97 | Driveways (ACP) (530-7010) | SY | 333 | $85.00 | $95.00 | $77.40 | $95.00 | $110.00 |
| 98 | Concrete sidewalks (4") (531-7001) | SY | 14,765 | $93.00 | $81.50 | $123.00 | $48.00 | $75.00 |
| 99 | Concrete sidewalks (6") (531-7003) | SY | 562 | $108.00 | $102.00 | $143.70 | $70.00 | $90.00 |
| 100 | Curb ramps (type 1) (531-7015) | SY | 193 | $250.00 | $160.00 | $172.00 | $160.00 | $145.00 |
| 101 | Curb ramps (type 7) (531-7020) | SY | 175 | $250.00 | $160.00 | $347.00 | $150.00 | $145.00 |
| 102 | Curb ramps (type 21) (531-7023) | SY | 16 | $250.00 | $175.00 | $376.60 | $205.00 | $170.00 |
| 103 | Curb ramps (type 22) (531-7024) | SY | 52 | $250.00 | $175.00 | $381.00 | $185.00 | $170.00 |
| 104 | Metal W-beam guard fence (steel post) (540-7002) | LF | 450 | $40.00 | $40.00 | $42.55 | $32.75 | $37.00 |
| 105 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 1 | $3,000.00 | $3,200.00 | $3,487.75 | $2,275.00 | $3,025.00 |
| 106 | Guardrail end treatment (install) (544-7001) | EACH | 3 | $3,200.00 | $4,200.00 | $4,715.00 | $3,550.00 | $4,100.00 |
| 107 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $500.00 | $325.00 | $575.00 | $200.00 | $500.00 |
| 108 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 2 | $25,000 | $38,000 | $34,385 | $25,000 | $37,400 |
| 109 | Pipe underdrains (type 6) (6") (556-7006) | LF | 5,875 | $20.00 | $16.75 | $34.00 | $27.50 | $16.00 |
| 110 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 8 | $1,000.00 | $2,120.00 | $1,725.00 | $1,500.00 | $1,500.00 |
| 111 | In RD IL (U/P) (type 2) (150W EQ) LED (610-7016) | EACH | 4 | $2,500.00 | $2,650.00 | $1,725.00 | $1,500.00 | $1,500.00 |
| 112 | In RD IL (type ST) 40T-8 (250W EQ) LED (610-7164) | EACH | 2 | $6,000.00 | $5,900.00 | $6,900.00 | $6,000.00 | $6,000.00 |
| 113 | HI MST IL pole (150 FT)(100 MPH) (613-7006) | EACH | 20 | $65,000 | $68,200 | $74,750 | $65,000 | $65,000 |
| 114 | LED HI MST IL asm(6 fixt) (type A)SHLD (614-7009) | EACH | 20 | $37,000 | $46,150 | $57,500 | $50,000 | $50,000 |
| 115 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 13,980 | $16.00 | $16.30 | $13.80 | $12.00 | $12.00 |
| 116 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 2,465 | $30.00 | $23.90 | $19.55 | $17.00 | $17.00 |
| 117 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 80 | $25.00 | $32.55 | $19.55 | $17.00 | $17.00 |
| 118 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 465 | $50.00 | $41.25 | $19.55 | $17.00 | $17.00 |
| 119 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 10 | $50.00 | $36.90 | $24.15 | $21.00 | $21.00 |
| 120 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 265 | $80.00 | $54.25 | $25.30 | $22.00 | $22.00 |
| 121 | Conduit (RM) (1") (618-7072) | LF | 360 | $40.00 | $35.80 | $26.45 | $23.00 | $23.00 |
| 122 | Install ground box (W/secure lid) (624-7014) | EACH | 64 | $2,400.00 | $2,335.00 | $2,760.00 | $2,400.00 | $2,400.00 |
| 123 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 5 | $12,000 | $9,225.00 | $8,970.00 | $7,800.00 | $7,800.00 |
| 124 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $10,000 | $8,140.00 | $8,050.00 | $7,000.00 | $7,000.00 |
| 125 | Aluminum signs (type A) (636-7001) | SF | 156.50 | $40.00 | $44.00 | $46.00 | $40.00 | $40.00 |
| 126 | Aluminum signs (type O) (636-7003) | SF | 231 | $40.00 | $54.25 | $36.80 | $32.00 | $32.00 |
| 127 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 10 | $920.00 | $1,165.00 | $897.00 | $780.00 | $700.00 |
| 128 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 12 | $1,000.00 | $1,355.00 | $1,095.95 | $953.00 | $750.00 |
| 129 | Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012) | EACH | 15 | $1,150.00 | $1,355.00 | $1,082.15 | $941.00 | $760.00 |
