TxDOT contract A00064192 bid tabulation
Widen Road - Add Shoulders, US 87 (Bexar/Wilson County Line to FM 1346). Let by Texas DOT on October 7, 2026, Wilson, San Antonio District. 8 bids received; low bid $39,881,467 by Hunter Industries, LTD., -21% against the engineer's estimate of $50,415,711.
- Owner
- Texas DOT
- Letting
- 07 OCT 2026
- Pay items
- 231
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $39,881,467 | Low | -21% |
| 2 | CK Newberry, LLC | $43,638,649 | +9.0% | -13% |
| 3 | Webber, LLC | $44,378,700 | +11% | -12% |
| 4 | Jordan Foster Construction, LLC | $47,525,791 | +19% | -6.0% |
| 5 | E-Z Bel Construction, LLC | $48,723,770 | +22% | -3.0% |
| 6 | Posillico Civil, Inc. | $48,887,304 | +23% | -3.0% |
| 7 | Joe Bland Construction LLC | $51,897,341 | +30% | +3.0% |
| 8 | J3 Company, LLC | $52,863,113 | +33% | +5.0% |
Engineer's estimate: $50,415,711.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. CK Newberry, LLC | 3. Webber, LLC | 4. Jordan Foster Construction, LLC | 5. E-Z Bel Construction, LLC | 6. Posillico Civil, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 238 | $4,075.00 | $635.24 | $1,000.00 | $9,049.22 | $5,990.64 | $4,750.00 | $6,302.00 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 2,604 | $9.00 | $8.60 | $6.00 | $9.01 | $8.00 | $1.00 | $14.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 4,397 | $10.50 | $16.10 | $8.00 | $13.17 | $10.00 | $1.00 | $19.00 |
| 4 | Removing concrete (medians) (104-7008) | SY | 87 | $16.35 | $16.10 | $25.00 | $24.37 | $32.00 | $1.00 | $70.00 |
| 5 | Removing concrete (driveways) (104-7011) | SY | 1,921 | $13.00 | $19.32 | $10.00 | $27.51 | $31.00 | $1.00 | $39.00 |
| 6 | Removing concrete (miscellaneous) (104-7045) | EACH | 2 | $815.00 | $805.00 | $1,000.00 | $435.19 | $1,100.00 | $449.00 | $1,503.00 |
| 7 | Removing concrete (miscellaneous) (104-7046) | SY | 1,633 | $8.00 | $19.32 | $6.00 | $13.80 | $10.00 | $23.50 | $4.00 |
| 8 | Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004) | SY | 195,136 | $5.00 | $2.84 | $6.00 | $4.35 | $5.50 | $9.25 | $2.00 |
| 9 | Excavation (roadway) (110-7001) | CY | 108,549 | $17.50 | $11.84 | $10.00 | $5.00 | $12.00 | $18.50 | $10.00 |
| 10 | Embankment (final)(OC)(type B) (132-7003) | CY | 68,259 | $30.00 | $8.60 | $10.00 | $10.00 | $10.00 | $18.00 | $11.00 |
| 11 | Embankment (final)(DC)(type C1) (132-7008) | CY | 63,203 | $40.00 | $10.72 | $11.00 | $25.14 | $25.00 | $25.00 | $10.00 |
| 12 | Embankment (final)(OC)(type C2) (132-7009) | CY | 33,992 | $35.00 | $10.72 | $12.00 | $25.14 | $13.00 | $9.00 | $12.00 |
| 13 | Compost manuf topsoil (2") (161-7001) | SY | 226,010 | $1.20 | $0.60 | $1.00 | $0.91 | $2.00 | $1.75 | $1.00 |
| 14 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 226,010 | $0.29 | $0.25 | $0.15 | $0.23 | $0.25 | $0.25 | $0.20 |
| 15 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 226,010 | $0.25 | $0.18 | $0.12 | $0.16 | $0.17 | $0.20 | $0.10 |
| 16 | Vegetative watering (168-7001) | TGL | 3,550 | $35.00 | $25.76 | $32.00 | $26.70 | $24.98 | $45.00 | $39.00 |
| 17 | Proof rolling (216-7001) | HR | 325 | $135.00 | $86.40 | $75.00 | $81.07 | $105.00 | $110.00 | $181.00 |
| 18 | FL BS (roadway del)(type D GR 1-2)(final pos) (247-7271) | CY | 78,033 | $50.00 | $55.69 | $65.00 | $55.00 | $67.00 | $70.00 | $63.15 |
| 19 | Cement (275-7001) | TON | 3,518 | $210.00 | $190.80 | $200.00 | $183.80 | $195.00 | $250.00 | $185.00 |
| 20 | Cement TRT (new base)(10") (275-7012) | SY | 230,476 | $4.00 | $1.73 | $1.60 | $2.62 | $2.50 | $2.25 | $2.50 |
| 21 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 46,109 | $4.54 | $4.94 | $4.50 | $3.50 | $3.60 | $4.75 | $4.00 |
| 22 | D-GR HMA type-B PG64-22 (341-7001) | TON | 27,086 | $90.00 | $84.17 | $90.00 | $80.00 | $82.00 | $84.25 | $75.00 |
| 23 | D-GR HMA type-C PG76-22 (341-7030) | TON | 31,008 | $90.00 | $93.40 | $90.00 | $93.00 | $96.00 | $91.50 | $90.00 |
| 24 | SP mixes SP-C sac-B PG76-22 (344-7031) | TON | 31,267 | $100.00 | $92.90 | $95.00 | $97.00 | $100.00 | $97.50 | $85.00 |
