TxDOT contract A00127796 bid tabulation

Construct New Road, US 87 (EAST OF US 385/US 87 INTERCHANGE to MOORE COUNTY LINE). Let by Texas DOT on September 4, 2025, Hartley, Amarillo District. 6 bids received; low bid $99,678,127 by FNF Construction, Inc., -41% against the engineer's estimate of $168,723,070.

Owner
Texas DOT
Letting
04 SEP 2025
Pay items
203
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1FNF Construction, Inc.$99,678,127Low-41%
2A. L. Helmcamp, Inc.$128,810,290+29%-24%
3Duininck, Inc.$131,938,195+32%-22%
4Webber, LLC$137,619,509+38%-18%
5Pulice Construction, Inc.$150,709,099+51%-11%
6Kiewit Infrastructure South Co.$182,077,390+83%+8.0%
TxDOT contract A00127796: bids by rank

Engineer's estimate: $168,723,070.

Bid tabulation

LinePay itemUnitQuantityEstimate1. FNF Construction, Inc.2. A. L. Helmcamp, Inc.3. Duininck, Inc.4. Webber, LLC5. Pulice Construction, Inc.6. Kiewit Infrastructure South Co.
1Preparing row (100-7001)ACRE21.69$5,000.00$3,100.00$10,000$62,500$250,000$694,861$1,873.93
2Preparation row (tree remove) (12"-24" diameter) (100-7004)EACH11$1,600.00$2,100.00$1,200.00$960.00$950.00$982.59$2,020.28
3Preparation row (tree remove) (24"-36" diameter) (100-7005)EACH5$2,000.00$5,200.00$2,400.00$3,500.00$3,500.00$3,620.05$3,030.42
4Preparation row (tree remove) (36"-48" diameter) (100-7006)EACH3$4,000.00$7,600.00$3,900.00$5,500.00$5,000.00$5,688.64$4,040.56
5Removing concrete (foundations) (104-7023)SY81$175.00$35.00$60.00$150.00$250.00$962.93$82.71
6Remove (10") TRT/untrt base & asphalt pavement (105-7030)SY4,623$10.00$6.00$10.00$17.00$7.00$3.91$9.13
7Remove (13") TRT/untrt base & asphalt pavement (105-7033)SY134,465$12.00$4.00$12.00$9.45$8.50$4.24$11.22
8Remove (16") TRT/untrt base & asphalt pavement (105-7036)SY11,768$20.00$5.00$15.00$11.50$11.00$4.75$14.13
9Excavation (roadway) (110-7001)CY263,404$23.00$7.00$10.00$17.50$24.00$2.30$12.00
10Excavation (special) (110-7003)CY89,780$28.00$9.50$11.00$6.95$24.00$2.30$15.00
11Embankment (final)(DC)(type B) (132-7004)CY358,999$26.00$3.65$14.00$27.50$25.00$1.96$25.00
12Drill seed (permanent_urban_clay) (164-7012)SY1,752,436$0.70$0.15$0.14$0.11$0.10$0.11$0.15
13Drill seed (temporary_warm) (164-7013)SY876,218$0.30$0.10$0.11$0.10$0.10$0.10$0.14
14Drill seed (temporary_cool) (164-7014)SY876,218$0.30$0.10$0.09$0.10$0.10$0.10$0.14
15Soil ret BLKT(SL_mod_clay_long) (169-7002)SY109,708$3.00$2.25$2.50$2.90$2.85$2.96$4.01
16FL BS(compacted in place)(type A,B or D GR4)(8") (247-7088)SY83,547$24.00$17.00$22.00$25.50$20.40$23.23$46.78
17FL BS(compacted in place)(type A,B or D GR4)(12") (247-7134)SY580,662$34.00$23.50$30.00$30.00$28.50$31.25$52.31
18Rework BS metal (type C)(15")(density control) (251-7094)SY29,245$20.00$1.00$6.30$16.50$15.50$48.57$12.08
19Rework BS metal (type C)(18")(density control) (251-7095)SY13,013$24.00$1.75$7.00$21.50$16.70$48.74$15.85
20Lime (com or QK)(slurry) or QK(dry) (260-7001)TON6,431$330.00$470.00$410.00$400.00$425.00$425.29$569.10
21Lime TRT (subgrade) (8") (260-7020)SY596,014$5.00$2.70$3.70$5.40$3.70$4.14$4.50
22Cement (290-7001)TON1,618$330.00$272.00$250.00$310.00$320.00$207.54$430.87
23Emulsion (standard yield) (290-7002)GAL1,242,301$4.00$2.25$4.75$3.00$2.75$3.19$4.10
24Emul TRT (existing matrl)(12") (290-7013)SY289,581$5.70$1.75$8.00$5.25$4.85$5.93$4.40
25Prime coat (MC-30) (310-7004)GAL166,058$4.70$5.00$5.00$4.40$4.45$10.14$5.79
26Emuls asphalt (erosion control)(MS-2) (314-7012)GAL118,431$4.00$4.00$4.00$3.75$3.40$6.08$2.09
27Aggregate (type-B, GR-4)(sac-B) (316-7173)CY6,038$250.00$111.65$160.00$145.00$100.00$270.63$235.47
28Asphalt (multi option) (316-7263)GAL252,401$4.40$2.75$3.40$3.85$3.50$6.08$5.37
29D-GR HMA type-B PG64-22 (341-7001)TON157,288$160.00$102.00$141.00$128.00$118.00$163.92$164.22
30SP mixes SP-D sac-A PG70-28 (344-7057)TON169,312$180.00$121.00$161.00$145.00$141.00$190.55$196.94
31Tack coat (344-7077)GAL74,949$6.00$4.50$5.00$7.65$7.60$12.39$9.01
32Planing asphalt concrete pavement(2") (354-7051)SY2,668$4.00$3.50$3.60$3.15$1.95$1.11$2.69
33Planing asphalt concrete pavement(3") (354-7052)SY433,104$3.30$2.50$1.50$2.95$1.80$1.28$3.48
34Planing asphalt concrete pavement(4") (354-7053)SY1,333$6.00$5.00$5.00$28.00$3.85$1.44$5.18
35Planing asphalt concrete pavement (0" to 5") (354-7089)SY4,117$5.00$4.00$2.50$12.00$2.25$1.61$5.68
36Concrete pavement (CRCP) (11") (360-7005)SY14,778$200.00$150.00$140.00$120.00$110.00$98.05$188.12
37Cut & restore asphalt paving (400-7008)SY1,666$250.00$260.00$150.00$250.00$6.70$123.97$356.08
38Flowable backfill (401-7001)CY5,655$220.00$270.00$215.00$175.00$120.00$181.00$214.22
39Trench excavation protection (402-7001)LF1,144$6.00$30.00$5.50$25.00$10.00$25.86$32.33
40Temporary special shoring (403-7001)SF5,311$65.00$65.00$30.00$50.00$31.03$166.48
41Drilled shaft (42 in) (416-7007)LF76$700.00$590.00$630.00$580.00$575.00$594.71$806.71
42Drilled shaft (sign mounts) (24 in) (416-7028)LF26$300.00$310.00$350.00$225.00$350.00$148.94$430.11
43Drilled shaft (sign mounts) (54 in) (416-7033)LF42$900.00$945.00$1,100.00$355.00$925.00$956.73$1,297.75
44Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF32$350.00$435.00$470.00$930.00$425.00$439.58$596.26
45Class A concrete (miscellaneous) (420-7002)CY3$2,430.00$2,600.00$1,500.00$2,470.00$915.35$7,419.26
46Riprap (concrete)(4 in) (432-7001)CY63$800.00$900.00$750.00$830.00$597.00$672.30$1,938.57
47Riprap (concrete)(5 in) (432-7002)CY82$800.00$900.00$850.00$830.00$579.00$708.50$1,679.28
48Riprap (mow strip)(4 in) (432-7013)CY236$800.00$710.00$850.00$1,000.00$739.00$781.51$968.05
49Gabion mattresses (galvanized)(18 in) (459-7008)SY604$250.00$165.00$170.00$330.00$139.00$309.71$443.12
50Gabions (3' X 3')(galvanized) (459-7010)CY207$400.00$365.00$480.00$705.00$311.00$550.56$787.73
51Concrete box culvert (3 FT X 2 FT) (462-7001)LF339$400.00$375.00$250.00$280.00$200.00$305.82$437.77
52Concrete box culvert (4 FT X 2 FT) (462-7003)LF2,032$450.00$460.00$300.00$320.00$275.00$343.23$489.44
53Concrete box culvert (4 FT X 3 FT) (462-7004)LF330$515.00$310.00$355.00$275.00$381.86$515.58
54Concrete box culvert (5 FT X 2 FT) (462-7006)LF1,489$550.00$605.00$390.00$395.00$315.00$422.21$558.11
55Concrete box culvert (5 FT X 3 FT) (462-7007)LF43$735.00$530.00$455.00$350.00$493.19$759.16
56Concrete box culvert (6 FT X 2 FT) (462-7010)LF354$715.00$400.00$480.00$325.00$514.56$622.23
57Concrete box culvert (6 FT X 3 FT) (462-7011)LF717$840.00$450.00$530.00$400.00$569.52$735.39
58Concrete box culvert (8 FT X 5 FT) (462-7022)LF117$900.00$1,275.00$660.00$755.00$585.00$825.40$1,044.69
59Concrete box culvert (3 FT X 2 FT)(extend) (462-7056)LF316$900.00$335.00$290.00$330.00$250.00$348.30$456.25
60Concrete box culvert (4 FT X 2 FT)(extend) (462-7058)LF1,496$900.00$425.00$285.00$405.00$260.00$425.93$506.31
61RC pipe (CL III)(24 in) (464-7005)LF4,007$175.00$130.00$100.00$120.00$120.00$131.10$192.79
62RC pipe (CL III)(48 in) (464-7011)LF4$350.00$355.00$590.00$300.00$365.00$327.11$518.22
63RC pipe (CL III)(60 in) (464-7013)LF372$475.00$555.00$320.00$405.00$370.00$433.91$441.38
64RC pipe (arch)(CL III)(des 1) (464-7040)LF2,146$275.00$250.00$180.00$200.00$175.00$212.02$317.44
65RC pipe (arch)(CL III)(des 3) (464-7042)LF1,092$360.00$275.00$200.00$300.00$200.00$317.05$285.93
66RC pipe (arch)(CL III)(des 4) (464-7043)LF164$335.00$250.00$355.00$225.00$369.49$320.31
67Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128)EACH5$8,000.00$10,000$7,800.00$9,900.00$10,000$10,850$14,860
68Inl(CMP)(pazd-CZ)(FG)(4FTX4FT-4FTX4FT) (465-7165)EACH2$8,000.00$20,000$13,000$14,000$20,000$15,537$32,038
69Wingwall (PW - 1) (HW=4 FT) (466-7174)EACH1$20,000$38,000$38,000$23,000$50,000$23,789$33,996
70Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH2$20,000$37,500$35,000$25,000$75,000$25,857$39,703
71Set (type I)(S= 3 FT)(HW= 3 FT)(4:1)(C) (467-7041)EACH2$12,500$8,500.00$14,000$9,100.00$15,000$9,308.69$10,729
72Set (type I)(S= 3 FT)(HW= 3 FT)(6:1)(C) (467-7042)EACH5$15,000$9,500.00$13,000$10,000$20,000$10,343$12,579
73Set (type I)(S= 4 FT)(HW= 3 FT)(4:1)(C) (467-7068)EACH4$13,000$7,250.00$10,000$9,600.00$15,000$9,825.84$9,618.95
74Set (type I)(S= 4 FT)(HW= 3 FT)(6:1)(C) (467-7069)EACH41$14,000$7,500.00$8,500.00$12,000$20,000$12,412$10,359
75Set (type I)(S= 4 FT)(HW= 4 FT)(6:1)(C) (467-7073)EACH4$12,000$12,000$12,500$25,000$12,929$15,538
76Set (type I)(S= 5 FT)(HW= 3 FT)(6:1)(C) (467-7097)EACH14$15,000$9,500.00$10,000$14,000$25,000$14,480$12,209
77Set (type I)(S= 5 FT)(HW= 5 FT)(6:1)(P) (467-7102)EACH2$17,500$17,000$16,000$35,000$16,549$22,531
78Set (type I)(S= 6 FT)(HW= 3 FT)(6:1)(C) (467-7126)EACH4$10,750$12,000$16,500$25,000$17,066$14,058
79Set (type I)(S= 6 FT)(HW= 4 FT)(6:1)(C) (467-7130)EACH3$15,000$11,000$17,000$28,000$17,583$20,311
80Set (type I)(S= 6 FT)(HW= 4 FT)(6:1)(P) (467-7131)EACH3$17,000$10,000$17,000$28,000$17,583$22,013
81Set (type I)(S= 8 FT)(HW= 6 FT)(6:1)(C) (467-7189)EACH2$19,000$42,000$40,000$22,000$65,000$22,755$54,125
82Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327)EACH4$2,600.00$2,750.00$1,500.00$2,800.00$5,000.00$2,896.03$4,498.58
83Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH118$2,600.00$2,750.00$1,700.00$2,500.00$3,000.00$2,585.75$5,061.31
84Set (type II) (60 in) (RCP) (6: 1) (P) (467-7408)EACH2$9,500.00$21,000$35,000$22,000$12,000$22,755$19,509
