TxDOT contract A00206976 bid tabulation
Construct Pedestrian Infrastructure, RM 12 (Old Kyle Road to FM 3237). Let by Texas DOT on November 4, 2026, Hays, Austin District. 9 bids received; low bid $950,337 by Lone Star Sitework, LLC, +1.1% against the engineer's estimate of $939,603.
- Owner
- Texas DOT
- Letting
- 04 NOV 2026
- Pay items
- 75
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lone Star Sitework, LLC | $950,337 | Low | +1.0% |
| 2 | STX Civil | $1,083,834 | +14% | +15% |
| 3 | Rucoba & Maya Construction, LLC | $1,103,755 | +16% | +17% |
| 4 | Myers Concrete Construction, LP | $1,122,792 | +18% | +19% |
| 5 | Ti-Zack Concrete, LLC | $1,135,337 | +19% | +21% |
| 6 | Centerline Technologies, LLC | $1,199,801 | +26% | +28% |
| 7 | Ratliff Hardscape, LTD. | $1,228,710 | +29% | +31% |
| 8 | E-Z Bel Construction, LLC | $1,272,000 | +34% | +35% |
| 9 | Tight Line Construction, LLC | $1,700,314 | +79% | +81% |
Engineer's estimate: $939,603.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Lone Star Sitework, LLC | 2. STX Civil | 3. Rucoba & Maya Construction, LLC | 4. Myers Concrete Construction, LP | 5. Ti-Zack Concrete, LLC | 6. Centerline Technologies, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pavers) (104-7010) | SY | 5 | $40.00 | $40.00 | $13.10 | $25.00 | $459.00 | $158.10 | $110.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 133 | $25.00 | $25.50 | $19.17 | $45.00 | $53.00 | $59.44 | $18.50 |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 26 | $40.00 | $33.50 | $13.10 | $45.00 | $88.00 | $60.81 | $16.00 |
| 4 | Removing concrete (rail) (104-7036) | LF | 6 | $60.00 | $20.00 | $16.39 | $75.00 | $124.00 | $263.50 | $115.00 |
| 5 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 3,093 | $7.00 | $16.75 | $7.67 | $45.00 | $15.00 | $30.67 | $21.00 |
| 6 | Block sodding (162-7002) | SY | 59 | $10.00 | $15.50 | $14.85 | $40.00 | $17.00 | $22.00 | $24.50 |
| 7 | Loose aggregate GRND cover (192-7022) | SY | 21 | $30.00 | $27.50 | $19.80 | $95.00 | $52.00 | $11.00 | $185.00 |
| 8 | FL BS (compacted in place)(type A GR 5)(final pos) (247-7179) | CY | 452 | $60.00 | $146.00 | $96.33 | $85.00 | $158.00 | $34.98 | $98.00 |
| 9 | Prime coat (multi option) (310-7015) | GAL | 123 | $10.00 | $25.00 | $10.05 | $20.00 | $10.00 | $11.00 | $9.50 |
| 10 | D-GR HMA type-B PG64-22 (341-7001) | TON | 135 | $90.00 | $325.00 | $194.75 | $300.00 | $383.00 | $220.00 | $178.00 |
| 11 | D-GR HMA type D PG76-22 (341-7056) | TON | 68 | $110.00 | $337.00 | $225.66 | $300.00 | $585.00 | $220.00 | $242.00 |
| 12 | Drilled shaft (30 in) (416-7005) | LF | 22 | $325.00 | $550.00 | $579.24 | $378.00 | $1.00 | $495.00 | $340.02 |
| 13 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 22 | $400.00 | $550.00 | $495.00 | $378.00 | $467.00 | $495.00 | $340.02 |
| 14 | Riprap (concrete)(4 in) (432-7001) | CY | 4 | $750.00 | $875.00 | $923.10 | $720.00 | $1,164.00 | $677.69 | $575.00 |
| 15 | Rail (handrail)(type E) (450-7062) | LF | 374 | $150.00 | $176.00 | $181.50 | $155.15 | $150.00 | $275.00 | $142.00 |
| 16 | RC pipe (arch)(CL III)(des 3) (464-7042) | LF | 5 | $250.00 | $575.00 | $1,059.06 | $1,200.00 | $607.00 | $440.00 | $750.00 |
| 17 | Inlet (comp)(type sidewalk bridge) (465-7336) | EACH | 2 | $15,000 | $3,150.00 | $22,282 | $11,000 | $14,262 | $16,500 | $8,500.00 |
| 18 | Headwall (CH - PW - A - 0) (des= 3) (466-7129) | EACH | 1 | $15,000 | $2,850.00 | $13,601 | $12,000 | $4,576.00 | $16,500 | $12,500 |
| 19 | Grate (471-7001) | EACH | 1 | $2,000.00 | $2,750.00 | $2,990.74 | $2,500.00 | $4,350.00 | $2,228.51 | $2,400.00 |
| 20 | Adjusting manholes (479-7001) | EACH | 2 | $2,500.00 | $750.00 | $1,004.65 | $1,800.00 | $1,457.00 | $395.25 | $1,200.00 |
| 21 | Adjusting inlets (479-7002) | EACH | 1 | $2,500.00 | $2,100.00 | $1,081.93 | $2,200.00 | $2,539.00 | $790.50 | $1,445.00 |
| 22 | Adjusting manholes (water valve box) (479-7007) | EACH | 2 | $1,500.00 | $600.00 | $587.33 | $600.00 | $935.00 | $395.25 | $750.00 |
| 23 | Adjusting manholes (water meter) (479-7008) | EACH | 4 | $1,500.00 | $780.00 | $649.16 | $500.00 | $580.00 | $197.63 | $750.00 |
| 24 | Removing structure (set) (496-7004) | EACH | 1 | $500.00 | $1,250.00 | $850.00 | $500.00 | $839.00 | $1,650.00 | $1,300.00 |
| 25 | Mobilization (500-7001) | LS | 1 | $91,000 | $31,100 | $86,717 | $100,000 | $94,451 | $110,591 | $183,896 |
| 26 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $2,000.00 | $1,300.00 | $7,434.69 | $1,932.00 | $5,522.00 | $2,750.00 | $950.00 |
| 27 | Portable changeable message sign (503-7001) | DAY | 193 | $100.00 | $90.00 | $77.72 | $70.00 | $110.00 | $1.10 | $50.00 |
| 28 | TMA (stationary) (505-7001) | DAY | 193 | $175.00 | $300.00 | $155.00 | $235.00 | $130.00 | $1.10 | $200.00 |
| 29 | Biodegradable erosion control logs (install) (6") (506-7042) | LF | 502 | $5.00 | $4.00 | $3.85 | $12.60 | $6.00 | $1.10 | $11.50 |
| 30 | Rock filter dams (install) (type 1) 6:1 (506-7047) | LF | 10 | $125.00 | $144.00 | $137.50 | $157.50 | $132.00 | $1.10 | $185.00 |
| 31 | Concrete curb & gutter (type II) (529-7009) | LF | 345 | $35.00 | $37.00 | $35.48 | $42.00 | $41.00 | $49.44 | $26.50 |
| 32 | Concrete gutter (modified) (529-7011) | LF | 457 | $40.00 | $39.00 | $36.61 | $45.00 | $41.00 | $49.44 | $28.00 |
| 33 | Concrete curb (type F1) (529-7017) | LF | 353 | $160.00 | $48.00 | $46.29 | $135.00 | $134.00 | $271.91 | $350.00 |
| 34 | Concrete curb & gutter (slotted) (529-7021) | LF | 589 | $40.00 | $41.00 | $52.73 | $52.00 | $48.00 | $47.98 | $31.00 |
| 35 | Driveways (concrete) (530-7006) | SY | 1,073 | $125.00 | $111.00 | $128.10 | $105.00 | $113.00 | $126.75 | $135.00 |
| 36 | Driveways (ACP) (530-7010) | SY | 391 | $60.00 | $76.00 | $96.92 | $105.00 | $87.00 | $93.50 | $155.00 |
| 37 | Concrete sidewalks (5") (531-7002) | SY | 1,155 | $82.50 | $108.00 | $103.60 | $88.00 | $98.00 | $105.57 | $125.00 |
| 38 | Curb ramps (type 2) (531-7006) | EACH | 3 | $3,500.00 | $2,700.00 | $2,747.15 | $2,500.00 | $2,521.00 | $2,248.88 | $18.50 |
| 39 | Curb ramps (type 10) (531-7011) | EACH | 3 | $3,500.00 | $2,400.00 | $2,747.15 | $3,300.00 | $2,521.00 | $2,248.88 | $2,100.00 |
| 40 | Concrete sidewalks (special) (type A) (531-7029) | SY | 4 | $500.00 | $495.00 | $6,274.01 | $4,909.20 | $4,529.00 | $244.21 | $132.00 |
| 41 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 255 | $16.00 | $26.00 | $27.50 | $14.69 | $18.00 | $27.50 | $14.89 |
| 42 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 60 | $23.00 | $83.00 | $71.50 | $42.00 | $52.00 | $71.50 | $52.16 |
| 43 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 45 | $18.00 | $30.00 | $38.50 | $39.38 | $49.00 | $38.50 | $18.38 |
| 44 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 120 | $28.00 | $97.00 | $55.00 | $44.10 | $54.00 | $55.00 | $37.01 |
| 45 | Electrical conductor (no.8) bare (620-7007) | LF | 370 | $3.50 | $1.80 | $1.71 | $2.10 | $3.00 | $1.71 | $1.77 |
| 46 | Electrical conductor (no.8) insulated (620-7008) | LF | 770 | $4.00 | $1.90 | $2.02 | $2.10 | $3.00 | $2.02 | $1.77 |
| 47 | Electrical conductor (no.6) bare (620-7009) | LF | 120 | $3.50 | $2.40 | $1.93 | $2.31 | $3.00 | $1.93 | $2.28 |
| 48 | Electrical conductor (no.6) insulated (620-7010) | LF | 240 | $4.00 | $2.50 | $2.69 | $2.47 | $3.00 | $2.70 | $2.28 |
| 49 | Ground box type D (162922)W/apron (624-7008) | EACH | 2 | $5,000.00 | $2,585.00 | $1,650.00 | $2,310.00 | $2,853.00 | $1,650.00 | $1,576.60 |
| 50 | Elc SRV type D 120/240 070(NS)AL(E)SP(O) (628-7169) | EACH | 1 | $7,500.00 | $11,830 | $8,250.00 | $8,295.00 | $10,245 | $8,250.00 | $6,269.29 |
| 51 | Aluminum signs (type A) (636-7001) | SF | 10 | $45.00 | $46.00 | $27.50 | $31.50 | $71.00 | $27.50 | $30.00 |
| 52 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 4 | $800.00 | $1,000.00 | $935.00 | $892.50 | $1,102.00 | $605.00 | $795.00 |
| 53 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 3 | $500.00 | $635.00 | $591.25 | $564.38 | $697.00 | $605.00 | $720.00 |
| 54 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $150.00 | $172.00 | $110.00 | $105.00 | $130.00 | $605.00 | $150.00 |
| 55 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 153 | $16.00 | $14.00 | $13.20 | $12.60 | $16.00 | $11.00 | $22.00 |
| 56 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 153 | $5.00 | $5.00 | $4.40 | $4.20 | $5.00 | $5.50 | $7.00 |
| 57 | Reflectorized pavement marking type I (W)4"(solid)(060MIL) (666-7403) | LF | 202 | $3.00 | $2.65 | $2.20 | $2.10 | $3.00 | $3.30 | $12.00 |
| 58 | Pavement surface preparation for marking (24") (678-7008) | LF | 153 | $1.00 | $0.75 | $0.55 | $0.53 | $1.00 | $1.10 | $2.00 |
| 59 | Install highway traffic signal (system) (680-7003) | EACH | 1 | $39,500 | $8,250.00 | $35,750 | $24,780 | $30,605 | $34,100 | $25,796 |
| 60 | Removing traffic signals (680-7004) | EACH | 1 | $6,500.00 | $2,370.00 | $7,840.00 | $2,205.00 | $2,723.00 | $5,500.00 | $7,598.86 |
| 61 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 4 | $350.00 | $470.00 | $489.50 | $462.00 | $571.00 | $489.50 | $398.22 |
| 62 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 8 | $350.00 | $470.00 | $489.50 | $462.00 | $571.00 | $489.50 | $398.22 |
| 63 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 2 | $620.00 | $1,090.00 | $759.00 | $903.00 | $1,115.00 | $759.00 | $693.28 |
| 64 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 4 | $300.00 | $305.00 | $220.00 | $189.00 | $233.00 | $220.00 | $299.61 |
| 65 | Traffic signal CBL (type A)(14 AWG)(2 conductor) (684-7028) | LF | 115 | $5.00 | $1.90 | $2.25 | $2.00 | $2.00 | $2.26 | $2.85 |
| 66 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 125 | $5.00 | $2.10 | $3.58 | $2.52 | $3.00 | $3.58 | $3.29 |
| 67 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 289 | $5.00 | $2.20 | $3.79 | $2.78 | $3.00 | $3.80 | $4.05 |
| 68 | Ins traffic signal PL AM(S)1 arm(24')lum (686-7027) | EACH | 1 | $13,000 | $17,050 | $15,180 | $11,760 | $14,525 | $15,180 | $13,803 |
| 69 | Ins traffic signal PL AM(S)1 arm(28')lum (686-7031) | EACH | 1 | $13,000 | $17,600 | $15,950 | $12,390 | $15,303 | $15,950 | $14,372 |
| 70 | Pedestrian detect push button (APS) (688-7001) | EACH | 2 | $1,000.00 | $1,530.00 | $1,133.00 | $1,260.00 | $1,556.00 | $1,133.00 | $860.38 |
| 71 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $4,000.00 | $4,130.00 | $4,576.00 | $3,255.00 | $4,020.00 | $4,576.00 | $3,825.12 |
| 72 | Spot tree trimming / brush removal (752-7002) | LF | 55 | $120.00 | $20.00 | $140.00 | $25.00 | $91.00 | $27.50 | $142.24 |
| 73 | Bonding course (3007-7001) | GAL | 58 | $4.00 | $30.00 | $8.50 | $15.00 | $45.00 | $5.50 | $13.65 |
| 74 | RVDS (presence and advance detection) (6008-7003) | EACH | 2 | $10,500 | $13,150 | $13,090 | $10,605 | $13,098 | $13,090 | $11,939 |
| 75 | ITS pole MNT cab (type 3)(conf 1) (6011-7031) | EACH | 1 | $12,000 | $7,150.00 | $8,250.00 | $1,155.00 | $1,427.00 | $8,250.00 | $7,607.41 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.