TxDOT contract A00209252 bid tabulation

Regional Goods Movement Program, SH 146 (AT IH 10 to .). Let by Texas DOT on May 6, 2026, Chambers, Beaumont District. 6 bids received; low bid $4,355,659 by R Construction Civil, LLC, -7.0% against the engineer's estimate of $4,682,082.

Owner
Texas DOT
Letting
06 MAY 2026
Pay items
178
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1R Construction Civil, LLC$4,355,659Low-7.0%
2Jfo Services, LLC$4,416,648+1.0%-6.0%
3Texas Materials Group, Inc.$4,430,314+2.0%-5.0%
4Isi Contracting, Inc.$4,484,431+3.0%-4.0%
5Icon GC, LLC$4,710,000+8.0%+1.0%
6MC2 Civil, LLC$5,564,976+28%+19%
TxDOT contract A00209252: bids by rank

Engineer's estimate: $4,682,082.

Bid tabulation

LinePay itemUnitQuantityEstimate1. R Construction Civil, LLC2. Jfo Services, LLC3. Texas Materials Group, Inc.4. Isi Contracting, Inc.5. Icon GC, LLC6. MC2 Civil, LLC
1Removing concrete (medians) (104-7008)SY1,758$20.00$11.00$15.72$14.00$35.00$39.00$10.00
2Removing concrete (driveways) (104-7011)SY2,139$24.00$11.00$30.53$19.00$37.00$10.00$10.00
3Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY268$28.00$12.00$37.42$26.00$21.00$10.00$10.00
4Removing concrete (curb or curb & gutter) (104-7018)LF4,954$15.30$8.00$5.41$8.50$6.25$31.00$10.00
5Removing concrete (rail W/ metal element) (104-7037)LF153$34.00$95.00$67.78$50.00$35.00$73.00$30.00
6Remove (24") TRT/untrt base & asphalt pavement (105-7044)SY615$17.20$55.00$54.97$20.00$72.00$22.00$20.00
7Subgr widen (OC) (112-7001)STA36.91$476.00$650.00$3,036.88$3,000.00$1,202.00$3,639.00$15,000
8Embankment (final)(OC)(type C) (132-7005)CY85$38.00$90.00$28.99$95.00$131.00$40.00$200.00
9Backfill (type A or B) (134-7004)STA36.91$200.00$1,125.00$1,068.20$2,450.00$1,897.00$250.00$2,000.00
10Hydro mulch seed (permanent_rural_sandy) (164-7017)SY6,964$0.48$0.65$0.50$0.50$0.50$1.00$0.60
11Hydro mulch seed (temporary_warm) (164-7021)SY6,964$0.36$0.30$0.28$0.50$0.28$1.00$0.60
12Vegetative watering (168-7001)TGL59$36.00$272.00$99.79$80.00$155.95$1.00$40.00
13Lime (quicklime (slurry)) (260-7003)TON114$320.00$355.00$372.39$375.00$389.00$422.00$300.00
14Lime TRT(subgrade)(6") (260-7024)SY7,036$5.45$8.40$8.65$18.00$15.00$10.00$11.00
15CM TRT(PT MX)(CL L)(tya)(GR1-2)(FN pos) (276-7057)CY1,172$140.00$235.00$264.53$158.11$173.00$142.00$200.00
16Prime coat (AE-P) (310-7001)GAL1,200$4.52$9.00$17.08$8.00$20.00$11.00$5.00
17D-GR HMA type D PG 64-22 (exempt) (341-7064)TON330$160.00$350.00$341.64$377.00$350.00$354.00$130.00
18Tack coat (341-7082)GAL360$4.00$7.00$17.08$4.00$44.00$14.00$5.00
19Concrete pavement (CPCD) (12") (360-7022)SY5,999$160.00$125.00$129.92$113.50$155.00$166.00$140.00
20Concrete pavement (CPCD)(fast TRK)(15") (360-7099)SY547$160.00$185.00$264.51$232.00$181.00$203.00$200.00
21Full - depth repair CPCD (12") (361-7023)CY21$1,200.00$860.00$2,597.12$1,700.00$1,953.00$871.00$500.00
22Cem stabil BKFL (400-7010)CY65$186.00$95.00$47.37$66.00$162.00$64.00$55.00
23Trench excavation protection (402-7001)LF162$8.00$15.00$11.39$37.00$105.00$0.01$10.00
24Temporary special shoring (403-7001)SF1,812$46.00$71.00$68.33$13.00$61.00$1.00$25.00
