TxDOT contract A00191471 bid tabulation
Construct Frontage Roads, SH 99 (Westheimer Parkway to Cinco Ranch Blvd). Let by Texas DOT on August 5, 2026, Fort Bend, Houston District. 8 bids received; low bid $25,954,400 by James Construction Group, LLC, -18% against the engineer's estimate of $31,713,552.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 231
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | James Construction Group, LLC | $25,954,400 | Low | -18% |
| 2 | Harper Brothers Construction LLC | $26,217,697 | +1.0% | -17% |
| 3 | MC2 Civil, LLC | $26,274,848 | +1.0% | -17% |
| 4 | Ser Construction Partners, LLC | $26,945,564 | +4.0% | -15% |
| 5 | Granite Construction Company | $29,417,878 | +13% | -7.0% |
| 6 | R Construction Civil, LLC | $29,643,710 | +14% | -7.0% |
| 7 | Pulice Construction, Inc. | $30,924,993 | +19% | -2.0% |
| 8 | V&S Construction Company LLC | $31,594,907 | +22% | 0.0% |
Engineer's estimate: $31,713,552.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. James Construction Group, LLC | 2. Harper Brothers Construction LLC | 3. MC2 Civil, LLC | 4. Ser Construction Partners, LLC | 5. Granite Construction Company | 6. R Construction Civil, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 118.18 | $4,000.00 | $6,097.40 | $3,050.00 | $750.00 | $1,650.00 | $14,380 | $900.00 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 17,365 | $10.00 | $4.20 | $8.50 | $9.00 | $6.40 | $4.20 | $9.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 1,165 | $20.00 | $3.00 | $10.00 | $9.00 | $6.40 | $3.70 | $3.15 |
| 4 | Removing concrete (sawcut) (104-7020) | LF | 1,567 | $11.00 | $15.00 | $6.50 | $12.00 | $20.00 | $6.50 | $9.75 |
| 5 | Removing concrete (retaining walls) (104-7025) | SY | 39 | $55.00 | $105.00 | $70.00 | $23.90 | $31.00 | $38.00 | |
| 6 | Removing concrete (wingwall) (104-7028) | CY | 7 | $800.00 | $157.68 | $1,100.00 | $200.00 | $119.90 | $260.00 | $67.00 |
| 7 | Removing concrete (rail) (104-7036) | LF | 961 | $10.00 | $9.00 | $9.00 | $10.00 | $5.40 | $9.25 | $13.00 |
| 8 | Removing concrete (flume) (104-7041) | SY | 443 | $14.00 | $5.00 | $16.00 | $5.00 | $6.40 | $5.00 | $12.00 |
| 9 | Remove (7"-13") TRT/untrt base & asphalt pavement (105-7058) | SY | 20,822 | $6.35 | $3.68 | $1.50 | $4.00 | $5.60 | $2.25 | $3.85 |
| 10 | Excavation (roadway) (110-7001) | CY | 33,714 | $10.00 | $12.36 | $13.00 | $15.00 | $20.00 | $10.00 | $23.00 |
| 11 | Embankment (final)(DC)(type C) (132-7006) | CY | 46,644 | $35.00 | $15.85 | $7.00 | $4.50 | $17.60 | $25.00 | $25.00 |
| 12 | Embankment (final)(DC)(type E)(csbe_rwall impr) (132-7038) | CY | 940 | $52.00 | $57.11 | $70.00 | $70.00 | $65.10 | $71.00 | $100.00 |
| 13 | Compost manuf topsoil (4") (161-7002) | SY | 33,175 | $2.20 | $0.95 | $2.00 | $1.00 | $0.80 | $3.00 | $1.00 |
| 14 | Block sodding (162-7002) | SY | 58,194 | $3.50 | $3.39 | $3.39 | $4.00 | $4.00 | $1.20 | $3.50 |
| 15 | Straw or hay mulch (162-7003) | SY | 16,912 | $0.75 | $0.10 | $0.10 | $0.35 | $0.30 | $0.30 | $0.10 |
| 16 | Broadcast seed (temporary_warm) (164-7005) | SY | 225 | $0.18 | $0.18 | $0.60 | $0.50 | $0.11 | $0.19 | |
| 17 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 33,175 | $0.33 | $0.18 | $0.18 | $0.10 | $0.10 | $0.06 | $0.19 |
| 18 | Drill seed (temporary_warm_cool) (164-7015) | SY | 4,471 | $0.20 | $0.20 | $0.25 | $0.20 | $3.29 | $0.20 | |
| 19 | Fertilizer (166-7001) | ACRE | 19.86 | $1,400.00 | $625.00 | $625.00 | $700.00 | $581.90 | $20.00 | $630.00 |
| 20 | Vegetative watering (168-7001) | TGL | 2,383 | $50.00 | $28.00 | $28.00 | $20.00 | $31.20 | $17.50 | $39.00 |
| 21 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 549.49 | $350.00 | $352.95 | $400.00 | $360.00 | $354.60 | $350.00 | $350.00 |
| 22 | Lime TRT (existing material)(6") (260-7006) | SY | 40,762 | $4.00 | $4.51 | $3.50 | $5.00 | $6.30 | $4.50 | $3.15 |
| 23 | Cem TRT(PLNT MX)(CL N)(type E)(GR 4)(6") (276-7343) | SY | 40,762 | $18.00 | $18.67 | $18.00 | $19.00 | $15.70 | $16.00 | $18.50 |
| 24 | Asphalt TRT base (GR 4)(PG 64) (292-7014) | TON | 2,288.47 | $112.00 | $145.00 | $130.00 | $140.00 | $122.20 | $150.00 | $182.00 |
| 25 | Concrete pavement (CRCP) (10") (360-7004) | SY | 13,247 | $83.85 | $85.00 | $88.00 | $83.60 | $92.00 | $93.00 | |
| 26 | Concrete pavement (CRCP) (12") (360-7006) | SY | 24,296 | $102.00 | $92.68 | $90.00 | $98.00 | $91.40 | $96.00 | $102.00 |
| 27 | Struct excavation (400-7001) | CY | 2,788 | $30.00 | $8.54 | $10.00 | $5.00 | $19.10 | $18.00 | $23.00 |
| 28 | Struct excavation (box) (400-7002) | CY | 5,755 | $10.03 | $9.00 | $5.00 | $20.00 | $0.01 | $24.00 | |
| 29 | Struct excavation (pipe) (400-7003) | CY | 2,581 | $18.00 | $10.03 | $10.00 | $5.00 | $16.50 | $0.01 | $24.00 |
| 30 | Cem stabil BKFL (400-7010) | CY | 4,623 | $75.00 | $58.45 | $65.00 | $55.00 | $59.10 | $58.00 | $76.00 |
| 31 | Cement stab backfill (inlet or MH) (400-7011) | CY | 268 | $55.00 | $57.38 | $200.00 | $55.00 | $75.00 | $58.00 | $76.00 |
| 32 | Trench excavation protection (402-7001) | LF | 5,933 | $6.00 | $1.07 | $5.00 | $5.00 | $0.10 | $2.00 | $5.50 |
| 33 | Temporary special shoring (403-7001) | SF | 19,291 | $23.00 | $44.40 | $15.00 | $1.00 | $5.00 | $50.00 | $32.00 |
| 34 | Drilled shaft (18 in) (416-7002) | LF | 160 | $150.00 | $151.04 | $115.00 | $200.00 | $115.70 | $95.00 | $125.00 |
| 35 | Drilled shaft (30 in) (416-7005) | LF | 6,873 | $250.00 | $197.76 | $175.00 | $210.00 | $217.20 | $200.00 | $200.00 |
| 36 | Drilled shaft (36 in) (416-7006) | LF | 286 | $285.00 | $289.11 | $390.00 | $400.00 | $503.80 | $370.00 | $375.00 |
| 37 | Drilled shaft (54 in) (416-7009) | LF | 404 | $675.00 | $458.16 | $950.00 | $970.00 | $1,098.90 | $950.00 | $800.00 |
| 38 | Drilled shaft (sign mounts) (42 in) (416-7031) | LF | 150 | $545.00 | $475.00 | $462.00 | $600.00 | $478.00 | $480.00 | $500.00 |
| 39 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 104 | $250.00 | $250.00 | $220.25 | $280.00 | $228.50 | $255.00 | $265.00 |
| 40 | Sound wall (419-7001) | SF | 106,040 | $56.00 | $32.87 | $32.00 | $32.00 | $34.80 | $35.00 | $40.00 |
| 41 | Class C concrete (abutment)(extend) (420-7016) | CY | 74.60 | $2,215.00 | $1,405.83 | $1,500.00 | $2,800.00 | $1,460.70 | $1,400.00 | $900.00 |
| 42 | Class C concrete (cap) (420-7022) | CY | 32.60 | $1,865.00 | $2,316.62 | $2,000.00 | $2,200.00 | $1,691.10 | $1,550.00 | $1,050.00 |
| 43 | Class C concrete (column) (420-7038) | CY | 26.20 | $1,440.00 | $1,191.83 | $2,200.00 | $1,500.00 | $1,200.20 | $2,100.00 | $1,250.00 |
| 44 | Class C concrete (rail foundation) (420-7052) | CY | 125 | $440.97 | $400.00 | $150.00 | $537.70 | $700.00 | $420.00 | |
| 45 | Class C concrete (sign column) (420-7057) | CY | 105.50 | $1,600.00 | $1,562.20 | $1,500.00 | $2,000.00 | $1,309.70 | $1,450.00 | $1,400.00 |
| 46 | Class C concrete (sign footing) (420-7151) | CY | 39.20 | $2,500.00 | $976.65 | $1,600.00 | $1,500.00 | $1,332.90 | $950.00 | $1,050.00 |
| 47 | Reinforced concrete slab (extend slab) (422-7003) | SF | 9,222 | $40.00 | $38.94 | $29.00 | $38.00 | $32.00 | $50.00 | $29.00 |
| 48 | Approach slab (422-7013) | CY | 52.40 | $850.00 | $705.33 | $950.00 | $900.00 | $578.90 | $915.24 | $800.00 |
| 49 | Retaining wall (MSE) (423-7001) | SF | 17,935 | $65.00 | $36.39 | $73.00 | $60.00 | $38.80 | $56.00 | $49.00 |
| 50 | Retaining wall (cast-in-place) (423-7016) | SF | 714 | $126.00 | $70.34 | $140.00 | $130.00 | $89.90 | $115.00 | $73.00 |
| 51 | Prestressed concrete girder (TX46) (425-7004) | LF | 641 | $225.00 | $221.90 | $250.00 | $232.00 | $282.80 | $315.00 | $210.00 |
| 52 | Prestressed concrete girder (TX54) (425-7005) | LF | 641 | $251.00 | $224.29 | $270.00 | $234.00 | $273.50 | $316.00 | $220.00 |
| 53 | Riprap (concrete)(4 in) (432-7001) | CY | 508.13 | $500.00 | $409.16 | $500.00 | $500.00 | $471.10 | $440.00 | $630.00 |
