Electrical conductor (no.6) bare, TxDOT 620-7009
Low bidders on TxDOT contracts carried a median of $2.50 per LF for this item, over the 24 months to 19 NOV 2026, across 276 low bids. Half of all 1,496 bids fell between $2.10 and $3.12.
- Owner
- Texas DOT
- Item
- 620-7009
- Unit
- LF
- Data through
- 19 NOV 2026
TxDOT prints this item as “ELEC CONDR (NO.6) BARE”.
TxDOT has bid this work under more than one code: 6206009 on lettings from 09 JAN 2020 to 02 AUG 2024 (2,332 bids); 620-7009 on lettings from 06 NOV 2024 to 12 NOV 2026 (1,516 bids); 620-6009 on lettings from 06 NOV 2024 to 04 MAR 2025 (34 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 132 | 132 | $1.46 | 632 | $1.50 |
| 2021 | 145 | 145 | $1.70 | 657 | $1.74 |
| 2022 | 95 | 95 | $2.00 | 353 | $2.00 |
| 2023 | 115 | 115 | $2.20 | 378 | $2.04 |
| 2024 | 102 | 102 | $2.20 | 385 | $2.40 |
| 2025 | 134 | 134 | $2.50 | 616 | $2.70 |
| 2026 | 138 | 138 | $2.45 | 860 | $2.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 55 | $3.00 | 329 | $3.00 |
| Houston District | 22 | $2.09 | 170 | $2.08 |
| Austin District | 28 | $2.40 | 152 | $2.40 |
| San Antonio District | 22 | $2.15 | 125 | $2.35 |
| Pharr District | 25 | $2.00 | 115 | $2.15 |
| Fort Worth District | 15 | $2.60 | 73 | $2.77 |
| Odessa District | 19 | $2.50 | 63 | $2.50 |
| Yoakum District | 9 | $2.63 | 60 | $2.50 |
| Atlanta District | 10 | $2.88 | 56 | $3.00 |
| Tyler District | 9 | $3.30 | 55 | $3.25 |
| Waco District | 8 | $2.33 | 53 | $2.92 |
| Lubbock District | 12 | $2.77 | 53 | $2.90 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 5 to 245 | 69 | $2.60 |
| 250 to 1,260 | 69 | $2.50 |
| 1,320 to 3,825 | 69 | $2.48 |
| 3,885 to 56,073 | 69 | $2.20 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Webber, LLC | 121 | 66 (55%) |
| James Construction Group, LLC | 85 | 46 (54%) |
| Ragle Construction, Inc. | 70 | 42 (60%) |
| Sice, Inc. | 50 | 31 (62%) |
| Florida Traffic Control Devices, Inc. | 94 | 29 (31%) |
| Hunter Industries, LTD. | 58 | 28 (48%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | A00222829 | Dallas District | 1,500 | $3.54 | $3.50 | $2.75 | 5 | Highway Intelligent Traffic Solutions, Inc. | TxDOT |
| 04 NOV 2026 | A00206976 | Austin District | 120 | $2.40 | $2.40 | $3.50 | 9 | Lone Star Sitework, LLC | TxDOT |
| 04 NOV 2026 | A00212892 | Dallas District | 3,341 | $3.30 | $3.20 | $4.00 | 6 | Indus Road & Bridge, Inc. | TxDOT |
| 04 NOV 2026 | A00129572 | Dallas District | 245 | $3.00 | $2.91 | $2.35 | 4 | Mario Sinacola & Sons Excavating, Inc. | TxDOT |
| 04 NOV 2026 | A00221850 | Houston District | 140 | $1.75 | $3.06 | $2.50 | 5 | Deco Contractors, Inc. | TxDOT |
| 03 NOV 2026 | A00206952 | Waco District | 30 | $2.15 | $2.85 | $3.00 | 9 | The Levy Company, Inc. | TxDOT |
| 03 NOV 2026 | A00218531 | Atlanta District | 462 | $2.65 | $2.88 | $3.50 | 10 | North Texas Traffic Systems Construction | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 41,836 | $2.47 | $2.51 | $2.49 | 6 | Austin Bridge & Road Services, LP | TxDOT |
| 03 NOV 2026 | A00222928 | Houston District | 2,500 | $2.75 | $3.09 | $1.75 | 7 | Traf-Tex, Inc. | TxDOT |
| 03 NOV 2026 | A00206455 | Dallas District | 9,010 | $1.80 | $2.50 | $2.50 | 13 | RCR Telecon LLC | TxDOT |
| 07 OCT 2026 | A00135746 | Dallas District | 170 | $5.60 | $2.86 | $4.00 | 9 | Garret Shields Infrastructure | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 2,340 | $1.95 | $2.05 | $1.89 | 8 | Hunter Industries, LTD. | TxDOT |
| 07 OCT 2026 | A00192619 | Dallas District | 8,195 | $1.47 | $2.25 | $2.15 | 6 | Sice, Inc. | TxDOT |
| 09 SEP 2026 | A00219945 | Austin District | 1,080 | $2.40 | $2.33 | $2.33 | 4 | Vaca Underground Utilities Inc | TxDOT |
| 09 SEP 2026 | A00220213 | Austin District | 2,200 | $2.40 | $2.40 | $2.33 | 5 | Vaca Underground Utilities Inc | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way