25Class C concrete (collar) (420-7061)EACH2$1,500.00$1,800.00$2,847.04$1,000.00$4,733.00$1,060.00$1,500.00
26CL E concrete (seal slab)(non-reinforced) (420-7070)CY108$500.00$525.00$293.15$1.00$765.00$307.00$200.00
27Riprap (concrete)(5 in) (432-7002)CY9$964.00$670.00$499.78$650.00$609.00$571.00$900.00
28Riprap (stone common)(dry)(18 in) (432-7033)CY40$200.00$222.00$310.74$260.00$252.00$521.00$150.00
29Rail (handrail)(type E) (450-7062)LF139$145.00$305.00$210.68$200.00$205.00$278.00$225.00
30Concrete box culvert (6 FT X 3 FT)(extend) (462-7066)LF36$1,114.00$1,300.00$1,388.28$1,050.00$2,186.00$984.00$1,100.00
31Concrete box culvert (7 FT X 4 FT)(extend) (462-7071)LF34$1,200.00$1,600.00$1,332.71$1,330.00$2,573.00$1,268.00$1,500.00
32RC pipe (CL III)(18 in) (464-7003)LF129$96.00$310.00$187.30$165.00$169.00$190.00$250.00
33RC pipe (CL III)(30 in) (464-7007)LF9$263.00$510.00$477.91$550.00$227.00$505.00$450.00
34RC pipe (CL III)(42 in) (464-7010)LF12$335.00$520.00$511.49$850.00$408.00$537.00$550.00
35RC pipe (CL III)(48 in) (464-7011)LF32$423.00$410.00$429.06$360.00$469.00$533.00$550.00
36Inlet (complete)(pco)(5FT)(none) (465-7021)EACH6$5,250.00$5,750.00$6,495.24$7,000.00$4,746.00$5,169.00$5,000.00
37Inlet (complete)(pco)(5FT)(left) (465-7022)EACH2$7,640.00$6,700.00$9,134.45$9,500.00$7,235.00$4,510.00$6,000.00
38Inlet (complete)(pcu)(5FT)(none) (465-7037)EACH1$9,000.00$5,600.00$7,370.99$7,500.00$5,388.00$5,167.00$6,500.00
39Inlet (complete)(pcu)(5FT)(right) (465-7039)EACH1$9,500.00$7,000.00$9,382.53$9,500.00$7,167.00$5,167.00$7,000.00
40Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH1$25,000$33,000$41,878$35,000$41,233$30,305$30,000
41Set (type I)(S= 7 FT)(HW= 5 FT)(3:1)(C) (467-7157)EACH1$17,835$4,600.00$11,626$12,000$12,692$3,174.00$20,000
42Set (type I)(S= 7 FT)(HW= 5 FT)(4:1)(C) (467-7158)EACH1$18,536$4,900.00$13,755$14,000$15,039$3,569.00$20,000
43Set (type II) (48 in) (RCP) (3: 1) (C) (467-7389)EACH1$7,200.00$5,300.00$6,090.95$6,500.00$6,556.00$7,782.00$7,000.00
44Set (type II) (48 in) (RCP) (4: 1) (C) (467-7390)EACH1$8,569.00$5,600.00$6,432.59$6,800.00$6,973.00$7,782.00$7,500.00
45Slot drain (gal steel) (18 in) (474-7005)LF22$3,000.00$627.00$806.59$325.00$778.00$77.00$500.00
46Adjusting inlets (cap) (479-7006)EACH19$3,000.00$550.00$1,399.57$2,950.00$986.00$445.00$500.00
47Clean existing culverts (480-7001)EACH2$1,500.00$885.00$6,516.10$5,700.00$341.00$3,291.00$3,000.00
48Removing structure (set) (496-7004)EACH5$540.00$605.00$1,604.71$500.00$1,238.00$669.00$500.00
49Removing structure (wingwall) (496-7005)EACH2$1,726.00$3,700.00$2,788.40$9,000.00$22,497$2,097.00$1,500.00
50Remove STR (driveway culvert) (496-7038)EACH3$740.00$3,300.00$1,801.99$450.00$1,402.00$341.00$500.00
51Mobilization (500-7001)LS1$430,000$150,000$398,482$605,000$200,000$214,677$550,000
52Barricades, signs and traffic handling (502-7001)MO16$7,500.00$9,400.00$1,992.93$8,250.00$6,500.00$8,028.00$40,000
53Portable changeable message sign (503-7002)EACH6$5,000.00$40,000$14,235$21,400$11,000$28,238$25,000
54TMA (stationary) (505-7001)DAY214$355.00$775.00$236.87$280.00$675.00$250.00$200.00
55TMA (mobile operation) (505-7003)DAY24$160.00$275.00$236.87$640.00$849.00$650.00$250.00