85Set (type II) (des 1) (RCP) (6: 1) (P) (467-7418)EACH35$3,000.00$2,250.00$3,300.00$3,000.00$5,000.00$3,102.90$3,989.69
86Set (type II) (des 3) (RCP) (6: 1) (C) (467-7433)EACH2$3,000.00$2,750.00$3,400.00$4,500.00$5,000.00$4,654.35$5,648.29
87Set (type II) (des 3) (RCP) (6: 1) (P) (467-7434)EACH26$3,000.00$2,750.00$3,500.00$4,500.00$5,000.00$4,654.35$3,005.85
88Set (type II) (des 4) (RCP) (6: 1) (C) (467-7441)EACH4$5,000.00$3,600.00$6,000.00$5,000.00$6,205.79$3,804.66
89Clean existing culverts (480-7001)EACH14$4,000.00$8,500.00$3,500.00$4,000.00$5,000.00$3,077.61$15,287
90Removing structure (inlet) (496-7002)EACH2$1,700.00$1,200.00$3,700.00$1,500.00$5,000.00$1,602.54$5,990.84
91Removing structure (set) (496-7004)EACH46$800.00$1,200.00$850.00$805.00$5,000.00$878.00$2,680.90
92Removing structure (wingwall) (496-7005)EACH14$2,000.00$1,500.00$2,000.00$1,500.00$5,000.00$1,653.45$5,759.87
93Removing structure (headwall) (496-7006)EACH8$2,000.00$1,500.00$1,900.00$1,500.00$5,000.00$1,653.42$2,379.54
94Removing structure (pipe) (496-7007)LF1,169$50.00$20.00$30.00$30.00$50.00$32.64$57.02
95Removing structure (box culvert) (496-7008)LF1,163$145.00$130.00$60.00$120.00$75.00$133.63$117.20
96Remove STR (barrier gate) (496-7043)EACH12$1,000.00$365.00$2,500.00$605.00$5,000.00$5,438.03$591.94
97Mobilization (500-7001)LS1$15,250,000$9,985,528$12,500,000$13,100,000$13,790,000$15,070,919$22,113,157
98Barricades, signs and traffic handling (502-7001)MO48$250,000$24,000$24,000$16,500$100,000$9,287.61$75,000
99Portable changeable message sign (503-7002)EACH2$15,000$24,500$20,000$17,500$25,000$23,845$38,927
100TMA (stationary) (505-7001)DAY250$150.00$215.00$500.00$250.00$750.00$407.32$603.00
101TMA (mobile operation) (505-7002)HR320$200.00$600.00$85.00$90.50$170.00$688.74$114.52
102Rock filter dams (install) (type 2) (506-7002)LF3,068$50.00$70.00$62.00$51.50$58.25$53.03$71.93
103Rock filter dams (remove) (506-7011)LF3,068$16.00$18.00$19.00$20.50$18.10$21.04$28.54
104Construction exits (install) (type 1) (506-7020)SY1,794$45.00$30.00$24.00$49.00$23.10$50.11$67.97
105Construction exits (remove) (506-7024)SY1,794$12.00$7.00$7.00$17.00$7.05$17.66$23.95
106Backhoe work (erosion & sediment control) (506-7030)HR80$170.00$120.00$210.00$150.00$200.00$156.67$281.66
107Blading work (erosion & sediment control) (506-7032)HR350$250.00$145.00$240.00$170.00$345.00$184.80$421.64
108Temporary sediment control fence (install) (506-7039)LF564$5.00$8.00$7.00$5.25$8.20$5.39$7.31
109Temporary sediment control fence (remove) (506-7041)LF564$2.00$1.00$1.20$1.40$1.75$1.46$1.98
110Biodegradable erosion control logs (install) (8") (506-7043)LF21,921$8.00$5.00$3.80$6.45$4.25$6.62$8.98
111Biodegradable erosion control logs (remove) (506-7046)LF21,921$3.00$1.00$1.05$1.40$1.00$1.46$1.98
112Constructing detours (508-7001)SY14,676$165.00$110.00$120.00$140.00$135.00$115.03$220.33
113Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017)LF1,710$35.00$13.00$30.00$25.00$20.00$25.70$20.21
114Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029)LF4,050$16.00$4.00$25.00$10.50$20.00$6.13$15.27
115Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041)LF1,710$35.00$11.00$30.00$26.00$20.00$20.14$24.12
116Portable concrete traffic barrier (connection hardware) (512-7070)EACH170$100.00$45.00$48.00$60.50$200.00$43.89$64.08
117Intersections (ACP) (530-7002)SY5,853$90.00$40.00$55.00$66.50$68.50$107.97$108.89
118Driveways (ACP) (530-7010)SY4,993$75.00$50.00$52.00$86.50$80.00$114.37$150.11
119Driveways (ACP) (type 1) (530-7011)SY6,517$55.00$6.00$30.00$6.85$46.25$48.54$56.10
120Mill rumble strips (asphalt) (shoulder) (533-7001)LF327,783$0.40$0.15$0.24$0.10$1.75$0.14$0.10
121Metal W-beam guard fence (steel post) (540-7002)LF3,300$40.00$31.00$30.00$27.00$44.00$32.32$42.09
122Downstream anchor terminal section (540-7015)EACH14$2,000.00$1,805.00$1,500.00$1,400.00$1,630.00$1,292.87$2,490.28
123Metal beam guard fence (long span system) (540-7027)EACH3$2,000.00$2,235.00$1,500.00$1,300.00$1,580.00$1,416.99$3,086.54
124Remove metal beam guard fence (542-7001)LF1,625$5.00$2.25$3.50$3.00$5.15$3.10$2.81
125Guardrail end treatment (install) (544-7001)EACH14$3,700.00$3,700.00$3,400.00$3,100.00$3,520.00$3,170.13$5,050.70
126Guardrail end treatment (remove) (544-7003)EACH10$450.00$205.00$340.00$300.00$480.00$341.32$280.59
127Crash cushion attenuator (move & reset) (545-7002)EACH3$285.00$1,600.00$3,500.00$2,520.00$1,572.13$3,507.43
128Crash cushion attenuator (remove) (545-7004)EACH2$2,300.00$2,500.00$1,200.00$1,660.00$837.78$1,402.97
129Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH2$5,000.00$11,000$10,000$10,980$8,724.32$13,328
130Wire fence (remove) (552-7011)LF64,541$2.00$0.75$2.50$2.00$5.65$2.03$2.99
131Mailbox install-S (RR-post) type 4 (560-7006)EACH1$225.00$245.00$300.00$600.00$325.80$315.42
132Mailbox install-S (TWW-post) type 4 (560-7008)EACH7$350.00$225.00$245.00$330.00$650.00$325.80$315.42
133Mailbox install-M (TWW-post) type 4 (560-7010)EACH4$650.00$560.00$600.00$655.00$1,300.00$915.35$788.53
134Relocate RD IL asm (trans-base) (610-7004)EACH4$2,700.00$3,730.00$4,000.00$3,700.00$3,660.00$3,780.36$5,127.87
135Conduit (PVC) (schedule 40) (2") (618-7030)LF793$18.00$27.00$28.00$25.50$25.50$26.37$35.78
136Conduit (PVC) (schedule 80) (2") (618-7054)LF1,237$20.00$34.00$36.00$33.00$32.50$33.61$45.60
137Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF338$30.00$45.00$48.00$44.50$44.00$45.51$61.73
138Electrical conductor (no.8) bare (620-7007)LF1,756$2.30$3.00$3.40$3.00$3.00$3.10$4.21
139Electrical conductor (no.8) insulated (620-7008)LF3,512$2.40$4.00$4.00$3.55$3.50$3.62$4.91
140Electrical conductor (no.4) bare (620-7011)LF612$3.75$4.50$4.70$4.30$4.25$4.40$5.96
141Electrical conductor (no.4) insulated (620-7012)LF1,836$4.00$4.75$5.20$4.70$4.65$4.80$6.52
142Ground box type D (162922)W/apron (624-7008)EACH12$2,500.00$2,194.00$2,400.00$2,200.00$2,150.00$2,223.74$3,016.39
143Elc SRV type D 120/240 100(NS)AL(N)SP(O) (628-7226)EACH6$11,000$10,485$11,300$10,500$10,280$10,627$14,416
144Aluminum signs (type G) (636-7002)SF271$41.00$32.00$35.00$47.50$47.00$28.29$44.45
145Replace existing aluminum signs(type A) (636-7004)SF42$50.00$32.00$35.00$47.50$58.00$23.01$44.45
146Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH39$1,200.00$737.00$800.00$705.00$700.00$661.95$1,039.44
147Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002)EACH88$1,200.00$1,006.00$1,100.00$960.00$950.00$848.12$1,419.36
148Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH270$1,200.00$830.00$900.00$805.00$800.00$848.12$1,168.47
149Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026)EACH14$1,200.00$1,220.00$1,350.00$1,100.00$1,100.00$1,091.18$1,720.44
150Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH2$1,500.00$1,118.00$1,200.00$1,000.00$1,000.00$1,204.96$1,577.07
151Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035)EACH3$1,500.00$1,220.00$1,350.00$1,200.00$1,150.00$1,287.70$1,720.44
152Remove SM RD SN sup&AM (644-7073)EACH97$160.00$102.00$120.00$100.00$100.00$113.76$143.37
153Install LRSS (struct steel) (647-7001)LB2,052$10.00$10.00$10.00$9.05$10.00$8.73$12.91
154Remove lrsa (647-7003)EACH2$1,300.00$762.00$850.00$805.00$4,000.00$775.72$1,075.27
155Install overhead sign support(30 FT bal tee) (650-7028)EACH2$70,000$59,000$65,000$58,000$57,800$59,731$81,022
156Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003)EACH48$145.00$135.00$145.00$105.00$105.00$101.36$186.39
157Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH80$40.00$26.00$50.00$45.50$30.00$46.28$35.07
158Install delineator assembly (D-SY)SZ 1(yflx)GND (658-7023)EACH3$145.00$132.00$145.00$105.00$105.00$102.39$186.39
159Install delineator assembly (D-DY)SZ 1(yflx)GND (658-7050)EACH908$145.00$132.00$145.00$105.00$105.00$102.91$186.39
160Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH181$145.00$132.00$145.00$105.00$105.00$100.32$186.39
161Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH75$145.00$132.00$145.00$105.00$105.00$97.22$186.39
162Remove delin & object marker assms (658-7078)EACH149$40.00$28.00$30.00$15.00$15.00$15.25$35.85
163Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF1,074$0.75$0.50$0.38$0.35$0.35$0.36$0.49
164Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF298,954$0.70$0.35$0.32$0.30$0.30$0.31$0.42
165Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF31$22.00$25.00$20.00$20.00$20.69$28.06
166Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF305,219$0.70$0.35$0.32$0.30$0.30$0.31$0.42
167Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH22$11.00$12.00$10.00$10.00$10.34$14.03
168Work zone pavement marking removing (W)6"(broken) (662-7065)LF2,150$0.85$1.75$1.60$1.50$1.50$1.55$2.10
169Work zone pavement marking removing (W)6"(solid) (662-7068)LF29,131$1.00$1.00$1.10$0.96$0.95$0.98$1.33
170Work zone pavement marking removing (W)24"(solid) (662-7077)LF164$17.00$22.00$25.00$20.00$20.00$20.69$28.06
171Work zone pavement marking removing (Y)6"(solid) (662-7100)LF28,152$1.00$1.00$1.00$0.96$0.95$0.98$1.33
172Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH16,289$1.50$1.00$1.20$1.55$1.45$3.99$2.81
173Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH5,314$1.50$1.00$1.20$1.55$1.45$4.02$2.81
174Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008)LF393$1.30$1.00$1.10$1.00$1.00$1.03$1.40
175Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023)LF85,006$2.00$1.00$1.10$1.00$1.00$1.03$1.40
176Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029)LF301$2.50$7.75$8.30$7.55$7.50$7.75$10.52
177Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035)LF373$10.00$13.00$14.00$12.50$12.50$12.93$17.54
178Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041)EACH173$200.00$254.00$280.00$250.00$250.00$258.57$350.74
179Reflectorized pavement marking type I(W)(lane drop arrow)(090MIL) (666-7059)EACH4$400.00$430.00$470.00$430.00$425.00$439.58$596.26
180Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065)EACH173$275.00$330.00$360.00$330.00$325.00$336.14$455.97
181Ref pavement marking type I(W)18"(yld tri)(090MIL) (666-7086)EACH1,283$44.00$60.00$65.00$58.00$57.50$59.47$80.67
182Type I high perf PM (W)6"(broken)(090MIL) (666-7289)LF55,345$0.85$1.00$0.88$0.81$0.80$0.83$1.12
183Type I high perf PM (W)6"(solid)(090MIL) (666-7292)LF221,051$0.80$0.75$0.83$0.76$0.75$0.78$1.05
184Type I high perf PM (Y)6"(broken)(090MIL) (666-7301)LF1,010$1.00$0.88$0.81$0.80$0.83$1.12
185Type I high perf PM (Y)6"(solid)(090MIL) (666-7304)LF213,354$0.80$0.75$0.83$0.76$0.75$0.78$1.05
186Pavement sler 6" (666-7347)LF7,872$0.50$1.25$1.20$1.10$1.10$1.14$1.54
187Plowable reflectorized pavement marker type II-C-R (672-7015)EACH45$90.00$102.00$110.00$100.00$100.00$103.42$140.30
188Recessed reflectorized pavement marker type I-C (672-7023)EACH243$52.00$55.00$50.50$50.00$51.71$70.15
189Recessed reflectorized pavement marker type II-A-A (672-7025)EACH259$52.00$55.00$50.50$50.00$51.71$70.15
190Recessed reflectorized pavement marker type II-C-R (672-7027)EACH4,868$39.00$47.00$50.00$45.50$45.00$46.54$63.13
191Eliminating existing PM & markers (4") (677-7001)LF35,718$1.25$0.75$0.85$0.76$0.75$0.78$1.05
192Eliminating existing PM & markers (24") (677-7008)LF12$10.00$11.00$10.00$10.00$10.34$14.03
193Eliminating existing PM & markers (arrow) (677-7009)EACH4$102.00$110.00$100.00$100.00$103.44$140.30
194Pavement surface preparation for marking (6") (678-7002)LF7,872$0.50$1.00$1.10$1.00$1.00$1.03$1.40
195Pavement surface preparation for marking (RPM) (678-7033)EACH45$2.00$10.00$11.00$10.00$10.00$10.34$14.03
196Full - width mowing (730-7019)CYC8$18,000$11,000$9,800.00$25,000$19,070$8,121.10$18,730
197Underseal course (3006-7001)GAL128,818$7.00$3.00$3.70$4.35$4.55$8.11$5.39
198Install DMS (pole MTD cabinet) (6004-7001)EACH2$20,000$44,000$48,000$43,000$42,750$44,216$59,977
199ITS pole (50 FT) (90 MPH) (6011-7005)EACH4$25,000$23,000$25,000$22,500$22,500$23,272$31,567
200ITS pole MNTD cab (type 2)(conf 1) (6011-7028)EACH4$1,000.00$7,272.00$8,000.00$7,200.00$7,130.00$7,369.38$9,996.19
201Installation of cellular modem (6015-7001)EACH6$4,500.00$3,470.00$3,800.00$3,400.00$3,400.00$3,516.61$4,770.11
202CCTV field equipment (digital) (6018-7002)EACH4$24,000$15,562$17,000$15,500$15,250$15,773$21,395
203CCTV mount (pole) (6018-7006)EACH4$5,000.00$1,863.00$2,000.00$1,800.00$1,830.00$1,887.60$2,560.43
TxDOT contract A00127796: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way