Rail (handrail)(type E), TxDOT 450-7062

Low bidders on TxDOT contracts carried a median of $178.00 per LF for this item, over the 24 months to 19 NOV 2026, across 28 low bids. Half of all 175 bids fell between $150.00 and $229.00.

Owner
Texas DOT
Item
450-7062
Unit
LF
Data through
19 NOV 2026

TxDOT prints this item as “RAIL (HANDRAIL)(TY E)”.

TxDOT has bid this work under more than one code: 4506051 on lettings from 10 JAN 2020 to 01 DEC 2021 (132 bids); 4506051001 on lettings from 04 FEB 2022 to 10 JUL 2024 (104 bids); 450-7062 on lettings from 06 NOV 2024 to 04 NOV 2026 (192 bids). They are combined here into one trend.

$178.00Low bidder's median, per LF
$190.00Median of all bids, per LF
28Contracts in the window
$166.00Engineer's estimate, median per LF

By year of letting

Rail (handrail)(type E), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201111$98.0068$105.24
20211313$100.0064$134.00
202288$149.5026$159.15
20231111$165.0052$183.50
20241111$163.3347$180.00
20251111$170.0065$200.00
20261616$187.57106$189.50

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District7$165.4850$188.75
Atlanta District3$130.0024$168.95
Austin District3$176.0021$176.00
Rail (handrail)(type E), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
24 to 567$235.00
67 to 1677$180.00
202 to 6227$180.00
838 to 5,0607$135.00
Rail (handrail)(type E), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Rail (handrail)(type E), TxDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00206976Austin District374$176.00$181.50$150.009Lone Star Sitework, LLCTxDOT
03 NOV 2026A00184974Austin District5,060$236.66$275.82$151.006Austin Bridge & Road Services, LPTxDOT
07 OCT 2026A00135746Dallas District414$180.00$160.00$160.009Garret Shields InfrastructureTxDOT
07 OCT 2026A00132124Lufkin District926$152.00$190.00$130.007Longview Bridge and Road, LTD.TxDOT
03 SEP 2026A00198323Dallas District50$375.00$247.67$200.008American Lighting and Signalization, LLCTxDOT
02 JUL 2026A00124174Lubbock District167$450.00$290.52$175.004Williams Brothers Construction Co., Inc.TxDOT
01 JUL 2026A00196687Dallas District110$140.00$200.00$225.009C & W Southern LLCTxDOT
03 JUN 2026A00191143Austin District1,772$135.00$143.50$145.006Dan Williams CompanyTxDOT
03 JUN 2026A00132662Abilene District30$235.00$235.00$190.001FNF Construction, Inc.TxDOT
02 JUN 2026A00064555Fort Worth District622$220.00$189.00$160.008Reyes TX, Inc.TxDOT
06 MAY 2026A00206714Atlanta District502$110.54$167.40$180.0011THK Construction LLCTxDOT
06 MAY 2026A00209252Beaumont District139$305.00$217.84$145.006R Construction Civil, LLCTxDOT
06 MAY 2026A00059994San Antonio District50$195.15$246.00$200.005Hunter Industries, LTD.TxDOT
07 APR 2026A00209966Amarillo District2,729$120.00$110.00n/a6L A Fuller & Sons Construction, LTD.TxDOT
04 MAR 2026A00062293Atlanta District2,105$130.00$143.00n/a7Highway 19 Construction LLCTxDOT
Latest TxDOT contracts carrying Rail (handrail)(type E)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy