Inlet (complete)(pco)(5FT)(none), TxDOT 465-7021
Low bidders on TxDOT contracts carried a median of $8,450.00 per EACH for this item, over the 24 months to 19 NOV 2026, across 14 low bids. Half of all 79 bids fell between $7,107.50 and $12,310.
- Owner
- Texas DOT
- Item
- 465-7021
- Unit
- EACH
- Data through
- 19 NOV 2026
TxDOT prints this item as “INLET (COMPL)(PCO)(5FT)(NONE)”.
TxDOT has bid this work under more than one code: 4656021001 on lettings from 06 FEB 2020 to 06 JUN 2024 (99 bids); 4656021002 on lettings from 08 MAR 2023 to 08 MAR 2023 (1 bids); 465-7021 on lettings from 06 NOV 2024 to 03 NOV 2026 (86 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 6 | 6 | $5,840.00 | 26 | $5,600.00 |
| 2021 | 5 | 5 | $6,615.11 | 22 | $6,000.00 |
| 2022 | 7 | 7 | $6,610.00 | 22 | $7,898.75 |
| 2023 | 8 | 8 | $8,064.64 | 19 | $8,756.96 |
| 2024 | 4 | 4 | $7,845.21 | 18 | $8,683.76 |
| 2025 | 9 | 9 | $8,400.00 | 51 | $9,500.00 |
| 2026 | 5 | 5 | $8,500.00 | 28 | $8,975.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 3 | $8,500.00 |
| 1 to 1 | 4 | $6,065.00 |
| 2 to 2 | 3 | $8,400.00 |
| 6 to 13 | 4 | $9,525.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Webber, LLC | 16 | 5 (31%) |
| Williams Brothers Construction Co., Inc. | 5 | 5 (100%) |
| James Construction Group, LLC | 7 | 2 (29%) |
| Jordan Foster Construction, LLC | 6 | 1 (17%) |
| East Texas Bridge, Inc. | 5 | 1 (20%) |
| Pulice Construction, Inc. | 7 | 0 (0%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 NOV 2026 | A00184974 | Austin District | 1 | $8,500.00 | $15,374 | n/a | 6 | Austin Bridge & Road Services, LP | TxDOT |
| 06 AUG 2026 | A00209034 | Corpus Christi District | 6 | $14,057 | $7,875.00 | $5,800.00 | 8 | STX Civil | TxDOT |
| 02 JUL 2026 | A00124174 | Lubbock District | 2 | $11,520 | $11,527 | n/a | 4 | Williams Brothers Construction Co., Inc. | TxDOT |
| 06 MAY 2026 | A00209252 | Beaumont District | 6 | $5,750.00 | $5,459.50 | $5,250.00 | 6 | R Construction Civil, LLC | TxDOT |
| 06 JAN 2026 | A00128788 | Corpus Christi District | 1 | $5,120.00 | $8,943.00 | $9,000.00 | 4 | J E Construction Services, LLC | TxDOT |
| 05 NOV 2025 | A00004604 | Waco District | 1 | $12,211 | $11,600 | $8,200.00 | 7 | James Construction Group, LLC | TxDOT |
| 04 SEP 2025 | A00128327 | Pharr District | 13 | $9,550.00 | $9,500.00 | $6,000.00 | 7 | Texas Cordia Construction, LLC | TxDOT |
| 02 JUL 2025 | A00195963 | Lubbock District | 1 | $8,500.00 | $10,000 | $10,000 | 3 | STX Civil | TxDOT |
| 04 JUN 2025 | A00207367 | Dallas District | 1 | $5,400.00 | $12,000 | $6,000.00 | 3 | Granite Construction Company | TxDOT |
| 04 JUN 2025 | A00060771 | Austin District | 2 | $8,400.00 | $8,700.00 | n/a | 9 | Jordan Foster Construction, LLC | TxDOT |
| 02 MAY 2025 | A00064833 | Dallas District | 6 | $9,500.00 | $8,850.00 | $6,460.00 | 6 | Highway 19 Construction LLC | TxDOT |
| 01 MAY 2025 | A00200563 | Atlanta District | 2 | $7,000.00 | $10,750 | $10,500 | 6 | THK Construction LLC | TxDOT |
| 03 APR 2025 | A00096030 | Pharr District | 1 | $6,080.00 | $6,800.00 | $5,548.00 | 3 | Reim Construction, Inc. | TxDOT |
| 05 MAR 2025 | A00213980 | Pharr District | 1 | $6,050.00 | $6,483.00 | $10,000 | 7 | Lucania Contractors LLC | TxDOT |
| 06 NOV 2024 | A00132358 | Beaumont District | 1 | $10,655 | $7,950.92 | $8,000.00 | 7 | Ser Construction Partners, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way