| 25 | Planing asphalt concrete pavement(2") (354-7051) | SY | 7,089 | $1.73 | $2.34 | $4.00 | $2.80 | $2.80 | $3.60 | $3.00 |
| 26 | Struct excavation (400-7001) | CY | 19,930 | $18.00 | $25.82 | $12.00 | $1.00 | $12.90 | $12.50 | $2.00 |
| 27 | Cem stabil BKFL (400-7010) | CY | 4,550 | $150.00 | $229.86 | $170.00 | $250.00 | $169.00 | $250.00 | $173.00 |
| 28 | Trench excavation protection (402-7001) | LF | 1,575 | $6.50 | $28.03 | $30.00 | $10.57 | $6.00 | $10.00 | $4.00 |
| 29 | Temporary special shoring (403-7001) | SF | 6,380 | $14.00 | $28.03 | $25.00 | $16.38 | $54.00 | $24.00 | $69.00 |
| 30 | Drilled shaft (42 in) (416-7007) | LF | 3,285 | $310.00 | $271.47 | $225.00 | $383.07 | $292.00 | $265.00 | $304.00 |
| 31 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 93 | $411.00 | $340.00 | $350.00 | $340.00 | $370.00 | $400.00 | $369.00 |
| 32 | Bridge sidewalk (422-7012) | SF | 464 | $10.95 | $150.00 | $215.00 | $30.87 | $230.00 | $750.00 | $460.00 |
| 33 | Retaining wall (drilled shaft) (fascia) (423-7019) | SF | 4,266 | $100.00 | $80.00 | $115.00 | $93.96 | $106.00 | $120.25 | $138.00 |
| 34 | Riprap (concrete)(4 in) (432-7001) | CY | 619 | $600.00 | $643.91 | $625.00 | $610.09 | $575.00 | $550.00 | $552.00 |
| 35 | Riprap (concrete)(flume) (432-7012) | CY | 69 | $1,400.00 | $471.47 | $475.00 | $757.33 | $890.00 | $525.00 | $1,057.00 |
| 36 | Riprap (mow strip)(4 in) (432-7013) | CY | 73 | $675.00 | $676.65 | $650.00 | $678.58 | $930.00 | $700.00 | $881.00 |
| 37 | Riprap (stone protection)(12 in) (432-7041) | CY | 2,024 | $319.00 | $35.00 | $200.00 | $209.26 | $230.00 | $208.50 | $303.00 |
| 38 | Riprap (stone protection)(24 in) (432-7045) | CY | 312 | $315.00 | $45.00 | $215.00 | $217.20 | $250.00 | $210.00 | $263.00 |
| 39 | Riprap (stone protection)(36 in) (432-7048) | CY | 550 | $340.00 | $55.00 | $225.00 | $235.82 | $280.00 | $210.00 | $311.00 |
| 40 | Rail (handrail)(type F) (450-7063) | LF | 487 | $210.00 | $222.97 | $250.00 | $167.72 | $200.00 | $188.00 | $296.00 |
| 41 | Concrete box culvert (3 FT X 3 FT) (462-7002) | LF | 506 | $375.00 | $455.23 | $375.00 | $271.45 | $320.00 | $400.00 | $553.00 |
| 42 | Concrete box culvert (4 FT X 4 FT) (462-7005) | LF | 274 | $370.00 | $521.38 | $500.00 | $335.67 | $390.00 | $525.00 | $748.00 |
| 43 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 636 | $415.00 | $446.08 | $450.00 | $373.90 | $410.00 | $480.00 | $757.00 |
| 44 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 147 | $700.00 | $593.71 | $925.00 | $481.16 | $500.00 | $750.00 | $802.00 |
| 45 | Concrete box culvert (6 FT X 5 FT) (462-7013) | LF | 855 | $900.00 | $645.97 | $625.00 | $561.24 | $580.00 | $700.00 | $996.00 |
| 46 | Concrete box culvert (8 FT X 4 FT) (462-7021) | LF | 183 | $975.00 | $969.88 | $950.00 | $767.09 | $770.00 | $1,000.00 | $1,218.00 |
| 47 | Concrete box culvert (10 FT X 6 FT) (462-7034) | LF | 864 | $1,560.00 | $1,275.24 | $1,300.00 | $1,071.32 | $1,200.00 | $1,300.00 | $1,776.00 |
| 48 | Concrete box culvert (10 FT X 9 FT) (462-7037) | LF | 1,304 | $1,350.00 | $1,550.54 | $1,400.00 | $1,443.92 | $1,310.00 | $1,300.00 | $2,162.00 |
| 49 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 241 | $550.00 | $476.53 | $450.00 | $326.68 | $600.00 | $520.00 | $494.00 |
| 50 | Concrete box culvert (3 FT X 3 FT)(extend) (462-7057) | LF | 90 | $800.00 | $544.93 | $525.00 | $294.17 | $580.00 | $550.00 | $564.00 |
| 51 | Concrete box culvert (4 FT X 4 FT)(extend) (462-7060) | LF | 357 | $975.00 | $706.39 | $650.00 | $548.36 | $780.00 | $550.00 | $674.00 |
| 52 | Concrete box culvert (6 FT X 3 FT)(extend) (462-7066) | LF | 108 | $1,100.00 | $784.87 | $750.00 | $1,446.03 | $800.00 | $600.00 | $893.00 |
| 53 | Concrete box culvert (8 FT X 4 FT)(extend) (462-7076) | LF | 309 | $1,200.00 | $969.88 | $900.00 | $1,315.45 | $900.00 | $1,000.00 | $1,265.00 |
| 54 | Concrete box culvert (10 FT X 8 FT)(extend) (462-7091) | LF | 144 | $1,300.00 | $1,906.12 | $1,800.00 | $1,522.66 | $1,500.00 | $1,200.00 | $2,412.00 |
| 55 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,587 | $100.00 | $76.24 | $85.00 | $97.39 | $100.00 | $78.00 | $149.00 |
| 56 | RC pipe (CL III)(24 in) (464-7005) | LF | 2,684 | $99.00 | $104.28 | $100.00 | $125.55 | $120.00 | $95.00 | $237.00 |
| 57 | RC pipe (CL III)(36 in) (464-7009) | LF | 602 | $185.00 | $250.04 | $240.00 | $210.81 | $180.00 | $181.00 | $256.00 |
| 58 | RC pipe (CL III)(42 in) (464-7010) | LF | 228 | $250.00 | $308.34 | $300.00 | $236.66 | $200.00 | $205.00 | $316.00 |
| 59 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 12 | $6,600.00 | $5,494.12 | $6,000.00 | $6,960.14 | $12,000 | $5,780.00 | $8,365.00 |
| 60 | Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128) | EACH | 5 | $12,000 | $8,857.86 | $8,500.00 | $9,163.94 | $13,000 | $12,000 | $11,977 |
| 61 | Inlet (complete)(armor curb slot) (465-7335) | EACH | 6 | $4,705.00 | $4,477.09 | $8,000.00 | $7,385.91 | $9,000.00 | $6,320.00 | $16,996 |
| 62 | Wingwall (PW - 1) (HW=10 FT) (466-7180) | EACH | 2 | $40,000 | $107,459 | $100,000 | $52,014 | $70,000 | $105,000 | $85,398 |
| 63 | Set (type I)(S= 3 FT)(HW= 3 FT)(3:1)(C) (467-7040) | EACH | 2 | $6,000.00 | $5,494.12 | $5,200.00 | $10,627 | $13,000 | $6,100.00 | $18,472 |
| 64 | Set (type I)(S= 3 FT)(HW= 3 FT)(4:1)(C) (467-7041) | EACH | 3 | $7,400.00 | $5,942.62 | $5,500.00 | $11,645 | $15,000 | $8,500.00 | $18,652 |
| 65 | Set (type I)(S= 3 FT)(HW= 4 FT)(3:1)(C) (467-7044) | EACH | 7 | $10,390 | $5,830.49 | $2,400.00 | $7,849.12 | $16,600 | $6,000.00 | $12,101 |
| 66 | Set (type I)(S= 3 FT)(HW= 4 FT)(4:1)(C) (467-7045) | EACH | 2 | $13,780 | $6,727.49 | $6,500.00 | $7,277.99 | $14,300 | $7,400.00 | $10,953 |
| 67 | Set (type I)(S= 4 FT)(HW= 5 FT)(3:1)(C) (467-7075) | EACH | 18 | $8,620.00 | $5,045.62 | $4,700.00 | $2,906.92 | $10,200 | $3,500.00 | $9,284.00 |
| 68 | Set (type I)(S= 5 FT)(HW= 4 FT)(4:1)(C) (467-7100) | EACH | 4 | $9,000.00 | $6,278.99 | $6,000.00 | $9,295.96 | $14,600 | $5,500.00 | $9,284.00 |
| 69 | Set (type I)(S= 5 FT)(HW= 4 FT)(6:1)(C) (467-7101) | EACH | 4 | $29,750 | $9,293.24 | $7,500.00 | $7,996.18 | $15,500 | $7,880.00 | $10,906 |
| 70 | Set (type I)(S= 6 FT)(HW= 4 FT)(3:1)(C) (467-7128) | EACH | 9 | $8,000.00 | $6,503.24 | $6,200.00 | $7,860.69 | $15,000 | $6,270.00 | $9,284.00 |
| 71 | Set (type I)(S= 6 FT)(HW= 4 FT)(4:1)(C) (467-7129) | EACH | 12 | $14,200 | $6,839.62 | $6,500.00 | $5,041.53 | $12,800 | $6,650.00 | $9,910.00 |
| 72 | Set (type I)(S= 6 FT)(HW= 4 FT)(6:1)(C) (467-7130) | EACH | 7 | $5,500.00 | $8,409.37 | $8,000.00 | $6,969.90 | $16,700 | $9,570.00 | $12,073 |
| 73 | Set (type I)(S= 6 FT)(HW= 6 FT)(3:1)(C) (467-7136) | EACH | 10 | $8,500.00 | $8,167.87 | $6,000.00 | $6,763.87 | $13,400 | $6,930.00 | $9,910.00 |
| 74 | Set (type I)(S= 8 FT)(HW= 5 FT)(3:1)(C) (467-7183) | EACH | 16 | $15,535 | $7,288.12 | $7,000.00 | $7,306.34 | $14,500 | $6,700.00 | $9,910.00 |
| 75 | Set (type I)(S= 10 FT)(HW= 7 FT)(3:1)(C) (467-7234) | EACH | 12 | $25,000 | $12,109 | $10,000 | $8,485.99 | $15,700 | $9,000.00 | $14,743 |
| 76 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 5 | $1,700.00 | $1,625.81 | $1,600.00 | $2,881.97 | $2,400.00 | $1,310.00 | $4,891.00 |
| 77 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 70 | $1,500.00 | $1,681.87 | $1,800.00 | $2,724.35 | $1,480.00 | $1,310.00 | $4,742.00 |
| 78 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 1 | $2,500.00 | $1,794.00 | $1,700.00 | $2,380.20 | $2,000.00 | $2,430.00 | $8,296.00 |
| 79 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 98 | $4,385.00 | $1,962.19 | $2,000.00 | $2,898.56 | $1,830.00 | $2,430.00 | $7,822.00 |
| 80 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 4 | $4,000.00 | $3,251.62 | $3,000.00 | $4,752.52 | $3,900.00 | $5,280.00 | $7,805.00 |
| 81 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 4 | $5,385.00 | $3,475.87 | $3,200.00 | $5,343.66 | $4,600.00 | $5,360.00 | $8,965.00 |
| 82 | Set (type II) (42 in) (RCP) (6: 1) (P) (467-7380) | EACH | 8 | $8,200.00 | $3,924.37 | $3,700.00 | $6,729.28 | $12,800 | $10,100 | $12,974 |
| 83 | Clean existing culverts (480-7001) | EACH | 12 | $3,000.00 | $3,924.37 | $3,700.00 | $5,473.94 | $5,800.00 | $1,880.00 | $1,171.00 |
| 84 | Removing structure (set) (496-7004) | EACH | 129 | $650.00 | $1,009.12 | $1,200.00 | $848.06 | $500.00 | $840.00 | $681.00 |
| 85 | Removing structure (wingwall) (496-7005) | EACH | 20 | $1,875.00 | $2,578.87 | $3,000.00 | $5,550.19 | $2,900.00 | $1,760.00 | $2,349.00 |
| 86 | Removing structure (headwall) (496-7006) | EACH | 20 | $1,685.00 | $2,578.87 | $3,000.00 | $5,550.19 | $3,000.00 | $2,370.00 | $3,876.00 |
| 87 | Removing structure (pipe) (496-7007) | LF | 1,817 | $25.00 | $32.52 | $30.00 | $31.10 | $33.00 | $37.40 | $26.00 |
| 88 | Removing structure (box culvert) (496-7008) | LF | 1,165 | $75.00 | $120.00 | $100.00 | $234.07 | $108.00 | $101.10 | $35.00 |
| 89 | Removing structure (abnd util)PVC(8"or less) (496-7056) | LF | 671 | $5.00 | $5.00 | $30.00 | $20.00 | $13.50 | $33.25 | $26.00 |
| 90 | Mobilization (500-7001) | LS | 1 | $4,265,093 | $2,614,518 | $4,000,000 | $4,400,000 | $4,728,816 | $3,500,000 | $4,500,000 |
| 91 | Barricades, signs and traffic handling (502-7001) | MO | 35 | $15,000 | $6,319.83 | $10,000 | $10,000 | $14,000 | $7,500.00 | $19,120 |
| 92 | Portable changeable message sign (503-7001) | DAY | 30 | $85.00 | $100.00 | $100.00 | $94.63 | $119.00 | $73.50 | $93.00 |
| 93 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $7,500.00 | $25,000 | $9,833.94 | $26,000 | $40,000 | $33,422 |
| 94 | TMA (stationary) (505-7001) | DAY | 60 | $220.00 | $250.00 | $500.00 | $212.87 | $400.00 | $453.00 | $327.00 |
| 95 | TMA (mobile operation) (505-7003) | DAY | 14 | $350.00 | $750.00 | $25.00 | $212.43 | $780.00 | $758.00 | $851.00 |
| 96 | Rock filter dams (install) (type 1) (506-7001) | LF | 777 | $40.25 | $41.79 | $40.00 | $38.62 | $39.00 | $35.00 | $45.00 |
| 97 | Rock filter dams (install) (type 2) (506-7002) | LF | 2,376 | $60.00 | $49.53 | $45.00 | $42.20 | $42.00 | $40.00 | $50.00 |
| 98 | Rock filter dams (remove) (506-7011) | LF | 3,153 | $14.50 | $9.94 | $7.00 | $6.47 | $6.45 | $10.00 | $17.00 |
| 99 | Construction exits (install) (type 1) (506-7020) | SY | 678 | $34.00 | $49.99 | $23.00 | $22.66 | $23.00 | $42.00 | $54.00 |
| 100 | Construction exits (remove) (506-7024) | SY | 678 | $10.60 | $14.36 | $5.00 | $4.84 | $4.85 | $15.00 | $11.00 |
| 101 | Temporary sediment control fence (install) (506-7039) | LF | 39,300 | $3.66 | $3.68 | $3.25 | $3.00 | $3.08 | $3.75 | $4.00 |
| 102 | Temporary sediment control fence (remove) (506-7041) | LF | 39,300 | $0.65 | $1.03 | $0.25 | $0.25 | $0.26 | $1.00 | $1.00 |
| 103 | Constructing detours (508-7001) | SY | 38,516 | $80.00 | $83.90 | $95.00 | $69.93 | $75.60 | $91.25 | $65.00 |
| 104 | One-way traffic control (flagger cont) (510-7001) | HR | 70 | $70.00 | $86.40 | $50.00 | $55.88 | $52.00 | $225.00 | $100.90 |
| 105 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 5,340 | $31.00 | $25.00 | $45.00 | $16.94 | $68.00 | $50.00 | $93.00 |
| 106 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 9,210 | $11.00 | $10.50 | $30.00 | $9.67 | $8.60 | $10.25 | $22.00 |
| 107 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 5,340 | $11.50 | $10.50 | $28.00 | $7.78 | $19.50 | $12.50 | $30.00 |
| 108 | Colored textured concrete (4") (527-7001) | SY | 34 | $98.00 | $91.89 | $90.00 | $84.20 | $440.00 | $186.00 | $98.00 |
| 109 | Concrete curb (type I) (529-7001) | LF | 1,348 | $10.75 | $14.20 | $25.00 | $13.01 | $15.00 | $31.00 | $26.00 |
| 110 | Concrete curb (type II) (529-7002) | LF | 515 | $6.75 | $15.72 | $26.00 | $14.40 | $15.00 | $31.25 | $29.00 |
| 111 | Concrete curb (doweled) (529-7012) | LF | 82 | $25.00 | $415.98 | $50.00 | $381.15 | $50.00 | $46.00 | $84.00 |
| 112 | Intersections (ACP) (530-7002) | SY | 2,634 | $130.00 | $64.20 | $110.00 | $80.90 | $78.00 | $131.00 | $95.00 |
| 113 | Driveways (concrete) (hes) (530-7007) | SY | 1,654 | $137.60 | $79.91 | $130.00 | $104.90 | $146.00 | $150.00 | $225.00 |
| 114 | Driveways (ACP) (530-7010) | SY | 8,856 | $50.90 | $51.32 | $45.00 | $49.91 | $23.00 | $83.25 | $23.00 |
| 115 | Concrete sidewalks (4") (531-7001) | SY | 1,304 | $84.00 | $71.66 | $85.00 | $72.26 | $90.00 | $100.00 | $161.00 |
| 116 | Curb ramps (type 1) (531-7005) | EACH | 5 | $2,650.00 | $2,205.91 | $3,000.00 | $2,021.22 | $3,200.00 | $3,270.00 | $4,947.00 |
| 117 | Curb ramps (type 2) (531-7006) | EACH | 3 | $3,155.00 | $2,169.53 | $3,800.00 | $1,987.88 | $3,200.00 | $6,250.00 | $4,955.00 |
| 118 | Curb ramps (type 22) (531-7014) | EACH | 2 | $4,245.00 | $3,437.84 | $4,000.00 | $3,150.00 | $10,000 | $5,100.00 | $5,298.00 |
| 119 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 63,701 | $0.23 | $0.24 | $0.35 | $0.61 | $0.16 | $0.15 | $0.10 |
| 120 | Concrete median (536-7002) | SY | 1,919 | $200.00 | $73.67 | $55.00 | $73.48 | $146.00 | $122.00 | $28.00 |
| 121 | Concrete directional island (536-7004) | SY | 120 | $145.00 | $73.67 | $140.00 | $67.50 | $330.00 | $123.00 | $138.00 |
| 122 | Metal W-beam guard fence (timber post) (540-7001) | LF | 362.50 | $27.00 | $27.99 | $30.00 | $27.99 | $29.00 | $29.00 | $31.00 |
| 123 | Metal W-beam guard fence (steel post) (540-7002) | LF | 275 | $34.00 | $38.22 | $42.00 | $38.20 | $39.00 | $46.00 | $41.00 |
| 124 | Short radius (28") (540-7013) | LF | 157 | $40.00 | $37.99 | $40.00 | $37.99 | $39.00 | $55.00 | $55.00 |
| 125 | Driveway terminal anchor section (540-7014) | EACH | 5 | $900.00 | $1,476.55 | $1,500.00 | $1,476.55 | $1,510.00 | $1,531.00 | $1,420.00 |
| 126 | Downstream anchor terminal section (540-7015) | EACH | 3 | $1,428.00 | $1,906.15 | $2,000.00 | $1,906.15 | $1,960.00 | $1,531.00 | $1,285.00 |
| 127 | Metal W-beam guard fence (special) (540-7017) | LF | 63 | $37.35 | $69.43 | $75.00 | $69.43 | $71.00 | $29.00 | $48.00 |
| 128 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 225 | $95.00 | $118.19 | $130.00 | $118.19 | $121.00 | $88.00 | $110.00 |
| 129 | Metal beam guard fence trans (31"-28") (540-7028) | EACH | 5 | $400.00 | $1,192.55 | $1,300.00 | $1,192.55 | $1,220.00 | $1,220.00 | $1,474.00 |
| 130 | Remove metal beam guard fence (542-7001) | LF | 1,925 | $2.85 | $2.00 | $2.25 | $2.00 | $2.05 | $4.00 | $3.00 |
| 131 | Remove terminal anchor section (542-7002) | EACH | 5 | $300.00 | $375.55 | $400.00 | $375.55 | $390.00 | $250.00 | $238.00 |
| 132 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $3,679.75 | $4,000.00 | $3,679.75 | $3,800.00 | $3,530.00 | $3,811.00 |
| 133 | Guardrail end treatment (remove) (544-7003) | EACH | 11 | $290.00 | $250.00 | $275.00 | $250.00 | $260.00 | $250.00 | $356.00 |
| 134 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 23 | $1,235.00 | $750.00 | $1,000.00 | $750.00 | $770.00 | $1,200.00 | $1,636.00 |
| 135 | Crash cushion attenuator (remove) (545-7004) | EACH | 16 | $783.50 | $750.00 | $1,000.00 | $750.00 | $770.00 | $1,090.00 | $875.00 |
| 136 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 18 | $7,650.00 | $7,250.00 | $10,000 | $7,250.00 | $7,400.00 | $5,270.00 | $8,621.00 |
| 137 | Gate (remove) (550-7016) | EACH | 20 | $460.00 | $150.00 | $1,000.00 | $500.00 | $1,690.00 | $750.00 | $480.00 |
| 138 | Pipe underdrains (type 8) (6") (556-7008) | LF | 475 | $40.00 | $20.00 | $45.00 | $44.15 | $31.00 | $135.00 | $61.00 |
| 139 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 42 | $350.00 | $215.00 | $215.00 | $215.00 | $310.00 | $305.00 | $216.00 |
| 140 | Mailbox install-D (TWG-post) type 2 (560-7003) | EACH | 9 | $300.00 | $220.00 | $220.00 | $220.00 | $360.00 | $345.00 | $292.00 |
| 141 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 6 | $700.00 | $620.00 | $620.00 | $620.00 | $560.00 | $735.00 | $680.00 |
| 142 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 375 | $8.95 | $11.00 | $11.00 | $11.00 | $12.00 | $27.50 | $12.00 |
| 143 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 475 | $24.00 | $22.00 | $22.00 | $22.00 | $24.00 | $28.00 | $24.00 |
| 144 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 520 | $17.00 | $23.00 | $23.00 | $23.00 | $25.00 | $30.00 | $25.00 |
| 145 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 950 | $25.60 | $24.00 | $24.00 | $24.00 | $26.00 | $32.50 | $26.00 |
| 146 | Electrical conductor (no.6) bare (620-7009) | LF | 2,340 | $1.89 | $1.95 | $2.00 | $1.95 | $2.15 | $3.75 | $2.00 |
| 147 | Electrical conductor (no.6) insulated (620-7010) | LF | 290 | $2.25 | $2.75 | $2.75 | $2.75 | $3.05 | $3.75 | $3.00 |
| 148 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 1,995 | $2.90 | $2.90 | $2.90 | $2.90 | $3.20 | $4.00 | $3.00 |
| 149 | Ground box type D (162922)W/apron (624-7008) | EACH | 12 | $1,696.75 | $1,600.00 | $1,600.00 | $1,600.00 | $1,760.00 | $2,030.00 | $1,735.00 |
| 150 | Remove ground box (624-7013) | EACH | 1 | $300.00 | $110.00 | $110.00 | $110.00 | $121.00 | $253.00 | $118.95 |
| 151 | Remove electrical services (628-7002) | EACH | 2 | $525.00 | $390.00 | $400.00 | $390.00 | $430.00 | $336.00 | $423.00 |
| 152 | Elc SRV type D 120/240 060(NS)AL(E)TP(O) (628-7123) | EACH | 2 | $7,000.00 | $6,200.00 | $6,500.00 | $6,200.00 | $6,800.00 | $7,570.00 | $6,723.00 |
| 153 | Aluminum signs (type A) (636-7001) | SF | 9 | $30.00 | $27.00 | $30.00 | $27.00 | $50.00 | $47.00 | $66.00 |
| 154 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 132 | $700.00 | $550.00 | $550.00 | $550.00 | $690.00 | $533.00 | $718.00 |
| 155 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 25 | $810.00 | $620.00 | $625.00 | $620.00 | $790.00 | $596.00 | $853.00 |
| 156 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 30 | $885.00 | $670.00 | $675.00 | $670.00 | $730.00 | $785.00 | $1,004.00 |
| 157 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 13 | $1,132.60 | $930.00 | $950.00 | $930.00 | $840.00 | $900.00 | $1,080.00 |
| 158 | Install small roadside sign support and assembly TYS80(1)SA(T-2EXT) (644-7029) | EACH | 2 | $1,200.00 | $1,000.00 | $1,100.00 | $1,000.00 | $880.00 | $960.00 | $1,231.00 |
| 159 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 3 | $1,300.00 | $980.00 | $1,100.00 | $980.00 | $1,080.00 | $990.00 | $1,236.00 |
| 160 | Remove SM RD SN sup&AM (644-7073) | EACH | 81 | $129.00 | $75.00 | $100.00 | $75.00 | $87.00 | $105.00 | $119.00 |
| 161 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002) | EACH | 50 | $43.00 | $15.00 | $16.00 | $15.00 | $36.00 | $78.00 | $32.00 |
| 162 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 231 | $76.00 | $65.00 | $65.00 | $65.00 | $115.00 | $115.00 | $65.00 |
| 163 | Remove delin & object marker assms (658-7078) | EACH | 132 | $15.00 | $15.00 | $15.00 | $15.00 | $11.50 | $35.00 | $20.00 |
| 164 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 155 | $40.00 | $12.00 | $12.00 | $12.00 | $51.00 | $19.00 | $44.00 |
| 165 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 48 | $50.00 | $14.00 | $15.00 | $14.00 | $51.00 | $19.00 | $44.00 |
| 166 | Work zone pavement marking non-removing (W)4"(broken) (662-7001) | LF | 13,270 | $0.30 | $0.30 | $0.50 | $0.35 | $0.31 | $0.30 | $0.30 |
| 167 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 29,279 | $0.35 | $0.25 | $0.30 | $0.25 | $0.26 | $0.25 | $0.25 |
| 168 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 57,436 | $0.30 | $0.25 | $0.30 | $0.25 | $0.26 | $0.25 | $0.25 |
| 169 | Work zone pavement marking removing (W)4"(broken) (662-7061) | LF | 18,760 | $1.00 | $1.17 | $1.00 | $0.72 | $1.20 | $1.25 | $1.00 |
| 170 | Work zone pavement marking removing (W)4"(solid) (662-7064) | LF | 125,063 | $0.85 | $0.74 | $1.00 | $0.63 | $0.76 | $0.75 | $0.75 |
| 171 | Work zone pavement marking removing (Y)4"(solid) (662-7097) | LF | 75,048 | $1.00 | $0.77 | $1.00 | $0.63 | $0.79 | $0.75 | $0.75 |
| 172 | Reflectorized pavement marking type I (W)6"(lane drop)(100MIL) (666-7012) | LF | 2,639 | $1.00 | $1.00 | $1.40 | $1.40 | $1.05 | $1.00 | $1.00 |
| 173 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 32,363 | $0.94 | $1.00 | $1.00 | $1.00 | $1.05 | $1.00 | $1.00 |
| 174 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 4,676 | $3.15 | $3.50 | $4.25 | $4.15 | $3.60 | $3.50 | $3.50 |
| 175 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,980 | $7.20 | $7.00 | $10.00 | $9.00 | $7.20 | $7.00 | $7.00 |
| 176 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 42 | $150.00 | $175.00 | $150.00 | $145.00 | $179.00 | $175.00 | $175.00 |
| 177 | Reflectorized pavement marking type I(W)(uturn arrow)(100MIL) (666-7051) | EACH | 26 | $200.00 | $250.00 | $225.00 | $210.00 | $260.00 | $250.00 | $250.00 |
| 178 | Reflectorized pavement marking type I(W)(lane drop arrow)(100MIL) (666-7060) | EACH | 22 | $245.00 | $350.00 | $250.00 | $230.00 | $360.00 | $350.00 | $350.00 |
| 179 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 54 | $170.00 | $175.00 | $150.00 | $150.00 | $179.00 | $175.00 | $175.00 |
| 180 | Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090) | EACH | 184 | $34.50 | $25.00 | $60.00 | $60.00 | $26.00 | $25.00 | $25.00 |
| 181 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 479 | $3.85 | $3.50 | $4.25 | $4.15 | $3.60 | $4.00 | $3.50 |
| 182 | Pavement sler 6" (666-7347) | LF | 107,122 | $0.21 | $0.25 | $0.25 | $0.23 | $0.26 | $0.25 | $0.25 |
| 183 | Pavement sler 8" (666-7348) | LF | 32,363 | $0.31 | $0.25 | $0.40 | $0.40 | $0.26 | $0.25 | $0.25 |
| 184 | Pavement sler 12" (666-7350) | LF | 5,155 | $1.00 | $1.50 | $1.00 | $1.00 | $1.55 | $1.50 | $1.50 |
| 185 | Pavement sler 24" (666-7352) | LF | 1,980 | $2.75 | $3.00 | $3.00 | $2.85 | $3.10 | $3.00 | $3.00 |
| 186 | Pavement sler (arrow) (666-7353) | EACH | 42 | $65.00 | $75.00 | $35.00 | $35.00 | $77.00 | $75.00 | $75.00 |
| 187 | Pavement sler (word) (666-7354) | EACH | 54 | $69.50 | $75.00 | $50.00 | $50.00 | $77.00 | $75.00 | $75.00 |
| 188 | Pavement sler (uturn arrow) (666-7358) | EACH | 26 | $98.76 | $100.00 | $65.00 | $65.00 | $103.00 | $100.00 | $100.00 |
| 189 | Pavement sler (LN reduct arrow) (666-7359) | EACH | 22 | $135.00 | $100.00 | $80.00 | $80.00 | $103.00 | $100.00 | $100.00 |
| 190 | Pavement sler (yld tri) (666-7365) | EACH | 184 | $14.00 | $10.00 | $14.00 | $13.50 | $10.50 | $10.00 | $10.00 |
| 191 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 11,862 | $0.67 | $0.69 | $0.75 | $0.75 | $0.71 | $0.70 | $0.50 |
| 192 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 47,332 | $0.63 | $0.59 | $0.70 | $0.68 | $0.61 | $0.60 | $0.50 |
| 193 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 241 | $0.65 | $0.69 | $0.75 | $0.75 | $0.71 | $0.70 | $0.50 |
| 194 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 45,048 | $0.60 | $0.59 | $0.70 | $0.68 | $0.61 | $0.60 | $0.50 |
| 195 | Reflectorized pavement marker type I-C (672-7002) | EACH | 783 | $4.33 | $4.50 | $4.50 | $4.55 | $4.60 | $4.50 | $4.50 |
| 196 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 130 | $4.28 | $4.50 | $5.00 | $4.55 | $4.60 | $4.50 | $4.50 |
| 197 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 604 | $4.25 | $4.50 | $5.00 | $4.55 | $4.60 | $4.50 | $4.50 |
| 198 | Eliminating existing PM & markers (4") (677-7001) | LF | 116,257 | $0.45 | $0.35 | $1.00 | $0.55 | $0.36 | $0.40 | $0.25 |
| 199 | Install highway traffic signal (isolated) (680-7002) | EACH | 2 | $25,000 | $34,300 | $35,000 | $34,300 | $38,000 | $43,300 | $37,194 |
| 200 | Removing traffic signals (680-7004) | EACH | 1 | $5,500.00 | $4,900.00 | $5,000.00 | $4,900.00 | $5,400.00 | $8,210.00 | $5,313.00 |
| 201 | Temporary traffic signals (681-7001) | EACH | 1 | $75,000 | $42,700 | $50,000 | $42,700 | $47,000 | $35,300 | $46,303 |
| 202 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 15 | $305.00 | $330.00 | $350.00 | $330.00 | $360.00 | $440.00 | $357.00 |
| 203 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 5 | $325.00 | $330.00 | $350.00 | $330.00 | $360.00 | $422.00 | $357.00 |
| 204 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 15 | $300.00 | $330.00 | $350.00 | $330.00 | $360.00 | $422.00 | $357.00 |
| 205 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 10 | $330.00 | $330.00 | $350.00 | $330.00 | $360.00 | $422.00 | $357.00 |
| 206 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 15 | $300.00 | $330.00 | $350.00 | $330.00 | $360.00 | $422.00 | $357.00 |
| 207 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 5 | $330.00 | $330.00 | $350.00 | $330.00 | $360.00 | $422.00 | $357.00 |
| 208 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 8 | $740.00 | $780.00 | $800.00 | $780.00 | $860.00 | $888.00 | $846.00 |
| 209 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 15 | $173.00 | $170.00 | $200.00 | $170.00 | $187.00 | $205.00 | $184.00 |
| 210 | Backplate W/reflectorized border(4 sec)aluminum (682-7040) | EACH | 5 | $260.00 | $250.00 | $275.00 | $250.00 | $280.00 | $331.00 | $271.00 |
| 211 | Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009) | LF | 2,480 | $2.89 | $2.20 | $2.25 | $2.20 | $2.40 | $2.75 | $2.00 |
| 212 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 3,920 | $4.33 | $3.25 | $3.25 | $3.25 | $3.60 | $5.80 | $3.50 |
| 213 | Traffic signal CBL (type C)(14 AWG)(2 conductor) (684-7080) | LF | 2,440 | $1.65 | $1.40 | $1.50 | $1.40 | $1.55 | $2.50 | $1.50 |
| 214 | Ins traffic signal PL AM(S)1 arm(36') (686-7037) | EACH | 1 | $12,000 | $13,700 | $15,000 | $13,700 | $15,100 | $17,100 | $14,856 |
| 215 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 2 | $14,000 | $17,800 | $20,000 | $17,800 | $19,600 | $22,000 | $19,302 |
| 216 | Ins traffic signal PL AM(S)1 arm(48')lum (686-7051) | EACH | 4 | $15,200 | $18,500 | $20,000 | $18,500 | $20,000 | $22,800 | $20,061 |
| 217 | Pedestrian pole assembly (687-7001) | EACH | 6 | $3,080.00 | $2,600.00 | $2,800.00 | $2,600.00 | $2,900.00 | $2,660.00 | $2,819.00 |
| 218 | Pedestrian detect push button (APS) (688-7001) | EACH | 8 | $1,500.00 | $1,100.00 | $1,200.00 | $1,100.00 | $1,210.00 | $1,070.00 | $1,192.00 |
| 219 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $3,200.00 | $4,400.00 | $4,500.00 | $4,400.00 | $4,800.00 | $5,510.00 | $4,771.00 |
| 220 | Removal of signal pole assembly (690-7051) | EACH | 1 | $1,200.00 | $310.00 | $325.00 | $310.00 | $340.00 | $1,520.00 | $336.00 |
| 221 | Full - width mowing (730-7019) | CYC | 12 | $5,600.00 | $6,500.00 | $1,600.00 | $6,500.00 | $4,200.00 | $7,500.00 | $10,923 |
| 222 | Litter removal (734-7002) | CYC | 35 | $1,700.00 | $2,000.00 | $1,500.00 | $1,800.00 | $2,600.00 | $1,740.00 | $5,750.00 |
| 223 | Debris removing-CNTR med/MN LNS/ramps (735-7002) | CYC | 35 | $11,000 | $2,000.00 | $2,200.00 | $1,200.00 | $3,200.00 | $2,500.00 | $5,750.00 |
| 224 | Cleaning / sweeping (center median) (738-7004) | CYC | 35 | $1,837.50 | $2,000.00 | $2,400.00 | $1,400.00 | $5,800.00 | $2,500.00 | $6,553.00 |
| 225 | Underseal course (3006-7001) | GAL | 54,356 | $4.00 | $4.24 | $4.00 | $3.50 | $3.60 | $4.75 | $3.50 |
| 226 | Bonding course (3007-7001) | GAL | 19,376 | $4.00 | $2.87 | $4.00 | $3.50 | $3.60 | $4.75 | $3.50 |
| 227 | Install bridge identification numbers (4019-7001) | EACH | 20 | $605.00 | $150.00 | $200.00 | $504.58 | $590.00 | $750.00 | $500.00 |
| 228 | ITS com CBL (ethernet) (6005-7001) | LF | 265 | $2.00 | $1.30 | $1.50 | $1.30 | $1.45 | $3.25 | $1.00 |
| 229 | RVDS (presence detection only) (6008-7001) | EACH | 7 | $8,200.00 | $5,600.00 | $6,000.00 | $5,600.00 | $6,200.00 | $15,400 | $6,072.00 |
| 230 | RVDS (advance detection only) (6008-7002) | EACH | 6 | $7,615.00 | $5,700.00 | $6,000.00 | $5,700.00 | $6,300.00 | $11,300 | $6,181.00 |
| 231 | CCTV field equip (digital) (install only) (6018-7001) | EACH | 2 | $800.00 | $670.00 | $675.00 | $670.00 | $740.00 | $1,030.00 | $727.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 7, 2026. Compiled by Mirage Metrics.