TxDOT contract A00135746 bid tabulation
Construct Pedestrian Infrastructure, IH 35E (DART Victory Station to At IH 35E Southbound Frontage Roads). Let by Texas DOT on October 7, 2026, Dallas, Dallas District. 9 bids received; low bid $1,177,500 by Garret Shields Infrastructure, -7.5% against the engineer's estimate of $1,273,638.
- Owner
- Texas DOT
- Letting
- 07 OCT 2026
- Pay items
- 74
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Garret Shields Infrastructure | $1,177,500 | Low | -8.0% |
| 2 | Yoko Excavating, LLC | $1,183,544 | +1.0% | -7.0% |
| 3 | Ragle Construction, Inc. | $1,186,545 | +1.0% | -7.0% |
| 4 | Axis Contracting, Inc. | $1,219,953 | +4.0% | -4.0% |
| 5 | WG Engineering & Construction, LLC | $1,230,042 | +4.0% | -3.0% |
| 6 | Gibson & Associates, Inc. | $1,276,196 | +8.0% | 0.0% |
| 7 | Ed Bell Construction Company | $1,332,948 | +13% | +5.0% |
| 8 | Tucan Contracting, LLC | $1,411,848 | +20% | +11% |
| 9 | JR West Texas Concrete LLC | $1,553,329 | +32% | +22% |
Engineer's estimate: $1,273,638.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Garret Shields Infrastructure | 2. Yoko Excavating, LLC | 3. Ragle Construction, Inc. | 4. Axis Contracting, Inc. | 5. WG Engineering & Construction, LLC | 6. Gibson & Associates, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 1,371 | $23.00 | $20.00 | $10.00 | $16.50 | $25.00 | $20.00 | $27.50 |
| 2 | Removing concrete (curb) (104-7016) | LF | 17 | $45.00 | $20.00 | $73.69 | $40.00 | $31.50 | $23.00 | $50.00 |
| 3 | Removing concrete (curb & gutter) (104-7017) | LF | 32 | $40.00 | $20.00 | $35.07 | $42.00 | $31.50 | $22.00 | $40.00 |
| 4 | Removing concrete (coping) (104-7027) | LF | 14 | $80.00 | $50.00 | $123.50 | $72.00 | $80.00 | $95.00 | $50.00 |
| 5 | Removing concrete (rail) (104-7036) | LF | 14 | $160.00 | $50.00 | $182.00 | $55.00 | $50.00 | $120.00 | $65.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 25 | $150.00 | $40.00 | $112.00 | $600.00 | $156.00 | $40.00 | $171.60 |
| 7 | Embankment (final)(DC)(type C1) (132-7008) | CY | 14 | $40.00 | $40.00 | $132.93 | $76.30 | $100.00 | $45.00 | $50.00 |
| 8 | Embankment (final)(DC)(type C2) (132-7010) | CY | 542 | $35.00 | $40.00 | $81.14 | $110.00 | $178.20 | $120.00 | $134.00 |
| 9 | Drilled shaft (24 in) (416-7004) | LF | 88 | $175.00 | $300.00 | $340.64 | $186.00 | $302.50 | $192.00 | $200.88 |
| 10 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 12 | $430.00 | $400.00 | $474.36 | $409.00 | $449.90 | $420.00 | $441.72 |
| 11 | Retaining wall (MSE) (423-7001) | SF | 3,391 | $100.00 | $100.00 | $104.00 | $48.00 | $123.20 | $110.00 | $114.93 |
| 12 | Riprap (concrete)(4 in) (432-7001) | CY | 72 | $1,200.00 | $600.00 | $650.00 | $687.00 | $650.00 | $620.00 | $702.00 |
| 13 | Rail (handrail)(type E) (450-7062) | LF | 414 | $160.00 | $180.00 | $131.13 | $148.00 | $143.00 | $300.00 | $160.00 |
| 14 | RC pipe (CL III)(24 in) (464-7005) | LF | 13 | $200.00 | $120.00 | $277.92 | $124.00 | $120.00 | $210.00 | $132.00 |
| 15 | RC pipe (CL IV)(30 in) (464-7023) | LF | 50 | $150.00 | $180.00 | $147.07 | $200.00 | $195.00 | $220.00 | $214.50 |
| 16 | Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128) | EACH | 3 | $8,000.00 | $5,000.00 | $3,891.41 | $4,690.00 | $8,000.00 | $9,210.00 | $8,800.00 |
| 17 | Removing structure (inlet) (496-7002) | EACH | 3 | $1,000.00 | $500.00 | $1,451.54 | $1,000.00 | $800.00 | $1,300.00 | $880.00 |
| 18 | Removing structure (pipe) (496-7007) | LF | 85 | $45.00 | $30.00 | $41.90 | $40.00 | $30.00 | $42.00 | $33.00 |
| 19 | Mobilization (500-7001) | LS | 1 | $116,000 | $100,000 | $98,365 | $125,000 | $108,000 | $98,500 | $188,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $25,000 | $5,000.00 | $2,500.00 | $60,000 | $1,980.00 | $6,574.00 | $4,000.00 |
| 21 | TMA (stationary) (505-7001) | DAY | 7 | $300.00 | $1,000.00 | $455.00 | $286.00 | $237.60 | $280.00 | $350.00 |
| 22 | TMA (mobile operation) (505-7002) | HR | 8 | $100.00 | $100.00 | $715.00 | $62.00 | $82.50 | $135.00 | $350.00 |
| 23 | Construction exits (install) (type 1) (506-7020) | SY | 122 | $40.00 | $30.00 | $40.01 | $36.00 | $30.00 | $50.00 | $58.30 |
| 24 | Construction exits (remove) (506-7024) | SY | 122 | $25.00 | $5.00 | $15.98 | $11.00 | $10.00 | $20.00 | $34.10 |
| 25 | Temporary sediment control fence (install) (506-7039) | LF | 122 | $5.00 | $5.00 | $9.27 | $8.00 | $5.00 | $5.00 | $3.30 |
| 26 | Temporary sediment control fence (remove) (506-7041) | LF | 122 | $3.50 | $1.00 | $4.22 | $3.00 | $3.00 | $2.00 | $2.20 |
| 27 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 389 | $7.00 | $5.00 | $5.74 | $6.25 | $2.00 | $6.00 | $4.24 |
| 28 | Biodegradable erosion control logs (remove) (506-7046) | LF | 389 | $4.00 | $1.00 | $3.21 | $1.25 | $1.50 | $2.00 | $0.83 |
| 29 | Concrete sidewalks (6") (531-7003) | SY | 677 | $100.00 | $100.00 | $157.76 | $76.00 | $88.00 | $95.00 | $95.04 |
| 30 | Curb ramps (type 1) (531-7005) | EACH | 1 | $3,200.00 | $2,800.00 | $2,714.82 | $1,570.00 | $3,100.00 | $3,600.00 | $3,348.00 |
| 31 | Curb ramps (type 2) (531-7006) | EACH | 1 | $4,000.00 | $2,800.00 | $3,337.36 | $1,730.00 | $3,100.00 | $3,200.00 | $3,348.00 |
| 32 | Pipe underdrains (type 6) (6") (556-7006) | LF | 243 | $50.00 | $20.00 | $41.60 | $34.00 | $34.39 | $50.00 | $10.00 |
| 33 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,170 | $30.00 | $25.00 | $22.68 | $14.50 | $15.95 | $20.00 | $15.66 |
| 34 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 330 | $25.00 | $27.00 | $26.28 | $16.50 | $18.15 | $22.00 | $17.82 |
| 35 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 60 | $65.00 | $38.00 | $46.20 | $32.50 | $35.75 | $32.00 | $35.10 |
| 36 | Electrical conductor (no.12) insulated (620-7004) | LF | 100 | $3.00 | $3.36 | $3.00 | $1.50 | $1.65 | $1.80 | $1.62 |
| 37 | Electrical conductor (no.8) bare (620-7007) | LF | 1,030 | $2.50 | $4.00 | $3.00 | $2.20 | $2.42 | $2.60 | $2.38 |
| 38 | Electrical conductor (no.8) insulated (620-7008) | LF | 2,480 | $3.00 | $4.25 | $3.00 | $2.40 | $2.64 | $2.80 | $2.59 |
| 39 | Electrical conductor (no.6) bare (620-7009) | LF | 170 | $4.00 | $5.60 | $3.60 | $2.60 | $2.86 | $3.00 | $2.81 |
| 40 | Electrical conductor (no.6) insulated (620-7010) | LF | 210 | $4.00 | $6.00 | $3.60 | $3.10 | $3.41 | $3.50 | $3.35 |
| 41 | ITS GND box (poly) type 1 (243624)W/aprn (623-7014) | EACH | 1 | $5,000.00 | $8,600.00 | $4,797.60 | $3,086.00 | $3,394.60 | $3,454.00 | $3,332.88 |
| 42 | Ground box type A (122311)W/apron (624-7002) | EACH | 2 | $2,800.00 | $2,000.00 | $2,158.01 | $1,327.00 | $1,459.70 | $1,350.00 | $1,433.16 |
| 43 | Ground box type D (162922)W/apron (624-7008) | EACH | 2 | $2,800.00 | $2,000.00 | $2,340.00 | $1,391.00 | $1,530.10 | $1,500.00 | $1,502.28 |
| 44 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $12,000 | $20,000 | $9,360.00 | $10,205 | $11,226 | $9,485.00 | $11,021 |
| 45 | Aluminum signs (type A) (636-7001) | SF | 18 | $45.00 | $40.00 | $51.60 | $35.00 | $38.50 | $35.00 | $38.50 |
| 46 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 4 | $1,000.00 | $1,000.00 | $1,062.00 | $755.00 | $830.50 | $805.00 | $830.50 |
| 47 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 3 | $1,000.00 | $450.00 | $1,104.60 | $735.00 | $808.50 | $805.00 | $808.50 |
| 48 | Install small roadside sign support and assembly (rail mount) (644-7063) | EACH | 1 | $4,200.00 | $6,000.00 | $6,099.61 | $7,500.00 | $8,250.00 | $7,805.00 | $8,250.00 |
| 49 | Remove SM RD SN sup&AM (644-7073) | EACH | 6 | $115.00 | $500.00 | $420.00 | $150.00 | $165.00 | $150.00 | $165.00 |
| 50 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 50 | $3.00 | $10.21 | $7.20 | $6.00 | $6.60 | $3.00 | $7.17 |
| 51 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 145 | $8.00 | $15.50 | $8.70 | $7.25 | $7.97 | $10.00 | $21.51 |
| 52 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 50 | $5.00 | $9.50 | $6.00 | $5.00 | $5.50 | $2.00 | $2.75 |
| 53 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 145 | $6.00 | $8.00 | $8.40 | $7.00 | $7.70 | $6.00 | $8.25 |
| 54 | Reflectorized pavement marking type I (Y)4"(solid)(100MIL) (666-7417) | LF | 24 | $5.00 | $18.00 | $12.00 | $10.00 | $11.00 | $3.00 | $3.59 |
| 55 | Eliminating existing PM & markers (6") (677-7002) | LF | 92 | $2.00 | $6.00 | $6.00 | $5.00 | $5.50 | $3.00 | $3.03 |
| 56 | Pavement surface preparation for marking (8") (678-7004) | LF | 50 | $3.00 | $9.00 | $4.80 | $4.00 | $4.40 | $2.00 | $1.10 |
| 57 | Pavement surface preparation for marking (24") (678-7008) | LF | 145 | $4.00 | $4.00 | $7.20 | $6.00 | $6.60 | $3.00 | $3.30 |
| 58 | Ins HY traffic signal (DPT sup CNT & cab)(iso) (680-7005) | EACH | 1 | $35,000 | $15,000 | $23,760 | $14,211 | $15,632 | $19,500 | $15,348 |
| 59 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 2 | $650.00 | $450.00 | $477.60 | $326.00 | $358.60 | $345.00 | $352.08 |
| 60 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 4 | $650.00 | $450.00 | $477.60 | $326.00 | $358.60 | $345.00 | $352.08 |
| 61 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 2 | $1,000.00 | $1,200.00 | $1,182.00 | $754.00 | $829.40 | $825.00 | $814.32 |
| 62 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 2 | $200.00 | $400.00 | $300.00 | $225.00 | $247.50 | $220.00 | $243.00 |
| 63 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 235 | $6.00 | $6.50 | $4.74 | $4.50 | $4.95 | $4.00 | $4.86 |
| 64 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 40 | $11.00 | $12.50 | $9.48 | $7.70 | $8.47 | $6.80 | $8.32 |
| 65 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 175 | $4.00 | $4.75 | $2.58 | $3.20 | $3.52 | $3.50 | $3.46 |
| 66 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 1 | $13,000 | $24,000 | $24,714 | $20,573 | $22,630 | $17,458 | $22,219 |
| 67 | Pedestrian pole assembly (687-7001) | EACH | 2 | $3,100.00 | $15,000 | $3,320.54 | $3,821.00 | $4,203.10 | $3,800.00 | $4,126.68 |
| 68 | Pedestrian detect push button (APS) (688-7001) | EACH | 2 | $1,100.00 | $1,250.00 | $1,291.10 | $1,125.00 | $1,237.50 | $1,100.00 | $1,215.00 |
| 69 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $5,000.00 | $7,000.00 | $4,713.82 | $3,823.00 | $4,205.30 | $3,788.00 | $4,128.84 |
| 70 | Removable bollard (5005-7001) | EACH | 5 | $3,200.00 | $1,000.00 | $840.00 | $1,295.00 | $2,900.00 | $1,200.00 | $2,165.90 |
| 71 | RVDS (pres and adv)(install only) (6008-7006) | EACH | 1 | $1,800.00 | $1,300.00 | $2,238.00 | $1,252.00 | $1,377.20 | $1,200.00 | $1,352.16 |
| 72 | CCTV field equip (digital) (install only) (6018-7001) | EACH | 1 | $3,000.00 | $2,250.00 | $2,238.00 | $1,252.00 | $1,377.20 | $1,200.00 | $1,352.16 |
| 73 | Automated pedestrian detection system (6067-7002) | EACH | 1 | $50,000 | $100,000 | $78,318 | $68,868 | $75,755 | $70,258 | $74,377 |
| 74 | Pedestrain illumination assembly (6099-7001) | EACH | 11 | $6,500.00 | $7,000.00 | $7,908.00 | $4,881.00 | $4,701.40 | $6,652.00 | $5,271.48 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.