| 130 | Install small roadside sign support and assembly type 10BWG(2)SB(P) (644-7019) | EACH | 2 | $1,300.00 | $2,200.00 | $1,857.25 | $1,615.00 | $1,350.00 |
| 131 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 4 | $1,000.00 | $1,450.00 | $1,242.00 | $1,080.00 | $960.00 |
| 132 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 1 | $1,200.00 | $1,550.00 | $1,151.15 | $1,001.00 | $980.00 |
| 133 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 1 | $1,200.00 | $1,520.00 | $1,151.15 | $1,001.00 | $960.00 |
| 134 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,400.00 | $2,000.00 | $1,813.55 | $1,577.00 | $1,400.00 |
| 135 | Install small roadside sign support and assembly TYS80(1)SB(P) (644-7037) | EACH | 2 | $1,200.00 | $1,475.00 | $1,267.30 | $1,102.00 | $955.00 |
| 136 | Install small roadside sign support and assembly TYS80(1)SB(T) (644-7040) | EACH | 1 | $1,400.00 | $1,725.00 | $1,518.00 | $1,320.00 | $970.00 |
| 137 | Install small roadside sign support and assembly TYS80(1)SB(U) (644-7042) | EACH | 1 | $1,600.00 | $2,035.00 | $1,889.45 | $1,643.00 | $1,350.00 |
| 138 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 4 | $3,000.00 | $3,475.00 | $2,070.00 | $1,800.00 | $1,800.00 |
| 139 | Install small roadside sign support and assembly (rail mount) (644-7063) | EACH | 2 | $4,000.00 | $8,250.00 | $7,225.45 | $6,283.00 | $2,000.00 |
| 140 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 11 | $920.00 | $795.00 | $784.30 | $682.00 | $450.00 |
| 141 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 5 | $920.00 | $895.00 | $910.80 | $792.00 | $550.00 |
| 142 | Remove SM RD SN sup&AM (644-7073) | EACH | 33 | $150.00 | $165.00 | $164.05 | $118.00 | $100.00 |
| 143 | Install overhead sign support(25 FT cant)(circ tube) (650-7024) | EACH | 2 | $90,000 | $76,000 | $83,375 | $115,500 | $72,500 |
| 144 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2 (658-7001) | EACH | 7 | $30.00 | $43.50 | $48.30 | $45.00 | $75.00 |
| 145 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 64 | $20.00 | $60.00 | $48.30 | $45.00 | $42.00 |
| 146 | Install delineator assembly (D-SY)SZ 1(yflx)GF2 (658-7021) | EACH | 3 | $37.00 | $43.50 | $48.30 | $45.00 | $55.00 |
| 147 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 19 | $20.00 | $60.00 | $48.30 | $45.00 | $42.00 |
| 148 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 39 | $20.00 | $60.00 | $48.30 | $45.00 | $42.00 |
| 149 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 41 | $150.00 | $165.00 | $135.70 | $90.00 | $100.00 |
| 150 | Install object marker assembly (OM-4)(TWT)wap (658-7073) | EACH | 18 | $150.00 | $485.00 | $562.35 | $489.00 | $300.00 |
| 151 | Remove delin & object marker assms (658-7078) | EACH | 38 | $25.00 | $40.00 | $131.25 | $50.00 | $15.00 |
| 152 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 45 | $2.00 | $33.00 | $14.95 | $13.00 | $12.00 |
| 153 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 7 | $2.00 | $33.00 | $14.95 | $13.00 | $14.00 |
| 154 | Install OM SM RD sign (2-OM-PW)Y (658-7319) | EACH | 2 | $2.00 | $38.00 | $20.70 | $18.00 | $13.00 |
| 155 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 145 | $0.50 | $2.20 | $2.30 | $0.35 | $2.00 |
| 156 | Work zone pavement marking non-removing (W)6"(DOT) (662-7006) | LF | 91 | $1.00 | $2.20 | $2.30 | $0.40 | $2.00 |
| 157 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 2,861 | $1.00 | $2.20 | $2.30 | $0.56 | $2.00 |
| 158 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 786 | $6.00 | $13.55 | $14.38 | $4.00 | $12.50 |
| 159 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 12 | $150.00 | $245.00 | $258.75 | $60.00 | $225.00 |
| 160 | Work zone pavement marking non-removing (W)(double arrow) (662-7019) | EACH | 2 | $150.00 | $352.50 | $373.75 | $90.00 | $325.00 |
| 161 | Work zone pavement marking non-removing (W)(uturn arrow) (662-7027) | EACH | 4 | $250.00 | $434.00 | $460.00 | $90.00 | $400.00 |
| 162 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 16 | $200.00 | $434.00 | $460.00 | $70.00 | $400.00 |
| 163 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 940 | $0.40 | $2.20 | $2.30 | $0.35 | $2.00 |
| 164 | Work zone pavement marking non-removing (Y)12"(solid) (662-7040) | LF | 404 | $4.00 | $9.25 | $9.78 | $2.00 | $8.50 |
| 165 | Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017) | LF | 471 | $1.30 | $2.20 | $2.30 | $1.00 | $2.00 |
| 166 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 5,160 | $1.00 | $2.20 | $2.30 | $0.87 | $2.00 |
| 167 | Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029) | LF | 1,449 | $3.00 | $5.45 | $5.75 | $2.90 | $5.00 |
| 168 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 786 | $13.00 | $10.85 | $11.50 | $6.80 | $10.00 |
| 169 | Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041) | EACH | 16 | $300.00 | $245.00 | $258.75 | $155.00 | $225.00 |
| 170 | Reflectorized pavement marking type I(W)(double arrow)(090MIL) (666-7044) | EACH | 2 | $375.00 | $355.00 | $373.75 | $200.00 | $325.00 |
| 171 | Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065) | EACH | 16 | $300.00 | $355.00 | $373.75 | $175.00 | $325.00 |
| 172 | Reflectorized pavement marking type I (Y)12"(solid)(090MIL) (666-7116) | LF | 490 | $3.00 | $6.00 | $6.33 | $3.00 | $5.50 |
| 173 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 3,529 | $0.70 | $1.65 | $1.73 | $0.69 | $1.50 |
| 174 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 5,463 | $0.65 | $1.65 | $1.73 | $0.69 | $1.50 |
| 175 | Reflectorized pavement marking type I (W)12"(DOT)(100MIL) (666-7424) | LF | 470 | $3.00 | $4.35 | $4.60 | $3.00 | $4.00 |
| 176 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 177 | $8.00 | $7.05 | $7.48 | $4.00 | $6.50 |
| 177 | Eliminating existing PM & markers (4") (677-7001) | LF | 967 | $0.50 | $1.90 | $2.01 | $1.00 | $1.75 |
| 178 | Eliminating existing PM & markers (8") (677-7004) | LF | 405 | $0.75 | $2.20 | $2.30 | $1.00 | $2.00 |
| 179 | Eliminating existing PM & markers (12") (677-7006) | LF | 186 | $1.00 | $3.25 | $3.45 | $1.79 | $3.00 |
| 180 | Eliminating existing PM & markers (24") (677-7008) | LF | 573 | $4.00 | $5.45 | $5.75 | $2.90 | $5.00 |
| 181 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 6 | $40.00 | $136.00 | $143.75 | $59.00 | $125.00 |
| 182 | Eliminating existing PM & markers (word) (677-7015) | EACH | 7 | $40.00 | $165.00 | $172.50 | $59.00 | $150.00 |
| 183 | Eliminating existing PM & markers (18")(yld tri) (677-7023) | EACH | 6 | $1.00 | $35.00 | $143.75 | $19.00 | $30.00 |
| 184 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $40,000 | $40,000 | $51,750 | $45,000 | $45,000 |
| 185 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 12 | $345.00 | $420.00 | $402.50 | $350.00 | $350.00 |
| 186 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 4 | $345.00 | $420.00 | $402.50 | $350.00 | $350.00 |
| 187 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 12 | $345.00 | $420.00 | $402.50 | $350.00 | $350.00 |
| 188 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 6 | $345.00 | $420.00 | $402.50 | $350.00 | $350.00 |
| 189 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 12 | $345.00 | $420.00 | $402.50 | $350.00 | $350.00 |
| 190 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 4 | $345.00 | $420.00 | $402.50 | $350.00 | $350.00 |
| 191 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 12 | $1,150.00 | $1,060.00 | $690.00 | $600.00 | $600.00 |
| 192 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 14 | $280.00 | $245.00 | $287.50 | $250.00 | $250.00 |
| 193 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 2 | $280.00 | $300.00 | $299.00 | $260.00 | $260.00 |
| 194 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 3,397 | $4.00 | $5.45 | $3.45 | $3.00 | $3.00 |
| 195 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 840 | $4.00 | $7.60 | $4.83 | $4.20 | $4.20 |
| 196 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 1,765 | $8.00 | $8.95 | $9.20 | $8.00 | $8.00 |
| 197 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 3,840 | $3.00 | $3.25 | $3.45 | $3.00 | $3.00 |
| 198 | Removing RDSD FLSH BCN AM (solar PWRD) (685-7006) | EACH | 10 | $1,200.00 | $815.00 | $1,035.00 | $900.00 | $900.00 |
| 199 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 2 | $27,500 | $18,700 | $18,975 | $16,500 | $16,500 |
| 200 | Ins traffic signal PL AM(S)1 arm(60')lum (686-7063) | EACH | 4 | $49,000 | $43,000 | $43,700 | $38,000 | $38,000 |
| 201 | Pedestrian pole assembly (687-7001) | EACH | 10 | $6,700.00 | $3,525.00 | $1,610.00 | $1,400.00 | $1,400.00 |
| 202 | Pedestrian detect push button (APS) (688-7001) | EACH | 12 | $1,000.00 | $1,115.00 | $977.50 | $850.00 | $850.00 |
| 203 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $6,500.00 | $5,075.00 | $4,140.00 | $3,600.00 | $3,600.00 |
| 204 | Full - width mowing (730-7019) | CYC | 4 | $500.00 | $5,575.00 | $6,562.40 | $3,600.00 | $1,000.00 |
| 205 | Anti-graffiti coating (permnent-type II) (740-7005) | SF | 77,686 | $1.10 | $1.40 | $1.65 | $1.27 | $1.27 |
| 206 | Underseal course (3006-7001) | GAL | 8,522 | $7.00 | $7.25 | $8.55 | $5.50 | $9.00 |
| 207 | Subsurface util locate (non-paved area) (5061-7001) | EACH | 8 | $1,750.00 | $1,200.00 | $1,380.00 | $1,700.00 | $1,200.00 |
| 208 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | $11,500 | $10,600 | $9,775.00 | $8,500.00 | $8,500.00 |
| 209 | RVDS (presence detection only) (6008-7001) | EACH | 4 | $8,000.00 | $9,600.00 | $6,900.00 | $6,000.00 | $6,000.00 |
| 210 | RVDS (presence and advance detection) (6008-7003) | EACH | 2 | $11,500 | $10,750 | $8,625.00 | $7,500.00 | $7,500.00 |
| 211 | Dead end roadway barricade (6012-7001) | LF | 48 | $120.00 | $50.00 | $185.05 | $150.00 | $130.00 |
| 212 | Long channel mount curb sys (remove) (6039-7003) | LF | 351 | $15.00 | $5.00 | $14.25 | $3.75 | $5.25 |
| 213 | Prefb PV MK W/wnty type B (W)(6")(solid) (6064-7002) | LF | 7,058 | $12.50 | $9.25 | $9.78 | $11.00 | $8.50 |
| 214 | Prefb PV MK W/wnty type B (Y)(6")(solid) (6064-7006) | LF | 7,062 | $12.50 | $9.25 | $9.78 | $11.00 | $8.50 |
| 215 | Aluminum electrical cond (#2 XHHW) (6071-7002) | LF | 43,950 | $4.00 | $3.25 | $2.30 | $2.00 | $2.00 |
| 216 | Aluminum electrical cond (#6 XHHW) (6071-7003) | LF | 120 | $2.00 | $2.55 | $2.02 | $1.75 | $1.75 |
| 217 | Aluminum electrical cond (#8 XHHW) (6071-7004) | LF | 9,720 | $1.90 | $2.45 | $2.02 | $1.75 | $1.75 |
| 218 | FL BS(compacted in place)(type A,B or D GR4)(6") (247-7065) | SY | 51,544 | $27.00 | $17.00 | $12.75 | $26.00 | $20.00 |
| 219 | Prime coat (MC-30) (310-7004) | GAL | 12,885 | $8.00 | $5.00 | $6.55 | $5.20 | $6.00 |
| 220 | D-GR HMA type D PG64-22 (341-7043) | TON | 5,673 | $181.00 | $130.00 | $155.00 | $200.00 | $180.00 |
| 221 | SP mixes SP-B PG70-28 (344-7006) | TON | 26,924 | $201.00 | $135.00 | $155.00 | $170.00 | $175.00 |
| 222 | Tack coat (344-7077) | GAL | 20,103 | $8.00 | $7.75 | $8.35 | $5.20 | $6.00 |
| 223 | Stone-MTRX-asphalt SMA-D sac-A PG76-28 (346-7010) | TON | 8,303 | $225.00 | $185.00 | $201.65 | $230.00 | $220.00 |
| 224 | Tack coat (346-7028) | GAL | 13,082 | $8.00 | $7.75 | $8.50 | $5.20 | $6.00 |
| 225 | Concrete curb (type III) (529-7004) | LF | 1,150 | $23.38 | $21.00 | $49.00 | $20.00 | $30.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.