Inlet (complete)(pco)(3FT)(both), TxDOT 465-7016
Low bidders on TxDOT contracts carried a median of $8,257.94 per EACH for this item, over the 24 months to 19 NOV 2026, across 28 low bids. Half of all 144 bids fell between $7,296.75 and $10,720.
- Owner
- Texas DOT
- Item
- 465-7016
- Unit
- EACH
- Data through
- 19 NOV 2026
TxDOT prints this item as “INLET (COMPL)(PCO)(3FT)(BOTH)”.
TxDOT has bid this work under more than one code: 4656016001 on lettings from 10 JAN 2020 to 10 JUL 2024 (353 bids); 465-7016 on lettings from 03 DEC 2024 to 04 NOV 2026 (144 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 23 | 23 | $5,400.00 | 127 | $6,035.00 |
| 2021 | 20 | 20 | $5,939.92 | 113 | $6,100.00 |
| 2022 | 13 | 13 | $7,200.00 | 51 | $7,760.00 |
| 2023 | 11 | 11 | $9,178.54 | 35 | $8,429.10 |
| 2024 | 13 | 13 | $9,000.00 | 31 | $9,317.00 |
| 2025 | 13 | 13 | $9,000.00 | 66 | $9,213.97 |
| 2026 | 14 | 14 | $7,643.50 | 74 | $8,350.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 4 | $9,230.05 | 25 | $8,200.00 |
| Pharr District | 4 | $5,570.00 | 20 | $7,588.84 |
| Corpus Christi District | 3 | $7,600.00 | 19 | $8,880.00 |
| Dallas District | 4 | $9,559.06 | 18 | $9,865.00 |
| Amarillo District | 5 | $11,500 | 13 | $13,000 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 7 | $7,315.00 |
| 2 to 4 | 7 | $9,050.00 |
| 4 to 11 | 7 | $9,000.00 |
| 11 to 133 | 7 | $8,530.42 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Webber, LLC | 45 | 11 (24%) |
| James Construction Group, LLC | 18 | 7 (39%) |
| Austin Bridge & Road Services, LP | 18 | 6 (33%) |
| Zachry Construction Corporation | 16 | 5 (31%) |
| Hunter Industries, LTD. | 16 | 4 (25%) |
| Williams Brothers Construction Co., Inc. | 13 | 4 (31%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00129572 | Dallas District | 6 | $11,750 | $11,875 | $8,750.00 | 4 | Mario Sinacola & Sons Excavating, Inc. | TxDOT |
| 05 AUG 2026 | A00068611 | Houston District | 21 | $7,287.00 | $7,082.19 | $6,500.00 | 7 | Ser Construction Partners, LLC | TxDOT |
| 02 JUL 2026 | A00124174 | Lubbock District | 54 | $14,890 | $15,384 | $6,500.00 | 4 | Williams Brothers Construction Co., Inc. | TxDOT |
| 02 JUL 2026 | A00027293 | Tyler District | 133 | $5,480.00 | $6,600.00 | $6,700.00 | 9 | Baker & Company Construction, LLC | TxDOT |
| 03 JUN 2026 | A00186691 | San Antonio District | 3 | $9,944.22 | $10,377 | n/a | 6 | STX Civil | TxDOT |
| 03 JUN 2026 | A00191143 | Austin District | 1 | $8,000.00 | $8,500.00 | $8,500.00 | 6 | Dan Williams Company | TxDOT |
| 03 JUN 2026 | A00063871 | El Paso District | 16 | $10,600 | $10,550 | $14,300 | 4 | Jordan Foster Construction, LLC | TxDOT |
| 02 JUN 2026 | A00065051 | San Antonio District | 1 | $7,217.46 | $8,200.00 | $6,933.00 | 7 | Hunter Industries, LTD. | TxDOT |
| 07 MAY 2026 | A00183308 | Pharr District | 1 | $5,500.00 | $7,878.00 | $6,500.00 | 5 | Ioc Company LLC | TxDOT |
| 07 MAY 2026 | A00031457 | San Antonio District | 1 | $8,515.88 | $8,515.88 | $9,500.00 | 3 | Webber, LLC | TxDOT |
| 07 MAY 2026 | A00185350 | Corpus Christi District | 5 | $8,659.30 | $8,000.00 | $6,000.00 | 8 | 3LW Civil LLC | TxDOT |
| 06 MAY 2026 | A00121011 | Pharr District | 8 | $6,500.00 | $7,297.91 | $5,356.00 | 6 | Ioc Company LLC | TxDOT |
| 04 MAR 2026 | A00215071 | Amarillo District | 2 | $4,300.00 | $4,300.00 | $12,200 | 1 | STX Civil | TxDOT |
| 06 JAN 2026 | A00128788 | Corpus Christi District | 11 | $4,900.00 | $8,890.00 | $10,500 | 4 | J E Construction Services, LLC | TxDOT |
| 05 NOV 2025 | A00004604 | Waco District | 14 | $8,530.42 | $8,530.42 | $8,000.00 | 7 | James Construction Group, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.