TxDOT contract A00197439 bid tabulation

Highway Improvement, RM 150 (0.476 MI SE of Darden Hill Rd to RM 1826). Let by Texas DOT on August 6, 2026, Hays, Austin District. 7 bids received; low bid $3,441,590 by STX Civil, +9.9% against the engineer's estimate of $3,130,181.

Owner
Texas DOT
Letting
06 AUG 2026
Pay items
86
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1STX Civil$3,441,590Low+10%
2Hunter Industries, LTD.$3,447,3420.0%+10%
3D&S Concrete Contractors LLC$3,562,474+4.0%+14%
4Texas Materials Group, Inc.$3,760,934+9.0%+20%
5D & D Contractors, Inc.$3,911,325+14%+25%
6Aaron Concrete Contractors, LLC$4,407,410+28%+41%
7Joe Bland Construction LLC$4,595,040+34%+47%
TxDOT contract A00197439: bids by rank

Engineer's estimate: $3,130,181.

Bid tabulation

LinePay itemUnitQuantityEstimate1. STX Civil2. Hunter Industries, LTD.3. D&S Concrete Contractors LLC4. Texas Materials Group, Inc.5. D & D Contractors, Inc.6. Aaron Concrete Contractors, LLC
1Preparing row (100-7002)STA97$2,500.00$770.09$976.80$500.00$1,400.00$772.57$1,350.00
2Removing concrete (driveways) (104-7011)SY1,475$15.00$21.80$26.40$40.00$40.00$23.05$26.00
3Excavation (roadway) (110-7001)CY9,098$10.00$9.31$25.30$23.00$32.00$17.26$31.00
4Embankment (final)(OC)(type B) (132-7003)CY3,573$6.50$15.35$25.30$28.00$15.00$6.36$19.00
5Furn & place topsoil (4") (160-7002)SY28,174$1.50$3.74$1.91$0.50$3.30$2.40$6.00
6Broadcast seed (temporary_warm_cool) (164-7007)SY28,174$0.15$0.31$0.19$0.70$0.18$0.22$0.21
7Drill seed (permanent_rural_clay) (164-7010)SY28,174$0.20$0.37$0.26$0.75$0.25$0.31$0.29
8Vegetative watering (168-7001)TGL475$10.00$43.61$26.40$10.00$40.00$14.60$35.00
9Soil ret BLKT(SL_steep_clay_long) (169-7006)SY28,174$2.00$1.37$0.89$1.00$0.85$1.04$1.00
10Soil ret BLKT(chan_temporary_4 PSF) (169-7030)SY180$2.00$1.43$1.58$4.00$1.50$1.84$2.00
11FL BS (compacted in place)(type A GR 5)(final pos) (247-7179)CY3,679$55.00$80.09$66.97$29.00$77.00$93.77$75.00
12Prime coat (multi option) (310-7015)GAL3,140$3.75$5.46$5.28$5.00$4.90$4.48$7.00
13D-GR HMA type-B PG64-22 (341-7001)TON2,590$82.00$126.80$97.21$165.00$99.00$163.12$132.00
14D-GR HMA type D PG76-22 (341-7056)TON1,317$108.00$128.62$106.47$170.00$120.00$192.56$149.00
15D-GR HMA type D PG76-22 (level-UP) (341-7059)TON401$110.00$132.45$110.87$170.00$166.00$198.69$218.00
16Tom-C PG76-22 sac-B (347-7002)TON2,096$121.00$188.26$131.76$165.00$141.00$213.41$197.00
17Cut & restoring pavement (400-7006)SY319$185.00$102.90$322.31$150.00$90.00$112.83$259.00
18Flowable backfill (401-7001)CY81$200.00$220.54$229.66$300.00$260.00$256.40$203.00
19Trench excavation protection (402-7001)LF99$10.00$8.48$12.39$20.00$10.00$12.27$42.00
20Riprap (concrete)(4 in) (432-7001)CY5$550.00$1,290.74$576.55$1,100.00$730.00$583.81$1,080.00
21Riprap (mow strip)(4 in) (432-7013)CY119$625.00$588.36$561.84$900.00$650.00$690.51$627.00
22Riprap (stone protection)(12 in) (432-7041)CY136$200.00$175.49$183.78$200.00$220.00$214.64$205.00
23Concrete box culvert (6 FT X 3 FT) (462-7011)LF162$575.00$735.88$764.04$700.00$668.00$742.16$675.00
24RC pipe (CL III)(18 in) (464-7003)LF273$80.00$95.92$105.02$105.00$71.00$117.27$94.00
25RC pipe (CL III)(24 in) (464-7005)LF70$150.00$117.39$643.04$160.00$88.00$120.55$112.00
26RC pipe (CL III)(36 in) (464-7009)LF110$200.00$204.77$474.67$250.00$182.00$311.44$193.00
27RC pipe (arch)(CL III)(des 3) (464-7042)LF380$270.00$269.05$257.29$310.00$242.00$276.72$228.00
28RC pipe (arch)(CL III)(des 4) (464-7043)LF132$345.00$335.36$514.58$350.00$308.00$357.11$279.00
29RC pipe (arch)(CL III)(des 5) (464-7044)LF176$250.00$441.21$383.31$450.00$398.00$480.62$369.00
30Headwall (CH - PW - S) (diameter= 36 in) (466-7120)EACH1$10,000$13,867$14,177$4,500.00$16,000$16,130$20,266
31Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH1$20,000$19,302$24,553$4,500.00$36,000$19,587$40,067
32Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH1$23,000$28,934$32,608$5,000.00$49,000$24,254$62,747
33Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH18$1,250.00$1,249.71$1,470.23$2,500.00$1,250.00$1,371.20$2,467.00
34Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH4$2,150.00$1,412.87$1,522.74$2,800.00$1,520.00$1,444.80$2,826.00
35Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365)EACH1$3,750.00$3,404.74$4,410.69$2,600.00$3,200.00$7,975.83$3,617.00
36Set (type II) (des 3) (RCP) (3: 1) (C) (467-7431)EACH2$4,000.00$1,984.87$1,596.25$2,650.00$1,420.00$2,032.28$2,320.00
37Set (type II) (des 3) (RCP) (4: 1) (C) (467-7432)EACH2$2,500.00$2,741.01$1,890.29$4,000.00$1,610.00$2,032.28$2,458.00
38Set (type II) (des 3) (RCP) (6: 1) (P) (467-7434)EACH10$4,000.00$4,087.87$2,310.36$5,000.00$1,849.00$1,246.11$2,856.00
39Set (type II) (des 4) (RCP) (4: 1) (C) (467-7440)EACH2$7,000.00$8,797.02$2,782.93$4,000.00$2,310.00$14,086$3,348.00
40Set (type II) (des 5) (RCP) (4: 1) (C) (467-7448)EACH2$7,250.00$10,005$6,300.98$4,000.00$3,420.00$23,019$4,497.00
41Removing & RE - lay pipe (18 in) (472-7004)LF223$50.00$54.04$52.51$125.00$49.00$25.70$108.00
42Removing structure (set) (496-7004)EACH50$375.00$645.56$572.11$400.00$175.00$419.54$609.00
43Removing structure (pipe) (496-7007)LF1,298$21.00$26.15$23.42$5.00$8.00$20.83$22.00
44Mobilization (500-7001)LS1$200,000$176,324$239,056$200,000$370,000$106,704$440,000
45Barricades, signs and traffic handling (502-7001)MO22$5,000.00$2,184.60$3,780.05$4,000.00$7,600.00$3,606.50$1,586.00
46Portable changeable message sign (503-7002)EACH2$12,000$7,497.52$17,052$3,000.00$4,000.00$2,299.66$21,574
47TMA (stationary) (505-7001)DAY50$190.00$101.13$284.20$200.00$275.00$350.77$307.00
48TMA (mobile operation) (505-7002)HR24$65.00$200.04$227.36$225.00$80.00$153.31$88.00
49Rock filter dams (install) (type 2) (506-7002)LF444$42.00$37.38$42.53$40.00$40.50$49.67$47.00
50Rock filter dams (remove) (506-7011)LF444$15.00$6.23$14.70$50.00$14.00$17.17$16.00
51Construction exits (install) (type 1) (506-7020)SY43$22.00$43.61$42.01$50.00$40.00$49.05$47.00
52Construction exits (remove) (506-7024)SY43$10.00$7.48$11.55$10.00$11.00$13.49$13.00
53Temporary sediment control fence (install) (506-7039)LF422$3.60$3.12$3.15$5.00$3.00$3.68$39.00
54Temporary sediment control fence (remove) (506-7041)LF422$1.00$0.62$1.05$1.00$1.00$1.23$1.00
55Constructing detours (508-7001)SY2,045$80.00$67.25$42.28$80.00$69.69$115.85$51.00
56Driveways (concrete) (530-7006)SY765$115.00$130.51$113.42$90.00$140.00$140.30$177.00
57Driveways (ACP) (530-7010)SY1,670$65.00$47.02$48.22$70.00$72.00$75.57$114.00
58Turnouts (ACP) (530-7018)SY507$85.00$54.84$48.40$36.00$82.00$44.16$96.00
59Metal W-beam guard fence (timber post) (540-7001)LF1,715.50$25.00$32.40$28.35$25.00$27.00$31.89$32.00
60Downstream anchor terminal section (540-7015)EACH7$1,350.00$1,619.93$1,417.72$1,400.00$1,350.00$1,594.43$1,583.00
61Remove metal beam guard fence (542-7001)LF268$3.00$3.12$1.73$5.00$1.65$3.07$2.00
62Guardrail end treatment (install) (544-7001)EACH7$3,200.00$311.52$3,670.32$3,555.00$3,495.00$4,047.40$4,097.00
63Guardrail end treatment (remove) (544-7003)EACH3$210.00$32.40$152.27$250.00$145.00$306.62$170.00
64Mailbox install-S (TWW-post) type 4 (560-7008)EACH9$315.00$311.52$262.54$500.00$250.00$325.60$463.00
65Mailbox install-D (TWW-post) type 4 (560-7009)EACH4$300.00$373.83$315.05$500.00$300.00$330.96$455.00
66Mailbox install-M (TWW-post) type 4 (560-7010)EACH9$625.00$747.66$630.10$500.00$600.00$651.19$996.00
67Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH29$640.00$841.11$708.86$700.00$675.00$827.87$850.00
68Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH2$675.00$961.99$810.73$750.00$772.00$946.85$879.00
69Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH2$1,000.00$1,246.10$1,050.16$700.00$1,000.00$1,226.48$1,184.00
70Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH2$500.00$574.46$484.13$200.00$461.00$565.41$651.00
71Remove SM RD SN sup&AM (644-7073)EACH33$90.00$105.92$89.26$75.00$85.00$104.25$73.00
72Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH10$36.00$46.64$26.25$50.00$25.00$30.67$33.00
73Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH24$105.00$74.14$115.52$110.00$110.00$134.92$117.00
74Work zone pavement marking removing (W)6"(solid) (662-7068)LF61,908$0.51$0.86$0.72$0.77$0.55$0.85$1.00
75Work zone pavement marking removing (Y)6"(broken) (662-7098)LF3,150$1.40$1.25$1.05$0.77$1.00$1.23$1.00
76Work zone pavement marking removing (Y)6"(solid) (662-7100)LF49,354$0.60$0.86$0.72$0.77$0.55$0.85$1.00
77Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265)LF19,349$0.65$1.01$0.85$0.69$0.97$0.99$1.00
78Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269)LF15,168$0.65$1.01$0.85$0.69$0.97$0.99$1.00
79Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273)LF3,371$0.75$1.08$0.91$0.74$1.00$1.07$1.00
80PRFB rumble strip (BLK)(1')(centerline) (668-7002)LF130$2.50$6.23$5.25$5.00$5.00$6.13$6.00
81PRFB rumble strip (BLK)(1')(edgeline) (668-7137)LF3,874$2.50$4.36$3.68$3.40$4.50$4.29$6.00
82Reflectorized pavement marker type I-A (672-7001)EACH62$4.50$4.36$3.68$4.00$5.50$4.29$7.00
83Reflectorized pavement marker type II-A-A (672-7004)EACH751$4.00$4.36$3.68$3.89$5.50$4.29$7.00
84Eliminating existing PM & markers (4") (677-7001)LF49,354$0.25$0.50$0.42$0.54$0.25$0.49$0.31
85Reloct RDSD FLSH BCN AM (solar PWRD) (685-7005)EACH1$2,500.00$5,607.43$4,725.74$1,000.00$4,500.00$5,519.18$6,448.00
86Bonding course (3007-7001)GAL4,818$3.00$4.00$3.52$5.00$4.20$4.54$6.00
TxDOT contract A00197439: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy