TxDOT contract A00191471 bid tabulation

Construct Frontage Roads, SH 99 (Westheimer Parkway to Cinco Ranch Blvd). Let by Texas DOT on August 5, 2026, Fort Bend, Houston District. 8 bids received; low bid $25,954,400 by James Construction Group, LLC, -18% against the engineer's estimate of $31,713,552.

Owner
Texas DOT
Letting
05 AUG 2026
Pay items
231
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1James Construction Group, LLC$25,954,400Low-18%
2Harper Brothers Construction LLC$26,217,697+1.0%-17%
3MC2 Civil, LLC$26,274,848+1.0%-17%
4Ser Construction Partners, LLC$26,945,564+4.0%-15%
5Granite Construction Company$29,417,878+13%-7.0%
6R Construction Civil, LLC$29,643,710+14%-7.0%
7Pulice Construction, Inc.$30,924,993+19%-2.0%
8V&S Construction Company LLC$31,594,907+22%0.0%
TxDOT contract A00191471: bids by rank

Engineer's estimate: $31,713,552.

Bid tabulation

LinePay itemUnitQuantityEstimate1. James Construction Group, LLC2. Harper Brothers Construction LLC3. MC2 Civil, LLC4. Ser Construction Partners, LLC5. Granite Construction Company6. R Construction Civil, LLC
1Preparing row (100-7002)STA118.18$4,000.00$6,097.40$3,050.00$750.00$1,650.00$14,380$900.00
2Removing concrete (pavement) (104-7001)SY17,365$10.00$4.20$8.50$9.00$6.40$4.20$9.00
3Removing concrete (riprap) (104-7006)SY1,165$20.00$3.00$10.00$9.00$6.40$3.70$3.15
4Removing concrete (sawcut) (104-7020)LF1,567$11.00$15.00$6.50$12.00$20.00$6.50$9.75
5Removing concrete (retaining walls) (104-7025)SY39$55.00$105.00$70.00$23.90$31.00$38.00
6Removing concrete (wingwall) (104-7028)CY7$800.00$157.68$1,100.00$200.00$119.90$260.00$67.00
7Removing concrete (rail) (104-7036)LF961$10.00$9.00$9.00$10.00$5.40$9.25$13.00
8Removing concrete (flume) (104-7041)SY443$14.00$5.00$16.00$5.00$6.40$5.00$12.00
9Remove (7"-13") TRT/untrt base & asphalt pavement (105-7058)SY20,822$6.35$3.68$1.50$4.00$5.60$2.25$3.85
10Excavation (roadway) (110-7001)CY33,714$10.00$12.36$13.00$15.00$20.00$10.00$23.00
11Embankment (final)(DC)(type C) (132-7006)CY46,644$35.00$15.85$7.00$4.50$17.60$25.00$25.00
12Embankment (final)(DC)(type E)(csbe_rwall impr) (132-7038)CY940$52.00$57.11$70.00$70.00$65.10$71.00$100.00
13Compost manuf topsoil (4") (161-7002)SY33,175$2.20$0.95$2.00$1.00$0.80$3.00$1.00
14Block sodding (162-7002)SY58,194$3.50$3.39$3.39$4.00$4.00$1.20$3.50
15Straw or hay mulch (162-7003)SY16,912$0.75$0.10$0.10$0.35$0.30$0.30$0.10
16Broadcast seed (temporary_warm) (164-7005)SY225$0.18$0.18$0.60$0.50$0.11$0.19
17Broadcast seed (temporary_warm_cool) (164-7007)SY33,175$0.33$0.18$0.18$0.10$0.10$0.06$0.19
18Drill seed (temporary_warm_cool) (164-7015)SY4,471$0.20$0.20$0.25$0.20$3.29$0.20
19Fertilizer (166-7001)ACRE19.86$1,400.00$625.00$625.00$700.00$581.90$20.00$630.00
20Vegetative watering (168-7001)TGL2,383$50.00$28.00$28.00$20.00$31.20$17.50$39.00
21Lime (com or QK)(slurry) or QK(dry) (260-7001)TON549.49$350.00$352.95$400.00$360.00$354.60$350.00$350.00
22Lime TRT (existing material)(6") (260-7006)SY40,762$4.00$4.51$3.50$5.00$6.30$4.50$3.15