| 54 | Riprap (concrete)(5 in) (432-7002) | CY | 210 | $550.00 | $400.23 | $510.00 | $600.00 | $405.10 | $440.00 | $810.00 |
| 55 | Riprap (concrete)(CL B) (432-7005) | CY | 2.80 | $800.00 | $833.27 | $800.00 | $1,000.00 | $1,260.30 | $1,550.00 | $895.00 |
| 56 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 261.80 | $540.00 | $472.30 | $500.00 | $800.00 | $2,000.00 | $725.00 | $950.00 |
| 57 | Riprap (concrete)(flume) (432-7012) | CY | 239 | $600.00 | $648.28 | $600.00 | $650.00 | $590.60 | $600.00 | $610.00 |
| 58 | Riprap (mow strip)(4 in) (432-7013) | CY | 302 | $600.00 | $677.31 | $700.00 | $600.00 | $533.10 | $600.00 | $735.00 |
| 59 | Bedding material (3 in) (432-7049) | CY | 33 | $140.00 | $104.82 | $450.00 | $150.00 | $127.50 | $90.00 | $85.00 |
| 60 | Rail (type SSTR) (450-7024) | LF | 5,679 | $75.00 | $60.40 | $86.23 | $70.00 | $55.30 | $78.00 | $113.00 |
| 61 | Rail (type PR11) (450-7044) | LF | 355 | $145.00 | $108.28 | $120.00 | $120.00 | $104.80 | $140.00 | $195.00 |
| 62 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 59 | $250.00 | $214.83 | $250.00 | $300.00 | $219.50 | $265.00 | $206.00 |
| 63 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 2,636 | $250.00 | $255.26 | $300.00 | $280.00 | $271.50 | $300.00 | $258.00 |
| 64 | Concrete box culvert (8 FT X 3 FT) (462-7020) | LF | 2,155 | $648.40 | $700.00 | $690.00 | $617.80 | $685.00 | $610.00 | |
| 65 | Concrete box culvert (8 FT X 7 FT)(extend) (462-7079) | LF | 153 | $988.43 | $1,400.00 | $1,400.00 | $922.00 | $891.00 | $820.00 | |
| 66 | Concrete box culvert (8 FT X 8 FT)(extend) (462-7080) | LF | 25 | $1,500.00 | $1,672.05 | $2,800.00 | $2,200.00 | $1,396.00 | $1,950.00 | $950.00 |
| 67 | RC pipe (CL III)(18 in) (464-7003) | LF | 143 | $100.00 | $64.97 | $95.00 | $88.00 | $94.00 | $86.00 | $90.00 |
| 68 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,860 | $100.00 | $79.85 | $110.00 | $108.00 | $102.80 | $97.00 | $80.00 |
| 69 | RC pipe (CL III)(30 in) (464-7007) | LF | 98 | $130.00 | $145.27 | $110.00 | $148.00 | $122.70 | $114.00 | $142.00 |
| 70 | RC pipe (CL III)(36 in) (464-7009) | LF | 75 | $154.58 | $250.00 | $226.00 | $140.60 | $148.00 | $165.00 | |
| 71 | RC pipe (CL III)(42 in) (464-7010) | LF | 122 | $166.05 | $260.00 | $254.00 | $187.70 | $190.00 | $270.00 | |
| 72 | RC pipe (CL V)(24 in) (464-7034) | LF | 46 | $152.00 | $115.78 | $160.00 | $150.00 | $107.30 | $124.00 | $190.00 |
| 73 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 4 | $7,000.00 | $4,165.09 | $7,000.00 | $3,500.00 | $2,768.40 | $4,900.00 | $4,550.00 |
| 74 | Junction box(complete)(PJB)(4FTX4FT) (465-7006) | EACH | 1 | $8,000.00 | $4,496.65 | $6,900.00 | $4,500.00 | $3,937.30 | $5,200.00 | $5,950.00 |
| 75 | Inlet (complete)(pod)(FG)(3FTX3FT) (465-7048) | EACH | 4 | $5,000.00 | $5,238.94 | $5,000.00 | $7,500.00 | $3,224.40 | $6,500.00 | $2,700.00 |
| 76 | Junct box (complete)(JB)(7FT X 7FT)(FTW) (465-7295) | EACH | 1 | $17,900 | $14,874 | $15,000 | $20,000 | $9,871.80 | $11,700 | $13,700 |
| 77 | Inlet (complete)(curb)(type C1)(none)(hou) (465-7309) | EACH | 18 | $6,940.00 | $5,705.08 | $7,500.00 | $9,000.00 | $7,580.70 | $6,900.00 | $5,500.00 |
| 78 | Inlet (complete)(curb)(type C1)(left)(hou) (465-7310) | EACH | 4 | $8,500.00 | $5,811.80 | $7,500.00 | $8,000.00 | $7,678.40 | $7,000.00 | $6,400.00 |
| 79 | Inlet (complete)(curb)(type C1)(right)(hou) (465-7311) | EACH | 7 | $7,040.00 | $8,111.44 | $9,500.00 | $10,000 | $7,951.30 | $9,200.00 | $6,550.00 |
| 80 | Inlet (complete)(curb)(type C1)(both)(hou) (465-7312) | EACH | 9 | $9,500.00 | $9,992.43 | $11,000 | $12,000 | $9,604.10 | $10,300 | $7,750.00 |
| 81 | Inlet (complete)(type A)(hou) (465-7313) | EACH | 1 | $4,034.57 | $5,000.00 | $4,000.00 | $3,732.10 | $5,400.00 | $3,700.00 | |
| 82 | Inlet (complete)(type aad)(hou) (465-7315) | EACH | 10 | $7,000.00 | $6,516.78 | $10,000 | $6,000.00 | $7,542.80 | $7,700.00 | $5,000.00 |
| 83 | Inlet (complete)(type azr)(hou) (465-7318) | EACH | 2 | $10,000 | $5,036.02 | $9,500.00 | $7,000.00 | $6,868.30 | $6,700.00 | $5,700.00 |
| 84 | Manh (complete)(type A)(hou) (465-7320) | EACH | 11 | $5,000.00 | $5,006.91 | $9,000.00 | $6,000.00 | $4,607.40 | $6,600.00 | $7,300.00 |
| 85 | Wingwall (PW - 1) (HW=13 FT) (466-7183) | EACH | 1 | $45,000 | $107,383 | $80,000 | $90,000 | $144,842 | $98,000 | $19,000 |
| 86 | Wingwall (PW - 2) (HW=16 FT) (466-7200) | EACH | 1 | $110,072 | $110,000 | $150,000 | $205,477 | $152,000 | $154,000 | |
| 87 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 1 | $1,500.00 | $1,192.99 | $1,500.00 | $1,500.00 | $1,168.60 | $1,620.00 | $2,250.00 |
| 88 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $1,900.00 | $1,551.29 | $2,000.00 | $1,800.00 | $1,683.60 | $1,950.00 | $2,800.00 |
| 89 | Pre-cast trench drain (in concrete pavemnt) (474-7022) | LF | 120 | $132.03 | $280.00 | $300.00 | $458.80 | $283.00 | $450.00 | |
| 90 | Adjusting inlets (479-7002) | EACH | 1 | $1,700.00 | $1,548.99 | $1,600.00 | $2,000.00 | $296.60 | $1,900.00 | $500.00 |
| 91 | Removing structure (inlet) (496-7002) | EACH | 9 | $900.00 | $730.78 | $990.00 | $1,000.00 | $557.20 | $870.00 | $790.00 |
| 92 | Removing structure (set) (496-7004) | EACH | 3 | $592.43 | $850.00 | $350.00 | $156.00 | $840.00 | $2,400.00 | |
| 93 | Removing structure (headwall) (496-7006) | EACH | 1 | $1,300.71 | $9,000.00 | $14,000 | $4,130.30 | $1,850.00 | $2,700.00 | |
| 94 | Removing structure (pipe) (496-7007) | LF | 286 | $30.00 | $11.56 | $15.00 | $20.00 | $13.60 | $24.00 | $37.00 |
| 95 | Removing structure (box culvert) (496-7008) | LF | 71 | $63.13 | $70.00 | $75.00 | $120.70 | $55.00 | $98.00 | |
| 96 | Remove STR (rail) (496-7017) | LF | 580 | $22.47 | $10.00 | $10.00 | $9.90 | $22.00 | $93.00 | |
| 97 | Removing structure (ret wall) (496-7019) | LF | 607 | $125.00 | $62.93 | $10.50 | $20.00 | $28.60 | $15.00 | $55.00 |
| 98 | Mobilization (500-7001) | LS | 1 | $2,832,504 | $2,500,000 | $2,155,000 | $2,500,000 | $2,500,000 | $2,930,000 | $2,800,000 |
| 99 | Barricades, signs and traffic handling (502-7001) | MO | 14 | $10,000 | $8,884.63 | $5,000.00 | $12,600 | $20,179 | $19,000 | $8,650.00 |
| 100 | Portable changeable message sign (503-7002) | EACH | 6 | $7,000.00 | $5,347.76 | $10,000 | $20,000 | $11,536 | $12,500 | $31,000 |
| 101 | TMA (stationary) (505-7001) | DAY | 48 | $250.00 | $239.40 | $300.00 | $250.00 | $312.40 | $191.67 | $735.00 |
| 102 | TMA (mobile operation) (505-7003) | DAY | 116 | $237.00 | $587.89 | $500.00 | $750.00 | $654.90 | $1,045.00 | $1,125.00 |
| 103 | Rock filter dams (install) (type 1) (506-7001) | LF | 25 | $30.00 | $30.00 | $40.00 | $39.10 | $42.69 | $32.00 | |
| 104 | Rock filter dams (install) (type 3) (506-7003) | LF | 100 | $42.00 | $43.00 | $110.00 | $111.20 | $53.79 | $44.00 | |
| 105 | Rock filter dams (install) (type 4) (506-7004) | LF | 20 | $85.00 | $48.00 | $48.00 | $50.00 | $51.50 | $54.56 | $50.00 |
| 106 | Rock filter dams (remove) (506-7011) | LF | 145 | $16.00 | $20.00 | $20.00 | $15.00 | $14.40 | $12.00 | $21.00 |
| 107 | Construction exits (install) (type 1) (506-7020) | SY | 738 | $30.00 | $30.00 | $30.00 | $40.00 | $30.80 | $27.00 | $31.00 |
| 108 | Construction exits (remove) (506-7024) | SY | 738 | $10.00 | $20.00 | $20.00 | $6.00 | $9.50 | $15.40 | $21.00 |
| 109 | Sandbags for erosion control (506-7035) | EACH | 28 | $15.00 | $5.00 | $5.00 | $20.00 | $20.10 | $0.32 | $5.00 |
| 110 | Temporary sediment control fence (install) (506-7039) | LF | 11,759 | $4.50 | $2.95 | $2.95 | $2.50 | $2.30 | $2.72 | $3.00 |
| 111 | Temporary sediment control fence (remove) (506-7041) | LF | 11,759 | $1.00 | $1.00 | $1.00 | $1.00 | $0.80 | $0.99 | $1.00 |
| 112 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 300 | $8.00 | $8.00 | $8.00 | $7.40 | $5.00 | $8.00 | |
| 113 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,396 | $8.00 | $8.50 | $8.50 | $8.00 | $7.10 | $6.80 | $9.00 |
| 114 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,696 | $1.90 | $2.00 | $2.00 | $1.00 | $0.80 | $1.00 | $2.00 |
| 115 | Constructing detours (508-7001) | SY | 1,592 | $110.00 | $125.73 | $150.00 | $92.00 | $99.90 | $110.14 | $125.00 |
| 116 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 8,329 | $25.00 | $10.98 | $11.00 | $13.00 | $15.50 | $9.13 | $28.00 |
| 117 | Portable concrete traffic barrier (des source)(low prof)(type 1) (512-7021) | LF | 6,240 | $20.00 | $9.76 | $12.00 | $13.00 | $14.00 | $8.75 | $26.00 |
| 118 | Portable concrete traffic barrier (des source)(low prof)(type 2) (512-7022) | LF | 180 | $25.00 | $8.54 | $20.00 | $13.00 | $15.50 | $20.92 | $49.00 |
| 119 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 5,779 | $10.00 | $5.61 | $8.00 | $9.00 | $10.20 | $5.70 | $9.00 |
| 120 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 5,040 | $10.00 | $3.51 | $7.00 | $9.00 | $10.90 | $4.52 | $8.00 |
| 121 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 120 | $14.50 | $3.51 | $8.00 | $9.00 | $14.20 | $10.28 | $11.00 |
| 122 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 8,329 | $18.00 | $10.86 | $11.00 | $10.00 | $15.50 | $8.17 | $20.00 |
| 123 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 6,240 | $12.00 | $9.66 | $11.50 | $10.00 | $14.00 | $7.19 | $6.00 |
| 124 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 180 | $28.00 | $9.66 | $24.00 | $10.00 | $15.50 | $18.41 | $7.00 |
| 125 | Concrete curb (mono) (type II) (529-7007) | LF | 14,017 | $10.00 | $3.62 | $7.00 | $5.00 | $3.80 | $3.41 | $10.00 |
| 126 | Concrete sidewalks (5") (531-7002) | SY | 8,231 | $80.00 | $58.48 | $75.00 | $63.00 | $62.20 | $48.84 | $84.00 |
| 127 | Metal W-beam guard fence (timber post) (540-7001) | LF | 450 | $28.00 | $25.50 | $28.50 | $32.00 | $34.50 | $25.62 | $42.00 |
| 128 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 1 | $1,750.00 | $1,750.00 | $2,450.00 | $2,500.00 | $2,369.00 | $1,758.42 | $3,050.00 |
| 129 | Remove metal beam guard fence (542-7001) | LF | 1,150 | $4.50 | $3.00 | $3.00 | $4.00 | $3.90 | $3.01 | $4.00 |
| 130 | Remove terminal anchor section (542-7002) | EACH | 2 | $310.00 | $200.00 | $250.00 | $250.00 | $463.50 | $200.96 | $300.00 |
| 131 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,170.00 | $3,500.00 | $3,650.00 | $4,000.00 | $3,914.00 | $3,516.84 | $5,100.00 |
| 132 | Guardrail end treatment (remove) (544-7003) | EACH | 7 | $300.00 | $200.00 | $200.00 | $350.00 | $358.40 | $200.96 | $450.00 |
| 133 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 5 | $3,000.00 | $3,000.00 | $4,950.00 | $1,600.00 | $1,512.00 | $3,858.72 | $1,585.00 |
| 134 | Crash cushion attenuator (remove) (545-7004) | EACH | 5 | $2,400.00 | $1,000.00 | $1,500.00 | $1,000.00 | $755.00 | $2,756.23 | $850.00 |
| 135 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 5 | $26,500 | $24,550 | $25,200 | $27,000 | $25,837 | $31,845 | $28,100 |
| 136 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 5 | $8,000.00 | $24,550 | $25,200 | $27,000 | $25,837 | $10,215 | $28,100 |
| 137 | Pipe underdrains (type 6) (6") (556-7006) | LF | 1,880 | $30.00 | $34.90 | $33.83 | $40.00 | $28.60 | $31.34 | $44.00 |
| 138 | Relocate RD IL asm (trans-base) (610-7004) | EACH | 7 | $1,325.00 | $2,695.00 | $1,400.00 | $2,796.80 | $1,338.38 | $1,400.00 | |
| 139 | Remove RD IL asm (trans-base) (610-7009) | EACH | 6 | $725.00 | $475.00 | $1,433.00 | $500.00 | $1,487.40 | $479.80 | $500.00 |
| 140 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 4 | $5,400.00 | $5,175.00 | $5,780.00 | $5,500.00 | $5,999.50 | $5,227.27 | $5,475.00 |
| 141 | In RD IL (type AL) 40T-8 (250W EQ) LED (610-7140) | EACH | 6 | $5,995.00 | $6,192.00 | $6,300.00 | $6,427.90 | $6,055.56 | $6,300.00 | |
| 142 | In RD IL (type SA) 50T-12 (400W EQ) LED (610-7200) | EACH | 8 | $5,400.00 | $5,675.00 | $6,378.00 | $6,000.00 | $6,620.40 | $5,732.32 | $6,000.00 |
