TxDOT contract A00125991 bid tabulation
Construct New Roadway Lanes, US 77 (1.5 MI N. OF SH 285 INTERSECTION to KENEDY/KLEBERG COUNTY LINE). Let by Texas DOT on July 1, 2025, Kleberg, Corpus Christi District. 6 bids received; low bid $178,365,453 by Anderson Columbia Co., Inc., -15% against the engineer's estimate of $209,462,582.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 222
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Anderson Columbia Co., Inc. | $178,365,453 | Low | -15% |
| 2 | Pulice Construction, Inc. | $179,222,220 | 0.0% | -14% |
| 3 | Webber, LLC | $188,625,328 | +6.0% | -10% |
| 4 | Posillico Civil, Inc. | $198,362,875 | +11% | -5.0% |
| 5 | Zachry Construction Corporation | $204,759,271 | +15% | -2.0% |
| 6 | J E Construction Services, LLC | $218,365,481 | +22% | +4.0% |
Engineer's estimate: $209,462,582.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Anderson Columbia Co., Inc. | 2. Pulice Construction, Inc. | 3. Webber, LLC | 4. Posillico Civil, Inc. | 5. Zachry Construction Corporation | 6. J E Construction Services, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 200 | $25,000 | $7,500.00 | $89,611 | $85,977 | $30,000 | $100,000 | $14,650 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 590 | $12.00 | $20.00 | $27.32 | $19.31 | $41.00 | $20.00 | $34.00 |
| 3 | Remove stab base and asphalt pavement (6"-20") (105-7123) | SY | 56,719 | $15.00 | $12.00 | $10.07 | $9.32 | $6.00 | $6.99 | $11.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 163,800 | $12.00 | $8.00 | $2.09 | $5.37 | $10.00 | $3.78 | $14.00 |
| 5 | Embankment (final)(OC)(type A) (132-7001) | CY | 1 | $0.01 | $70.00 | $2,183.23 | $250.00 | $147.00 | $120.00 | $340.00 |
| 6 | Embankment (final)(DC)(type C) (132-7006) | CY | 1,465,700 | $18.00 | $20.00 | $16.13 | $11.75 | $15.00 | $25.00 | $16.00 |
| 7 | Compost manuf topsoil (4") (161-7002) | SY | 720,302 | $2.00 | $2.20 | $1.26 | $1.66 | $3.00 | $1.67 | $3.00 |
| 8 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 149 | $450.00 | $2,400.00 | $583.98 | $561.72 | $563.00 | $515.72 | $630.00 |
| 9 | Drill seed (temporary_warm_cool) (164-7047) | ACRE | 149 | $440.00 | $1,500.00 | $583.98 | $561.72 | $563.00 | $515.72 | $630.00 |
| 10 | Vegetative watering (168-7001) | TGL | 26,320 | $15.00 | $28.00 | $26.20 | $6.65 | $33.00 | $10.00 | $15.00 |
| 11 | Soil ret BLKT(SL_steep_sand_long) (169-7008) | SY | 9,992 | $5.50 | $1.60 | $4.05 | $3.89 | $4.00 | $3.57 | $5.00 |
| 12 | FL BS (compacted in place)(type A GR 1-2) (12") (247-7113) | SY | 255 | $80.00 | $150.00 | $95.59 | $41.03 | $50.00 | $42.60 | $69.00 |
| 13 | FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348) | CY | 122,317 | $100.00 | $100.00 | $100.76 | $62.24 | $100.00 | $92.78 | $120.00 |
| 14 | Geogrid base reinforcement (type 2) (250-7002) | SY | 1,194 | $2.00 | $7.00 | $6.88 | $2.82 | $8.00 | $3.39 | $4.00 |
| 15 | Lime (com or QK)(slurry) (260-7005) | TON | 8,097 | $300.00 | $300.00 | $385.36 | $209.20 | $400.00 | $293.24 | $360.00 |
| 16 | Lime TRT (subgrade) (8") (260-7020) | SY | 405,169 | $4.00 | $3.00 | $1.68 | $2.42 | $3.00 | $2.04 | $4.00 |
| 17 | Cement (275-7001) | TON | 4,577 | $215.00 | $240.00 | $189.13 | $362.73 | $360.00 | $166.88 | $195.00 |
| 18 | Cement TRT (new base)(10") (275-7012) | SY | 163,000 | $3.00 | $4.20 | $1.63 | $2.10 | $3.00 | $2.54 | $4.00 |
| 19 | Cement TRT (new base)(12") (275-7013) | SY | 229,319 | $2.50 | $3.30 | $1.61 | $2.27 | $3.00 | $2.39 | $5.00 |
| 20 | Cement TRT (new base)(14") (275-7014) | SY | 1,194 | $5.00 | $12.00 | $2.47 | $8.07 | $6.00 | $4.15 | $7.00 |
| 21 | Prime coat (MC-30) (310-7004) | GAL | 76,177 | $7.00 | $5.20 | $4.00 | $6.46 | $7.00 | $4.16 | $6.00 |
| 22 | Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212) | CY | 3,935 | $150.00 | $185.00 | $181.94 | $176.43 | $183.00 | $235.63 | $206.00 |
| 23 | Asphalt (multi option) (316-7275) | GAL | 147,776 | $7.00 | $4.40 | $5.20 | $6.15 | $8.00 | $3.95 | $5.00 |
| 24 | D-GR HMA type-B sac-B PG70-22 (341-7007) | TON | 100,530 | $130.00 | $109.00 | $122.93 | $142.42 | $114.00 | $120.80 | $157.00 |
| 25 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 19,579 | $120.00 | $136.00 | $127.51 | $147.23 | $145.00 | $154.47 | $172.00 |
| 26 | Tack coat (341-7082) | GAL | 31,867 | $4.00 | $4.80 | $3.38 | $3.53 | $5.00 | $4.67 | $5.00 |
| 27 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 26,502 | $150.00 | $172.00 | $171.29 | $156.76 | $170.00 | $183.00 | $214.00 |
| 28 | Flexible pavement structure repair(7") (351-7006) | SY | 1,000 | $50.00 | $100.00 | $113.75 | $25.00 | $91.00 | $100.31 | $90.00 |
| 29 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 3,855 | $3.00 | $10.00 | $2.62 | $3.07 | $5.00 | $2.67 | $7.00 |
| 30 | Plane concrete pavement(0" to 1") (354-7064) | SY | 1,301 | $3.00 | $10.00 | $6.10 | $7.19 | $8.00 | $10.16 | $7.00 |
| 31 | Planing asphalt concrete pavement (1" to 2") (354-7076) | SY | 846 | $3.00 | $10.00 | $9.48 | $11.04 | $12.00 | $9.37 | $7.00 |
| 32 | Struct excavation (pipe) (400-7003) | CY | 14,680 | $55.00 | $7.00 | $10.39 | $6.07 | $120.00 | $0.01 | $7.00 |
| 33 | Cem stabil BKFL (400-7010) | CY | 12,390.90 | $200.00 | $150.00 | $113.29 | $92.00 | $89.00 | $83.11 | $124.00 |
| 34 | Cement stab backfill (inlet or MH) (400-7011) | CY | 1,261 | $125.00 | $150.00 | $93.57 | $92.00 | $89.00 | $82.70 | $112.00 |
| 35 | Trench excavation protection (402-7001) | LF | 2,502 | $3.00 | $1.00 | $2.61 | $6.50 | $24.00 | $13.79 | $8.00 |
| 36 | Foundation load test (D4945) (pile) (405-7002) | EACH | 28 | $20,000 | $4,400.00 | $20,793 | $4,000.00 | $20,516 | $13,026 | $24,000 |
| 37 | Prestressed concrete pil (18 in SQ) (409-7002) | LF | 39,896 | $150.00 | $148.00 | $147.29 | $198.00 | $202.00 | $116.22 | $235.00 |
| 38 | Drilled shaft (18 in) (416-7002) | LF | 1,260 | $275.00 | $140.00 | $121.68 | $156.68 | $123.00 | $106.54 | $120.00 |
| 39 | Drilled shaft (24 in) (416-7004) | LF | 62 | $265.00 | $350.00 | $210.45 | $203.94 | $408.00 | $330.52 | $467.00 |
| 40 | Drilled shaft (36 in) (416-7006) | LF | 6,806 | $340.00 | $280.00 | $460.80 | $238.00 | $480.00 | $246.25 | $302.00 |
| 41 | Drilled shaft (42 in) (416-7007) | LF | 108 | $515.00 | $820.00 | $534.16 | $759.00 | $852.00 | $615.14 | $1,895.00 |
| 42 | Drilled shaft (sign mounts) (36 in) (416-7030) | LF | 80 | $515.00 | $680.00 | $393.59 | $624.00 | $625.00 | $367.23 | $710.00 |
| 43 | Drilled shaft (sign mounts) (54 in) (416-7033) | LF | 102 | $875.00 | $1,100.00 | $743.40 | $971.00 | $924.00 | $780.39 | $1,100.00 |
| 44 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 836 | $972.32 | $1,000.00 | $732.74 | $914.00 | $1,005.00 | $647.08 | $1,240.00 |
| 45 | Class C concrete (abutment) (420-7012) | CY | 821.02 | $1,500.00 | $2,800.00 | $1,305.71 | $1,473.15 | $1,606.00 | $1,131.96 | $1,840.00 |
| 46 | Class C concrete (cap) (420-7022) | CY | 1,184.38 | $1,500.00 | $2,700.00 | $1,705.02 | $1,436.99 | $2,255.00 | $1,605.71 | $2,740.00 |
| 47 | Class C concrete (column) (420-7038) | CY | 814 | $1,500.00 | $2,200.00 | $1,587.66 | $1,430.24 | $1,790.00 | $821.81 | $2,290.00 |
| 48 | Class C concrete (footing) (420-7044) | CY | 920.90 | $1,600.00 | $2,600.00 | $1,091.61 | $2,163.14 | $1,265.00 | $982.00 | $1,340.00 |
| 49 | Class C concrete (rail foundation) (420-7052) | CY | 1,192 | $825.00 | $1,100.00 | $467.16 | $538.22 | $814.00 | $542.37 | $790.00 |
| 50 | Reinforced concrete slab (422-7001) | SF | 336,495 | $42.00 | $32.00 | $22.00 | $28.24 | $22.00 | $25.30 | $32.00 |
| 51 | Reinforced concrete slab (box beam) (422-7005) | SF | 53,196 | $24.00 | $60.00 | $19.83 | $36.15 | $38.00 | $31.14 | $41.00 |
| 52 | Approach slab (422-7013) | CY | 1,680.93 | $1,000.00 | $900.00 | $761.27 | $563.16 | $626.00 | $800.00 | $1,140.00 |
| 53 | Shear key (422-7020) | CY | 44.16 | $643.00 | $1,000.00 | $1,930.64 | $820.12 | $307.00 | $557.07 | $1,200.00 |
| 54 | Retaining wall (MSE) (423-7001) | SF | 318,368 | $100.00 | $58.00 | $35.77 | $99.87 | $105.00 | $84.96 | $111.00 |
| 55 | Prestressed concrete girder (TX54) (425-7005) | LF | 38,077.24 | $275.00 | $230.00 | $283.92 | $201.77 | $192.00 | $197.49 | $270.00 |
| 56 | Prestressed concrete box beam (4B20) (425-7026) | LF | 1,692 | $300.00 | $360.00 | $303.23 | $226.73 | $510.00 | $196.54 | $480.00 |
| 57 | Prestressed concrete X-beam (5XB28) (425-7037) | LF | 3,802.86 | $290.00 | $350.00 | $288.60 | $310.17 | $464.00 | $199.26 | $440.00 |
| 58 | Riprap (concrete)(4 in) (432-7001) | CY | 75 | $2,020.00 | $600.00 | $434.04 | $568.80 | $526.00 | $493.30 | $700.00 |
| 59 | Riprap (concrete)(5 in) (432-7002) | CY | 1,177 | $675.00 | $550.00 | $434.05 | $493.64 | $569.00 | $557.45 | $710.00 |
| 60 | Riprap (concrete)(6 in) (432-7003) | CY | 76 | $850.00 | $550.00 | $434.05 | $681.61 | $594.00 | $568.34 | $722.00 |
| 61 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 2,459.70 | $575.00 | $550.00 | $434.05 | $499.68 | $601.00 | $541.30 | $705.00 |
| 62 | Riprap (mow strip)(4 in) (432-7013) | CY | 1,451 | $700.00 | $600.00 | $467.34 | $595.11 | $688.00 | $470.92 | $700.00 |
| 63 | Riprap (stone protection)(12 in) (432-7041) | CY | 1,203 | $300.00 | $220.00 | $280.10 | $181.23 | $230.00 | $287.56 | $470.00 |
| 64 | Rail (type SSTR) (450-7024) | LF | 40,689.20 | $65.00 | $78.00 | $71.17 | $56.60 | $71.00 | $57.00 | $84.00 |
| 65 | Rail (type T80SS) (450-7028) | LF | 748.10 | $150.00 | $210.00 | $255.80 | $134.91 | $147.00 | $206.23 | $174.00 |
| 66 | Retrofit rail (type SSTR) (451-7024) | LF | 1,763 | $175.00 | $260.00 | $91.45 | $166.78 | $121.00 | $91.80 | $220.00 |
| 67 | Armor joint (sealed) (454-7003) | LF | 115 | $185.00 | $210.00 | $159.61 | $205.84 | $253.00 | $130.71 | $194.00 |
| 68 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 2,054.83 | $250.00 | $280.00 | $242.28 | $203.86 | $285.00 | $180.74 | $284.00 |
| 69 | Concrete box culvert (5 FT X 2 FT) (462-7006) | LF | 5,415 | $500.00 | $510.00 | $443.40 | $422.08 | $567.00 | $448.99 | $560.00 |
| 70 | RC pipe (CL III)(18 in) (464-7003) | LF | 4,887 | $85.00 | $132.00 | $81.95 | $70.80 | $79.00 | $68.62 | $78.00 |
| 71 | RC pipe (CL III)(24 in) (464-7005) | LF | 6,696 | $225.00 | $119.00 | $87.28 | $86.58 | $99.00 | $80.89 | $105.00 |
| 72 | RC pipe (CL III)(30 in) (464-7007) | LF | 1,709 | $155.00 | $158.00 | $109.20 | $145.14 | $139.00 | $113.37 | $134.00 |
| 73 | RC pipe (CL III)(36 in) (464-7009) | LF | 898 | $250.00 | $196.00 | $146.27 | $179.97 | $190.00 | $152.68 | $188.00 |
| 74 | RC pipe (arch)(CL III)(des 3) (464-7042) | LF | 492 | $275.00 | $258.00 | $206.64 | $220.52 | $254.00 | $190.59 | $240.00 |
| 75 | Manh (complete)(PRM)(48IN) (465-7002) | EACH | 2 | $8,250.00 | $10,000 | $4,177.50 | $8,968.64 | $8,588.00 | $6,497.36 | $6,060.00 |
| 76 | Manh (complete)(PRM)(60IN) (465-7003) | EACH | 61 | $8,750.00 | $11,000 | $6,527.05 | $8,142.60 | $8,356.00 | $7,396.73 | $6,420.00 |
| 77 | Inlet (complete)(pcu)(5FT)(left) (465-7038) | EACH | 5 | $10,750 | $12,000 | $7,015.67 | $11,727 | $10,990 | $8,863.28 | $9,380.00 |
| 78 | Inlet (complete)(pcu)(5FT)(right) (465-7039) | EACH | 4 | $11,000 | $12,000 | $7,577.06 | $11,812 | $11,798 | $8,863.28 | $10,275 |
| 79 | Inlet(complete)(pazd)(FG)(3FTX3FT-3FTX3FT) (465-7158) | EACH | 23 | $3,620.00 | $5,800.00 | $4,354.24 | $11,379 | $7,429.00 | $5,898.91 | $5,200.00 |
| 80 | Inlet(complete)(pazd)(FG)(5FTX5FT-4FTX4FT) (465-7162) | EACH | 4 | $11,000 | $9,600.00 | $6,407.47 | $11,589 | $10,386 | $7,714.45 | $9,700.00 |
| 81 | Inlet (complete) (type MSE2) (465-7352) | EACH | 79 | $7,750.00 | $7,200.00 | $5,076.79 | $8,495.36 | $9,896.00 | $6,524.35 | $20,135 |
