TxDOT contract A00059994 bid tabulation
Construct Ramps, IH 37 (LP 13 to IH 410). Let by Texas DOT on May 6, 2026, Bexar, San Antonio District. 5 bids received; low bid $33,122,615 by Hunter Industries, LTD., -3.5% against the engineer's estimate of $34,315,721.
- Owner
- Texas DOT
- Letting
- 06 MAY 2026
- Pay items
- 385
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $33,122,615 | Low | -3.0% |
| 2 | Jordan Foster Construction, LLC | $33,402,427 | +1.0% | -3.0% |
| 3 | Capital Excavation Company | $34,315,676 | +4.0% | 0.0% |
| 4 | Urban Infraconstruction LLC | $34,417,509 | +4.0% | 0.0% |
| 5 | J3 Company, LLC | $35,211,397 | +6.0% | +3.0% |
Engineer's estimate: $34,315,721.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. Jordan Foster Construction, LLC | 3. Capital Excavation Company | 4. Urban Infraconstruction LLC | 5. J3 Company, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 112 | $10,000 | $4,070.00 | $7,455.89 | $2,800.00 | $6,000.00 | $8,000.00 |
| 2 | Removing concrete (mowstrip) (104-7003) | SY | 1,388 | $30.00 | $19.80 | $10.20 | $19.00 | $19.44 | $15.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 1,676 | $12.00 | $23.10 | $10.20 | $16.30 | $19.18 | $20.00 |
| 4 | Removing concrete (medians) (104-7008) | SY | 5,783 | $18.00 | $23.10 | $6.00 | $12.95 | $13.79 | $20.00 |
| 5 | Removing concrete (driveways) (104-7011) | SY | 215 | $20.00 | $26.40 | $14.00 | $41.70 | $19.10 | $25.00 |
| 6 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 1,403 | $18.00 | $19.80 | $8.00 | $16.30 | $16.21 | $15.00 |
| 7 | Removing concrete (curb) (104-7016) | LF | 4,789 | $5.00 | $16.50 | $3.00 | $14.35 | $3.86 | $6.00 |
| 8 | Removing concrete (traffic barrier) (104-7035) | LF | 175 | $10.00 | $60.50 | $25.00 | $51.45 | $74.97 | $25.00 |
| 9 | Remove (18"-22") TRT/untrt base & asphalt pavement (105-7018) | SY | 19,952 | $10.00 | $14.55 | $7.00 | $10.00 | $12.88 | $15.00 |
| 10 | Remove (15") TRT/untrt base & asphalt pavement (105-7035) | SY | 873 | $8.00 | $10.99 | $24.00 | $39.60 | $27.58 | $30.00 |
| 11 | Excavation (roadway) (110-7001) | CY | 28,142 | $18.00 | $24.20 | $21.00 | $9.00 | $15.00 | $30.00 |
| 12 | Embankment (final)(DC)(type C1) (132-7008) | CY | 5,090 | $16.00 | $37.47 | $29.00 | $54.00 | $40.00 | $60.00 |
| 13 | Embankment (final)(OC)(type C2) (132-7009) | CY | 13,729 | $8.00 | $37.02 | $29.00 | $23.00 | $45.00 | $35.00 |
| 14 | Embankment (final)(OC)(type C2)(DS) (132-7039) | CY | 7,348 | $40.00 | $65.12 | $46.00 | $130.00 | $58.00 | $115.00 |
| 15 | Furn & place topsoil (4") (160-7002) | SY | 77,020 | $1.50 | $1.93 | $2.50 | $3.20 | $2.20 | $3.00 |
| 16 | Drill seed (permanent_urban_clay) (164-7012) | SY | 77,020 | $0.22 | $0.25 | $0.25 | $0.19 | $0.25 | $0.25 |
| 17 | Drill seed (temporary_warm_cool) (164-7015) | SY | 75,524 | $0.20 | $0.22 | $0.15 | $0.19 | $0.19 | $0.15 |
| 18 | Vegetative watering (168-7001) | TGL | 2,400 | $25.00 | $29.70 | $30.00 | $41.05 | $30.00 | $20.14 |
| 19 | Soil ret BLKT(SL_mod_clay_long_roll) (169-7010) | SY | 149,838 | $3.00 | $2.75 | $1.50 | $1.29 | $2.98 | $1.45 |
| 20 | Irrigation system (170-7001) | LS | 1 | $35,000 | $72,541 | $75,000 | $152,535 | $180,520 | $145,000 |
| 21 | Mulch (192-7001) | CY | 1,394 | $85.00 | $75.36 | $78.00 | $53.70 | $103.00 | $60.00 |
| 22 | Plant bed preparation (192-7009) | SY | 12,557 | $9.50 | $6.14 | $6.35 | $6.45 | $4.00 | $8.00 |
| 23 | Plant material (15 gal) (tree) (192-7037) | EACH | 498 | $150.00 | $224.96 | $230.00 | $177.00 | $315.00 | $212.00 |
| 24 | Plant material (min 4' TRNK HT)(palm) (192-7063) | EACH | 39 | $700.00 | $1,284.13 | $1,330.00 | $810.00 | $1,293.00 | $767.00 |
| 25 | Landscape establish (193-7001) | MO | 9 | $3,500.00 | $5,775.84 | $6,000.00 | $7,000.00 | $3,125.00 | $5,230.00 |
| 26 | Irrig sys oper and maintenance (193-7007) | MO | 9 | $3,500.00 | $3,491.28 | $3,600.00 | $4,830.00 | $2,083.00 | $2,090.00 |
| 27 | Proof rolling (216-7001) | HR | 19 | $100.00 | $121.00 | $142.00 | $96.20 | $328.57 | $200.00 |
| 28 | FL BS(cip)(type D, GR 1-2 or 5)(final pos) (247-7192) | CY | 8,341 | $60.00 | $68.84 | $85.00 | $70.00 | $60.00 | $65.00 |
| 29 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 285 | $350.00 | $385.00 | $312.00 | $370.00 | $308.00 | $360.00 |
| 30 | Lime TRT (existing material)(6") (260-7006) | SY | 18,923 | $4.40 | $4.40 | $6.15 | $5.60 | $10.31 | $10.00 |
| 31 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 8,853 | $4.50 | $7.70 | $3.95 | $4.05 | $4.16 | $5.00 |
| 32 | D-GR HMA type-B PG64-22 (341-7001) | TON | 21,800 | $95.00 | $101.20 | $83.00 | $85.90 | $68.63 | $92.00 |
| 33 | D-GR HMA type D PG70-22 (341-7048) | TON | 1,165 | $115.00 | $117.70 | $84.00 | $86.65 | $97.10 | $105.00 |
| 34 | SP mixes SP-C sac-B PG76-22 (344-7031) | TON | 9,610 | $95.00 | $113.30 | $100.00 | $104.00 | $90.49 | $110.00 |
| 35 | Stone-MTRX-asphalt SMA-C sac-A PG76-22 (346-7001) | TON | 15,182 | $150.00 | $169.40 | $136.00 | $141.00 | $127.60 | $145.00 |
| 36 | Flexible pavement structure repair(6") (351-7005) | SY | 1,172 | $50.00 | $55.19 | $61.00 | $63.40 | $35.08 | $70.00 |
| 37 | Planing asphalt concrete pavement(2") (354-7051) | SY | 50,431 | $1.80 | $2.20 | $1.70 | $1.74 | $3.00 | $2.25 |
| 38 | Planing asphalt concrete pavement (1" to 2") (354-7076) | SY | 3,512 | $2.10 | $2.20 | $3.05 | $3.15 | $1.50 | $4.00 |
| 39 | Planing asphalt concrete pavement (2.5") (354-7082) | SY | 84,987 | $3.00 | $2.20 | $1.80 | $1.85 | $2.00 | $2.50 |
| 40 | Cut & restoring pavement (400-7006) | SY | 99 | $175.00 | $238.60 | $220.00 | $134.00 | $69.14 | $200.00 |
| 41 | Flowable backfill (401-7001) | CY | 194 | $185.00 | $326.45 | $198.00 | $228.00 | $200.00 | $220.00 |
| 42 | Trench excavation protection (402-7001) | LF | 1,800 | $9.00 | $45.18 | $2.30 | $10.00 | $2.10 | $5.00 |
| 43 | Temporary special shoring (403-7001) | SF | 21,393 | $25.00 | $1.99 | $28.00 | $1.70 | $29.76 | $20.00 |
| 44 | Drilled shaft (24 in) (416-7004) | LF | 60 | $260.00 | $275.00 | $220.00 | $215.00 | $230.00 | $240.00 |
| 45 | Drilled shaft (30 in) (416-7005) | LF | 1,980 | $320.00 | $218.82 | $180.00 | $210.00 | $179.01 | $150.00 |
| 46 | Drilled shaft (36 in) (416-7006) | LF | 672 | $250.00 | $291.20 | $290.00 | $290.00 | $350.59 | $180.00 |
| 47 | Drilled shaft (48 in) (416-7008) | LF | 438 | $270.00 | $583.89 | $600.00 | $530.00 | $489.66 | $340.00 |
| 48 | Drilled shaft (non - reinforced) (12 in) (416-7024) | LF | 7 | $140.00 | $165.00 | $165.00 | $177.00 | $150.00 | $185.00 |
| 49 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 22 | $280.00 | $200.00 | $220.00 | $215.00 | $260.00 | $300.00 |
| 50 | Drilled shaft (sign mounts) (42 in) (416-7031) | LF | 1,000 | $360.00 | $390.00 | $470.00 | $480.00 | $420.00 | $460.00 |
| 51 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 108 | $900.00 | $700.00 | $830.00 | $750.00 | $830.00 | $900.00 |
| 52 | Drilled shaft (traffic signal pole) (24 in) (416-7042) | LF | 24 | $240.00 | $200.00 | $280.00 | $215.00 | $270.00 | $300.00 |
| 53 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 91 | $420.00 | $305.00 | $390.00 | $330.00 | $330.00 | $410.00 |
| 54 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 88 | $570.00 | $415.00 | $520.00 | $450.00 | $490.00 | $550.00 |
| 55 | Sound wall (419-7001) | SF | 13,720 | $55.00 | $50.65 | $53.00 | $52.25 | $70.00 | $60.00 |
| 56 | Class C concrete (abutment) (420-7012) | CY | 22.20 | $1,100.00 | $1,600.00 | $2,100.00 | $2,270.00 | $1,700.00 | $1,250.00 |
| 57 | Class C concrete (cap) (420-7022) | CY | 84.90 | $1,000.00 | $1,600.00 | $2,100.00 | $1,990.00 | $2,000.00 | $1,500.00 |
| 58 | Class C concrete (column) (420-7038) | CY | 92.70 | $1,550.00 | $1,600.00 | $2,000.00 | $1,880.00 | $1,500.00 | $1,500.00 |
| 59 | Class C concrete (footing) (420-7044) | CY | 124 | $1,400.00 | $1,600.00 | $1,450.00 | $2,120.00 | $1,400.00 | $1,250.00 |
| 60 | Class C concrete (rail foundation) (420-7052) | CY | 84 | $500.00 | $525.66 | $600.00 | $900.00 | $350.00 | $750.00 |
| 61 | Class C concrete (sign column) (420-7057) | CY | 467 | $1,200.00 | $1,800.00 | $1,350.00 | $1,100.00 | $1,000.00 | $1,400.00 |
| 62 | Class C concrete (collar) (420-7061) | EACH | 14 | $1,000.00 | $750.00 | $1,400.00 | $980.00 | $400.00 | $2,500.00 |
| 63 | Class C concrete (vehicle defl wall) (420-7062) | CY | 217.80 | $500.00 | $1,400.00 | $1,200.00 | $1,350.00 | $1,200.00 | $1,250.00 |
| 64 | Reinforced concrete slab (422-7001) | SF | 7,000 | $20.00 | $36.50 | $36.00 | $34.75 | $30.00 | $45.00 |
| 65 | Approach slab (422-7013) | CY | 51 | $750.00 | $800.00 | $780.00 | $960.00 | $600.00 | $750.00 |
| 66 | Retaining wall (MSE) (423-7001) | SF | 31,007 | $73.00 | $53.50 | $65.00 | $60.00 | $63.00 | $65.00 |
| 67 | Prestressed concrete girder (TX28) (425-7001) | LF | 992 | $200.00 | $220.00 | $210.00 | $260.00 | $230.91 | $250.00 |
| 68 | Riprap (concrete)(4 in) (432-7001) | CY | 169.10 | $575.00 | $485.09 | $500.00 | $870.00 | $510.32 | $550.00 |
| 69 | Riprap (concrete)(CL B) (432-7005) | CY | 24 | $600.00 | $520.26 | $920.00 | $1,070.00 | $924.94 | $600.00 |
| 70 | Riprap (mow strip)(4 in) (432-7013) | CY | 273.60 | $605.00 | $583.90 | $600.00 | $900.00 | $963.66 | $700.00 |
| 71 | Riprap (stone protection)(18 in) (432-7043) | CY | 59 | $250.00 | $202.82 | $450.00 | $242.00 | $262.78 | $275.00 |
| 72 | Cleaning and sealing existing joints (438-7001) | LF | 160 | $70.00 | $48.52 | $39.00 | $23.70 | $50.00 | $55.00 |
| 73 | Rail (type SSTR) (450-7024) | LF | 3,061 | $70.00 | $100.00 | $73.00 | $90.15 | $55.00 | $110.00 |
| 74 | Rail (type C223) (450-7034) | LF | 83 | $250.00 | $300.00 | $340.00 | $360.00 | $255.00 | $300.00 |
| 75 | Rail (handrail)(type E) (450-7062) | LF | 50 | $200.00 | $195.15 | $290.00 | $246.00 | $185.86 | $300.00 |
| 76 | Rail (type SSTR)(mod) (450-7066) | LF | 500 | $150.00 | $350.00 | $188.00 | $208.00 | $280.00 | $200.00 |
| 77 | Retrofit rail (type SSTR) (451-7024) | LF | 1,126 | $250.00 | $350.00 | $380.00 | $270.00 | $125.00 | $220.00 |
| 78 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 85 | $200.00 | $225.00 | $300.00 | $320.00 | $249.18 | $220.00 |
| 79 | Header type expansion joint (454-7009) | CF | 34 | $500.00 | $492.79 | $390.00 | $490.00 | $300.00 | $500.00 |
| 80 | Joint sealant (454-7010) | LF | 160 | $20.00 | $30.33 | $24.00 | $19.20 | $20.00 | $40.00 |
| 81 | Concrete box culvert (4 FT X 2 FT)(extend) (462-7058) | LF | 24 | $700.00 | $446.18 | $1,410.00 | $570.00 | $489.35 | $1,500.00 |
| 82 | Concrete box culvert (5 FT X 3 FT)(extend) (462-7062) | LF | 654 | $900.00 | $491.37 | $550.00 | $600.00 | $457.80 | $600.00 |
| 83 | Concrete box culvert (8 FT X 4 FT)(extend) (462-7076) | LF | 838 | $1,105.00 | $734.22 | $750.00 | $840.00 | $754.84 | $800.00 |
| 84 | Concrete box culvert (10 FT X 6 FT)(extend) (462-7089) | LF | 86 | $1,600.00 | $1,005.32 | $1,300.00 | $1,360.00 | $977.81 | $1,800.00 |
| 85 | RC pipe (CL III)(18 in) (464-7003) | LF | 938 | $90.00 | $110.70 | $105.00 | $117.00 | $183.76 | $110.00 |
| 86 | RC pipe (CL III)(24 in) (464-7005) | LF | 473 | $120.00 | $129.90 | $110.00 | $185.00 | $179.16 | $135.00 |
| 87 | Inlet (complete)(pco)(3FT)(left) (465-7014) | EACH | 4 | $7,500.00 | $5,083.10 | $10,000 | $8,200.00 | $8,776.27 | $8,000.00 |
| 88 | Inlet (complete)(pco)(3FT)(right) (465-7015) | EACH | 4 | $8,500.00 | $5,083.10 | $10,000 | $8,100.00 | $8,776.27 | $8,000.00 |
| 89 | Inlet(complete)(pazd)(FG)(3FTX3FT-3FTX3FT) (465-7158) | EACH | 1 | $8,000.00 | $6,325.63 | $13,000 | $5,500.00 | $6,407.02 | $8,000.00 |
| 90 | Inlet (complete)(armor curb slot) (465-7335) | EACH | 8 | $3,000.00 | $4,758.08 | $8,000.00 | $4,840.00 | $7,280.55 | $7,500.00 |
| 91 | Inlet(complete)(type MSE1) (465-7362) | EACH | 4 | $5,000.00 | $9,079.05 | $11,000 | $8,300.00 | $4,852.02 | $10,000 |
| 92 | Inlet (complete)(type sidewalk bridge)(mod) (465-7374) | EACH | 15 | $20,000 | $21,432 | $19,000 | $19,000 | $23,472 | $22,500 |
| 93 | Wingwall (FW - 0) (HW=5 FT) (466-7147) | EACH | 1 | $18,000 | $11,296 | $45,000 | $21,800 | $44,445 | $30,000 |
| 94 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 1 | $25,000 | $33,887 | $50,000 | $7,000.00 | $25,218 | $30,000 |
| 95 | Wingwall (SW - 0) (HW=10 FT) (mod) (466-7228) | EACH | 1 | $70,000 | $46,256 | $85,000 | $47,700 | $88,676 | $80,000 |
| 96 | Set (type I)(S= 4 FT)(HW= 3 FT)(6:1)(C) (467-7069) | EACH | 1 | $12,000 | $6,061.31 | $13,500 | $18,600 | $12,717 | $11,500 |
| 97 | Set (type I)(S= 4 FT)(HW= 4 FT)(4:1)(C) (467-7072) | EACH | 1 | $13,500 | $6,569.62 | $13,500 | $18,500 | $12,683 | $13,500 |
| 98 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 5 | $1,357.00 | $1,355.49 | $1,370.00 | $2,540.00 | $1,911.00 | $2,000.00 |
| 99 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 1 | $1,400.00 | $1,637.89 | $1,510.00 | $2,970.00 | $2,054.90 | $2,000.00 |
| 100 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $1,300.00 | $1,637.89 | $1,510.00 | $2,970.00 | $2,054.88 | $2,000.00 |
| 101 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $2,000.00 | $1,807.32 | $1,700.00 | $3,320.00 | $2,084.92 | $2,000.00 |
| 102 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 4 | $2,100.00 | $1,807.32 | $1,880.00 | $3,380.00 | $2,252.45 | $2,000.00 |
| 103 | Thermoplastic pipe (HDPE) (18") (468-7007) | LF | 42 | $60.00 | $110.70 | $102.00 | $430.00 | $215.60 | $105.00 |
| 104 | Adjusting inlets (cap) (479-7006) | EACH | 4 | $3,000.00 | $3,671.12 | $4,800.00 | $3,220.00 | $2,736.07 | $3,000.00 |
| 105 | Clean existing culverts (480-7001) | EACH | 8 | $3,700.00 | $2,823.94 | $2,600.00 | $5,300.00 | $3,424.08 | $5,000.00 |
| 106 | Pipe (PVC) (schedule 80) (12 in) (481-7030) | LF | 150 | $150.00 | $97.14 | $77.00 | $155.00 | $181.97 | $50.00 |
| 107 | Removing structure (inlet) (496-7002) | EACH | 10 | $1,000.00 | $2,823.94 | $1,580.00 | $2,090.00 | $2,035.55 | $1,000.00 |
| 108 | Removing structure (set) (496-7004) | EACH | 4 | $800.00 | $1,411.97 | $900.00 | $1,080.00 | $2,518.19 | $1,000.00 |
| 109 | Removing structure (wingwall) (496-7005) | EACH | 3 | $5,000.00 | $1,411.97 | $3,100.00 | $17,100 | $9,223.02 | $3,000.00 |
| 110 | Removing structure (headwall) (496-7006) | EACH | 2 | $5,000.00 | $1,411.97 | $2,800.00 | $5,900.00 | $4,629.01 | $3,000.00 |
| 111 | Removing structure (pipe) (496-7007) | LF | 100 | $20.00 | $32.76 | $45.00 | $21.65 | $125.00 | $75.00 |
| 112 | Remove STR (rail) (496-7017) | LF | 129 | $20.00 | $25.65 | $21.00 | $45.70 | $63.91 | $75.00 |
| 113 | Mobilization (500-7001) | LS | 1 | $3,176,905 | $2,749,227 | $3,306,840 | $2,775,000 | $2,578,955 | $3,000,000 |
| 114 | Barricades, signs and traffic handling (502-7001) | MO | 27 | $15,000 | $8,382.88 | $20,500 | $38,000 | $29,388 | $28,000 |
| 115 | Portable changeable message sign (503-7001) | DAY | 12 | $75.00 | $150.00 | $114.00 | $260.00 | $144.95 | $250.00 |
| 116 | Portable changeable message sign (503-7002) | EACH | 3 | $7,500.00 | $5,000.00 | $7,000.00 | $25,700 | $12,807 | $10,000 |
| 117 | TMA (stationary) (505-7001) | DAY | 710 | $200.00 | $150.00 | $360.00 | $340.00 | $541.25 | $150.00 |
| 118 | TMA (mobile operation) (505-7003) | DAY | 14 | $120.00 | $750.00 | $780.00 | $940.00 | $1,434.31 | $1,000.00 |
| 119 | Rock filter dams (install) (type 2) (506-7002) | LF | 1,210 | $40.00 | $49.59 | $43.00 | $38.65 | $42.00 | $40.00 |
| 120 | Rock filter dams (remove) (506-7011) | LF | 1,210 | $12.00 | $20.80 | $7.75 | $12.90 | $8.00 | $8.00 |
| 121 | Construction exits (install) (type 1) (506-7020) | SY | 720 | $25.00 | $40.16 | $20.00 | $26.85 | $25.00 | $20.00 |
| 122 | Construction exits (remove) (506-7024) | SY | 720 | $5.00 | $13.10 | $4.90 | $12.90 | $6.00 | $8.00 |
| 123 | Temporary sediment control fence (install) (506-7039) | LF | 9,050 | $4.00 | $4.09 | $3.25 | $3.45 | $3.30 | $3.25 |
| 124 | Temporary sediment control fence (remove) (506-7041) | LF | 9,050 | $1.00 | $1.05 | $0.25 | $1.05 | $0.80 | $0.75 |
| 125 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 640 | $5.30 | $6.99 | $6.90 | $6.45 | $6.00 | $5.00 |
| 126 | Biodegradable erosion control logs (remove) (506-7046) | LF | 640 | $1.00 | $1.05 | $1.00 | $1.05 | $4.00 | $0.75 |
| 127 | Constructing detours (508-7001) | SY | 9,261 | $78.00 | $105.19 | $106.00 | $120.00 | $121.19 | $128.00 |
| 128 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 11,610 | $30.00 | $25.00 | $35.00 | $74.50 | $49.39 | $25.00 |
| 129 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 3,340 | $20.00 | $30.00 | $25.00 | $18.90 | $43.41 | $25.00 |
| 130 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 240 | $35.00 | $30.00 | $70.00 | $18.90 | $48.65 | $30.00 |
| 131 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 12,260 | $7.00 | $11.00 | $5.85 | $14.20 | $11.36 | $8.00 |
| 132 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 6,120 | $6.00 | $14.00 | $10.00 | $10.30 | $7.89 | $8.00 |
| 133 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 280 | $20.00 | $14.00 | $20.00 | $10.30 | $14.06 | $10.00 |
| 134 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 11,610 | $10.00 | $10.00 | $8.55 | $31.00 | $14.52 | $12.00 |
| 135 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 3,340 | $8.00 | $10.00 | $9.30 | $18.90 | $20.09 | $12.00 |
| 136 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 240 | $10.00 | $10.00 | $29.00 | $18.90 | $29.15 | $12.00 |
| 137 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 50 | $95.00 | $350.00 | $260.00 | $167.00 | $245.00 | $250.00 |
| 138 | Permanent CTB (single slope) (type 3) (42 ) (514-7002) | LF | 125 | $250.00 | $350.00 | $310.00 | $246.00 | $265.00 | $250.00 |
| 139 | Colored textured concrete (4") (527-7001) | SY | 5,595 | $95.00 | $83.16 | $84.00 | $110.00 | $154.50 | $80.00 |
| 140 | Concrete curb (type I) (529-7001) | LF | 12,202 | $16.00 | $14.38 | $14.50 | $17.05 | $44.62 | $15.00 |
| 141 | Intersections (concrete) (530-7001) | SY | 214 | $140.00 | $102.68 | $160.00 | $206.00 | $142.90 | $140.00 |
| 142 | Intersections (ACP) (530-7002) | SY | 205 | $70.00 | $72.60 | $133.00 | $132.00 | $82.90 | $125.00 |
| 143 | Concrete sidewalks (5") (531-7002) | SY | 5,289 | $75.00 | $72.76 | $68.00 | $86.85 | $106.53 | $70.00 |
| 144 | Curb ramps (type 1) (531-7005) | EACH | 10 | $2,800.00 | $2,966.00 | $3,200.00 | $1,990.00 | $3,917.29 | $2,500.00 |
| 145 | Curb ramps (type 2) (531-7006) | EACH | 1 | $3,200.00 | $2,656.47 | $3,200.00 | $2,940.00 | $3,919.01 | $2,500.00 |
| 146 | Curb ramps (type 7) (531-7010) | EACH | 6 | $2,800.00 | $2,945.21 | $3,200.00 | $1,970.00 | $3,917.25 | $2,500.00 |
| 147 | Curb ramps (type 21) (531-7023) | SY | 531 | $250.00 | $202.12 | $108.00 | $310.00 | $245.53 | $200.00 |
| 148 | Metal W-beam guard fence (timber post) (540-7001) | LF | 3,075 | $25.00 | $25.80 | $26.00 | $27.70 | $25.80 | $25.80 |
| 149 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 16 | $2,250.00 | $2,406.00 | $1,910.00 | $2,050.00 | $1,906.00 | $1,906.00 |
| 150 | Downstream anchor terminal section (540-7015) | EACH | 6 | $1,200.00 | $1,234.00 | $1,230.00 | $1,330.00 | $1,234.00 | $1,234.00 |
| 151 | Metal beam guard fence (long span system) (540-7027) | EACH | 1 | $1,000.00 | $1,174.00 | $1,170.00 | $1,260.00 | $1,174.00 | $1,174.00 |
| 152 | Remove metal beam guard fence (542-7001) | LF | 4,029 | $3.00 | $2.75 | $2.75 | $2.95 | $2.75 | $2.75 |
| 153 | Remove terminal anchor section (542-7002) | EACH | 6 | $220.00 | $265.00 | $270.00 | $280.00 | $265.00 | $265.00 |
| 154 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 12 | $300.00 | $234.00 | $230.00 | $250.00 | $234.00 | $234.00 |
| 155 | Guardrail end treatment (install) (544-7001) | EACH | 9 | $3,200.00 | $3,459.00 | $3,500.00 | $3,720.00 | $3,459.00 | $3,459.00 |
| 156 | Guardrail end treatment (remove) (544-7003) | EACH | 7 | $300.00 | $266.00 | $270.00 | $290.00 | $266.00 | $266.00 |
| 157 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 11 | $1,500.00 | $724.00 | $720.00 | $780.00 | $724.00 | $724.00 |
| 158 | Crash cushion attenuator (remove) (545-7004) | EACH | 5 | $850.00 | $677.00 | $680.00 | $730.00 | $677.00 | $677.00 |
| 159 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 5 | $7,000.00 | $7,695.00 | $7,700.00 | $8,300.00 | $7,695.00 | $7,695.00 |
| 160 | Pipe underdrains (type 6) (6") (556-7006) | LF | 2,701 | $25.00 | $37.65 | $21.00 | $32.80 | $51.57 | $25.00 |
| 161 | Pipe underdrains (type 8) (6") (556-7008) | LF | 6,448 | $35.00 | $41.51 | $22.00 | $31.65 | $34.00 | $25.00 |
| 162 | Remove RD IL asm (trans-base) (610-7009) | EACH | 19 | $1,000.00 | $365.00 | $550.00 | $390.00 | $320.00 | $333.67 |
| 163 | Replace luminaire W/(150W EQ) LED (610-7011) | EACH | 12 | $600.00 | $500.00 | $550.00 | $540.00 | $470.00 | $490.08 |
| 164 | Replace luminaire W/(250W EQ) LED (610-7012) | EACH | 17 | $700.00 | $515.00 | $660.00 | $550.00 | $450.00 | $469.23 |
| 165 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 6 | $1,900.00 | $1,540.00 | $2,000.00 | $1,650.00 | $1,900.00 | $1,981.18 |
| 166 | HI MST IL pole (150 FT)( 80 MPH) (613-7005) | EACH | 3 | $60,000 | $47,500 | $56,000 | $51,024 | $52,900 | $55,160 |
| 167 | LED HI MST IL asm(6 fixt) (type A)SHLD (614-7009) | EACH | 3 | $40,000 | $43,500 | $45,000 | $46,700 | $47,600 | $49,634 |
| 168 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 8,800 | $12.00 | $11.00 | $9.35 | $11.80 | $8.30 | $8.65 |
| 169 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 1,560 | $20.00 | $12.00 | $12.00 | $12.90 | $11.00 | $11.47 |
| 170 | Conduit (PVC) (schedule 40) (3") (concrete encse) (618-7038) | LF | 15,330 | $25.00 | $21.00 | $15.00 | $22.55 | $24.00 | $25.03 |
| 171 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 2,315 | $17.90 | $11.00 | $10.50 | $11.80 | $14.00 | $14.60 |
| 172 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 4,395 | $30.00 | $20.00 | $31.00 | $21.50 | $22.00 | $22.94 |
| 173 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 1,905 | $22.50 | $12.00 | $15.50 | $12.90 | $16.00 | $16.68 |
| 174 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 3,945 | $32.00 | $23.00 | $35.00 | $24.70 | $27.50 | $28.68 |
| 175 | Conduit (PVC) (schedule 80) (3") (concrete encse) (618-7063) | LF | 4,030 | $50.00 | $22.00 | $16.50 | $23.65 | $26.00 | $27.11 |
| 176 | Conduit (RM) (2") (618-7078) | LF | 140 | $50.00 | $27.00 | $57.00 | $29.00 | $68.00 | $70.91 |
| 177 | Conduit (RM) (3") (618-7082) | LF | 440 | $60.00 | $55.00 | $61.00 | $59.10 | $52.00 | $54.22 |
| 178 | Conduit (prepare) (618-7090) | LF | 4,530 | $3.00 | $1.65 | $1.10 | $1.75 | $1.60 | $1.67 |
| 179 | Electrical conductor (no.14) insulated (620-7002) | LF | 11,325 | $1.10 | $0.95 | $1.10 | $1.00 | $0.90 | $0.94 |
| 180 | Electrical conductor (no.8) bare (620-7007) | LF | 1,115 | $1.90 | $1.75 | $1.65 | $1.90 | $1.65 | $1.72 |
| 181 | Electrical conductor (no.8) insulated (620-7008) | LF | 3,840 | $2.10 | $1.55 | $1.80 | $1.65 | $1.55 | $1.62 |
| 182 | Electrical conductor (no.6) bare (620-7009) | LF | 6,825 | $2.30 | $1.75 | $2.20 | $1.90 | $1.70 | $1.77 |
| 183 | Electrical conductor (no.6) insulated (620-7010) | LF | 5,125 | $2.50 | $1.95 | $2.30 | $2.10 | $2.15 | $2.24 |
| 184 | Electrical conductor (no.4) bare (620-7011) | LF | 6,780 | $2.80 | $2.60 | $3.30 | $2.80 | $2.85 | $2.97 |
| 185 | Electrical conductor (no.4) insulated (620-7012) | LF | 17,050 | $3.10 | $2.80 | $3.45 | $3.00 | $2.90 | $3.02 |
| 186 | Electrical conductor (no.2) insulated (620-7016) | LF | 7,760 | $4.90 | $4.25 | $4.80 | $4.55 | $4.50 | $4.69 |
| 187 | Tray cable (3 conductor) (12 AWG) (621-7002) | LF | 2,485 | $3.00 | $2.35 | $2.75 | $2.50 | $2.55 | $2.66 |
| 188 | Tray cable (4 conductor) (14 AWG) (621-7005) | LF | 4,900 | $3.25 | $3.20 | $3.70 | $3.45 | $3.55 | $3.70 |
| 189 | ITS GND box(pcast) type 1 (243636)W/aprn (623-7002) | EACH | 31 | $5,400.00 | $5,500.00 | $4,700.00 | $5,900.00 | $4,800.00 | $5,005.10 |
| 190 | ITS GND box(pcast) type 2 (366036)W/aprn (623-7008) | EACH | 2 | $8,500.00 | $7,200.00 | $8,000.00 | $7,700.00 | $7,600.00 | $7,924.74 |
| 191 | Ground box type A (122311) (624-7001) | EACH | 14 | $1,200.00 | $965.00 | $1,100.00 | $1,040.00 | $1,000.00 | $1,042.73 |
| 192 | Ground box type A (122311)W/apron (624-7002) | EACH | 12 | $1,500.00 | $965.00 | $1,570.00 | $1,040.00 | $1,300.00 | $1,355.55 |
| 193 | Ground box type D (162922) (624-7007) | EACH | 1 | $1,500.00 | $1,025.00 | $1,320.00 | $1,100.00 | $1,200.00 | $1,251.27 |
| 194 | Ground box type D (162922)W/apron (624-7008) | EACH | 24 | $1,800.00 | $1,100.00 | $1,960.00 | $1,180.00 | $1,600.00 | $1,668.37 |
| 195 | Remove ground box (624-7013) | EACH | 41 | $440.00 | $245.00 | $880.00 | $260.00 | $780.00 | $813.33 |
| 196 | Timber pole (CL 2) 40 FT (627-7003) | EACH | 70 | $4,600.00 | $1,425.00 | $2,000.00 | $1,530.00 | $2,000.00 | $2,085.46 |
| 197 | Remove electrical services (628-7002) | EACH | 5 | $790.00 | $545.00 | $880.00 | $590.00 | $400.00 | $417.09 |
| 198 | Elc SRV type A 120/240 060(NS)SS(E)SP(O) (628-7009) | EACH | 1 | $9,700.00 | $6,000.00 | $9,500.00 | $6,400.00 | $8,060.00 | $8,404.39 |
| 199 | Elc SRV type A 120/240 100(NS)SS(E)SP(O) (628-7025) | EACH | 1 | $9,200.00 | $6,600.00 | $10,200 | $7,100.00 | $8,400.00 | $8,758.92 |
| 200 | Elc SRV type D 120/240 060(NS)SS(N)SP(O) (628-7156) | EACH | 4 | $8,400.00 | $5,100.00 | $8,500.00 | $5,500.00 | $6,400.00 | $6,673.46 |
| 201 | Elc SRV type D 120/240 070(NS)SS(E)PS(U) (628-7190) | EACH | 1 | $9,000.00 | $6,600.00 | $9,800.00 | $7,100.00 | $6,700.00 | $6,986.28 |
| 202 | Elc SRV type T 120/240 000(NS)GS(N)SP(U) (628-7327) | EACH | 1 | $7,000.00 | $3,600.00 | $7,200.00 | $3,870.00 | $4,400.00 | $4,588.00 |
| 203 | Aluminum signs (type A) (636-7001) | SF | 340 | $45.00 | $25.00 | $39.00 | $26.85 | $39.00 | $23.25 |
| 204 | Aluminum signs (type G) (636-7002) | SF | 205 | $30.00 | $28.00 | $43.00 | $30.10 | $32.00 | $43.40 |
| 205 | Aluminum signs (type O) (636-7003) | SF | 6,137 | $30.00 | $26.80 | $39.00 | $28.80 | $32.00 | $33.37 |
| 206 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 21 | $720.00 | $750.00 | $620.00 | $810.00 | $600.00 | $600.00 |
| 207 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 32 | $800.00 | $850.00 | $670.00 | $920.00 | $650.00 | $650.00 |
| 208 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $950.00 | $1,215.00 | $770.00 | $1,310.00 | $750.00 | $750.00 |
| 209 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 14 | $1,000.00 | $1,100.00 | $850.00 | $1,190.00 | $825.00 | $825.00 |
| 210 | Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049) | EACH | 2 | $2,100.00 | $2,125.00 | $1,690.00 | $2,290.00 | $1,650.00 | $1,650.00 |
| 211 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 2 | $2,200.00 | $2,203.82 | $2,800.00 | $2,950.00 | $2,500.00 | $2,958.81 |
| 212 | Install small roadside sign support and assembly (rail mount) (644-7063) | EACH | 1 | $4,500.00 | $4,565.30 | $6,200.00 | $6,400.00 | $2,200.00 | $5,713.56 |
| 213 | Remove SM RD SN sup&AM (644-7073) | EACH | 72 | $115.00 | $135.39 | $72.00 | $78.40 | $70.00 | $149.64 |
| 214 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 4 | $120.00 | $82.61 | $51.00 | $56.00 | $50.00 | $50.00 |
| 215 | Install LRSS (struct steel) (647-7001) | LB | 1,381 | $7.00 | $8.00 | $8.80 | $8.60 | $6.45 | $6.73 |
| 216 | Remove lrsa (647-7003) | EACH | 5 | $1,200.00 | $500.00 | $880.00 | $540.00 | $530.00 | $552.65 |
| 217 | Install overhead sign support(30 FT cant)(span only) (650-7034) | EACH | 1 | $20,000 | $23,900 | $25,000 | $25,700 | $26,900 | $28,049 |
| 218 | Install overhead sign support(90 FT BRDG)(span only) (650-7101) | EACH | 1 | $111,000 | $87,300 | $102,000 | $93,777 | $98,600 | $102,813 |
| 219 | Install overhead sign support(100 FT BRDG)(span only) (650-7111) | EACH | 1 | $115,000 | $99,300 | $120,000 | $106,667 | $113,378 | $118,223 |
| 220 | Install overhead sign support(110 FT BRDG)(span only) (650-7121) | EACH | 3 | $130,000 | $112,500 | $139,000 | $120,847 | $128,196 | $133,673 |
| 221 | Install overhead sign support(130 FT BRDG)(span only) (650-7141) | EACH | 1 | $135,000 | $142,000 | $172,000 | $152,535 | $157,748 | $164,488 |
| 222 | Remove overhd sign sup (650-7193) | EACH | 1 | $15,000 | $5,500.00 | $10,500 | $5,900.00 | $7,700.00 | $8,029.01 |
| 223 | Remove overhd sign sup (sign only) (650-7194) | EACH | 12 | $1,000.00 | $660.00 | $1,790.00 | $1,750.00 | $440.00 | $458.80 |
| 224 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 39 | $20.00 | $25.00 | $15.50 | $27.00 | $15.00 | $15.00 |
| 225 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 35 | $40.00 | $43.50 | $26.00 | $46.95 | $25.00 | $25.00 |
| 226 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 11 | $30.00 | $25.00 | $15.50 | $27.00 | $15.00 | $32.65 |
| 227 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 21 | $30.00 | $43.50 | $26.00 | $46.95 | $25.00 | $40.81 |
| 228 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 9 | $85.00 | $105.00 | $154.00 | $113.00 | $150.00 | $87.06 |
| 229 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 69 | $10.00 | $32.50 | $51.00 | $35.10 | $50.00 | $47.61 |
| 230 | Install OM SM RD sign (2-OM-PW)Y (658-7319) | EACH | 2 | $20.00 | $32.50 | $51.00 | $35.10 | $50.00 | $47.62 |
| 231 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 6,306 | $0.30 | $0.80 | $0.31 | $0.85 | $0.30 | $0.30 |
| 232 | Work zone pavement marking non-removing (W)6"(DOT) (662-7006) | LF | 387 | $1.10 | $2.10 | $0.31 | $2.25 | $0.30 | $0.30 |
| 233 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 25,905 | $0.25 | $0.43 | $0.31 | $0.45 | $0.30 | $0.30 |
| 234 | Work zone pavement marking non-removing (W)8"(DOT) (662-7010) | LF | 67 | $0.80 | $2.20 | $1.05 | $2.40 | $1.00 | $1.00 |
| 235 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 16,944 | $0.50 | $0.60 | $0.42 | $0.65 | $0.40 | $0.40 |
| 236 | Work zone pavement marking non-removing (W)12"(DOT) (662-7013) | LF | 782 | $1.79 | $2.25 | $2.10 | $2.45 | $2.00 | $2.00 |
| 237 | Work zone pavement marking non-removing (W)12"(solid) (662-7015) | LF | 2,027 | $3.00 | $2.35 | $2.60 | $2.55 | $2.50 | $2.50 |
| 238 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 1,902 | $4.00 | $4.75 | $3.40 | $5.15 | $3.25 | $3.25 |
| 239 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 67 | $88.00 | $82.00 | $104.00 | $88.55 | $100.00 | $100.00 |
| 240 | Work zone pavement marking non-removing (W)(double arrow) (662-7019) | EACH | 5 | $100.00 | $95.00 | $156.00 | $103.00 | $150.00 | $150.00 |
| 241 | Work zone pavement marking non-removing (W)(uturn arrow) (662-7027) | EACH | 4 | $125.00 | $115.00 | $156.00 | $124.00 | $150.00 | $150.00 |
| 242 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 45 | $95.00 | $95.00 | $104.00 | $103.00 | $100.00 | $100.00 |
| 243 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 20,375 | $0.30 | $0.30 | $0.37 | $0.30 | $0.35 | $0.35 |
| 244 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 3,191 | $1.00 | $0.95 | $1.55 | $1.05 | $1.50 | $1.50 |
| 245 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 32 | $1.90 | $2.15 | $2.10 | $2.30 | $2.00 | $2.00 |
| 246 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 26,110 | $0.75 | $0.75 | $0.99 | $0.80 | $0.95 | $0.95 |
| 247 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 2,234 | $1.40 | $1.50 | $1.30 | $1.60 | $1.25 | $1.25 |
| 248 | Work zone pavement marking removing (W)12"(solid) (662-7075) | LF | 337 | $5.00 | $3.25 | $6.25 | $3.50 | $6.00 | $6.00 |
| 249 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 183 | $7.00 | $5.35 | $12.50 | $5.80 | $12.00 | $12.00 |
| 250 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 10 | $180.00 | $135.00 | $156.00 | $146.00 | $150.00 | $150.00 |
| 251 | Work zone pavement marking removing (W)(word) (662-7092) | EACH | 9 | $250.00 | $160.00 | $156.00 | $173.00 | $150.00 | $150.00 |
| 252 | Work zone pavement marking removing (W)36"(yld tri) (662-7094) | EACH | 37 | $80.00 | $57.00 | $15.50 | $61.55 | $15.00 | $15.00 |
| 253 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 22,448 | $0.80 | $0.75 | $0.99 | $0.80 | $0.95 | $0.95 |
| 254 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 3,187 | $0.90 | $1.72 | $2.80 | $9.95 | $2.00 | $2.00 |
| 255 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 1,693 | $1.40 | $1.72 | $2.80 | $9.95 | $2.00 | $2.00 |
| 256 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 374 | $1.20 | $1.67 | $2.10 | $1.80 | $2.00 | $2.00 |
| 257 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 65 | $2.00 | $1.85 | $2.10 | $2.00 | $2.00 | $2.00 |
| 258 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 16,459 | $0.90 | $0.95 | $0.99 | $1.05 | $0.95 | $0.95 |
| 259 | Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027) | LF | 759 | $1.40 | $1.85 | $2.35 | $2.00 | $2.25 | $2.25 |
| 260 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 2,925 | $3.50 | $3.85 | $3.15 | $4.15 | $3.00 | $3.00 |
| 261 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,837 | $7.00 | $7.65 | $6.25 | $8.25 | $6.00 | $6.00 |
| 262 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 69 | $150.00 | $135.00 | $156.00 | $146.00 | $150.00 | $150.00 |
| 263 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 6 | $200.00 | $190.00 | $260.00 | $205.00 | $250.00 | $250.00 |
| 264 | Reflectorized pavement marking type I(W)(uturn arrow)(100MIL) (666-7051) | EACH | 5 | $250.00 | $200.00 | $310.00 | $216.00 | $300.00 | $300.00 |
| 265 | Reflectorized pavement marking type I (W)(number)(100MIL) (666-7063) | EACH | 3 | $200.00 | $280.00 | $260.00 | $300.00 | $250.00 | $250.00 |
| 266 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 47 | $190.00 | $160.00 | $210.00 | $173.00 | $200.00 | $200.00 |
| 267 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 113 | $3.00 | $3.85 | $3.15 | $4.15 | $3.00 | $3.00 |
| 268 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 29,789 | $0.65 | $0.93 | $0.94 | $1.00 | $0.90 | $0.90 |
| 269 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 30,014 | $0.65 | $0.93 | $0.94 | $1.00 | $0.90 | $0.90 |
| 270 | Pavement sler 6" (666-7347) | LF | 73,655 | $0.20 | $0.22 | $0.37 | $0.24 | $0.35 | $0.35 |
| 271 | Pavement sler 8" (666-7348) | LF | 16,524 | $0.40 | $0.37 | $0.47 | $0.40 | $0.45 | $0.45 |
| 272 | Pavement sler 12" (666-7350) | LF | 3,797 | $1.30 | $0.88 | $1.55 | $0.95 | $1.50 | $1.50 |
| 273 | Pavement sler 24" (666-7352) | LF | 1,837 | $2.50 | $2.60 | $3.15 | $2.80 | $3.00 | $3.00 |
| 274 | Pavement sler (arrow) (666-7353) | EACH | 69 | $40.00 | $25.00 | $78.00 | $27.00 | $75.00 | $75.00 |
| 275 | Pavement sler (word) (666-7354) | EACH | 47 | $50.00 | $32.00 | $78.00 | $34.55 | $75.00 | $75.00 |
| 276 | Pavement sler (double arrow) (666-7356) | EACH | 6 | $60.00 | $38.00 | $104.00 | $41.05 | $100.00 | $100.00 |
| 277 | Pavement sler (uturn arrow) (666-7358) | EACH | 5 | $60.00 | $40.00 | $104.00 | $43.20 | $100.00 | $100.00 |
| 278 | Pavement sler (symbol) (666-7363) | EACH | 2 | $60.00 | $95.00 | $260.00 | $103.00 | $250.00 | $250.00 |
| 279 | Pavement sler (number) (666-7367) | EACH | 3 | $100.00 | $11.00 | $78.00 | $11.90 | $75.00 | $75.00 |
| 280 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 8,729 | $0.57 | $0.70 | $0.63 | $0.75 | $0.60 | $0.60 |
| 281 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 4,749 | $0.55 | $0.64 | $0.63 | $0.70 | $0.60 | $0.60 |
| 282 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 4,560 | $0.49 | $0.64 | $0.63 | $0.70 | $0.60 | $0.60 |
| 283 | Prefabricated PM type C (multi)(shield) (668-7135) | EACH | 2 | $2,500.00 | $3,300.00 | $3,100.00 | $3,560.00 | $3,000.00 | $3,000.00 |
| 284 | Reflectorized pavement marker type I-C (672-7002) | EACH | 24 | $3.50 | $5.00 | $4.70 | $5.40 | $4.50 | $4.50 |
| 285 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 6 | $3.50 | $5.00 | $4.70 | $5.40 | $4.50 | $4.50 |
| 286 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 1,171 | $4.20 | $5.00 | $4.70 | $5.40 | $4.50 | $4.50 |
| 287 | Eliminating existing PM & markers (4") (677-7001) | LF | 11,240 | $0.20 | $0.85 | $0.61 | $0.90 | $0.58 | $0.58 |
| 288 | Eliminating existing PM & markers (8") (677-7004) | LF | 4,644 | $0.90 | $1.40 | $0.83 | $1.50 | $0.80 | $0.80 |
| 289 | Eliminating existing PM & markers (12") (677-7006) | LF | 302 | $1.50 | $2.00 | $3.15 | $2.15 | $3.00 | $3.00 |
| 290 | Eliminating existing PM & markers (24") (677-7008) | LF | 74 | $2.50 | $2.75 | $6.25 | $2.95 | $6.00 | $6.00 |
| 291 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 3 | $70.00 | $40.00 | $156.00 | $43.20 | $150.00 | $150.00 |
| 292 | Eliminating existing PM & markers (word) (677-7015) | EACH | 2 | $75.00 | $45.00 | $156.00 | $48.60 | $150.00 | $150.00 |
| 293 | Pavement surface preparation for marking (6") (678-7002) | LF | 73,655 | $0.08 | $0.05 | $0.02 | $0.05 | $0.02 | $0.02 |
| 294 | Pavement surface preparation for marking (8") (678-7004) | LF | 16,524 | $0.15 | $0.05 | $0.04 | $0.05 | $0.04 | $0.04 |
| 295 | Pavement surface preparation for marking (12") (678-7006) | LF | 3,797 | $0.40 | $0.30 | $0.21 | $0.30 | $0.20 | $0.20 |
| 296 | Pavement surface preparation for marking (24") (678-7008) | LF | 1,837 | $1.00 | $0.50 | $0.26 | $0.55 | $0.25 | $0.25 |
| 297 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 69 | $26.00 | $11.00 | $10.50 | $11.90 | $10.00 | $10.00 |
| 298 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 6 | $30.00 | $15.00 | $21.00 | $16.20 | $20.00 | $20.00 |
| 299 | Pavement surface preparation for marking (uturn arr) (678-7012) | EACH | 5 | $15.00 | $20.00 | $21.00 | $21.60 | $20.00 | $20.00 |
| 300 | Pavement surface preparation for marking (number) (678-7015) | EACH | 3 | $15.00 | $15.00 | $21.00 | $16.20 | $20.00 | $20.00 |
| 301 | Pavement surface preparation for marking (word) (678-7016) | EACH | 47 | $20.00 | $15.00 | $21.00 | $16.20 | $20.00 | $20.00 |
| 302 | Pavement surface preparation for marking (shield) (678-7025) | EACH | 2 | $90.00 | $50.00 | $21.00 | $54.00 | $20.00 | $20.00 |
| 303 | Install highway traffic signal (system) (680-7003) | EACH | 2 | $40,000 | $59,000 | $64,000 | $63,377 | $1,900.00 | $1,981.19 |
| 304 | Install highway traffic signal (upgrade) (680-7011) | EACH | 1 | $7,500.00 | $7,200.00 | $13,800 | $7,700.00 | $1,900.00 | $1,981.18 |
| 305 | Removing traffic signals (diamond) (680-7012) | EACH | 1 | $19,100 | $6,900.00 | $16,500 | $7,400.00 | $6,100.00 | $6,360.64 |
| 306 | Temporary traffic signals (681-7001) | EACH | 8 | $77,500 | $31,600 | $28,000 | $33,900 | $47,200 | $49,217 |
| 307 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 10 | $325.00 | $265.00 | $360.00 | $280.00 | $310.00 | $323.25 |
| 308 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 42 | $335.00 | $265.00 | $360.00 | $280.00 | $310.00 | $323.25 |
| 309 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 10 | $325.00 | $265.00 | $360.00 | $280.00 | $310.00 | $323.25 |
| 310 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 42 | $335.00 | $265.00 | $360.00 | $280.00 | $310.00 | $323.25 |
| 311 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 10 | $325.00 | $265.00 | $360.00 | $280.00 | $310.00 | $323.25 |
| 312 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 41 | $340.00 | $265.00 | $360.00 | $280.00 | $310.00 | $323.25 |
| 313 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 20 | $830.00 | $720.00 | $790.00 | $770.00 | $760.00 | $792.47 |
| 314 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 49 | $180.00 | $150.00 | $193.00 | $161.00 | $160.00 | $166.84 |
| 315 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 2 | $250.00 | $215.00 | $250.00 | $231.00 | $230.00 | $239.83 |
| 316 | Traffic signal CBL (type A)(12 AWG)(9 conductor) (684-7014) | LF | 20,845 | $5.50 | $4.80 | $5.75 | $5.15 | $5.35 | $5.58 |
| 317 | Traffic signal CBL (type A)(14 AWG)(3 conductor) (684-7029) | LF | 8,815 | $2.85 | $1.75 | $2.20 | $1.90 | $1.65 | $1.72 |
| 318 | Traffic signal CBL (type A)(14 AWG)(4 conductor) (684-7030) | LF | 760 | $2.20 | $2.00 | $2.40 | $2.15 | $2.10 | $2.19 |
| 319 | Ins traffic signal PL AM(S)1 arm(44')ilsn (686-7046) | EACH | 2 | $19,500 | $15,000 | $17,400 | $16,100 | $15,900 | $16,579 |
| 320 | Ins traffic signal PL AM(S)1 arm(44')lum&ilsn (686-7048) | EACH | 1 | $21,000 | $16,800 | $19,700 | $18,000 | $17,800 | $18,561 |
| 321 | Ins traffic signal PL AM(S)1 arm(48')ilsn (686-7050) | EACH | 2 | $19,500 | $17,100 | $18,400 | $18,400 | $16,600 | $17,309 |
| 322 | Ins traffic signal PL AM(S)1 arm(48')lum&ilsn (686-7052) | EACH | 2 | $20,050 | $18,900 | $20,000 | $20,300 | $18,400 | $19,186 |
| 323 | Ins traffic signal PL AM(S)1 arm(55')ilsn (686-7058) | EACH | 1 | $37,000 | $38,100 | $42,000 | $40,900 | $37,600 | $39,207 |
| 324 | Ins traffic signal PL AM(S)1 arm(55')lum&ilsn (686-7060) | EACH | 2 | $50,000 | $39,300 | $43,000 | $42,200 | $38,000 | $39,624 |
| 325 | Ins traffic signal PL AM(S)1 arm(65')lum&ilsn (686-7068) | EACH | 1 | $52,000 | $40,100 | $45,000 | $43,100 | $39,700 | $41,396 |
| 326 | Pedestrian pole assembly (687-7001) | EACH | 30 | $3,100.00 | $2,300.00 | $1,490.00 | $2,470.00 | $1,300.00 | $1,355.55 |
| 327 | Remove pedestrian pole assembly (687-7005) | EACH | 5 | $1,050.00 | $245.00 | $990.00 | $260.00 | $99.00 | $103.23 |
| 328 | Pedestrian detect push button (APS) (688-7001) | EACH | 20 | $1,100.00 | $1,030.00 | $1,020.00 | $1,110.00 | $910.00 | $948.88 |
| 329 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $3,500.00 | $2,710.00 | $4,200.00 | $2,910.00 | $3,600.00 | $3,753.82 |
| 330 | Removal of conduit (690-7001) | LF | 1,630 | $3.00 | $2.30 | $3.30 | $2.45 | $7.55 | $7.87 |
| 331 | Removal of ground boxes (690-7006) | EACH | 16 | $220.00 | $245.00 | $220.00 | $260.00 | $110.00 | $114.70 |
| 332 | Removal of cables (690-7009) | LF | 35,035 | $1.10 | $0.50 | $1.40 | $0.55 | $0.65 | $0.68 |
| 333 | Removal of timber poles (690-7021) | EACH | 69 | $1,010.00 | $245.00 | $440.00 | $260.00 | $330.00 | $344.10 |
| 334 | Removal of signal head assembly (690-7024) | EACH | 33 | $100.00 | $245.00 | $55.00 | $260.00 | $36.00 | $37.54 |
| 335 | Removal of signal related signs (690-7027) | EACH | 14 | $75.00 | $245.00 | $55.00 | $260.00 | $31.00 | $32.32 |
| 336 | Removal of pedestrian push buttons (690-7030) | EACH | 18 | $50.00 | $40.00 | $110.00 | $42.95 | $18.00 | $18.77 |
| 337 | Removal of traffic signal pole FND (690-7033) | LF | 16 | $400.00 | $2,825.00 | $390.00 | $3,030.00 | $250.00 | $364.96 |
| 338 | Removal of control cabinet(GRND MNT) (690-7038) | EACH | 1 | $1,150.00 | $245.00 | $880.00 | $260.00 | $410.00 | $427.52 |
| 339 | Removal of signal pole assembly (690-7051) | EACH | 8 | $1,840.00 | $900.00 | $1,320.00 | $970.00 | $320.00 | $333.67 |
| 340 | Remove radar vehicle detection system (690-7136) | EACH | 3 | $500.00 | $245.00 | $550.00 | $260.00 | $160.00 | $166.84 |
| 341 | Replace transformer base cover (690-7198) | EACH | 17 | $100.00 | $200.00 | $330.00 | $215.00 | $390.00 | $406.66 |
| 342 | Replace breakaway fuse holder (690-7220) | EACH | 17 | $200.00 | $202.00 | $220.00 | $215.00 | $200.00 | $208.55 |
| 343 | Full - width mowing (730-7019) | CYC | 10 | $6,000.00 | $6,824.94 | $4,400.00 | $5,200.00 | $5,574.22 | $6,000.00 |
| 344 | Litter removal (734-7002) | CYC | 54 | $2,900.00 | $2,357.37 | $1,260.00 | $530.00 | $2,738.92 | $3,250.00 |
| 345 | Debris removing-CNTR med/MN LNS/ramps (735-7001) | MI | 54 | $150.00 | $589.34 | $3,250.00 | $1,030.00 | $2,468.29 | $1,500.00 |
| 346 | Cleaning / sweeping (outside main lane) (738-7028) | CYC | 27 | $5,000.00 | $3,969.93 | $1,680.00 | $1,470.00 | $1,600.00 | $2,000.00 |
| 347 | Cleaning / sweeping (frontage road) (738-7050) | CYC | 27 | $5,000.00 | $2,977.45 | $2,100.00 | $184.00 | $1,600.00 | $2,500.00 |
| 348 | Cleaning / sweeping(entrance/exit ramp) (738-7071) | CYC | 27 | $2,500.00 | $1,984.96 | $1,680.00 | $184.00 | $1,600.00 | $2,500.00 |
| 349 | Anti-graffiti coating (permnent-type II) (740-7005) | SF | 51,987 | $1.00 | $0.81 | $0.77 | $0.84 | $0.87 | $1.00 |
| 350 | Underseal course (3006-7001) | GAL | 28,999 | $3.70 | $4.84 | $3.95 | $4.05 | $3.40 | $4.50 |
| 351 | Bonding course (3007-7001) | GAL | 4,519 | $2.90 | $3.52 | $3.55 | $3.45 | $3.17 | $5.00 |
| 352 | Install bridge identification numbers (4019-7001) | EACH | 5 | $500.00 | $549.48 | $350.00 | $280.00 | $300.00 | $500.00 |
| 353 | Ilsn (8D) (6001-7004) | EACH | 11 | $4,250.00 | $5,700.00 | $4,700.00 | $217.00 | $3,300.00 | $3,441.00 |
| 354 | Install DMS (foundation MTD cabinet) (6004-7002) | EACH | 2 | $18,020 | $20,000 | $14,300 | $21,500 | $19,200 | $20,020 |
| 355 | ITS RVSD (data collect & wwa) sys (6010-7001) | EACH | 1 | $13,900 | $17,100 | $15,900 | $18,400 | $12,500 | $13,034 |
| 356 | Remove ITS RSVD (DC only) (6010-7003) | EACH | 2 | $500.00 | $245.00 | $550.00 | $260.00 | $380.00 | $396.24 |
| 357 | ITS pole MNT cab (type 1)(conf 2) (6011-7017) | EACH | 2 | $6,400.00 | $6,500.00 | $5,800.00 | $7,000.00 | $5,100.00 | $5,317.92 |
| 358 | Ground box (prepare) (6013-7006) | EACH | 4 | $440.00 | $290.00 | $880.00 | $310.00 | $230.00 | $239.83 |
| 359 | CCTV field equipment (digital) (6018-7002) | EACH | 2 | $8,000.00 | $8,000.00 | $1,650.00 | $8,600.00 | $1,700.00 | $1,772.64 |
| 360 | Remove CCTV field equipment (6018-7008) | EACH | 2 | $2,000.00 | $245.00 | $550.00 | $260.00 | $430.00 | $448.38 |
| 361 | Fiber optic CBL (single-mode)(12 fiber) (6027-7001) | LF | 9,185 | $4.50 | $4.80 | $2.20 | $5.15 | $3.20 | $3.34 |
| 362 | Fiber optic patch panel (12 position) (6027-7005) | EACH | 8 | $1,450.00 | $2,752.00 | $940.00 | $2,960.00 | $1,000.00 | $1,042.73 |
| 363 | Fiber optic CBL(single-mode)(144 fiber) (6027-7006) | LF | 11,080 | $4.00 | $6.20 | $3.85 | $6.65 | $7.65 | $7.98 |
| 364 | Fiber optic patch panel (36 positions) (6027-7007) | EACH | 1 | $3,300.00 | $6,400.00 | $1,980.00 | $6,900.00 | $1,300.00 | $1,355.55 |
| 365 | Fiber optic patch panel (144 positions) (6027-7008) | EACH | 1 | $8,600.00 | $25,000 | $6,300.00 | $26,900 | $2,300.00 | $2,398.28 |
| 366 | Fiber optic CBL (SNGL-mode)(48 fiber) (6027-7013) | LF | 70 | $6.00 | $6.25 | $5.50 | $6.70 | $400.00 | $417.09 |
| 367 | Fiber optic CBL (48 SMF)(aerial) (6027-7016) | LF | 9,690 | $20.00 | $6.80 | $4.40 | $7.30 | $10.00 | $10.43 |
| 368 | Remove fiber optic cable (6027-7018) | LF | 48,400 | $1.45 | $3.00 | $1.10 | $3.20 | $0.95 | $0.99 |
| 369 | Ethernet switch (install only) (6036-7001) | EACH | 7 | $1,010.00 | $275.00 | $830.00 | $300.00 | $400.00 | $417.09 |
| 370 | Install wrong way driver detection sys (6038-7001) | EACH | 2 | $62,500 | $61,100 | $71,000 | $65,633 | $48,500 | $50,572 |
| 371 | Remove wrong way driver detection sys (6038-7003) | EACH | 1 | $5,000.00 | $485.00 | $1,980.00 | $520.00 | $630.00 | $656.92 |
| 372 | Remove existing GND MT comm cabinet (6050-7002) | EACH | 3 | $4,090.00 | $2,900.00 | $2,200.00 | $3,120.00 | $200.00 | $208.55 |
| 373 | Install GND MT comm cabinet foundation (6050-7003) | EACH | 1 | $5,630.00 | $7,800.00 | $4,600.00 | $8,400.00 | $4,500.00 | $4,692.28 |
| 374 | ITS GRND MNT cab (type 4) (conf 1) (6050-7007) | EACH | 1 | $19,000 | $7,425.00 | $11,700 | $8,000.00 | $40,600 | $42,335 |
| 375 | ITS GRND MNT cab (type 6)(conf 2) (6050-7009) | EACH | 2 | $21,000 | $13,220 | $17,200 | $14,200 | $29,000 | $30,239 |
| 376 | Remove DMS (6054-7003) | EACH | 2 | $10,000 | $2,500.00 | $6,100.00 | $2,690.00 | $4,000.00 | $4,170.92 |
| 377 | Remove existing fiber hub (6080-7002) | EACH | 1 | $9,700.00 | $4,825.00 | $8,300.00 | $5,200.00 | $1,000.00 | $1,042.73 |
| 378 | LCS signal unit (remove) (6095-7001) | EACH | 2 | $490.00 | $2,025.00 | $550.00 | $2,180.00 | $1,400.00 | $1,459.82 |
| 379 | Feds processor unit (6100-7001) | EACH | 2 | $28,000 | $15,245 | $21,000 | $16,400 | $15,200 | $15,849 |
| 380 | Feds fish eye camera assembly (6100-7002) | EACH | 6 | $5,500.00 | $3,965.00 | $6,800.00 | $4,260.00 | $3,800.00 | $3,962.37 |
| 381 | Lifetime feds data collect & reporting (6100-7004) | EACH | 2 | $800.00 | $11,525 | $13,100 | $12,400 | $11,400 | $11,887 |
| 382 | Fed ethernet repeater (6100-7005) | EACH | 2 | $1,500.00 | $1,565.00 | $3,000.00 | $1,680.00 | $1,500.00 | $1,564.10 |
| 383 | Feds comm cable (ethernet - CAT5E) (6100-7006) | LF | 2,600 | $0.25 | $1.60 | $3.30 | $1.70 | $1.40 | $1.46 |
| 384 | Temporary travel time system (2 sys) (6105-7001) | DAY | 191 | $50.00 | $425.00 | $55.00 | $211.00 | $750.00 | $350.00 |
| 385 | Existing manhole adjustments (7041-7002) | EACH | 1 | $5,000.00 | $5,000.00 | $8,200.00 | $1,680.00 | $1,342.48 | $3,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.