| 143 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 720 | $15.00 | $11.15 | $5.95 | $12.00 | $6.20 | $11.26 | $12.00 |
| 144 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 2,055 | $12.00 | $11.25 | $6.36 | $13.00 | $6.60 | $11.36 | $12.00 |
| 145 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 4,360 | $20.00 | $11.75 | $11.92 | $14.00 | $12.40 | $11.87 | $12.00 |
| 146 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 50 | $18.85 | $12.40 | $21.00 | $12.90 | $19.04 | $20.00 | |
| 147 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 6,120 | $32.50 | $42.55 | $35.00 | $44.20 | $32.83 | $34.00 | |
| 148 | Conduit (RM) (2") (618-7078) | LF | 380 | $30.00 | $38.15 | $35.58 | $42.00 | $36.90 | $38.54 | $40.00 |
| 149 | ITS multi-duct CND (PVC-80)(bore) (619-7006) | LF | 12,180 | $37.50 | $42.49 | $40.00 | $44.10 | $37.88 | $39.00 | |
| 150 | Electrical conductor (no.14) insulated (620-7002) | LF | 6,710 | $1.55 | $0.57 | $1.70 | $0.60 | $1.57 | $1.60 | |
| 151 | Electrical conductor (no.12) bare (620-7003) | LF | 230 | $1.75 | $1.50 | $1.39 | $1.70 | $1.40 | $1.52 | $1.55 |
| 152 | Electrical conductor (no.12) insulated (620-7004) | LF | 460 | $1.80 | $1.60 | $1.45 | $1.80 | $1.50 | $1.62 | $1.65 |
| 153 | Electrical conductor (no.8) bare (620-7007) | LF | 7,855 | $2.00 | $2.20 | $1.20 | $2.40 | $1.20 | $2.22 | $2.35 |
| 154 | Electrical conductor (no.8) insulated (620-7008) | LF | 15,910 | $2.50 | $2.25 | $1.51 | $2.50 | $1.60 | $2.27 | $2.35 |
| 155 | Electrical conductor (no.6) bare (620-7009) | LF | 8,850 | $2.35 | $1.66 | $2.60 | $1.70 | $2.37 | $2.50 | |
| 156 | Electrical conductor (no.6) insulated (620-7010) | LF | 4,425 | $2.65 | $2.20 | $2.80 | $2.30 | $2.68 | $2.80 | |
| 157 | ITS GND box(pcast) type 1 (243636)W/aprn (623-7002) | EACH | 14 | $4,475.00 | $5,160.95 | $4,800.00 | $5,357.70 | $4,520.20 | $4,700.00 | |
| 158 | Remove ITS ground box (623-7041) | EACH | 9 | $475.00 | $906.00 | $500.00 | $940.10 | $479.80 | $480.00 | |
| 159 | Ground box type A (122311)W/apron (624-7002) | EACH | 8 | $1,400.00 | $1,295.00 | $946.03 | $1,400.00 | $982.10 | $1,308.08 | $1,350.00 |
| 160 | Ground box type C (162911)W/apron (624-7006) | EACH | 5 | $1,925.00 | $1,104.03 | $2,100.00 | $1,146.10 | $1,944.44 | $2,000.00 | |
| 161 | Remove ground box (624-7013) | EACH | 11 | $375.00 | $255.00 | $486.00 | $300.00 | $504.50 | $257.58 | $270.00 |
| 162 | Relocate electrical services (628-7001) | EACH | 1 | $2,595.00 | $3,605.00 | $2,750.00 | $3,741.80 | $2,621.21 | $2,700.00 | |
| 163 | Remove electrical services (628-7002) | EACH | 2 | $815.00 | $725.00 | $1,241.00 | $750.00 | $1,287.90 | $732.33 | $740.00 |
| 164 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 1 | $11,000 | $8,450.00 | $9,800.00 | $9,000.00 | $9,978.80 | $8,535.35 | $8,600.00 |
| 165 | Elc SRV type A 240/480 060(SS)SS(E)GC(O) (628-7054) | EACH | 2 | $9,800.00 | $10,327 | $11,000 | $10,719 | $9,898.99 | $10,300 | |
| 166 | Elc SRV type A 240/480 060(SS)SS(E)SP(U) (628-7058) | EACH | 2 | $7,500.00 | $7,195.00 | $7,964.00 | $8,000.00 | $8,266.90 | $7,267.68 | $7,600.00 |
| 167 | Aluminum signs (type G) (636-7002) | SF | 30 | $38.40 | $65.00 | $35.00 | $66.80 | $65.55 | $38.00 | |
| 168 | Aluminum signs (type O) (636-7003) | SF | 857.25 | $50.00 | $35.75 | $32.76 | $38.00 | $34.00 | $33.35 | $38.00 |
| 169 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 16 | $630.00 | $615.00 | $615.00 | $750.00 | $710.70 | $780.00 | $940.00 |
| 170 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 18 | $800.00 | $825.00 | $825.00 | $1,000.00 | $1,014.60 | $820.00 | $1,250.00 |
| 171 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 1 | $830.00 | $985.00 | $985.00 | $1,500.00 | $1,030.00 | $1,000.00 | $1,900.00 |
| 172 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 4 | $875.00 | $1,050.00 | $1,050.00 | $1,300.00 | $2,575.00 | $1,250.00 | $1,600.00 |
| 173 | Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049) | EACH | 1 | $1,800.00 | $1,950.00 | $1,950.00 | $2,800.00 | $721.00 | $2,200.00 | $3,500.00 |
| 174 | Remove SM RD SN sup&AM (644-7073) | EACH | 22 | $110.00 | $150.00 | $150.00 | $125.00 | $154.50 | $100.00 | $150.00 |
| 175 | Install LRSS (struct steel) (647-7001) | LB | 325 | $7.50 | $11.00 | $8.00 | $11.20 | $11.00 | $11.00 | |
| 176 | Relocate lrsa (647-7002) | EACH | 1 | $3,500.00 | $5,000.00 | $2,400.00 | $9,000.00 | $2,401.50 | $2,355.14 | $11,500 |
| 177 | Remove lrsa (647-7003) | EACH | 5 | $1,345.00 | $625.00 | $2,100.00 | $800.00 | $2,171.70 | $2,129.78 | $1,000.00 |
| 178 | Install overhead sign support(35 FT cant)(span only) (650-7041) | EACH | 1 | $25,000 | $23,385 | $31,000 | $24,000 | $32,133 | $31,512 | $24,000 |
| 179 | Install overhead sign support(40 FT cant)(span only) (650-7048) | EACH | 3 | $29,000 | $24,575 | $29,000 | $25,000 | $29,374 | $28,807 | $25,000 |
| 180 | Remove overhd sign sup (650-7193) | EACH | 4 | $12,000 | $4,250.00 | $6,702.79 | $4,500.00 | $6,958.40 | $6,823.92 | $4,400.00 |
| 181 | Remove overhd sign sup (sign only) (650-7194) | EACH | 2 | $2,180.00 | $1,775.00 | $776.78 | $2,000.00 | $806.40 | $790.80 | $1,800.00 |
| 182 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 35 | $6.00 | $25.00 | $25.00 | $25.00 | $206.00 | $15.00 | $33.00 |
| 183 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 18 | $30.00 | $35.00 | $35.00 | $30.00 | $206.00 | $22.00 | $40.00 |
| 184 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 6 | $12.00 | $25.00 | $25.00 | $25.00 | $206.00 | $15.00 | $32.00 |
| 185 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 6 | $35.00 | $25.00 | $35.00 | $30.00 | $206.00 | $22.00 | $42.00 |
| 186 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 9,041 | $1.50 | $1.65 | $2.87 | $1.75 | $1.70 | $1.67 | $3.65 |
| 187 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 30,161 | $1.00 | $1.65 | $1.28 | $1.75 | $1.70 | $1.67 | $1.60 |
| 188 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 1,331 | $1.50 | $2.25 | $2.30 | $2.40 | $2.30 | $2.27 | $2.80 |
| 189 | Work zone pavement marking removing (W)6"(BKN W/marker) (662-7080) | LF | 560 | $1.50 | $1.88 | $3.45 | $2.00 | $1.90 | $1.90 | $4.20 |
| 190 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 8 | $150.00 | $150.00 | $195.00 | $160.00 | $154.50 | $151.52 | $240.00 |
| 191 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 16,796 | $1.30 | $1.65 | $1.28 | $1.75 | $1.70 | $1.67 | $1.60 |
| 192 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 76 | $2.00 | $2.00 | $5.00 | $2.00 | $9.30 | $1.00 | $6.00 |
| 193 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 18,008 | $1.00 | $0.88 | $1.05 | $0.90 | $0.90 | $0.89 | $1.30 |
| 194 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 4,578 | $1.10 | $0.88 | $1.05 | $0.90 | $0.90 | $0.89 | $3.10 |
| 195 | Reflectorized pavement marking type III (W)(8")(solid) (666-7239) | LF | 4,510 | $2.00 | $1.25 | $2.50 | $1.40 | $1.30 | $1.26 | $3.10 |
| 196 | Reflectorized pavement marking type III (W)(12")(solid) (666-7242) | LF | 2,656 | $3.50 | $3.15 | $4.50 | $3.50 | $3.20 | $3.18 | $5.50 |
| 197 | Reflectorized pavement marking type III (W)(12")(DOT) (666-7243) | LF | 459 | $3.00 | $3.15 | $5.00 | $3.50 | $3.20 | $3.18 | $6.10 |
| 198 | Reflectorized pavement marking type III (W)(24")(solid) (666-7244) | LF | 62 | $7.60 | $8.00 | $10.00 | $9.00 | $8.20 | $8.08 | $12.50 |
| 199 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 12,568 | $1.20 | $0.88 | $1.05 | $0.90 | $0.90 | $0.89 | $1.30 |
| 200 | Reflectorized pavement marking type III (BLK)(6")(shadow) (666-7262) | LF | 3,411 | $0.90 | $0.89 | $1.05 | $1.00 | $0.90 | $0.90 | $1.30 |
| 201 | Pavement sler (arrow) (666-7353) | EACH | 8 | $20.00 | $50.00 | $5.00 | $55.00 | $51.50 | $50.51 | $6.10 |