| 82 | Set (type I)(S= 5 FT)(HW= 3 FT)(4:1)(C) (467-7096) | EACH | 31 | $7,500.00 | $6,500.00 | $15,231 | $15,826 | $12,355 | $7,674.37 | $13,000 |
| 83 | Set (type I)(S= 5 FT)(HW= 3 FT)(6:1)(C) (467-7097) | EACH | 23 | $20,000 | $8,900.00 | $15,860 | $17,697 | $12,774 | $9,376.31 | $13,800 |
| 84 | Set (type I)(S= 5 FT)(HW= 3 FT)(6:1)(P) (467-7098) | EACH | 7 | $11,950 | $9,900.00 | $15,860 | $16,885 | $13,642 | $10,715 | $14,200 |
| 85 | Set (type I)(S= 5 FT)(HW= 4 FT)(4:1)(C) (467-7100) | EACH | 3 | $15,420 | $8,300.00 | $15,788 | $15,143 | $12,361 | $8,274.55 | $13,000 |
| 86 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 3 | $2,250.00 | $2,300.00 | $1,845.32 | $1,982.65 | $5,699.00 | $2,077.95 | $1,610.00 |
| 87 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 14 | $1,500.00 | $2,300.00 | $1,845.33 | $1,753.61 | $5,699.00 | $2,077.95 | $1,670.00 |
| 88 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $2,500.00 | $2,600.00 | $2,001.41 | $1,796.36 | $6,186.00 | $2,211.16 | $2,222.00 |
| 89 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 20 | $2,450.00 | $2,600.00 | $2,157.23 | $2,007.09 | $6,410.00 | $2,294.42 | $2,535.00 |
| 90 | Set (type II) (36 in) (RCP) (6: 1) (C) (467-7367) | EACH | 2 | $6,000.00 | $4,500.00 | $2,729.02 | $9,221.24 | $6,410.00 | $4,671.15 | $5,750.00 |
| 91 | Set (type II) (des 3) (RCP) (4: 1) (C) (467-7432) | EACH | 6 | $7,800.00 | $4,500.00 | $2,469.12 | $6,670.03 | $5,865.00 | $3,302.31 | $6,200.00 |
| 92 | Set (type II) (des 3) (RCP) (6: 1) (C) (467-7433) | EACH | 6 | $8,500.00 | $5,500.00 | $2,469.12 | $7,601.15 | $5,865.00 | $3,302.31 | $6,300.00 |
| 93 | Removing structure (set) (496-7004) | EACH | 16 | $523.00 | $700.00 | $674.44 | $727.48 | $241.00 | $715.12 | $840.00 |
| 94 | Removing structure (wingwall) (496-7005) | EACH | 8 | $1,800.00 | $3,000.00 | $2,619.85 | $1,589.46 | $434.00 | $633.10 | $1,300.00 |
| 95 | Removing structure (pipe) (496-7007) | LF | 472 | $22.00 | $24.00 | $21.87 | $16.33 | $113.00 | $18.05 | $22.00 |
| 96 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $26,422 | $60,000 | $45,744 | $109,921 | $56,402 | $25,075 | $61,000 |
| 97 | Remove STR (rail) (496-7017) | LF | 584 | $23.00 | $150.00 | $26.80 | $29.82 | $67.00 | $34.05 | $36.00 |
| 98 | Mobilization (500-7001) | LS | 1 | $18,640,312 | $10,400,000 | $17,922,016 | $18,492,258 | $18,125,000 | $20,000,000 | $19,580,500 |
| 99 | Barricades, signs and traffic handling (502-7001) | MO | 72 | $15,000 | $4,000.00 | $6,491.36 | $25,555 | $5,000.00 | $50,000 | $8,400.00 |
| 100 | Portable changeable message sign (503-7002) | EACH | 4 | $13,000 | $60,000 | $30,091 | $19,225 | $15,600 | $25,000 | $24,220 |
| 101 | TMA (stationary) (505-7001) | DAY | 171 | $235.00 | $260.00 | $365.80 | $78.98 | $484.00 | $250.00 | $380.00 |
| 102 | TMA (mobile operation) (505-7003) | DAY | 25 | $322.00 | $820.00 | $1,226.22 | $36.14 | $646.00 | $275.00 | $690.00 |
| 103 | Rock filter dams (install) (type 2) (506-7007) | CY | 143 | $26.00 | $400.00 | $57.18 | $201.00 | $194.00 | $174.44 | $215.00 |
| 104 | Rock filter dams (remove) (506-7012) | CY | 143 | $2.00 | $205.00 | $17.67 | $22.00 | $25.00 | $36.73 | $28.00 |
| 105 | Construction exits (install) (type 1) (506-7020) | SY | 2,652 | $18.00 | $62.00 | $45.75 | $65.00 | $56.00 | $32.14 | $105.00 |
| 106 | Construction exits (remove) (506-7024) | SY | 2,652 | $8.00 | $37.00 | $15.60 | $15.00 | $13.00 | $4.59 | $14.00 |
| 107 | Temporary sediment control fence (install) (506-7039) | LF | 1,500 | $4.00 | $5.00 | $5.20 | $10.00 | $7.00 | $4.18 | $15.00 |
| 108 | Temporary sediment control fence (remove) (506-7041) | LF | 1,500 | $1.50 | $2.70 | $1.56 | $3.00 | $2.00 | $1.65 | $2.45 |
| 109 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,300 | $5.00 | $7.00 | $8.31 | $8.25 | $8.00 | $7.35 | $9.00 |
| 110 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,300 | $3.00 | $2.70 | $2.07 | $2.00 | $2.00 | $1.65 | $3.00 |
| 111 | Constructing detours (508-7001) | SY | 10,636 | $114.00 | $104.00 | $30.65 | $81.14 | $32.00 | $98.46 | $126.00 |
| 112 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 3,360 | $50.00 | $30.00 | $57.16 | $61.63 | $78.00 | $38.01 | $78.00 |
| 113 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 3,270 | $12.00 | $16.00 | $9.02 | $10.93 | $7.00 | $10.00 | $16.00 |
| 114 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 3,360 | $14.00 | $18.00 | $8.59 | $28.58 | $16.00 | $10.35 | $17.00 |
| 115 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 1,530 | $100.00 | $97.00 | $90.55 | $105.59 | $139.00 | $85.80 | $170.00 |
| 116 | Permanent CTB (single slope)(42)(mod) (514-7004) | LF | 18 | $250.00 | $340.00 | $226.28 | $581.56 | $300.00 | $323.09 | $420.00 |
| 117 | Permanent CTB (tran SSCB to SSTR) (mod) (514-7038) | LF | 12 | $400.00 | $270.00 | $498.49 | $483.05 | $235.00 | $347.93 | $265.00 |
| 118 | Permanent CTB (tran T80SS to SSTR)(mod) (514-7051) | LF | 120 | $500.00 | $354.00 | $159.53 | $233.06 | $213.00 | $305.49 | $240.00 |
| 119 | Concrete curb (type IV) (529-7005) | LF | 140 | $50.00 | $66.00 | $17.93 | $22.00 | $75.00 | $36.73 | $34.00 |
| 120 | Concrete curb & gutter (type II) (529-7009) | LF | 2,488 | $40.00 | $55.00 | $17.15 | $20.00 | $45.00 | $41.32 | $55.00 |
| 121 | Intersections (ACP) (530-7002) | SY | 4,064 | $50.00 | $153.00 | $260.26 | $69.12 | $91.00 | $120.55 | $120.00 |
| 122 | Intersections (ACP) (type 1) (530-7003) | SY | 3,110 | $55.00 | $125.00 | $268.86 | $67.31 | $47.00 | $107.87 | $118.00 |
| 123 | Driveways (ACP) (530-7010) | SY | 4,961 | $50.00 | $61.00 | $204.85 | $10.92 | $25.00 | $45.10 | $76.00 |
| 124 | Concrete sidewalks (5") (531-7002) | SY | 294 | $150.00 | $103.00 | $74.86 | $145.60 | $83.00 | $84.35 | $84.00 |
| 125 | Curb ramps (type 7) (531-7010) | EACH | 4 | $4,000.00 | $3,870.00 | $3,118.89 | $3,197.61 | $4,225.00 | $3,063.72 | $4,200.00 |
| 126 | Curb ramps (type 22) (531-7014) | EACH | 2 | $5,100.00 | $3,660.00 | $3,118.93 | $3,331.54 | $4,540.00 | $3,375.83 | $4,400.00 |
| 127 | Metal W-beam guard fence (timber post) (540-7001) | LF | 2,225 | $30.00 | $25.00 | $29.19 | $23.19 | $23.00 | $25.38 | $28.00 |
| 128 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 30 | $2,500.00 | $3,000.00 | $2,424.57 | $1,907.00 | $1,907.00 | $1,949.58 | $2,115.00 |
| 129 | Downstream anchor terminal section (540-7015) | EACH | 2 | $2,000.00 | $1,520.00 | $1,377.60 | $1,408.00 | $1,408.00 | $1,284.49 | $1,570.00 |
| 130 | Metal beam guard fence trans (non - sym) (540-7016) | EACH | 2 | $1,500.00 | $735.00 | $1,482.27 | $680.00 | $680.00 | $708.83 | $760.00 |
| 131 | Remove metal beam guard fence (542-7001) | LF | 1,349 | $3.00 | $3.00 | $2.20 | $3.00 | $3.00 | $7.35 | $4.00 |
| 132 | Remove terminal anchor section (542-7002) | EACH | 6 | $278.00 | $300.00 | $242.45 | $275.00 | $275.00 | $529.92 | $305.00 |
| 133 | Cable barrier system (install)(TL-4) (543-7002) | LF | 17,755 | $15.00 | $15.00 | $17.08 | $17.65 | $18.00 | $11.72 | $20.00 |
| 134 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 14 | $3,250.00 | $3,000.00 | $3,113.37 | $3,325.00 | $3,325.00 | $2,537.31 | $3,680.00 |
| 135 | Guardrail end treatment (install) (544-7001) | EACH | 30 | $3,000.00 | $3,500.00 | $3,361.34 | $3,222.00 | $3,222.00 | $3,513.17 | $3,600.00 |
| 136 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 10 | $2,136.00 | $950.00 | $1,675.15 | $875.00 | $875.00 | $1,991.34 | $4,700.00 |
| 137 | Crash cushion attenuator (remove) (545-7004) | EACH | 4 | $1,240.00 | $863.00 | $892.67 | $800.00 | $800.00 | $1,191.15 | $890.00 |
| 138 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 6 | $40,000 | $34,000 | $32,952 | $26,850 | $26,850 | $34,240 | $33,480 |
| 139 | Crash cushion attenuator (install)(R)(N)(TL3) (545-7010) | EACH | 3 | $35,400 | $33,000 | $29,315 | $25,115 | $25,115 | $30,826 | $32,000 |
| 140 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 4 | $8,800.00 | $8,960.00 | $8,816.61 | $8,300.00 | $8,300.00 | $9,530.30 | $13,660 |
| 141 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 2 | $1,701.58 | $1,560.00 | $1,458.35 | $1,875.50 | $2,000.00 | $1,287.89 | $2,040.00 |
| 142 | In RD IL (U/P) (type 2) (150W EQ) LED (610-7016) | EACH | 18 | $1,866.99 | $1,525.00 | $1,487.94 | $1,413.60 | $2,000.00 | $1,314.02 | $2,100.00 |
| 143 | In RD IL (type SA) 40T-10 (250W EQ) LED (610-7126) | EACH | 2 | $5,474.34 | $5,600.00 | $5,526.76 | $5,208.00 | $5,326.00 | $4,880.70 | $5,400.00 |
| 144 | HI MST IL pole (150 FT)(100 MPH) (613-7006) | EACH | 18 | $82,099 | $71,000 | $77,455 | $65,638 | $66,751 | $68,402 | $68,080 |
| 145 | LED HI MST IL asm (6 fixt) (type B) (614-7003) | EACH | 18 | $46,948 | $50,000 | $49,139 | $46,267 | $45,750 | $43,395 | $46,630 |
| 146 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,710 | $22.00 | $12.00 | $5.29 | $11.40 | $14.00 | $4.67 | $15.00 |
| 147 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 5,615 | $21.32 | $18.00 | $8.59 | $17.00 | $15.00 | $7.59 | $16.00 |
| 148 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 6,790 | $32.00 | $35.00 | $7.98 | $32.25 | $34.00 | $7.05 | $35.00 |
| 149 | Conduit (RM) (3/4") (618-7070) | LF | 962 | $30.50 | $18.00 | $51.90 | $16.62 | $22.00 | $45.84 | $23.00 |
| 150 | Electrical conductor (no.12) insulated (620-7004) | LF | 12,889 | $2.69 | $1.60 | $1.02 | $1.50 | $1.00 | $0.91 | $2.00 |
| 151 | Electrical conductor (no.6) insulated (620-7010) | LF | 41,226 | $2.29 | $2.50 | $1.99 | $2.32 | $3.00 | $1.75 | $3.00 |
| 152 | Ground box type A (122311)W/apron (624-7002) | EACH | 55 | $1,150.00 | $1,333.00 | $1,043.43 | $1,240.30 | $1,304.00 | $921.45 | $1,400.00 |
| 153 | Ground box type D (162922)W/apron (624-7008) | EACH | 12 | $2,000.00 | $1,666.00 | $1,367.53 | $1,540.80 | $1,413.00 | $1,207.66 | $1,500.00 |
| 154 | Elc SRV type A 240/480 060(SS)SS(E)GC(O) (628-7054) | EACH | 12 | $10,500 | $13,020 | $12,118 | $12,056 | $7,826.00 | $10,702 | $7,900.00 |
| 155 | Elc SRV type D 120/240 060(NS)SS(N)GC(O) (628-7152) | EACH | 4 | $9,750.00 | $9,933.00 | $9,132.29 | $9,201.00 | $10,000 | $8,064.81 | $11,000 |
| 156 | Aluminum signs (type G) (636-7002) | SF | 946 | $35.00 | $31.00 | $30.15 | $42.00 | $35.00 | $22.95 | $36.00 |
| 157 | Aluminum signs (type O) (636-7003) | SF | 925 | $60.00 | $26.00 | $32.43 | $23.90 | $39.00 | $27.54 | $40.00 |
| 158 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 64 | $1,000.00 | $880.00 | $847.28 | $915.00 | $978.00 | $642.67 | $1,000.00 |
| 159 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 22 | $1,500.00 | $1,000.00 | $961.66 | $1,125.00 | $841.00 | $734.49 | $1,100.00 |
| 160 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 14 | $1,000.00 | $1,070.00 | $1,029.24 | $1,050.00 | $894.00 | $780.39 | $1,055.00 |
| 161 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 32 | $1,400.00 | $1,220.00 | $1,174.79 | $1,200.00 | $999.00 | $872.20 | $1,165.00 |
| 162 | Install small roadside sign support and assembly TYS80(1)SA(U-2EXT) (644-7033) | EACH | 2 | $1,200.00 | $2,150.00 | $2,063.68 | $1,850.00 | $1,288.00 | $1,124.68 | $1,385.00 |
| 163 | Install small roadside sign support and assembly TYS80(1)SA(U-exal) (644-7036) | EACH | 5 | $1,245.00 | $1,550.00 | $1,497.06 | $1,950.00 | $1,419.00 | $1,239.44 | $1,330.00 |
| 164 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 22 | $3,000.00 | $2,180.00 | $2,105.26 | $2,100.00 | $1,950.00 | $1,703.09 | $2,600.00 |
| 165 | In bridge MNT clearance sign assembly(type S) (644-7062) | EACH | 8 | $3,500.00 | $2,250.00 | $2,167.61 | $2,200.00 | $2,234.00 | $1,950.97 | $2,770.00 |
| 166 | Install small roadside sign support and assembly (rail mount) (644-7063) | EACH | 9 | $8,250.00 | $4,100.00 | $3,950.60 | $8,250.00 | $5,104.00 | $4,457.40 | $3,780.00 |
| 167 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 6 | $810.00 | $800.00 | $764.14 | $750.00 | $657.00 | $573.82 | $665.00 |
| 168 | Remove SM RD SN sup&AM (644-7073) | EACH | 36 | $175.00 | $102.00 | $98.76 | $90.00 | $84.00 | $73.44 | $470.00 |
| 169 | Install LRSS (struct steel) (647-7001) | LB | 7,218 | $8.00 | $6.50 | $6.22 | $5.91 | $9.00 | $4.18 | $9.00 |
| 170 | Install overhead sign support(30 FT bal tee) (650-7028) | EACH | 2 | $71,600 | $63,400 | $66,844 | $58,710 | $57,881 | $50,496 | $59,090 |
| 171 | Install overhead sign support(35 FT cant) (650-7038) | EACH | 1 | $80,000 | $66,000 | $65,304 | $61,155 | $58,696 | $50,955 | $60,060 |
| 172 | Install overhead sign support(65 FT BRDG) (650-7074) | EACH | 2 | $75,000 | $86,300 | $80,369 | $79,942 | $73,642 | $64,359 | $76,000 |
| 173 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 191 | $75.00 | $106.00 | $101.89 | $110.00 | $110.00 | $114.76 | $125.00 |
| 174 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 241 | $25.00 | $48.00 | $46.51 | $38.00 | $38.00 | $55.09 | $43.00 |
| 175 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 62 | $32.00 | $48.00 | $46.78 | $40.00 | $40.00 | $59.68 | $45.00 |
| 176 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 50 | $40.00 | $48.00 | $46.78 | $45.00 | $45.00 | $59.68 | $51.00 |
| 177 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 145 | $25.00 | $48.00 | $46.78 | $38.00 | $38.00 | $59.68 | $42.00 |
| 178 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 16 | $20.00 | $48.00 | $46.78 | $40.00 | $40.00 | $59.68 | $44.00 |
| 179 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 251 | $37.00 | $48.00 | $46.78 | $45.00 | $40.00 | $59.68 | $51.00 |
| 180 | Install delineator assembly (D-DW)SZ 1(WFLX)GND (658-7045) | EACH | 97 | $60.00 | $107.00 | $102.93 | $95.00 | $95.00 | $114.76 | $106.00 |
| 181 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 33 | $115.00 | $97.00 | $93.58 | $110.00 | $110.00 | $114.76 | $124.00 |
| 182 | Work zone pavement marking removing (W)4"(broken) (662-7061) | LF | 901 | $1.00 | $1.20 | $1.14 | $1.10 | $1.00 | $1.01 | $2.00 |
| 183 | Work zone pavement marking removing (W)4"(solid) (662-7064) | LF | 70,678 | $0.50 | $0.35 | $0.34 | $0.32 | $1.00 | $0.29 | $1.00 |
| 184 | Work zone pavement marking removing (Y)4"(solid) (662-7097) | LF | 19,883 | $0.54 | $0.50 | $0.47 | $0.46 | $1.00 | $0.42 | $1.00 |
| 185 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 13,921 | $1.70 | $2.30 | $2.65 | $1.50 | $2.00 | $0.78 | $4.00 |
| 186 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,235 | $1.70 | $2.40 | $2.65 | $1.50 | $2.00 | $1.38 | $4.00 |
| 187 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 2,396 | $1.25 | $1.20 | $1.14 | $1.10 | $1.00 | $1.01 | $2.00 |
| 188 | Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017) | LF | 254 | $1.75 | $3.30 | $3.14 | $3.00 | $3.00 | $2.75 | $4.00 |
| 189 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 20,558 | $1.50 | $1.00 | $0.91 | $0.88 | $1.00 | $0.81 | $1.00 |
| 190 | Reflectorized pavement marking type I (W)12"(lane drop)(090MIL) (666-7026) | LF | 647 | $1.00 | $2.00 | $2.07 | $2.00 | $2.00 | $1.84 | $3.00 |
| 191 | Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029) | LF | 1,545 | $1.75 | $1.60 | $1.56 | $1.50 | $2.00 | $1.38 | $2.00 |
| 192 | Reflectorized pavement marking type I (Y)12"(solid)(090MIL) (666-7116) | LF | 230 | $6.00 | $2.00 | $2.07 | $2.00 | $2.00 | $1.84 | $2.00 |
| 193 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 24,460 | $0.60 | $0.78 | $0.74 | $0.72 | $1.00 | $0.66 | $1.00 |
| 194 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 115,366 | $0.75 | $0.65 | $0.63 | $0.60 | $1.00 | $0.55 | $1.00 |
| 195 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 440 | $1.00 | $2.00 | $2.07 | $2.00 | $2.00 | $1.84 | $2.00 |
| 196 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 119,810 | $0.75 | $0.65 | $0.63 | $0.60 | $1.00 | $0.55 | $1.00 |
| 197 | Mobile retroreflectivity data collect (667-7001) | MI | 13,475 | $1.20 | $0.01 | $0.05 | $0.01 | $1.00 | $0.01 | $0.05 |
| 198 | Prefabricated PM type B (W)(6")(broken)contrast (668-7012) | LF | 2,364 | $12.00 | $20.00 | $19.74 | $19.00 | $19.00 | $17.45 | $22.00 |
| 199 | Prefabricated PM type C (W)(12")(solid) (668-7087) | LF | 1,811 | $10.00 | $9.00 | $8.31 | $8.00 | $8.00 | $7.35 | $9.00 |
| 200 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 555 | $30.00 | $17.00 | $16.65 | $16.00 | $16.00 | $14.69 | $18.00 |
| 201 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 12 | $250.00 | $216.00 | $207.93 | $200.00 | $200.00 | $183.62 | $222.00 |
| 202 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 6 | $375.00 | $380.00 | $363.88 | $350.00 | $350.00 | $321.34 | $390.00 |
| 203 | Prefabricated PM type C (W)(uturn arrow) (668-7096) | EACH | 6 | $400.00 | $400.00 | $389.84 | $375.00 | $375.00 | $344.29 | $420.00 |
| 204 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 4 | $500.00 | $570.00 | $545.81 | $525.00 | $525.00 | $482.01 | $585.00 |
| 205 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 18 | $350.00 | $300.00 | $285.90 | $275.00 | $275.00 | $252.47 | $305.00 |
| 206 | Prefabricated PM type C (W)(18")(yld tri) (668-7110) | EACH | 54 | $40.00 | $20.00 | $18.71 | $18.00 | $18.00 | $16.53 | $20.00 |
| 207 | Reflectorized pavement marker type I-C (672-7002) | EACH | 75 | $7.50 | $8.00 | $7.80 | $7.50 | $8.00 | $6.89 | $9.00 |
| 208 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 634 | $7.00 | $8.00 | $7.80 | $7.50 | $8.00 | $6.89 | $9.00 |
| 209 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2,752 | $5.25 | $8.00 | $7.80 | $7.50 | $8.00 | $6.89 | $8.00 |
| 210 | Eliminating existing PM & markers (4") (677-7001) | LF | 43,166 | $0.36 | $0.40 | $0.38 | $0.37 | $1.00 | $0.34 | $1.00 |
| 211 | Eliminating existing PM & markers (rumble strip) (677-7030) | LF | 12,122 | $0.50 | $4.00 | $0.15 | $2.00 | $35.00 | $2.85 | $1.00 |
| 212 | Full-width mowing (rural) (730-7016) | ACRE | 660 | $52.00 | $215.00 | $138.83 | $150.00 | $37.00 | $298.38 | $69.00 |
| 213 | Replacing elastomeric bearing pads (787-7001) | EACH | 636 | $10,000 | $486.00 | $2,799.81 | $450.00 | $6,255.00 | $1,937.70 | $1,565.00 |
| 214 | Tip testing(drilled shaft) (4003-7001) | EACH | 4 | $8,900.00 | $4,300.00 | $18,747 | $4,000.00 | $4,200.00 | $3,672.42 | $4,450.00 |
| 215 | Install DMS (foundation MTD cabinet) (6004-7002) | EACH | 2 | $19,500 | $17,000 | $16,717 | $15,850 | $15,218 | $14,763 | $15,555 |
| 216 | System integration (6009-7001) | LS | 1 | $5,000.00 | $10,000 | $2,661.63 | $9,250.00 | $16,305 | $2,350.50 | $16,652 |
| 217 | ITS pole MNT cab (type 2)(conf 2) (6011-7002) | EACH | 4 | $6,700.00 | $9,000.00 | $9,056.46 | $8,433.00 | $7,609.00 | $7,997.82 | $7,760.00 |
| 218 | ITS pole (55 FT)(130 MPH) (6011-7007) | EACH | 4 | $24,750 | $25,200 | $27,853 | $23,402 | $22,962 | $24,597 | $23,420 |
| 219 | CCTV field equip (digital) (install only) (6018-7001) | EACH | 4 | $3,500.00 | $1,300.00 | $752.42 | $1,183.00 | $1,250.00 | $664.49 | $1,275.00 |
| 220 | ITS system support equipment (6037-7001) | LS | 1 | $4,000.00 | $10,450 | $4,550.66 | $9,700.00 | $5,435.00 | $4,018.83 | $5,545.00 |
| 221 | Installation of cellular router (6052-7002) | EACH | 6 | $1,500.00 | $625.00 | $468.36 | $580.00 | $788.00 | $413.61 | $805.00 |
| 222 | Water line (cip) (7023-7036) | LS | 1 | $2,100,000 | $1,800,000 | $1,947,797 | $1,346,676 | $1,276,299 | $1,721,808 | $2,240,300 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.