J3 Company, LLC: TxDOT bid record
J3 Company, LLC submitted 42 bids on Texas DOT contracts in the data, from 07 FEB 2020 to 07 OCT 2026, and was the low bidder on 9 of them (21%). When it was not low, its total sat a median +12% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $59,284,547
- Latest bid
- 07 OCT 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 8 | 2 | 25% |
| 2021 | 7 | 1 | 14% |
| 2022 | 3 | 0 | 0% |
| 2023 | 5 | 3 | 60% |
| 2024 | 10 | 2 | 20% |
| 2025 | 1 | 0 | 0% |
| 2026 | 8 | 1 | 13% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| San Antonio District | 39 | 8 | 21% |
| Austin District | 2 | 1 | 50% |
| San Angelo District | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Portable changeable message sign | 503-7002 | EACH | 26 | 16 (62%) | $6,000.00 | $10,000 |
| Reflectorized pavement marking type I (W)8"(solid)(100MIL) | 666-7024 | LF | 25 | 15 (60%) | $1.00 | $1.10 |
| Remove SM RD SN sup&AM | 644-7073 | EACH | 36 | 14 (39%) | $100.00 | $110.00 |
| Temporary sediment control fence (remove) | 506-7041 | LF | 38 | 13 (34%) | $0.83 | $1.00 |
| Temporary sediment control fence (install) | 506-7039 | LF | 38 | 12 (32%) | $3.50 | $4.00 |
| Construction exits (remove) | 506-7024 | SY | 36 | 12 (33%) | $8.50 | $10.00 |
| Reflectorized pavement marker type II-A-A | 672-7004 | EACH | 32 | 12 (38%) | $5.50 | $5.00 |
| Biodegradable erosion control logs (remove) | 506-7046 | LF | 24 | 12 (50%) | $1.00 | $1.40 |
| Construction exits (install) (type 1) | 506-7020 | SY | 33 | 10 (30%) | $20.00 | $30.00 |
| Reflectorized pavement marking type I (W)24"(solid)(100MIL) | 666-7036 | LF | 27 | 10 (37%) | $7.24 | $8.00 |
| Eliminating existing pavement marking & markers (4") | 677-6001 | LF | 22 | 9 (41%) | $0.51 | $0.60 |
| Concrete sidewalks (4") | 531-7001 | SY | 17 | 9 (53%) | $55.00 | $80.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Hunter Industries, LTD. | 17 | 9 of 17 |
| Capital Excavation Company | 16 | 7 of 16 |
| Harper Brothers Construction LLC | 15 | 6 of 15 |
| Jordan Foster Construction, LLC | 13 | 3 of 13 |
| Dan Williams Company | 12 | 6 of 12 |
| E-Z Bel Construction, LLC | 12 | 3 of 12 |
| Relmco, Inc. | 11 | 9 of 11 |
| Dean Word Company, LTD. | 11 | 5 of 11 |
| Salinas Construction Technologies, LTD. | 8 | 2 of 8 |
| Angel Brothers Holdings Corp. | 8 | 3 of 8 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 07 OCT 2026 | A00064192 | San Antonio District | Widen Road - Add Shoulders, US 87 (Bexar/Wilson County Line to FM 1346) | 8 of 8 | $52,863,113 | +33% |
| 02 SEP 2026 | A00184856 | San Antonio District | Bridge Replacement, CR 33 (On Waring-Welfare Road to at Joshua Creek) | 5 of 8 | $820,372 | +24% |
| 06 AUG 2026 | A00136986 | San Antonio District | Bridge Replacement, IH 10 (At SH 80 to .) | 3 of 8 | $6,294,204 | +9.0% |
| 01 JUL 2026 | A00193362 | San Antonio District | Hazard Elimination & Safety, IH 35 (SBFR IH 35 at Loma Vista to SBFR IH 35 at Peach Ave) | 1 of 7 | $12,034,296 | Low, 12% under the second |
| 03 JUN 2026 | A00186691 | San Antonio District | Construct Pedestrian Infrastructure, SH 16 (SL 98 to Lehmann Dr.) | 5 of 6 | $6,126,351 | +43% |
| 02 JUN 2026 | A00065051 | San Antonio District | Highway Improvement, FM 466 (At Eastwood Dr. to .) | 3 of 7 | $3,089,270 | +13% |
| 06 MAY 2026 | A00059994 | San Antonio District | Construct Ramps, IH 37 (LP 13 to IH 410) | 5 of 5 | $35,211,397 | +6.0% |
| 04 MAR 2026 | A00197420 | San Antonio District | Rehabilitate Existing Roadway, FM 2790 (FM 471 to Medina/Atascosa C/L) | 8 of 9 | $14,542,659 | +23% |
| 06 FEB 2025 | A00033961 | San Antonio District | Rehabilitate Existing Roadway, FM 140 (US 57 to IH 35) | 6 of 6 | $19,280,786 | +30% |
| 06 NOV 2024 | A00064418 | San Antonio District | Bridge Replacement, IH 35 (At Chacon Creek to .) | 3 of 7 | $14,399,556 | +12% |
| 10 JUL 2024 | 07243208 | San Antonio District | RM 473 Widen road - add shoulders from OLD NO. 9 HWY to RM 1376 | 7 of 8 | $6,634,821 | +48% |
| 06 JUN 2024 | 06243214 | San Antonio District | VA Bridge maintenance from VARIOUS LOCATIONS DISTRICTWIDE | 3 of 5 | $11,657,310 | +27% |
| 03 MAY 2024 | 05243215 | San Antonio District | UA 281 Bridge replacement from AT ATASCOSA RIVER | 5 of 7 | $5,241,891 | +7.0% |
| 03 MAY 2024 | 05243239 | San Antonio District | PR 29A State park improvements from ON PR 29A to IN GARNER STATE PARK | 3 of 4 | $1,615,890 | +19% |
| 02 MAY 2024 | 05243039 | San Antonio District | CS Construct pedestrian infrastructure from D L VEST STREET to TO FM 1346 SIDEWALKS | 2 of 9 | $685,875 | +10% |
| 04 APR 2024 | 04243025 | San Antonio District | FM 1341 Bridge replacement from AT CYPRUS CREEK | 1 of 9 | $1,193,211 | Low, 19% under the second |
| 05 MAR 2024 | 03243017 | San Antonio District | US 90 Hazard elimination & safety from A SH 211 | 1 of 6 | $6,869,482 | Low, 13% under the second |
| 05 MAR 2024 | 03243020 | San Antonio District | US 281 Hazard elimination & safety from IH 410 to SAVA ST | 2 of 6 | $2,409,197 | 0.0% |
| 02 FEB 2024 | 02243205 | San Antonio District | FM 3351 Bridge replacement from AT CIBOLO CREEK | 2 of 9 | $12,867,778 | +2.0% |
| 02 NOV 2023 | 11233208 | San Antonio District | IH 410 Intersection improvements with right and/or left from AT SOUTHCROS | 1 of 3 | $8,150,777 | Low, 12% under the second |
| 02 AUG 2023 | 08233033 | San Antonio District | RM 473 Hazard elimination & safety from RM 474 to 0.1 MI EAST OF RM 474 | 1 of 4 | $640,687 | Low, 2.0% under the second |
| 02 AUG 2023 | 08233048 | San Antonio District | CS Construct pedestrian infrastructure from ON EL CAMINO REAL FROM TRAIL ST to HOSPITAL BLVD (HWY 97) | 1 of 7 | $1,044,921 | Low, 0.0% under the second |
| 28 JUN 2023 | 06233623 | San Antonio District | VA Widen road - add shoulders from ON POST OAK TR., IN FAIR OAKS RANCH to FROM POST OAK TR. TO ROLLING ACRES | 3 of 4 | $2,232,373 | +4.0% |
| 01 JUN 2023 | 06233039 | San Antonio District | CR Bridge replacement from CR 2615 @ MEDINA RIVER | 2 of 4 | $831,628 | +14% |
| 07 SEP 2022 | 09223039 | San Antonio District | FM 2790 Rehabilitate existing roadway from FISCHER RD. to IH 410 | 2 of 8 | $7,997,716 | +4.0% |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.