56Rock filter dams (install) (type 2) (506-7002)LF180$46.00$90.00$39.86$50.00$39.00$125.00$50.00
57Rock filter dams (remove) (506-7011)LF180$13.60$20.00$11.39$17.00$11.14$53.00$5.00
58Temporary SDMT cont fence (inlet protection) (506-7040)LF406$12.20$13.00$3.42$6.00$3.34$6.00$5.00
59Temporary sediment control fence (remove) (506-7041)LF406$6.10$3.00$1.42$2.00$1.39$3.00$1.00
60Biodegradable erosion control logs (install) (12") (506-7044)LF218$8.00$9.00$7.97$7.00$7.64$9.00$5.00
61Biodegradable erosion control logs (remove) (506-7046)LF218$2.49$1.00$2.28$2.00$2.23$3.00$1.00
62Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF1,160$35.00$105.00$81.73$29.00$35.00$94.00$65.00
63Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF360$40.00$100.00$77.96$46.00$35.00$88.00$65.00
64Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF4,300$8.00$14.00$15.65$5.50$7.00$13.00$9.00
65Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF520$12.00$14.00$22.93$19.00$2.00$16.00$9.00
66Portable concrete traffic barrier (stockpile)(low prof)(type 1) (512-7045)LF1,720$15.00$8.00$24.16$13.00$10.00$13.00$10.00
67Portable concrete traffic barrier (stockpile)(low prof)(type 2) (512-7046)LF200$13.00$14.00$45.79$50.00$10.00$16.00$12.00
68Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF1,160$10.00$6.00$9.78$10.00$20.00$22.00$9.00
69Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF360$15.00$7.00$14.43$14.00$7.00$23.00$9.00
70Permanent CTB (single slope) (type 1) (42 ) (514-7001)LF253$92.63$205.00$114.21$120.00$120.00$127.00$100.00
71Concrete curb (type II) (529-7002)LF136$58.00$19.00$21.95$35.00$110.00$8.00$70.00
72Concrete curb & gutter (type II) (529-7009)LF2,958$86.00$16.00$29.89$17.00$10.00$20.00$70.00
73Concrete curb (slotted) (529-7013)LF2,604$30.00$17.00$17.11$24.00$35.00$14.00$65.00
74Driveways (concrete) (530-7006)SY1,604$142.00$90.00$87.40$113.00$75.00$125.00$130.00
75Concrete sidewalks (4") (531-7001)SY293$110.00$58.00$56.82$57.00$120.00$70.00$130.00
76Curb ramps (type 1) (531-7005)EACH5$5,000.00$2,400.00$2,076.63$3,900.00$6,456.00$1,038.00$3,000.00
77Curb ramps (type 21) (531-7023)SY2$230.00$1,800.00$2,578.37$5,300.00$6,450.00$616.00$3,000.00
78Curb ramps (type 22) (531-7024)SY4$120.00$1,800.00$2,471.64$5,500.00$12,692$615.00$3,000.00
79Concrete sidewalks (special) (531-7025)SY6$150.00$485.00$3,572.18$1,250.00$2,227.00$457.00$250.00
80Concrete median (536-7002)SY418$500.00$65.00$99.41$138.00$144.00$80.00$100.00
81Concrete directional island (536-7004)SY66$110.00$107.00$189.80$300.00$207.00$53.00$80.00
82Crash cushion attenuator (install)(L)(N)(TL3) (545-7006)EACH2$27,950$30,000$31,317$34,000$26,958$38,869$35,000
83Conduit (PVC) (schedule 40) (2") (618-7030)LF1,190$8.00$15.00$14.98$4.00$13.90$17.00$5.00
84Conduit (PVC) (schedule 40) (3") (concrete encse) (618-7038)LF4,790$40.00$13.00$13.67$17.50$12.68$64.00$17.00
85Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF359$15.00$41.00$42.52$49.00$39.46$25.00$50.00
86Conduit (PVC) (schedule 80) (3") (bore) (618-7061)LF280$28.00$50.00$52.00$70.00$48.26$29.00$70.00
87Conduit (PVC) (schedule 80) (4") (bore) (618-7065)LF29$32.96$44.00$45.85$250.00$42.55$36.00$250.00
88ITS multi-duct CND (PVC-40) (619-7001)LF3,130$44.00$22.00$22.49$22.00$20.87$26.00$22.00
89Electrical conductor (no.14) insulated (620-7002)LF3,820$1.00$1.00$1.14$0.70$1.06$2.00$1.00
90Electrical conductor (no.8) bare (620-7007)LF315$1.75$1.80$1.94$1.85$1.80$3.00$2.00
91Electrical conductor (no.4) bare (620-7011)LF2,205$2.89$3.00$3.42$3.00$3.17$5.00$3.00
92ITS GND box(pcast) type 1 (243636)W/aprn (623-7002)EACH2$4,600.00$4,400.00$4,991.43$6,750.00$4,632.17$5,606.00$6,500.00
93Ground box type A (122311) (624-7001)EACH1$1,129.00$1,200.00$1,283.45$975.00$1,191.07$960.00$1,000.00
94Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH18$756.00$600.00$740.23$700.00$547.45$702.00$518.00
95Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH10$735.00$600.00$740.23$850.00$661.45$780.00$626.00
96Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009)EACH7$751.00$600.00$797.17$775.00$612.85$746.00$580.00
97Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012)EACH5$835.00$650.00$797.17$950.00$686.81$842.00$650.00
98Install small roadside sign support and assembly type 10BWG(1)SB(U) (644-7015)EACH3$1,060.00$750.00$911.05$1,300.00$935.12$979.00$885.00
99Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025)EACH1$800.00$650.00$911.06$950.00$707.95$827.00$670.00
100Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035)EACH5$1,300.00$900.00$1,366.58$1,475.00$1,136.94$1,125.00$1,076.00
101Install small roadside sign support and assembly TYS80(1)SB(U) (644-7042)EACH2$1,290.00$850.00$968.00$1,350.00$958.37$1,102.00$907.00
102Install small roadside sign support and assembly TYS80(1)SB(U-WC) (644-7046)EACH2$2,450.00$850.00$9.11$1,400.00$1,039.73$1,114.00$984.00
103In bridge MNT clearance sign assembly(type S) (644-7062)EACH2$2,800.00$1,800.00$2,277.64$3,500.00$3,144.55$3,949.00$2,976.00
104Remove SM RD SN sup&AM (644-7073)EACH53$105.00$140.00$227.76$120.00$73.96$92.00$70.00
105Remove BRDG MNT clearance sign assembly (644-7074)EACH2$587.00$1,200.00$398.59$1,200.00$581.15$724.00$550.00
106Install delineator assembly (D-SW)SZ 1(WFLX)SRF(BR) (658-7008)EACH38$65.00$130.00$142.35$100.00$100.38$157.00$95.00
107Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH4$18.00$36.00$29.04$25.00$19.02$46.00$18.00
108Install delineator assembly (D-SY)SZ 1(yflx)SRF (658-7025)EACH5$100.00$120.00$142.35$100.00$100.38$157.00$95.00
109Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH4$100.00$98.00$96.80$70.00$100.38$117.00$95.00
110Install OM SM RD sign (1-OM-PW)Y (658-7317)EACH43$24.00$10.00$34.16$40.00$15.85$13.00$15.00
111Install OM SM RD sign (1-OM-PW)R (658-7318)EACH10$28.00$10.00$34.17$40.00$15.85$13.00$15.00
112Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF4,300$0.32$1.00$0.34$0.45$0.39$1.00$0.37
113Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF10,753$0.38$1.00$0.34$0.45$0.39$1.00$0.37
114Work zone pavement marking non-removing (W)8"(DOT) (662-7010)LF360$0.80$4.00$0.51$1.50$0.69$2.00$0.65
115Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF14,854$0.65$2.00$0.46$0.75$0.69$2.00$0.65
116Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF672$3.56$9.00$3.42$4.50$5.81$4.00$5.50
117Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF13,642$0.36$1.00$0.34$0.45$0.39$1.00$0.37
118Work zone pavement marking removing (W)(arrow) (662-7082)EACH44$200.00$230.00$85.41$98.00$132.08$395.00$125.00
119Work zone pavement marking removing (W)(double arrow) (662-7083)EACH7$424.00$330.00$101.36$111.00$264.16$527.00$250.00
120Work zone pavement marking removing (W)(word) (662-7092)EACH44$200.00$280.00$85.41$98.00$137.36$171.00$130.00
121Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017)LF344$1.20$6.00$1.14$2.75$1.43$3.00$1.35
122Reflectorized pavement marking type II (W) 8" (solid) (666-7179)LF6,845$0.40$2.00$0.91$0.55$0.79$3.00$0.75
123Pavement sler 6" (666-7347)LF12,140$0.14$0.25$0.28$0.15$0.26$0.20$0.25
124Pavement sler 8" (666-7348)LF6,681$0.20$0.50$0.34$0.25$0.53$0.20$0.50
125Pavement sler 24" (666-7352)LF728$1.50$2.25$0.40$2.25$3.17$0.20$3.00
126Pavement sler (arrow) (666-7353)EACH35$15.00$50.00$28.47$22.25$21.13$13.00$20.00
127Pavement sler (word) (666-7354)EACH26$30.00$50.00$28.47$22.25$21.13$13.00$20.00
128Pavement sler (double arrow) (666-7356)EACH17$28.00$50.00$28.47$33.50$31.70$20.00$30.00
129Pavement sler (uturn arrow) (666-7358)EACH4$28.85$50.00$28.47$33.50$31.70$26.00$30.00
130Pavement sler (yld tri) (666-7365)EACH20$10.00$5.50$28.47$1.75$5.28$7.00$5.00
131Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407)LF2,900$0.99$1.10$0.85$0.80$0.90$2.00$0.85
132Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410)LF4,991$0.65$1.10$0.85$0.80$0.90$2.00$0.85
133Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419)LF130$0.56$1.30$1.14$0.80$1.06$2.00$1.00
134Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422)LF4,428$0.56$1.10$0.85$0.80$0.95$2.00$0.90
135Prefabricated PM type C (W)(24")(solid) (668-7089)LF680$14.50$18.00$17.08$19.00$17.96$33.00$17.00
136Prefabricated PM type C (W)(arrow) (668-7091)EACH35$217.00$280.00$284.70$275.00$285.29$461.00$270.00
137Prefabricated PM type C (W)(double arrow) (668-7093)EACH17$280.00$450.00$284.70$475.00$594.92$527.00$463.03
138Prefabricated PM type C (W)(uturn arrow) (668-7096)EACH4$250.00$400.00$313.18$475.00$491.34$527.00$465.00
139Prefabricated PM type C (W)(word) (668-7103)EACH26$338.00$375.00$284.70$335.00$390.96$527.00$370.00
140Prefabricated PM type C (W)(36")(yld tri) (668-7111)EACH12$48.00$115.00$74.02$55.00$57.06$434.00$54.00
141Reflectorized pavement marker type I-C (672-7002)EACH192$3.50$8.00$6.83$7.00$5.28$8.00$5.00
142Reflectorized pavement marker type II-A-A (672-7004)EACH88$4.50$8.00$6.83$7.00$5.28$8.00$5.00
143Reflectorized pavement marker type II-C-R (672-7006)EACH113$4.50$8.00$6.83$7.00$5.28$8.00$5.00
144Eliminating existing PM & markers (6") (677-7002)LF26,362$0.25$1.00$0.34$0.50$0.42$0.40$0.40
145Eliminating existing PM & markers (8") (677-7004)LF20,884$0.75$1.00$0.43$0.90$0.48$0.40$0.45
146Eliminating existing PM & markers (24") (677-7008)LF1,280$2.22$2.30$1.28$3.00$3.17$1.00$3.00
147Eliminating existing PM & markers (arrow) (677-7009)EACH51$41.00$130.00$56.94$50.00$42.27$26.00$40.00
148Eliminating existing PM & markers (word) (677-7015)EACH44$35.00$130.00$56.94$50.00$42.27$33.00$40.00
149Pavement surface preparation for marking (6") (678-7002)LF12,449$0.05$0.15$0.02$0.05$0.08$0.20$0.08
150Pavement surface preparation for marking (8") (678-7004)LF7,189$0.26$0.18$0.03$0.10$0.11$0.20$0.10
151Pavement surface preparation for marking (arrow) (678-7009)EACH35$75.00$11.00$28.47$11.00$5.28$0.20$5.00
152Pavement surface preparation for marking (double arrow) (678-7010)EACH17$75.00$16.00$28.47$11.00$10.57$26.00$10.00
153Pavement surface preparation for marking (uturn arr) (678-7012)EACH4$75.00$16.00$28.47$11.00$10.57$26.00$10.00
154Pavement surface preparation for marking (word) (678-7016)EACH26$135.00$16.00$28.47$11.00$5.28$26.00$5.00
155Pavement surface preparation for marking (36")(yld tri) (678-7023)EACH20$50.00$5.50$28.47$11.00$2.11$13.00$2.00
156Vehicle signal section (12")LED(green) (682-7001)EACH6$300.00$250.00$279.01$360.00$258.93$384.00$300.00
157Vehicle signal section (12")LED(green arrow) (682-7002)EACH10$300.00$250.00$279.01$360.00$258.93$384.00$300.00
158Vehicle signal section (12")LED(yel) (682-7003)EACH4$300.00$250.00$279.01$360.00$258.93$384.00$300.00
159Vehicle signal section (12")LED(yel arrow) (682-7004)EACH8$300.00$250.00$279.01$360.00$258.93$384.00$300.00
160Vehicle signal section (12")LED(red) (682-7005)EACH4$300.00$250.00$279.01$360.00$258.93$384.00$300.00
161Vehicle signal section (12")LED(red arrow) (682-7006)EACH8$300.00$250.00$279.01$360.00$258.93$384.00$300.00
162Pedestrian signal section (LED)(countdown) (682-7018)EACH16$500.00$625.00$684.43$900.00$635.17$845.00$650.00
163Back plate (12")(3 sect) (682-7052)EACH8$105.00$240.00$255.10$275.00$236.73$251.00$200.00
164Back plate (12")(4 sect) (682-7053)EACH4$127.00$260.00$285.84$840.00$265.27$327.00$250.00
165Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009)LF3,380$3.00$3.20$3.53$3.30$3.28$4.00$3.50
166Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010)LF945$3.92$3.20$3.64$3.50$3.38$5.00$3.50
167Pedestrian pole assembly (687-7001)EACH12$1,000.00$3,600.00$4,059.88$2,300.00$3,767.67$3,766.00$3,000.00
168Relocate pedestrian pole assembly (687-7003)EACH3$5,357.00$1,700.00$1,905.24$2,700.00$1,768.11$2,469.00$2,000.00
169Removal of ground boxes (690-7006)EACH8$300.00$350.00$380.37$875.00$352.99$141.00$120.00
170Replace of ground boxes (690-7007)EACH8$1,500.00$1,200.00$1,314.19$1,200.00$1,219.60$705.00$600.00
171Removal of signal related signs (690-7027)EACH2$140.00$220.00$245.99$130.00$228.28$37.00$30.00
172Spot tree trimming / brush removal (752-7002)LF35$1.10$160.00$34.16$110.00$50.00$66.00$500.00
173Drain inlet cleaning (764-7001)EACH19$330.00$575.00$227.76$500.00$52.84$856.00$300.00
174Storm sewer cleaning (pipe)(12"-18"diameter) (764-7007)LF166$3.10$16.00$9.11$16.00$4.76$10.00$5.00
175Storm sewer cleaning (pipe)(19"-24"diameter) (764-7008)LF1,208$8.25$19.00$9.11$2.00$5.02$10.00$8.00
176Storm sewer cleaning (pipe)(25"-30"diameter) (764-7009)LF1,198$4.00$27.00$9.11$2.00$5.28$10.00$12.00
177Fiber optic CBL(single-mode)(144 fiber) (6027-7006)LF11,080$5.00$4.40$4.63$4.15$4.30$5.00$3.50
178Fiber optic CBL (single-mode)(6 fiber) (6027-7011)LF15,755$2.20$2.00$2.08$1.75$1.93$2.00$1.50
TxDOT contract A00209252: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy