Low bidders on TxDOT contracts carried a median of $272.02 per LF for this item, over the 24 months to 19 NOV 2026, across 10 low bids. Half of all 71 bids fell between $238.50 and $327.50.
- Owner
- Texas DOT
- Item
- 464-7042
- Unit
- LF
- Data through
- 19 NOV 2026
TxDOT prints this item as “RC PIPE (ARCH)(CL III)(DES 3)”.
TxDOT has bid this work under more than one code: 4646032001 on lettings from 09 JAN 2020 to 01 FEB 2024 (161 bids); 464-7042 on lettings from 04 MAR 2025 to 04 NOV 2026 (71 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 5 | $200.00 | 18 | $186.31 |
| 2021 | 14 | 14 | $162.50 | 75 | $210.00 |
| 2022 | 8 | 8 | $235.25 | 36 | $250.00 |
| 2023 | 7 | 7 | $278.11 | 26 | $267.81 |
| 2024 | 1 | 1 | $333.00 | 6 | $341.50 |
| 2025 | 5 | 5 | $262.59 | 33 | $258.00 |
| 2026 | 5 | 5 | $299.28 | 38 | $312.50 |
Bid prices as published, not adjusted for inflation.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Dan Williams Company | 11 | 5 (45%) |
| Webber, LLC | 10 | 4 (40%) |
| Hunter Industries, LTD. | 17 | 3 (18%) |
| Texas Materials Group, Inc. | 12 | 2 (17%) |
| Gilvin-Terrill, LTD. | 5 | 2 (40%) |
| Jordan Foster Construction, LLC | 10 | 1 (10%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00206976 | Austin District | 5 | $575.00 | $750.00 | $250.00 | 9 | Lone Star Sitework, LLC | TxDOT |
| 03 SEP 2026 | A00061184 | Austin District | 98 | $299.28 | $266.27 | $275.00 | 8 | Hunter Industries, LTD. | TxDOT |
| 06 AUG 2026 | A00197439 | Austin District | 380 | $269.05 | $269.05 | $270.00 | 7 | STX Civil | TxDOT |
| 03 JUN 2026 | A00191143 | Austin District | 8 | $450.00 | $473.00 | $285.00 | 6 | Dan Williams Company | TxDOT |
| 06 MAY 2026 | A00193147 | Austin District | 178 | $257.00 | $257.50 | $268.00 | 8 | Hunter Industries, LTD. | TxDOT |
| 06 NOV 2025 | A00062085 | Austin District | 41 | $285.00 | $305.00 | $310.00 | 8 | Webber, LLC | TxDOT |
| 04 SEP 2025 | A00127796 | Amarillo District | 1,092 | $275.00 | $280.47 | $360.00 | 6 | FNF Construction, Inc. | TxDOT |
| 08 AUG 2025 | A00196581 | Laredo District | 34 | $220.00 | $249.31 | $300.00 | 4 | Anderson Columbia Co., Inc. | TxDOT |
| 01 JUL 2025 | A00125991 | Corpus Christi District | 492 | $258.00 | $230.26 | $275.00 | 6 | Anderson Columbia Co., Inc. | TxDOT |
| 04 MAR 2025 | A00190692 | San Antonio District | 680 | $262.59 | $250.00 | $326.00 | 9 | Hunter Industries, LTD. | TxDOT |
| 01 FEB 2024 | 02243008 | Yoakum District | 160 | $333.00 | $341.50 | $240.00 | 6 | Clark Construction of Texas, Inc. | TxDOT |
| 03 AUG 2023 | 08233204 | Yoakum District | 211 | $262.00 | $262.00 | $300.00 | 1 | Hunter Industries, LTD. | TxDOT |
| 03 AUG 2023 | 08233205 | Fort Worth District | 476 | $207.48 | $260.43 | $300.00 | 4 | Sema Construction, Inc. | TxDOT |
| 03 AUG 2023 | 08233246 | Houston District | 55 | $500.00 | $500.00 | $400.00 | 1 | Main Lane Industries LTD. | TxDOT |
| 02 JUN 2023 | 06233205 | Abilene District | 84 | $325.00 | $362.50 | $300.00 | 4 | Bontke Brothers Construction Company | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way