| 202 | Pavement sler (word) (666-7354) | EACH | 7 | $25.00 | $50.00 | $5.00 | $55.00 | $51.50 | $50.51 | $6.10 |
| 203 | Pavement sler (double arrow) (666-7356) | EACH | 1 | $25.00 | $50.00 | $5.00 | $55.00 | $51.50 | $50.51 | $6.10 |
| 204 | Pavement sler (uturn arrow) (666-7358) | EACH | 2 | $30.00 | $50.00 | $5.00 | $55.00 | $51.50 | $50.51 | $6.10 |
| 205 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 7 | $250.00 | $250.00 | $267.42 | $275.00 | $257.50 | $252.53 | $330.00 |
| 206 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 1 | $400.00 | $300.00 | $362.34 | $325.00 | $309.00 | $303.03 | $440.00 |
| 207 | Prefabricated PM type C (W)(uturn arrow) (668-7096) | EACH | 2 | $300.00 | $275.00 | $373.98 | $300.00 | $283.30 | $277.78 | $460.00 |
| 208 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 9 | $315.00 | $250.00 | $318.12 | $275.00 | $257.50 | $252.53 | $390.00 |
| 209 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 637 | $6.00 | $7.00 | $6.00 | $7.50 | $7.20 | $7.07 | $7.50 |
| 210 | Eliminating existing PM & markers (6") (677-7002) | LF | 15,062 | $2.00 | $0.35 | $0.49 | $0.40 | $0.40 | $0.35 | $0.60 |
| 211 | Eliminating existing PM & markers (8") (677-7004) | LF | 1,822 | $2.00 | $0.40 | $0.98 | $0.50 | $0.40 | $0.40 | $1.25 |
| 212 | Eliminating existing PM & markers (12") (677-7006) | LF | 302 | $0.65 | $2.00 | $0.70 | $0.70 | $0.66 | $2.50 | |
| 213 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 2 | $25.00 | $70.00 | $25.00 | $25.80 | $25.26 | $89.00 | |
| 214 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 1 | $29.00 | $75.00 | $30.00 | $29.90 | $29.29 | $96.00 | |
| 215 | Eliminating existing PM & markers (word) (677-7015) | EACH | 2 | $25.00 | $75.00 | $25.00 | $25.80 | $25.26 | $95.00 | |
| 216 | Pavement surface preparation for marking (6") (678-7002) | LF | 37,375 | $1.25 | $0.03 | $0.02 | $0.03 | $0.10 | $0.03 | $0.03 |
| 217 | Pavement surface preparation for marking (8") (678-7004) | LF | 4,510 | $1.25 | $0.05 | $0.04 | $0.05 | $0.10 | $0.05 | $0.05 |
| 218 | Pavement surface preparation for marking (12") (678-7006) | LF | 3,115 | $1.25 | $0.10 | $0.08 | $0.10 | $0.10 | $0.10 | $0.10 |
| 219 | Pavement surface preparation for marking (24") (678-7008) | LF | 62 | $1.00 | $0.35 | $0.16 | $0.35 | $0.40 | $0.35 | $0.20 |
| 220 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 7 | $25.00 | $15.00 | $1.00 | $15.00 | $15.50 | $15.15 | $1.25 |
| 221 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 1 | $17.00 | $15.00 | $1.00 | $15.00 | $15.50 | $15.15 | $1.25 |
| 222 | Pavement surface preparation for marking (uturn arr) (678-7012) | EACH | 2 | $20.00 | $15.00 | $1.00 | $15.00 | $15.50 | $15.15 | $1.25 |
| 223 | Pavement surface preparation for marking (word) (678-7016) | EACH | 9 | $40.00 | $15.00 | $1.00 | $15.00 | $15.50 | $15.15 | $1.25 |
| 224 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 329 | $1.00 | $1.00 | $0.25 | $1.00 | $1.00 | $1.01 | $0.35 |
| 225 | Remove luminaire pole (690-7127) | EACH | 6 | $475.00 | $1,500.00 | $500.00 | $1,487.40 | $479.80 | $500.00 | |
| 226 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 84 | $100.00 | $300.00 | $600.00 | $175.00 | $463.50 | $325.00 | $450.00 |
| 227 | ITS pole MNT cab (type 2)(conf 2) (6011-7002) | EACH | 1 | $7,475.00 | $5,000.00 | $8,000.00 | $7,709.20 | $7,550.51 | $7,800.00 | |
| 228 | ITS pole (40 FT)(rem) (6011-7018) | EACH | 1 | $1,990.00 | $1,425.00 | $4,970.00 | $1,500.00 | $5,150.10 | $1,439.39 | $1,450.00 |
| 229 | FO CBL (96 SMF) (6027-7029) | LF | 12,060 | $6.05 | $4.23 | $6.50 | $4.40 | $6.11 | $6.20 | |
| 230 | Install wrong way driver detection sys (6038-7001) | EACH | 1 | $52,775 | $55,200 | $55,000 | $57,279 | $53,308 | $54,000 | |
| 231 | Remove wrong way driver detection sys (6038-7003) | EACH | 1 | $2,500.00 | $1,260.00 | $3,000.00 | $1,307.10 | $2,525.25 | $2,600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.