23Cem TRT(PLNT MX)(CL N)(type E)(GR 4)(6") (276-7343)SY40,762$18.00$18.67$18.00$19.00$15.70$16.00$18.50
24Asphalt TRT base (GR 4)(PG 64) (292-7014)TON2,288.47$112.00$145.00$130.00$140.00$122.20$150.00$182.00
25Concrete pavement (CRCP) (10") (360-7004)SY13,247$83.85$85.00$88.00$83.60$92.00$93.00
26Concrete pavement (CRCP) (12") (360-7006)SY24,296$102.00$92.68$90.00$98.00$91.40$96.00$102.00
27Struct excavation (400-7001)CY2,788$30.00$8.54$10.00$5.00$19.10$18.00$23.00
28Struct excavation (box) (400-7002)CY5,755$10.03$9.00$5.00$20.00$0.01$24.00
29Struct excavation (pipe) (400-7003)CY2,581$18.00$10.03$10.00$5.00$16.50$0.01$24.00
30Cem stabil BKFL (400-7010)CY4,623$75.00$58.45$65.00$55.00$59.10$58.00$76.00
31Cement stab backfill (inlet or MH) (400-7011)CY268$55.00$57.38$200.00$55.00$75.00$58.00$76.00
32Trench excavation protection (402-7001)LF5,933$6.00$1.07$5.00$5.00$0.10$2.00$5.50
33Temporary special shoring (403-7001)SF19,291$23.00$44.40$15.00$1.00$5.00$50.00$32.00
34Drilled shaft (18 in) (416-7002)LF160$150.00$151.04$115.00$200.00$115.70$95.00$125.00
35Drilled shaft (30 in) (416-7005)LF6,873$250.00$197.76$175.00$210.00$217.20$200.00$200.00
36Drilled shaft (36 in) (416-7006)LF286$285.00$289.11$390.00$400.00$503.80$370.00$375.00
37Drilled shaft (54 in) (416-7009)LF404$675.00$458.16$950.00$970.00$1,098.90$950.00$800.00
38Drilled shaft (sign mounts) (42 in) (416-7031)LF150$545.00$475.00$462.00$600.00$478.00$480.00$500.00
39Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF104$250.00$250.00$220.25$280.00$228.50$255.00$265.00
40Sound wall (419-7001)SF106,040$56.00$32.87$32.00$32.00$34.80$35.00$40.00
41Class C concrete (abutment)(extend) (420-7016)CY74.60$2,215.00$1,405.83$1,500.00$2,800.00$1,460.70$1,400.00$900.00
42Class C concrete (cap) (420-7022)CY32.60$1,865.00$2,316.62$2,000.00$2,200.00$1,691.10$1,550.00$1,050.00
43Class C concrete (column) (420-7038)CY26.20$1,440.00$1,191.83$2,200.00$1,500.00$1,200.20$2,100.00$1,250.00
44Class C concrete (rail foundation) (420-7052)CY125$440.97$400.00$150.00$537.70$700.00$420.00
45Class C concrete (sign column) (420-7057)CY105.50$1,600.00$1,562.20$1,500.00$2,000.00$1,309.70$1,450.00$1,400.00
46Class C concrete (sign footing) (420-7151)CY39.20$2,500.00$976.65$1,600.00$1,500.00$1,332.90$950.00$1,050.00
47Reinforced concrete slab (extend slab) (422-7003)SF9,222$40.00$38.94$29.00$38.00$32.00$50.00$29.00
48Approach slab (422-7013)CY52.40$850.00$705.33$950.00$900.00$578.90$915.24$800.00
49Retaining wall (MSE) (423-7001)SF17,935$65.00$36.39$73.00$60.00$38.80$56.00$49.00
50Retaining wall (cast-in-place) (423-7016)SF714$126.00$70.34$140.00$130.00$89.90$115.00$73.00
51Prestressed concrete girder (TX46) (425-7004)LF641$225.00$221.90$250.00$232.00$282.80$315.00$210.00
52Prestressed concrete girder (TX54) (425-7005)LF641$251.00$224.29$270.00$234.00$273.50$316.00$220.00
53Riprap (concrete)(4 in) (432-7001)CY508.13$500.00$409.16$500.00$500.00$471.10$440.00$630.00
54Riprap (concrete)(5 in) (432-7002)CY210$550.00$400.23$510.00$600.00$405.10$440.00$810.00
55Riprap (concrete)(CL B) (432-7005)CY2.80$800.00$833.27$800.00$1,000.00$1,260.30$1,550.00$895.00
56Riprap (concrete) (CL B) (4 in) (432-7007)CY261.80$540.00$472.30$500.00$800.00$2,000.00$725.00$950.00
57Riprap (concrete)(flume) (432-7012)CY239$600.00$648.28$600.00$650.00$590.60$600.00$610.00
58Riprap (mow strip)(4 in) (432-7013)CY302$600.00$677.31$700.00$600.00$533.10$600.00$735.00
59Bedding material (3 in) (432-7049)CY33$140.00$104.82$450.00$150.00$127.50$90.00$85.00
60Rail (type SSTR) (450-7024)LF5,679$75.00$60.40$86.23$70.00$55.30$78.00$113.00
61Rail (type PR11) (450-7044)LF355$145.00$108.28$120.00$120.00$104.80$140.00$195.00
62Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF59$250.00$214.83$250.00$300.00$219.50$265.00$206.00
63Concrete box culvert (3 FT X 2 FT) (462-7001)LF2,636$250.00$255.26$300.00$280.00$271.50$300.00$258.00
64Concrete box culvert (8 FT X 3 FT) (462-7020)LF2,155$648.40$700.00$690.00$617.80$685.00$610.00
65Concrete box culvert (8 FT X 7 FT)(extend) (462-7079)LF153$988.43$1,400.00$1,400.00$922.00$891.00$820.00
66Concrete box culvert (8 FT X 8 FT)(extend) (462-7080)LF25$1,500.00$1,672.05$2,800.00$2,200.00$1,396.00$1,950.00$950.00
67RC pipe (CL III)(18 in) (464-7003)LF143$100.00$64.97$95.00$88.00$94.00$86.00$90.00
68RC pipe (CL III)(24 in) (464-7005)LF1,860$100.00$79.85$110.00$108.00$102.80$97.00$80.00
69RC pipe (CL III)(30 in) (464-7007)LF98$130.00$145.27$110.00$148.00$122.70$114.00$142.00
70RC pipe (CL III)(36 in) (464-7009)LF75$154.58$250.00$226.00$140.60$148.00$165.00
71RC pipe (CL III)(42 in) (464-7010)LF122$166.05$260.00$254.00$187.70$190.00$270.00
72RC pipe (CL V)(24 in) (464-7034)LF46$152.00$115.78$160.00$150.00$107.30$124.00$190.00
73Junction box(complete)(PJB)(3FTX3FT) (465-7005)EACH4$7,000.00$4,165.09$7,000.00$3,500.00$2,768.40$4,900.00$4,550.00
74Junction box(complete)(PJB)(4FTX4FT) (465-7006)EACH1$8,000.00$4,496.65$6,900.00$4,500.00$3,937.30$5,200.00$5,950.00
75Inlet (complete)(pod)(FG)(3FTX3FT) (465-7048)EACH4$5,000.00$5,238.94$5,000.00$7,500.00$3,224.40$6,500.00$2,700.00
76Junct box (complete)(JB)(7FT X 7FT)(FTW) (465-7295)EACH1$17,900$14,874$15,000$20,000$9,871.80$11,700$13,700
77Inlet (complete)(curb)(type C1)(none)(hou) (465-7309)EACH18$6,940.00$5,705.08$7,500.00$9,000.00$7,580.70$6,900.00$5,500.00
78Inlet (complete)(curb)(type C1)(left)(hou) (465-7310)EACH4$8,500.00$5,811.80$7,500.00$8,000.00$7,678.40$7,000.00$6,400.00
79Inlet (complete)(curb)(type C1)(right)(hou) (465-7311)EACH7$7,040.00$8,111.44$9,500.00$10,000$7,951.30$9,200.00$6,550.00
80Inlet (complete)(curb)(type C1)(both)(hou) (465-7312)EACH9$9,500.00$9,992.43$11,000$12,000$9,604.10$10,300$7,750.00
81Inlet (complete)(type A)(hou) (465-7313)EACH1$4,034.57$5,000.00$4,000.00$3,732.10$5,400.00$3,700.00
82Inlet (complete)(type aad)(hou) (465-7315)EACH10$7,000.00$6,516.78$10,000$6,000.00$7,542.80$7,700.00$5,000.00
83Inlet (complete)(type azr)(hou) (465-7318)EACH2$10,000$5,036.02$9,500.00$7,000.00$6,868.30$6,700.00$5,700.00
