TxDOT contract A00197439 bid tabulation
Highway Improvement, RM 150 (0.476 MI SE of Darden Hill Rd to RM 1826). Let by Texas DOT on August 6, 2026, Hays, Austin District. 7 bids received; low bid $3,441,590 by STX Civil, +9.9% against the engineer's estimate of $3,130,181.
- Owner
- Texas DOT
- Letting
- 06 AUG 2026
- Pay items
- 86
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | STX Civil | $3,441,590 | Low | +10% |
| 2 | Hunter Industries, LTD. | $3,447,342 | 0.0% | +10% |
| 3 | D&S Concrete Contractors LLC | $3,562,474 | +4.0% | +14% |
| 4 | Texas Materials Group, Inc. | $3,760,934 | +9.0% | +20% |
| 5 | D & D Contractors, Inc. | $3,911,325 | +14% | +25% |
| 6 | Aaron Concrete Contractors, LLC | $4,407,410 | +28% | +41% |
| 7 | Joe Bland Construction LLC | $4,595,040 | +34% | +47% |
Engineer's estimate: $3,130,181.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. STX Civil | 2. Hunter Industries, LTD. | 3. D&S Concrete Contractors LLC | 4. Texas Materials Group, Inc. | 5. D & D Contractors, Inc. | 6. Aaron Concrete Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 97 | $2,500.00 | $770.09 | $976.80 | $500.00 | $1,400.00 | $772.57 | $1,350.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 1,475 | $15.00 | $21.80 | $26.40 | $40.00 | $40.00 | $23.05 | $26.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 9,098 | $10.00 | $9.31 | $25.30 | $23.00 | $32.00 | $17.26 | $31.00 |
| 4 | Embankment (final)(OC)(type B) (132-7003) | CY | 3,573 | $6.50 | $15.35 | $25.30 | $28.00 | $15.00 | $6.36 | $19.00 |
| 5 | Furn & place topsoil (4") (160-7002) | SY | 28,174 | $1.50 | $3.74 | $1.91 | $0.50 | $3.30 | $2.40 | $6.00 |
| 6 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 28,174 | $0.15 | $0.31 | $0.19 | $0.70 | $0.18 | $0.22 | $0.21 |
| 7 | Drill seed (permanent_rural_clay) (164-7010) | SY | 28,174 | $0.20 | $0.37 | $0.26 | $0.75 | $0.25 | $0.31 | $0.29 |
| 8 | Vegetative watering (168-7001) | TGL | 475 | $10.00 | $43.61 | $26.40 | $10.00 | $40.00 | $14.60 | $35.00 |
| 9 | Soil ret BLKT(SL_steep_clay_long) (169-7006) | SY | 28,174 | $2.00 | $1.37 | $0.89 | $1.00 | $0.85 | $1.04 | $1.00 |
| 10 | Soil ret BLKT(chan_temporary_4 PSF) (169-7030) | SY | 180 | $2.00 | $1.43 | $1.58 | $4.00 | $1.50 | $1.84 | $2.00 |
| 11 | FL BS (compacted in place)(type A GR 5)(final pos) (247-7179) | CY | 3,679 | $55.00 | $80.09 | $66.97 | $29.00 | $77.00 | $93.77 | $75.00 |
| 12 | Prime coat (multi option) (310-7015) | GAL | 3,140 | $3.75 | $5.46 | $5.28 | $5.00 | $4.90 | $4.48 | $7.00 |
| 13 | D-GR HMA type-B PG64-22 (341-7001) | TON | 2,590 | $82.00 | $126.80 | $97.21 | $165.00 | $99.00 | $163.12 | $132.00 |
| 14 | D-GR HMA type D PG76-22 (341-7056) | TON | 1,317 | $108.00 | $128.62 | $106.47 | $170.00 | $120.00 | $192.56 | $149.00 |
| 15 | D-GR HMA type D PG76-22 (level-UP) (341-7059) | TON | 401 | $110.00 | $132.45 | $110.87 | $170.00 | $166.00 | $198.69 | $218.00 |
| 16 | Tom-C PG76-22 sac-B (347-7002) | TON | 2,096 | $121.00 | $188.26 | $131.76 | $165.00 | $141.00 | $213.41 | $197.00 |
| 17 | Cut & restoring pavement (400-7006) | SY | 319 | $185.00 | $102.90 | $322.31 | $150.00 | $90.00 | $112.83 | $259.00 |
| 18 | Flowable backfill (401-7001) | CY | 81 | $200.00 | $220.54 | $229.66 | $300.00 | $260.00 | $256.40 | $203.00 |
| 19 | Trench excavation protection (402-7001) | LF | 99 | $10.00 | $8.48 | $12.39 | $20.00 | $10.00 | $12.27 | $42.00 |
| 20 | Riprap (concrete)(4 in) (432-7001) | CY | 5 | $550.00 | $1,290.74 | $576.55 | $1,100.00 | $730.00 | $583.81 | $1,080.00 |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 119 | $625.00 | $588.36 | $561.84 | $900.00 | $650.00 | $690.51 | $627.00 |
| 22 | Riprap (stone protection)(12 in) (432-7041) | CY | 136 | $200.00 | $175.49 | $183.78 | $200.00 | $220.00 | $214.64 | $205.00 |
| 23 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 162 | $575.00 | $735.88 | $764.04 | $700.00 | $668.00 | $742.16 | $675.00 |
| 24 | RC pipe (CL III)(18 in) (464-7003) | LF | 273 | $80.00 | $95.92 | $105.02 | $105.00 | $71.00 | $117.27 | $94.00 |
| 25 | RC pipe (CL III)(24 in) (464-7005) | LF | 70 | $150.00 | $117.39 | $643.04 | $160.00 | $88.00 | $120.55 | $112.00 |
| 26 | RC pipe (CL III)(36 in) (464-7009) | LF | 110 | $200.00 | $204.77 | $474.67 | $250.00 | $182.00 | $311.44 | $193.00 |
| 27 | RC pipe (arch)(CL III)(des 3) (464-7042) | LF | 380 | $270.00 | $269.05 | $257.29 | $310.00 | $242.00 | $276.72 | $228.00 |
| 28 | RC pipe (arch)(CL III)(des 4) (464-7043) | LF | 132 | $345.00 | $335.36 | $514.58 | $350.00 | $308.00 | $357.11 | $279.00 |
| 29 | RC pipe (arch)(CL III)(des 5) (464-7044) | LF | 176 | $250.00 | $441.21 | $383.31 | $450.00 | $398.00 | $480.62 | $369.00 |
| 30 | Headwall (CH - PW - S) (diameter= 36 in) (466-7120) | EACH | 1 | $10,000 | $13,867 | $14,177 | $4,500.00 | $16,000 | $16,130 | $20,266 |
| 31 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 1 | $20,000 | $19,302 | $24,553 | $4,500.00 | $36,000 | $19,587 | $40,067 |
| 32 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 1 | $23,000 | $28,934 | $32,608 | $5,000.00 | $49,000 | $24,254 | $62,747 |
| 33 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 18 | $1,250.00 | $1,249.71 | $1,470.23 | $2,500.00 | $1,250.00 | $1,371.20 | $2,467.00 |
| 34 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 4 | $2,150.00 | $1,412.87 | $1,522.74 | $2,800.00 | $1,520.00 | $1,444.80 | $2,826.00 |
| 35 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 1 | $3,750.00 | $3,404.74 | $4,410.69 | $2,600.00 | $3,200.00 | $7,975.83 | $3,617.00 |
| 36 | Set (type II) (des 3) (RCP) (3: 1) (C) (467-7431) | EACH | 2 | $4,000.00 | $1,984.87 | $1,596.25 | $2,650.00 | $1,420.00 | $2,032.28 | $2,320.00 |
| 37 | Set (type II) (des 3) (RCP) (4: 1) (C) (467-7432) | EACH | 2 | $2,500.00 | $2,741.01 | $1,890.29 | $4,000.00 | $1,610.00 | $2,032.28 | $2,458.00 |
| 38 | Set (type II) (des 3) (RCP) (6: 1) (P) (467-7434) | EACH | 10 | $4,000.00 | $4,087.87 | $2,310.36 | $5,000.00 | $1,849.00 | $1,246.11 | $2,856.00 |
| 39 | Set (type II) (des 4) (RCP) (4: 1) (C) (467-7440) | EACH | 2 | $7,000.00 | $8,797.02 | $2,782.93 | $4,000.00 | $2,310.00 | $14,086 | $3,348.00 |
| 40 | Set (type II) (des 5) (RCP) (4: 1) (C) (467-7448) | EACH | 2 | $7,250.00 | $10,005 | $6,300.98 | $4,000.00 | $3,420.00 | $23,019 | $4,497.00 |
| 41 | Removing & RE - lay pipe (18 in) (472-7004) | LF | 223 | $50.00 | $54.04 | $52.51 | $125.00 | $49.00 | $25.70 | $108.00 |
| 42 | Removing structure (set) (496-7004) | EACH | 50 | $375.00 | $645.56 | $572.11 | $400.00 | $175.00 | $419.54 | $609.00 |
| 43 | Removing structure (pipe) (496-7007) | LF | 1,298 | $21.00 | $26.15 | $23.42 | $5.00 | $8.00 | $20.83 | $22.00 |
| 44 | Mobilization (500-7001) | LS | 1 | $200,000 | $176,324 | $239,056 | $200,000 | $370,000 | $106,704 | $440,000 |
| 45 | Barricades, signs and traffic handling (502-7001) | MO | 22 | $5,000.00 | $2,184.60 | $3,780.05 | $4,000.00 | $7,600.00 | $3,606.50 | $1,586.00 |
| 46 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $7,497.52 | $17,052 | $3,000.00 | $4,000.00 | $2,299.66 | $21,574 |
| 47 | TMA (stationary) (505-7001) | DAY | 50 | $190.00 | $101.13 | $284.20 | $200.00 | $275.00 | $350.77 | $307.00 |
| 48 | TMA (mobile operation) (505-7002) | HR | 24 | $65.00 | $200.04 | $227.36 | $225.00 | $80.00 | $153.31 | $88.00 |
| 49 | Rock filter dams (install) (type 2) (506-7002) | LF | 444 | $42.00 | $37.38 | $42.53 | $40.00 | $40.50 | $49.67 | $47.00 |
| 50 | Rock filter dams (remove) (506-7011) | LF | 444 | $15.00 | $6.23 | $14.70 | $50.00 | $14.00 | $17.17 | $16.00 |
| 51 | Construction exits (install) (type 1) (506-7020) | SY | 43 | $22.00 | $43.61 | $42.01 | $50.00 | $40.00 | $49.05 | $47.00 |
| 52 | Construction exits (remove) (506-7024) | SY | 43 | $10.00 | $7.48 | $11.55 | $10.00 | $11.00 | $13.49 | $13.00 |
| 53 | Temporary sediment control fence (install) (506-7039) | LF | 422 | $3.60 | $3.12 | $3.15 | $5.00 | $3.00 | $3.68 | $39.00 |
| 54 | Temporary sediment control fence (remove) (506-7041) | LF | 422 | $1.00 | $0.62 | $1.05 | $1.00 | $1.00 | $1.23 | $1.00 |
| 55 | Constructing detours (508-7001) | SY | 2,045 | $80.00 | $67.25 | $42.28 | $80.00 | $69.69 | $115.85 | $51.00 |
| 56 | Driveways (concrete) (530-7006) | SY | 765 | $115.00 | $130.51 | $113.42 | $90.00 | $140.00 | $140.30 | $177.00 |
| 57 | Driveways (ACP) (530-7010) | SY | 1,670 | $65.00 | $47.02 | $48.22 | $70.00 | $72.00 | $75.57 | $114.00 |
| 58 | Turnouts (ACP) (530-7018) | SY | 507 | $85.00 | $54.84 | $48.40 | $36.00 | $82.00 | $44.16 | $96.00 |
| 59 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,715.50 | $25.00 | $32.40 | $28.35 | $25.00 | $27.00 | $31.89 | $32.00 |
| 60 | Downstream anchor terminal section (540-7015) | EACH | 7 | $1,350.00 | $1,619.93 | $1,417.72 | $1,400.00 | $1,350.00 | $1,594.43 | $1,583.00 |
| 61 | Remove metal beam guard fence (542-7001) | LF | 268 | $3.00 | $3.12 | $1.73 | $5.00 | $1.65 | $3.07 | $2.00 |
| 62 | Guardrail end treatment (install) (544-7001) | EACH | 7 | $3,200.00 | $311.52 | $3,670.32 | $3,555.00 | $3,495.00 | $4,047.40 | $4,097.00 |
| 63 | Guardrail end treatment (remove) (544-7003) | EACH | 3 | $210.00 | $32.40 | $152.27 | $250.00 | $145.00 | $306.62 | $170.00 |
| 64 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 9 | $315.00 | $311.52 | $262.54 | $500.00 | $250.00 | $325.60 | $463.00 |
| 65 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 4 | $300.00 | $373.83 | $315.05 | $500.00 | $300.00 | $330.96 | $455.00 |
| 66 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 9 | $625.00 | $747.66 | $630.10 | $500.00 | $600.00 | $651.19 | $996.00 |
| 67 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 29 | $640.00 | $841.11 | $708.86 | $700.00 | $675.00 | $827.87 | $850.00 |
| 68 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $675.00 | $961.99 | $810.73 | $750.00 | $772.00 | $946.85 | $879.00 |
| 69 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $1,000.00 | $1,246.10 | $1,050.16 | $700.00 | $1,000.00 | $1,226.48 | $1,184.00 |
| 70 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 2 | $500.00 | $574.46 | $484.13 | $200.00 | $461.00 | $565.41 | $651.00 |
| 71 | Remove SM RD SN sup&AM (644-7073) | EACH | 33 | $90.00 | $105.92 | $89.26 | $75.00 | $85.00 | $104.25 | $73.00 |
| 72 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 10 | $36.00 | $46.64 | $26.25 | $50.00 | $25.00 | $30.67 | $33.00 |
| 73 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 24 | $105.00 | $74.14 | $115.52 | $110.00 | $110.00 | $134.92 | $117.00 |
| 74 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 61,908 | $0.51 | $0.86 | $0.72 | $0.77 | $0.55 | $0.85 | $1.00 |
| 75 | Work zone pavement marking removing (Y)6"(broken) (662-7098) | LF | 3,150 | $1.40 | $1.25 | $1.05 | $0.77 | $1.00 | $1.23 | $1.00 |
| 76 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 49,354 | $0.60 | $0.86 | $0.72 | $0.77 | $0.55 | $0.85 | $1.00 |
| 77 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 19,349 | $0.65 | $1.01 | $0.85 | $0.69 | $0.97 | $0.99 | $1.00 |
| 78 | Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269) | LF | 15,168 | $0.65 | $1.01 | $0.85 | $0.69 | $0.97 | $0.99 | $1.00 |
| 79 | Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273) | LF | 3,371 | $0.75 | $1.08 | $0.91 | $0.74 | $1.00 | $1.07 | $1.00 |
| 80 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 130 | $2.50 | $6.23 | $5.25 | $5.00 | $5.00 | $6.13 | $6.00 |
| 81 | PRFB rumble strip (BLK)(1')(edgeline) (668-7137) | LF | 3,874 | $2.50 | $4.36 | $3.68 | $3.40 | $4.50 | $4.29 | $6.00 |
| 82 | Reflectorized pavement marker type I-A (672-7001) | EACH | 62 | $4.50 | $4.36 | $3.68 | $4.00 | $5.50 | $4.29 | $7.00 |
| 83 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 751 | $4.00 | $4.36 | $3.68 | $3.89 | $5.50 | $4.29 | $7.00 |
| 84 | Eliminating existing PM & markers (4") (677-7001) | LF | 49,354 | $0.25 | $0.50 | $0.42 | $0.54 | $0.25 | $0.49 | $0.31 |
| 85 | Reloct RDSD FLSH BCN AM (solar PWRD) (685-7005) | EACH | 1 | $2,500.00 | $5,607.43 | $4,725.74 | $1,000.00 | $4,500.00 | $5,519.18 | $6,448.00 |
| 86 | Bonding course (3007-7001) | GAL | 4,818 | $3.00 | $4.00 | $3.52 | $5.00 | $4.20 | $4.54 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.