84Manh (complete)(type A)(hou) (465-7320)EACH11$5,000.00$5,006.91$9,000.00$6,000.00$4,607.40$6,600.00$7,300.00
85Wingwall (PW - 1) (HW=13 FT) (466-7183)EACH1$45,000$107,383$80,000$90,000$144,842$98,000$19,000
86Wingwall (PW - 2) (HW=16 FT) (466-7200)EACH1$110,072$110,000$150,000$205,477$152,000$154,000
87Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305)EACH1$1,500.00$1,192.99$1,500.00$1,500.00$1,168.60$1,620.00$2,250.00
88Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH1$1,900.00$1,551.29$2,000.00$1,800.00$1,683.60$1,950.00$2,800.00
89Pre-cast trench drain (in concrete pavemnt) (474-7022)LF120$132.03$280.00$300.00$458.80$283.00$450.00
90Adjusting inlets (479-7002)EACH1$1,700.00$1,548.99$1,600.00$2,000.00$296.60$1,900.00$500.00
91Removing structure (inlet) (496-7002)EACH9$900.00$730.78$990.00$1,000.00$557.20$870.00$790.00
92Removing structure (set) (496-7004)EACH3$592.43$850.00$350.00$156.00$840.00$2,400.00
93Removing structure (headwall) (496-7006)EACH1$1,300.71$9,000.00$14,000$4,130.30$1,850.00$2,700.00
94Removing structure (pipe) (496-7007)LF286$30.00$11.56$15.00$20.00$13.60$24.00$37.00
95Removing structure (box culvert) (496-7008)LF71$63.13$70.00$75.00$120.70$55.00$98.00
96Remove STR (rail) (496-7017)LF580$22.47$10.00$10.00$9.90$22.00$93.00
97Removing structure (ret wall) (496-7019)LF607$125.00$62.93$10.50$20.00$28.60$15.00$55.00
98Mobilization (500-7001)LS1$2,832,504$2,500,000$2,155,000$2,500,000$2,500,000$2,930,000$2,800,000
99Barricades, signs and traffic handling (502-7001)MO14$10,000$8,884.63$5,000.00$12,600$20,179$19,000$8,650.00
100Portable changeable message sign (503-7002)EACH6$7,000.00$5,347.76$10,000$20,000$11,536$12,500$31,000
101TMA (stationary) (505-7001)DAY48$250.00$239.40$300.00$250.00$312.40$191.67$735.00
102TMA (mobile operation) (505-7003)DAY116$237.00$587.89$500.00$750.00$654.90$1,045.00$1,125.00
103Rock filter dams (install) (type 1) (506-7001)LF25$30.00$30.00$40.00$39.10$42.69$32.00
104Rock filter dams (install) (type 3) (506-7003)LF100$42.00$43.00$110.00$111.20$53.79$44.00
105Rock filter dams (install) (type 4) (506-7004)LF20$85.00$48.00$48.00$50.00$51.50$54.56$50.00
106Rock filter dams (remove) (506-7011)LF145$16.00$20.00$20.00$15.00$14.40$12.00$21.00
107Construction exits (install) (type 1) (506-7020)SY738$30.00$30.00$30.00$40.00$30.80$27.00$31.00
108Construction exits (remove) (506-7024)SY738$10.00$20.00$20.00$6.00$9.50$15.40$21.00
109Sandbags for erosion control (506-7035)EACH28$15.00$5.00$5.00$20.00$20.10$0.32$5.00
110Temporary sediment control fence (install) (506-7039)LF11,759$4.50$2.95$2.95$2.50$2.30$2.72$3.00
111Temporary sediment control fence (remove) (506-7041)LF11,759$1.00$1.00$1.00$1.00$0.80$0.99$1.00
112Biodegradable erosion control logs (install) (8") (506-7043)LF300$8.00$8.00$8.00$7.40$5.00$8.00
113Biodegradable erosion control logs (install) (12") (506-7044)LF1,396$8.00$8.50$8.50$8.00$7.10$6.80$9.00
114Biodegradable erosion control logs (remove) (506-7046)LF1,696$1.90$2.00$2.00$1.00$0.80$1.00$2.00
115Constructing detours (508-7001)SY1,592$110.00$125.73$150.00$92.00$99.90$110.14$125.00
116Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013)LF8,329$25.00$10.98$11.00$13.00$15.50$9.13$28.00
117Portable concrete traffic barrier (des source)(low prof)(type 1) (512-7021)LF6,240$20.00$9.76$12.00$13.00$14.00$8.75$26.00
118Portable concrete traffic barrier (des source)(low prof)(type 2) (512-7022)LF180$25.00$8.54$20.00$13.00$15.50$20.92$49.00
119Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF5,779$10.00$5.61$8.00$9.00$10.20$5.70$9.00
120Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF5,040$10.00$3.51$7.00$9.00$10.90$4.52$8.00
121Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF120$14.50$3.51$8.00$9.00$14.20$10.28$11.00
122Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037)LF8,329$18.00$10.86$11.00$10.00$15.50$8.17$20.00
123Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF6,240$12.00$9.66$11.50$10.00$14.00$7.19$6.00
124Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF180$28.00$9.66$24.00$10.00$15.50$18.41$7.00
125Concrete curb (mono) (type II) (529-7007)LF14,017$10.00$3.62$7.00$5.00$3.80$3.41$10.00
126Concrete sidewalks (5") (531-7002)SY8,231$80.00$58.48$75.00$63.00$62.20$48.84$84.00
127Metal W-beam guard fence (timber post) (540-7001)LF450$28.00$25.50$28.50$32.00$34.50$25.62$42.00
128Metal beam guard fence trans (thrie-beam) (540-7005)EACH1$1,750.00$1,750.00$2,450.00$2,500.00$2,369.00$1,758.42$3,050.00
129Remove metal beam guard fence (542-7001)LF1,150$4.50$3.00$3.00$4.00$3.90$3.01$4.00
130Remove terminal anchor section (542-7002)EACH2$310.00$200.00$250.00$250.00$463.50$200.96$300.00
131Guardrail end treatment (install) (544-7001)EACH2$3,170.00$3,500.00$3,650.00$4,000.00$3,914.00$3,516.84$5,100.00
132Guardrail end treatment (remove) (544-7003)EACH7$300.00$200.00$200.00$350.00$358.40$200.96$450.00
133Crash cushion attenuator (move & reset) (545-7002)EACH5$3,000.00$3,000.00$4,950.00$1,600.00$1,512.00$3,858.72$1,585.00
134Crash cushion attenuator (remove) (545-7004)EACH5$2,400.00$1,000.00$1,500.00$1,000.00$755.00$2,756.23$850.00
135Crash cushion attenuator (install)(L)(N)(TL3) (545-7006)EACH5$26,500$24,550$25,200$27,000$25,837$31,845$28,100
136Cca (install)(N)(TL3)(work zone) (545-7018)EACH5$8,000.00$24,550$25,200$27,000$25,837$10,215$28,100
137Pipe underdrains (type 6) (6") (556-7006)LF1,880$30.00$34.90$33.83$40.00$28.60$31.34$44.00
138Relocate RD IL asm (trans-base) (610-7004)EACH7$1,325.00$2,695.00$1,400.00$2,796.80$1,338.38$1,400.00
139Remove RD IL asm (trans-base) (610-7009)EACH6$725.00$475.00$1,433.00$500.00$1,487.40$479.80$500.00
140In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124)EACH4$5,400.00$5,175.00$5,780.00$5,500.00$5,999.50$5,227.27$5,475.00
141In RD IL (type AL) 40T-8 (250W EQ) LED (610-7140)EACH6$5,995.00$6,192.00$6,300.00$6,427.90$6,055.56$6,300.00
142In RD IL (type SA) 50T-12 (400W EQ) LED (610-7200)EACH8$5,400.00$5,675.00$6,378.00$6,000.00$6,620.40$5,732.32$6,000.00
143Conduit (PVC) (schedule 40) (2") (618-7030)LF720$15.00$11.15$5.95$12.00$6.20$11.26$12.00
144Conduit (PVC) (schedule 80) (2") (618-7054)LF2,055$12.00$11.25$6.36$13.00$6.60$11.36$12.00
145Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF4,360$20.00$11.75$11.92$14.00$12.40$11.87$12.00
146Conduit (PVC) (schedule 80) (3") (618-7060)LF50$18.85$12.40$21.00$12.90$19.04$20.00
147Conduit (PVC) (schedule 80) (3") (bore) (618-7061)LF6,120$32.50$42.55$35.00$44.20$32.83$34.00
148Conduit (RM) (2") (618-7078)LF380$30.00$38.15$35.58$42.00$36.90$38.54$40.00
149ITS multi-duct CND (PVC-80)(bore) (619-7006)LF12,180$37.50$42.49$40.00$44.10$37.88$39.00
150Electrical conductor (no.14) insulated (620-7002)LF6,710$1.55$0.57$1.70$0.60$1.57$1.60
151Electrical conductor (no.12) bare (620-7003)LF230$1.75$1.50$1.39$1.70$1.40$1.52$1.55
152Electrical conductor (no.12) insulated (620-7004)LF460$1.80$1.60$1.45$1.80$1.50$1.62$1.65
153Electrical conductor (no.8) bare (620-7007)LF7,855$2.00$2.20$1.20$2.40$1.20$2.22$2.35
154Electrical conductor (no.8) insulated (620-7008)LF15,910$2.50$2.25$1.51$2.50$1.60$2.27$2.35
155Electrical conductor (no.6) bare (620-7009)LF8,850$2.35$1.66$2.60$1.70$2.37$2.50
156Electrical conductor (no.6) insulated (620-7010)LF4,425$2.65$2.20$2.80$2.30$2.68$2.80
157ITS GND box(pcast) type 1 (243636)W/aprn (623-7002)EACH14$4,475.00$5,160.95$4,800.00$5,357.70$4,520.20$4,700.00
158Remove ITS ground box (623-7041)EACH9$475.00$906.00$500.00$940.10$479.80$480.00
159Ground box type A (122311)W/apron (624-7002)EACH8$1,400.00$1,295.00$946.03$1,400.00$982.10$1,308.08$1,350.00
160Ground box type C (162911)W/apron (624-7006)EACH5$1,925.00$1,104.03$2,100.00$1,146.10$1,944.44$2,000.00
161Remove ground box (624-7013)EACH11$375.00$255.00$486.00$300.00$504.50$257.58$270.00
162Relocate electrical services (628-7001)EACH1$2,595.00$3,605.00$2,750.00$3,741.80$2,621.21$2,700.00
163Remove electrical services (628-7002)EACH2$815.00$725.00$1,241.00$750.00$1,287.90$732.33$740.00
164Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048)EACH1$11,000$8,450.00$9,800.00$9,000.00$9,978.80$8,535.35$8,600.00
165Elc SRV type A 240/480 060(SS)SS(E)GC(O) (628-7054)EACH2$9,800.00$10,327$11,000$10,719$9,898.99$10,300
166Elc SRV type A 240/480 060(SS)SS(E)SP(U) (628-7058)EACH2$7,500.00$7,195.00$7,964.00$8,000.00$8,266.90$7,267.68$7,600.00
167Aluminum signs (type G) (636-7002)SF30$38.40$65.00$35.00$66.80$65.55$38.00
168Aluminum signs (type O) (636-7003)SF857.25$50.00$35.75$32.76$38.00$34.00$33.35$38.00
169Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH16$630.00$615.00$615.00$750.00$710.70$780.00$940.00
170Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH18$800.00$825.00$825.00$1,000.00$1,014.60$820.00$1,250.00
171Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH1$830.00$985.00$985.00$1,500.00$1,030.00$1,000.00$1,900.00
172Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH4$875.00$1,050.00$1,050.00$1,300.00$2,575.00$1,250.00$1,600.00
173Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049)EACH1$1,800.00$1,950.00$1,950.00$2,800.00$721.00$2,200.00$3,500.00
174Remove SM RD SN sup&AM (644-7073)EACH22$110.00$150.00$150.00$125.00$154.50$100.00$150.00
175Install LRSS (struct steel) (647-7001)LB325$7.50$11.00$8.00$11.20$11.00$11.00
176Relocate lrsa (647-7002)EACH1$3,500.00$5,000.00$2,400.00$9,000.00$2,401.50$2,355.14$11,500
177Remove lrsa (647-7003)EACH5$1,345.00$625.00$2,100.00$800.00$2,171.70$2,129.78$1,000.00
178Install overhead sign support(35 FT cant)(span only) (650-7041)EACH1$25,000$23,385$31,000$24,000$32,133$31,512$24,000
179Install overhead sign support(40 FT cant)(span only) (650-7048)EACH3$29,000$24,575$29,000$25,000$29,374$28,807$25,000
180Remove overhd sign sup (650-7193)EACH4$12,000$4,250.00$6,702.79$4,500.00$6,958.40$6,823.92$4,400.00
181Remove overhd sign sup (sign only) (650-7194)EACH2$2,180.00$1,775.00$776.78$2,000.00$806.40$790.80$1,800.00
182Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH35$6.00$25.00$25.00$25.00$206.00$15.00$33.00
183Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH18$30.00$35.00$35.00$30.00$206.00$22.00$40.00
184Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031)EACH6$12.00$25.00$25.00$25.00$206.00$15.00$32.00
185Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036)EACH6$35.00$25.00$35.00$30.00$206.00$22.00$42.00
186Work zone pavement marking removing (W)6"(broken) (662-7065)LF9,041$1.50$1.65$2.87$1.75$1.70$1.67$3.65
187Work zone pavement marking removing (W)6"(solid) (662-7068)LF30,161$1.00$1.65$1.28$1.75$1.70$1.67$1.60
188Work zone pavement marking removing (W)8"(solid) (662-7072)LF1,331$1.50$2.25$2.30$2.40$2.30$2.27$2.80
189Work zone pavement marking removing (W)6"(BKN W/marker) (662-7080)LF560$1.50$1.88$3.45$2.00$1.90$1.90$4.20
190Work zone pavement marking removing (W)(arrow) (662-7082)EACH8$150.00$150.00$195.00$160.00$154.50$151.52$240.00
191Work zone pavement marking removing (Y)6"(solid) (662-7100)LF16,796$1.30$1.65$1.28$1.75$1.70$1.67$1.60
192Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH76$2.00$2.00$5.00$2.00$9.30$1.00$6.00
193Reflectorized pavement marking type III (W)(6")(solid) (666-7236)LF18,008$1.00$0.88$1.05$0.90$0.90$0.89$1.30
194Reflectorized pavement marking type III (W)(6")(broken) (666-7237)LF4,578$1.10$0.88$1.05$0.90$0.90$0.89$3.10
195Reflectorized pavement marking type III (W)(8")(solid) (666-7239)LF4,510$2.00$1.25$2.50$1.40$1.30$1.26$3.10
196Reflectorized pavement marking type III (W)(12")(solid) (666-7242)LF2,656$3.50$3.15$4.50$3.50$3.20$3.18$5.50
197Reflectorized pavement marking type III (W)(12")(DOT) (666-7243)LF459$3.00$3.15$5.00$3.50$3.20$3.18$6.10
198Reflectorized pavement marking type III (W)(24")(solid) (666-7244)LF62$7.60$8.00$10.00$9.00$8.20$8.08$12.50
199Reflectorized pavement marking type III (Y)(6")(solid) (666-7248)LF12,568$1.20$0.88$1.05$0.90$0.90$0.89$1.30
200Reflectorized pavement marking type III (BLK)(6")(shadow) (666-7262)LF3,411$0.90$0.89$1.05$1.00$0.90$0.90$1.30
201Pavement sler (arrow) (666-7353)EACH8$20.00$50.00$5.00$55.00$51.50$50.51$6.10
202Pavement sler (word) (666-7354)EACH7$25.00$50.00$5.00$55.00$51.50$50.51$6.10
203Pavement sler (double arrow) (666-7356)EACH1$25.00$50.00$5.00$55.00$51.50$50.51$6.10
204Pavement sler (uturn arrow) (666-7358)EACH2$30.00$50.00$5.00$55.00$51.50$50.51$6.10
205Prefabricated PM type C (W)(arrow) (668-7091)EACH7$250.00$250.00$267.42$275.00$257.50$252.53$330.00
206Prefabricated PM type C (W)(double arrow) (668-7093)EACH1$400.00$300.00$362.34$325.00$309.00$303.03$440.00
207Prefabricated PM type C (W)(uturn arrow) (668-7096)EACH2$300.00$275.00$373.98$300.00$283.30$277.78$460.00
208Prefabricated PM type C (W)(word) (668-7103)EACH9$315.00$250.00$318.12$275.00$257.50$252.53$390.00
209Reflectorized pavement marker type II-C-R (672-7006)EACH637$6.00$7.00$6.00$7.50$7.20$7.07$7.50
210Eliminating existing PM & markers (6") (677-7002)LF15,062$2.00$0.35$0.49$0.40$0.40$0.35$0.60
211Eliminating existing PM & markers (8") (677-7004)LF1,822$2.00$0.40$0.98$0.50$0.40$0.40$1.25
212Eliminating existing PM & markers (12") (677-7006)LF302$0.65$2.00$0.70$0.70$0.66$2.50
213Eliminating existing PM & markers (arrow) (677-7009)EACH2$25.00$70.00$25.00$25.80$25.26$89.00
214Eliminating existing PM & markers (double arrow) (677-7010)EACH1$29.00$75.00$30.00$29.90$29.29$96.00
215Eliminating existing PM & markers (word) (677-7015)EACH2$25.00$75.00$25.00$25.80$25.26$95.00
216Pavement surface preparation for marking (6") (678-7002)LF37,375$1.25$0.03$0.02$0.03$0.10$0.03$0.03
217Pavement surface preparation for marking (8") (678-7004)LF4,510$1.25$0.05$0.04$0.05$0.10$0.05$0.05
218Pavement surface preparation for marking (12") (678-7006)LF3,115$1.25$0.10$0.08$0.10$0.10$0.10$0.10
219Pavement surface preparation for marking (24") (678-7008)LF62$1.00$0.35$0.16$0.35$0.40$0.35$0.20
220Pavement surface preparation for marking (arrow) (678-7009)EACH7$25.00$15.00$1.00$15.00$15.50$15.15$1.25
221Pavement surface preparation for marking (double arrow) (678-7010)EACH1$17.00$15.00$1.00$15.00$15.50$15.15$1.25
222Pavement surface preparation for marking (uturn arr) (678-7012)EACH2$20.00$15.00$1.00$15.00$15.50$15.15$1.25
223Pavement surface preparation for marking (word) (678-7016)EACH9$40.00$15.00$1.00$15.00$15.50$15.15$1.25
224Pavement surface preparation for marking (RPM) (678-7033)EACH329$1.00$1.00$0.25$1.00$1.00$1.01$0.35
225Remove luminaire pole (690-7127)EACH6$475.00$1,500.00$500.00$1,487.40$479.80$500.00
226Tree removal (4" - 12" diameter) (752-7005)EACH84$100.00$300.00$600.00$175.00$463.50$325.00$450.00
227ITS pole MNT cab (type 2)(conf 2) (6011-7002)EACH1$7,475.00$5,000.00$8,000.00$7,709.20$7,550.51$7,800.00
228ITS pole (40 FT)(rem) (6011-7018)EACH1$1,990.00$1,425.00$4,970.00$1,500.00$5,150.10$1,439.39$1,450.00
229FO CBL (96 SMF) (6027-7029)LF12,060$6.05$4.23$6.50$4.40$6.11$6.20
230Install wrong way driver detection sys (6038-7001)EACH1$52,775$55,200$55,000$57,279$53,308$54,000
231Remove wrong way driver detection sys (6038-7003)EACH1$2,500.00$1,260.00$3,000.00$1,307.10$2,525.25$2,600.00
TxDOT contract A00191471: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy