TxDOT contract A00063871 bid tabulation
Widen Road - Add Lanes, US 54 (KENWORTHY Street to FM 2529 (MCCOMBS Street)). Let by Texas DOT on June 3, 2026, El Paso, El Paso District. 4 bids received; low bid $69,133,971 by Jordan Foster Construction, LLC, -19% against the engineer's estimate of $85,671,123.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 349
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jordan Foster Construction, LLC | $69,133,971 | Low | -19% |
| 2 | Dan Williams Company | $73,079,126 | +6.0% | -15% |
| 3 | International Eagle Enterprises, Inc. | $76,555,951 | +11% | -11% |
| 4 | Sundt Construction, Inc. | $86,673,637 | +25% | +1.0% |
Engineer's estimate: $85,671,123.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Jordan Foster Construction, LLC | 2. Dan Williams Company | 3. International Eagle Enterprises, Inc. | 4. Sundt Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 166 | $7,500.00 | $986.97 | $8,500.00 | $5,000.00 | $32,800 |
| 2 | Tree protection (install) (100-7014) | LF | 747 | $12.00 | $4.00 | $10.00 | $20.00 | $3.00 |
| 3 | Tree protection (remove) (100-7016) | LF | 747 | $1.40 | $3.00 | $0.85 | $2.00 | $2.00 |
| 4 | Removing concrete (pavement) (104-7001) | SY | 16,327 | $35.00 | $49.00 | $13.00 | $50.00 | $54.00 |
| 5 | Removing concrete (riprap) (104-7006) | SY | 1,324 | $14.00 | $14.50 | $12.00 | $40.00 | $20.00 |
| 6 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 601 | $15.57 | $11.25 | $18.00 | $30.00 | $35.00 |
| 7 | Removing concrete (curb) (104-7016) | LF | 18,675 | $8.00 | $4.40 | $3.00 | $14.00 | $3.00 |
| 8 | Removing concrete (retaining walls) (104-7025) | SY | 310 | $100.00 | $25.50 | $20.00 | $40.00 | $165.00 |
| 9 | Removing concrete (traffic barrier) (104-7035) | LF | 80 | $30.28 | $13.10 | $40.00 | $100.00 | $100.00 |
| 10 | Removing concrete (rail) (104-7036) | LF | 701 | $45.00 | $13.10 | $10.00 | $20.00 | $10.00 |
| 11 | Removing concrete (flume) (104-7041) | SY | 6,214 | $68.00 | $15.10 | $4.00 | $25.00 | $30.00 |
| 12 | Remove (2"-8") TRT/untrt base & asphalt pavement (105-7053) | SY | 31,795 | $15.00 | $1.50 | $2.50 | $2.50 | $4.00 |
| 13 | Excavation (roadway) (110-7001) | CY | 25,262 | $15.00 | $6.90 | $4.85 | $10.00 | $9.25 |
| 14 | Embankment (final)(DC)(type A) (132-7002) | CY | 434,660 | $20.00 | $14.00 | $18.00 | $16.50 | $19.00 |
| 15 | Irrigation system (170-7001) | LS | 1 | $675,000 | $750,000 | $375,000 | $739,000 | |
| 16 | Plant soil mix (planting soil) (192-7004) | CY | 2,909 | $116.00 | $74.00 | $50.00 | $74.00 | |
| 17 | Plant bed preparation (192-7009) | SY | 1,936 | $23.00 | $2.20 | $20.00 | $2.20 | |
| 18 | Vegetation barrier (192-7014) | SY | 171,075 | $2.68 | $1.50 | $1.75 | $3.00 | $1.80 |
| 19 | Loose aggregate GRND cover (type I) (192-7024) | CY | 12,977 | $120.00 | $105.50 | $80.00 | $75.00 | $98.00 |
| 20 | Plant material (30 gal) (tree) (192-7039) | EACH | 543 | $725.00 | $796.00 | $550.00 | $796.00 | |
| 21 | Plant material (3 gal) (shrub) (192-7046) | EACH | 733 | $40.50 | $42.00 | $50.00 | $42.00 | |
| 22 | Plant material (5 gal) (shrub) (192-7047) | EACH | 63 | $48.00 | $51.00 | $65.00 | $51.00 | |
| 23 | Landscape establish (193-7001) | MO | 3 | $2,050.00 | $8,000.00 | $5,000.00 | $8,000.00 | |
| 24 | Irrig sys oper and maintenance (193-7007) | MO | 3 | $2,050.00 | $4,320.00 | $5,000.00 | $4,320.00 | |
| 25 | Plant replace (3 gal) (193-7014) | EACH | 38 | $40.50 | $48.50 | $50.00 | $48.50 | |
| 26 | Plant replace (5 gal) (193-7015) | EACH | 6 | $47.75 | $60.00 | $65.00 | $60.00 | |
| 27 | Plant replace (30 gal) (193-7018) | EACH | 27 | $685.00 | $940.00 | $400.00 | $939.00 | |
| 28 | Cement (275-7001) | TON | 744 | $385.00 | $253.00 | $270.00 | $300.00 | $231.00 |
| 29 | Cement TRT (subgrade)(6") (275-7022) | SY | 122,627 | $8.50 | $2.00 | $2.00 | $2.50 | $5.00 |
| 30 | Prime coat (multi option) (310-7015) | GAL | 24,526 | $9.00 | $6.50 | $5.50 | $8.00 | $7.25 |
| 31 | D-GR HMA type-C PG64-22 (341-7015) | TON | 26,979 | $110.00 | $90.00 | $100.00 | $115.00 | $94.00 |
| 32 | Tack coat (341-7082) | GAL | 18,396 | $8.00 | $6.50 | $6.50 | $8.00 | $8.35 |
| 33 | Concrete pavement (CRCP) (8") (360-7002) | SY | 24,740 | $105.00 | $84.00 | $95.00 | $85.00 | $104.00 |
| 34 | Concrete pavement (CRCP) (11") (360-7005) | SY | 88,153 | $110.00 | $95.00 | $95.00 | $105.00 | $90.00 |
| 35 | Concrete pavement (CRCP) (12") (360-7006) | SY | 1,998 | $115.00 | $110.00 | $130.00 | $120.00 | $130.00 |
| 36 | Struct excavation (400-7001) | CY | 26,105 | $24.00 | $2.50 | $1.00 | $8.00 | $1.00 |
| 37 | Cem stabil BKFL (400-7010) | CY | 11,110 | $185.00 | $167.00 | $200.00 | $156.00 | $300.00 |
| 38 | Flowable backfill (401-7001) | CY | 72 | $520.00 | $290.00 | $375.00 | $170.00 | $400.00 |
| 39 | Trench excavation protection (402-7001) | LF | 21,514 | $7.00 | $3.00 | $4.50 | $7.00 | $2.00 |
| 40 | Drilled shaft (18 in) (416-7002) | LF | 256 | $122.00 | $201.00 | $225.00 | $405.00 | $160.00 |
| 41 | Drilled shaft (36 in) (416-7006) | LF | 1,792 | $400.00 | $287.00 | $275.00 | $420.00 | $230.00 |
| 42 | Drilled shaft (42 in) (416-7007) | LF | 63 | $350.00 | $505.00 | $550.00 | $560.00 | $510.00 |
| 43 | Drilled shaft (54 in) (416-7009) | LF | 1,157 | $600.00 | $535.00 | $575.00 | $500.00 | $600.00 |
| 44 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 72 | $350.00 | $300.00 | $310.00 | $332.00 | $299.47 |
| 45 | Drilled shaft (sign mounts) (48 in) (416-7032) | LF | 536 | $725.00 | $635.00 | $650.00 | $705.00 | $634.00 |
| 46 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 496 | $1,200.00 | $740.00 | $750.00 | $820.00 | $739.79 |
| 47 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 112 | $430.00 | $440.00 | $440.00 | $485.00 | $437.81 |
| 48 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 88 | $700.00 | $600.00 | $600.00 | $660.00 | $597.51 |
| 49 | Class A concrete (flume) (420-7006) | CY | 78 | $715.00 | $660.00 | $750.00 | $500.00 | $869.00 |
| 50 | Class C concrete (abutment)(HPC) (420-7013) | CY | 319.80 | $1,500.00 | $1,200.00 | $950.00 | $1,400.00 | $1,400.00 |
| 51 | Class C concrete (cap)(HPC) (420-7023) | CY | 495.60 | $1,700.00 | $1,200.00 | $1,400.00 | $2,000.00 | $1,400.00 |
| 52 | Class C concrete (column)(HPC) (420-7039) | CY | 304.20 | $1,600.00 | $1,200.00 | $1,400.00 | $1,200.00 | $1,500.00 |
| 53 | Class C concrete (rail foundation) (420-7052) | CY | 92 | $560.00 | $925.00 | $525.00 | $750.00 | $925.00 |
| 54 | Reinforced concrete slab (HPC) (422-7002) | SF | 69,908 | $35.00 | $26.00 | $30.00 | $30.00 | $29.00 |
| 55 | Approach slab (HPC) (422-7014) | CY | 712.60 | $800.00 | $525.00 | $700.00 | $455.00 | $600.00 |
| 56 | Retaining wall (MSE) (423-7001) | SF | 65,324 | $100.00 | $50.00 | $50.50 | $71.00 | $81.00 |
| 57 | Prestressed concrete girder (TX40) (425-7003) | LF | 8,248.87 | $280.00 | $285.00 | $260.00 | $280.00 | $300.00 |
| 58 | Concrete paint finish (427-7002) | SF | 88,093 | $8.00 | $0.41 | $0.55 | $0.60 | $0.41 |
| 59 | Riprap (concrete)(4 in) (432-7001) | CY | 2,589.25 | $500.00 | $575.00 | $515.00 | $450.00 | $800.00 |
| 60 | Riprap (concrete)(6 in) (432-7003) | CY | 10 | $550.00 | $615.00 | $950.00 | $1,500.00 | $800.00 |
| 61 | Riprap (concrete)(flume) (432-7012) | CY | 495 | $800.00 | $535.00 | $650.00 | $650.00 | $635.00 |
| 62 | STR steel (rails/posts/plates) (442-7011) | LB | 6,583 | $5.00 | $19.00 | $8.00 | $10.00 | $11.00 |
| 63 | Rail (type SSTR) (450-7024) | LF | 8,050 | $70.00 | $69.00 | $75.00 | $60.00 | $90.00 |
| 64 | Rail (handrail)(type D) (450-7061) | LF | 189 | $80.00 | $192.00 | $175.00 | $135.00 | $140.00 |
| 65 | Rail (handrail)(type F) (450-7063) | LF | 143 | $194.00 | $213.00 | $195.00 | $140.00 | $168.00 |
| 66 | Rail (type SSTR)(mod) (450-7066) | LF | 2,695 | $80.00 | $70.00 | $90.00 | $160.00 | $80.00 |
| 67 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 730 | $295.00 | $255.00 | $195.00 | $250.00 | $220.00 |
| 68 | Concrete box culvert (4 FT X 3 FT) (462-7004) | LF | 245 | $425.00 | $395.00 | $425.00 | $375.00 | $330.00 |
| 69 | Concrete box culvert (4 FT X 4 FT) (462-7005) | LF | 3,194 | $570.00 | $430.00 | $450.00 | $410.00 | $355.00 |
| 70 | Concrete box culvert (6 FT X 4 FT) (462-7012) | LF | 1,063 | $640.00 | $667.00 | $650.00 | $620.00 | $500.00 |
| 71 | RC pipe (CL III)(24 in) (464-7005) | LF | 8,084 | $100.00 | $104.00 | $105.00 | $110.00 | $100.00 |
| 72 | RC pipe (CL III)(36 in) (464-7009) | LF | 5,337 | $190.00 | $188.00 | $200.00 | $200.00 | $145.00 |
| 73 | RC pipe (CL III)(48 in) (464-7011) | LF | 1,408 | $275.00 | $292.00 | $320.00 | $325.00 | $210.00 |
| 74 | RC pipe (CL IV)(24 in) (464-7021) | LF | 55 | $450.00 | $135.00 | $200.00 | $190.00 | $100.00 |
| 75 | RC pipe (CL IV)(36 in) (464-7024) | LF | 580 | $220.00 | $215.00 | $220.00 | $220.00 | $165.00 |
| 76 | RC pipe (CL V)(36 in) (464-7037) | LF | 18 | $290.00 | $270.00 | $475.00 | $800.00 | $280.00 |
| 77 | RC pipe (CL V)(48 in) (464-7039) | LF | 75 | $202.00 | $390.00 | $450.00 | $1,100.00 | $341.00 |
| 78 | Manh (complete)(PRM)(60IN) (465-7003) | EACH | 9 | $10,169 | $9,850.00 | $9,500.00 | $8,800.00 | $9,400.00 |
| 79 | Manh (complete)(PRM)(72IN) (465-7004) | EACH | 24 | $11,000 | $12,700 | $13,500 | $11,000 | $16,600 |
| 80 | Junction box(complete)(PJB)(5FTX5FT) (465-7009) | EACH | 18 | $7,825.00 | $11,000 | $11,500 | $9,500.00 | $15,400 |
| 81 | Junction box(complete)(PJB)(8FTX8FT) (465-7012) | EACH | 4 | $11,171 | $19,000 | $20,000 | $20,000 | $22,000 |
| 82 | Inlet (complete)(pco)(3FT)(both) (465-7016) | EACH | 16 | $14,300 | $10,600 | $10,500 | $9,000.00 | $10,700 |
| 83 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 50 | $15,000 | $8,500.00 | $7,000.00 | $5,500.00 | $7,100.00 |
| 84 | Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128) | EACH | 21 | $9,278.00 | $9,900.00 | $9,000.00 | $6,800.00 | $9,000.00 |
| 85 | Inlet (complete)(PSL)(FG)(5FTX5FT-3FTX3FT) (465-7134) | EACH | 1 | $7,825.00 | $14,000 | $14,000 | $13,000 | $19,100 |
| 86 | Inlet (complete)(PSL)(FG)(5FTX5FT-4FTX4FT) (465-7135) | EACH | 1 | $11,171 | $12,000 | $12,000 | $10,000 | $10,200 |
| 87 | Inlet (complete)(PSL)(FG)(8FTX8FT-3FTX3FT) (465-7143) | EACH | 1 | $20,000 | $21,500 | $24,000 | $18,000 | $28,300 |
| 88 | Inlet (complete)(PSL)(FG)(8FTX8FT-4FTX4FT) (465-7144) | EACH | 1 | $22,000 | $20,500 | $20,000 | $18,000 | $27,100 |
| 89 | Inl(CMP)(pazd-CZ)(FG)(3FTX3FT-3FTX3FT) (465-7163) | EACH | 2 | $6,000.00 | $9,500.00 | $8,000.00 | $6,000.00 | $11,600 |
| 90 | Inl(CMP)(pazd-CZ)(FG)(4FTX4FT-4FTX4FT) (465-7165) | EACH | 27 | $10,400 | $9,800.00 | $9,000.00 | $6,000.00 | $12,000 |
| 91 | Inl(CMP)(pazd-CZ)(FG)(5FTX5FT-4FTX4FT) (465-7167) | EACH | 7 | $9,000.00 | $11,500 | $11,000 | $8,500.00 | $13,600 |
| 92 | JCT box (complete)(special) (465-7332) | EACH | 1 | $33,001 | $17,800 | $24,000 | $25,000 | $46,200 |
| 93 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $3,000.00 | $3,000.00 | $1,900.00 | $5,000.00 | $4,000.00 |
| 94 | Jack bor or tun pipe(24 in)(RC)(CL V) (476-7031) | LF | 46 | $1,500.00 | $3,050.00 | $3,500.00 | $3,300.00 | $3,900.00 |
| 95 | Jack bor or tun pipe(36 in)(RC)(CL V) (476-7033) | LF | 46 | $1,500.00 | $3,400.00 | $4,000.00 | $3,500.00 | $4,300.00 |
| 96 | Jack bor or tun pipe(48 in)(RC)(CL V) (476-7035) | LF | 383 | $1,500.00 | $3,500.00 | $3,400.00 | $4,000.00 | $3,400.00 |
| 97 | Removing structure (inlet) (496-7002) | EACH | 21 | $1,500.00 | $250.00 | $1,600.00 | $1,500.00 | $2,500.00 |
| 98 | Removing structure (pipe) (496-7007) | LF | 4,688 | $29.00 | $28.00 | $30.00 | $15.00 | $30.00 |
| 99 | Removing structure (box culvert) (496-7008) | LF | 10 | $50.00 | $242.00 | $550.00 | $1,500.00 | $2,000.00 |
| 100 | Mobilization (500-7001) | LS | 1 | $7,709,876 | $6,150,215 | $6,900,000 | $7,200,000 | $9,600,000 |
| 101 | Barricades, signs and traffic handling (502-7001) | MO | 36 | $16,760 | $15,900 | $20,000 | $15,000 | $25,000 |
| 102 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $14,100 | $15,000 | $20,000 | $30,000 |
| 103 | TMA (stationary) (505-7001) | DAY | 310 | $176.00 | $285.00 | $195.00 | $150.00 | $200.00 |
| 104 | TMA (mobile operation) (505-7003) | DAY | 310 | $300.00 | $315.00 | $1.00 | $300.00 | $600.00 |
| 105 | Temporary sediment control fence (install) (506-7039) | LF | 18,623 | $5.17 | $3.20 | $4.35 | $5.00 | $5.00 |
| 106 | Temporary sediment control fence (remove) (506-7041) | LF | 18,623 | $1.60 | $0.90 | $1.35 | $1.00 | $2.00 |
| 107 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 14,994 | $5.86 | $5.25 | $4.35 | $12.00 | $9.75 |
| 108 | Biodegradable erosion control logs (remove) (506-7046) | LF | 14,994 | $1.00 | $1.75 | $1.35 | $1.00 | $4.25 |
| 109 | Constructing detours (508-7001) | SY | 2,581 | $20.00 | $41.50 | $47.00 | $75.00 | $95.00 |
| 110 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 2,220 | $67.58 | $104.00 | $115.00 | $136.00 | $105.00 |
| 111 | Portable concrete traffic barrier (des source)(low prof)(type 1) (512-7021) | LF | 12,020 | $28.00 | $11.00 | $7.50 | $9.00 | $17.00 |
| 112 | Portable concrete traffic barrier (des source)(low prof)(type 2) (512-7022) | LF | 380 | $40.00 | $11.20 | $7.00 | $9.00 | $30.00 |
| 113 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 4,980 | $5.50 | $3.25 | $7.50 | $5.00 | $10.00 |
| 114 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 9,260 | $7.25 | $4.00 | $5.00 | $4.00 | $12.00 |
| 115 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 480 | $10.00 | $4.00 | $5.00 | $4.00 | $32.00 |
| 116 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 2,220 | $7.00 | $11.75 | $8.00 | $7.00 | $11.00 |
| 117 | Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041) | LF | 962 | $8.00 | $12.00 | $7.50 | $8.00 | $13.00 |
| 118 | Portable concrete traffic barrier (stockpile)(low prof)(type 1) (512-7045) | LF | 12,020 | $18.57 | $12.00 | $5.25 | $8.00 | $9.00 |
| 119 | Portable concrete traffic barrier (stockpile)(low prof)(type 2) (512-7046) | LF | 380 | $10.00 | $12.00 | $5.50 | $8.00 | $20.00 |
| 120 | Permanent CTB (F-shape) (type 3) (514-7015) | LF | 80 | $356.86 | $200.00 | $250.00 | $120.00 | $300.00 |
| 121 | Colored textured concrete (4") (527-7001) | SY | 5,283 | $90.00 | $62.00 | $70.00 | $75.00 | $89.00 |
| 122 | Colored textured concrete (6") (527-7003) | SY | 295 | $118.69 | $85.00 | $95.00 | $80.00 | $80.00 |
| 123 | Concrete curb (type I) (529-7001) | LF | 2,106 | $20.00 | $16.00 | $15.00 | $12.00 | $18.00 |
| 124 | Concrete curb (type II) (529-7002) | LF | 4,055 | $12.75 | $23.50 | $20.00 | $15.00 | $21.00 |
| 125 | Concrete curb (mono) (type I) (529-7006) | LF | 20,772 | $20.00 | $14.50 | $10.00 | $8.00 | $9.00 |
| 126 | Concrete curb (mono) (type II) (529-7007) | LF | 5,948 | $25.00 | $16.00 | $20.00 | $9.50 | $7.00 |
| 127 | Concrete curb (type F2) (529-7015) | LF | 332 | $277.51 | $90.00 | $110.00 | $55.00 | $120.00 |
| 128 | Driveways (concrete) (hes) (530-7007) | SY | 153 | $100.00 | $102.00 | $115.00 | $90.00 | $111.00 |
| 129 | Concrete sidewalks (4") (531-7001) | SY | 15,501 | $75.00 | $49.00 | $55.00 | $45.00 | $58.50 |
| 130 | Curb ramps (type 1) (531-7005) | EACH | 6 | $2,755.00 | $2,000.00 | $1,800.00 | $1,800.00 | $2,300.00 |
| 131 | Curb ramps (type 2) (531-7006) | EACH | 1 | $3,573.00 | $2,350.00 | $2,200.00 | $1,800.00 | $3,000.00 |
| 132 | Curb ramps (type 3) (531-7007) | EACH | 4 | $2,750.00 | $3,350.00 | $1,900.00 | $1,800.00 | $3,700.00 |
| 133 | Curb ramps (type 7) (531-7010) | EACH | 7 | $2,150.00 | $2,400.00 | $2,030.00 | $1,800.00 | $2,400.00 |
| 134 | Curb ramps (type 20) (531-7012) | EACH | 2 | $4,000.00 | $2,300.00 | $2,030.00 | $2,500.00 | $3,300.00 |
| 135 | Curb ramps (type 21) (531-7013) | EACH | 2 | $2,750.00 | $2,100.00 | $1,900.00 | $1,800.00 | $2,700.00 |
| 136 | Curb ramps (type 22) (531-7014) | EACH | 6 | $2,859.00 | $2,700.00 | $2,000.00 | $2,500.00 | $3,700.00 |
| 137 | Metal W-beam guard fence (steel post) (540-7002) | LF | 2,700 | $86.36 | $49.00 | $40.00 | $35.00 | $35.00 |
| 138 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 13 | $2,500.00 | $3,050.00 | $3,000.00 | $2,620.00 | $2,400.00 |
| 139 | Downstream anchor terminal section (540-7015) | EACH | 9 | $1,800.00 | $2,000.00 | $1,800.00 | $1,500.00 | $1,500.00 |
| 140 | Remove metal beam guard fence (542-7001) | LF | 815 | $8.00 | $3.40 | $5.50 | $5.00 | $10.00 |
| 141 | Remove terminal anchor section (542-7002) | EACH | 4 | $380.00 | $493.00 | $400.00 | $800.00 | $250.00 |
| 142 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $450.00 | $590.00 | $400.00 | $1,000.00 | $250.00 |
| 143 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 3 | $380.00 | $99.00 | $400.00 | $1,000.00 | $250.00 |
| 144 | Cable barrier system (install)(TL-4) (543-7002) | LF | 8,206 | $15.97 | $19.00 | $14.00 | $28.00 | $37.00 |
| 145 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 6 | $6,000.00 | $4,300.00 | $4,000.00 | $5,500.00 | $3,600.00 |
| 146 | Cable barrier (remove) (543-7037) | LF | 1,040 | $6.00 | $4.00 | $5.00 | $2.00 | $5.00 |
| 147 | Cable barrier terminal section (remove) (543-7038) | EACH | 2 | $955.00 | $209.00 | $900.00 | $500.00 | $600.00 |
| 148 | Guardrail end treatment (install) (544-7001) | EACH | 20 | $5,167.00 | $4,000.00 | $3,750.00 | $3,300.00 | $3,800.00 |
| 149 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 4 | $1,500.00 | $3,800.00 | $1,000.00 | $1,200.00 | $500.00 |
| 150 | Crash cushion attenuator (remove) (545-7004) | EACH | 3 | $1,000.00 | $320.00 | $1,000.00 | $850.00 | $500.00 |
| 151 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $8,980.00 | $15,500 | $10,000 | $35,000 | $20,000 |
| 152 | Pipe underdrains (type 6) (6") (556-7006) | LF | 6,458 | $40.00 | $34.00 | $25.00 | $25.00 | $21.00 |
| 153 | Remove RD IL asm (CTB mount) (610-7008) | EACH | 17 | $400.00 | $835.00 | $835.00 | $925.00 | $834.90 |
| 154 | Remove RD IL asm (trans-base) (610-7009) | EACH | 3 | $1,000.00 | $1,800.00 | $1,775.00 | $1,970.00 | $1,773.20 |
| 155 | HI MST IL pole (150 FT)( 80 MPH) (613-7005) | EACH | 16 | $52,500 | $54,000 | $54,000 | $59,200 | $53,821 |
| 156 | LED HI MST IL asm (6 fixt) (type A) (614-7002) | EACH | 11 | $46,000 | $46,500 | $46,200 | $51,200 | $46,173 |
| 157 | LED HI MST IL asm(6 fixt) (type A)SHLD (614-7009) | EACH | 5 | $46,500 | $47,000 | $47,000 | $52,000 | $46,911 |
| 158 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 17,955 | $35.00 | $20.00 | $20.00 | $22.00 | $19.92 |
| 159 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 5,315 | $30.00 | $32.00 | $31.75 | $35.00 | $31.73 |
| 160 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 1,900 | $30.00 | $26.50 | $26.25 | $29.00 | $26.18 |
| 161 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 2,290 | $35.00 | $37.00 | $36.75 | $40.00 | $36.68 |
| 162 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 600 | $26.80 | $30.00 | $30.00 | $33.50 | $29.95 |
| 163 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 750 | $43.00 | $40.00 | $40.00 | $44.50 | $39.96 |
| 164 | Conduit (RM) (2") (618-7078) | LF | 205 | $56.00 | $44.50 | $44.50 | $50.00 | $44.40 |
| 165 | Conduit (prepare) (618-7090) | LF | 12,910 | $4.00 | $4.00 | $3.90 | $4.35 | $3.89 |
| 166 | Fiber optic cable road marker (619-7014) | EACH | 48 | $150.00 | $167.00 | $166.35 | $185.00 | $166.32 |
| 167 | Electrical conductor (no.14) insulated (620-7002) | LF | 12,735 | $1.60 | $2.90 | $2.90 | $3.20 | $2.86 |
| 168 | Electrical conductor (no.10) insulated (620-7006) | LF | 7,680 | $2.50 | $3.30 | $3.30 | $3.65 | $3.29 |
| 169 | Electrical conductor (no.6) insulated (620-7010) | LF | 32,045 | $3.20 | $4.00 | $3.95 | $4.40 | $3.95 |
| 170 | Electrical conductor (no.4) insulated (620-7012) | LF | 29,320 | $4.00 | $5.25 | $5.25 | $5.75 | $5.22 |
| 171 | Electrical conductor (no.2) insulated (620-7016) | LF | 6,695 | $4.65 | $6.70 | $6.65 | $7.35 | $6.62 |
| 172 | ITS GND box type 1 (122422)W/apron (623-7026) | EACH | 19 | $3,000.00 | $3,100.00 | $3,080.00 | $3,400.00 | $3,079.12 |
| 173 | ITS GND box type 2 (243636)W/apron (623-7033) | EACH | 2 | $4,000.00 | $5,200.00 | $5,115.00 | $5,600.00 | $5,113.38 |
| 174 | Remove ITS ground box (623-7041) | EACH | 6 | $845.00 | $640.00 | $637.15 | $705.00 | $637.14 |
| 175 | Ground box type A (122311)W/apron (624-7002) | EACH | 99 | $2,000.00 | $1,640.00 | $1,640.00 | $1,815.00 | $1,637.67 |
| 176 | Ground box type C (162911)W/apron (624-7006) | EACH | 26 | $1,600.00 | $1,900.00 | $1,885.00 | $2,090.00 | $1,883.34 |
| 177 | Ground box type D (162922) (624-7007) | EACH | 2 | $1,450.00 | $1,700.00 | $1,675.00 | $1,850.00 | $1,670.39 |
| 178 | Remove ground box (624-7013) | EACH | 10 | $435.00 | $320.00 | $320.00 | $350.00 | $318.57 |
| 179 | Remove electrical services (628-7002) | EACH | 1 | $1,150.00 | $1,250.00 | $1,240.00 | $1,375.00 | $1,235.22 |
| 180 | Elc SRV type A 240/480 100(NS)SS(E)GC(O) (628-7076) | EACH | 4 | $11,000 | $11,400 | $11,400 | $12,650 | $11,395 |
| 181 | Elc SRV type D 120/240 060(NS)SS(N)GC(O) (628-7152) | EACH | 1 | $10,500 | $9,650.00 | $9,700.00 | $10,675 | $9,618.25 |
| 182 | Elc SRV type D 120/240 125(NS)GS(N)GC(O) (628-7268) | EACH | 5 | $9,000.00 | $8,700.00 | $8,700.00 | $9,587.00 | $8,640.82 |
| 183 | Aluminum signs (type A) (636-7001) | SF | 469 | $45.00 | $41.50 | $41.50 | $46.00 | $41.40 |
| 184 | Aluminum signs (type G) (636-7002) | SF | 270.75 | $45.00 | $45.00 | $45.00 | $50.00 | $44.81 |
| 185 | Aluminum signs (type O) (636-7003) | SF | 2,296 | $40.00 | $51.50 | $51.25 | $57.00 | $51.22 |
| 186 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 54 | $750.00 | $985.00 | $985.00 | $1,090.00 | $981.14 |
| 187 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 89 | $990.00 | $1,050.00 | $1,025.00 | $1,150.00 | $1,024.63 |
| 188 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 1 | $1,200.00 | $1,100.00 | $1,100.00 | $1,220.00 | $1,098.81 |
| 189 | Install small roadside sign support and assembly type 10BWG(2)SA(P) (644-7017) | EACH | 2 | $1,560.00 | $1,400.00 | $1,365.00 | $1,510.00 | $1,362.29 |
| 190 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 3 | $782.00 | $1,500.00 | $1,500.00 | $1,655.00 | $1,491.12 |
| 191 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 5 | $1,371.50 | $1,400.00 | $1,400.00 | $1,540.00 | $1,388.89 |
| 192 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 14 | $1,120.00 | $1,520.00 | $1,525.00 | $1,685.00 | $1,516.61 |
| 193 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 1 | $1,000.00 | $1,850.00 | $1,835.00 | $2,030.00 | $1,831.42 |
| 194 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 3 | $2,650.00 | $2,700.00 | $2,680.00 | $2,975.00 | $2,679.00 |
| 195 | In bridge MNT clearance sign assembly(type S) (644-7062) | EACH | 5 | $3,500.00 | $3,400.00 | $3,315.00 | $3,677.00 | $3,314.00 |
| 196 | Install small roadside sign support and assembly (rail mount) (644-7063) | EACH | 4 | $4,713.00 | $6,000.00 | $6,000.00 | $6,570.00 | $5,920.20 |
| 197 | Install small roadside sign support and assembly (inst sign only) (644-7064) | EACH | 1 | $600.00 | $134.00 | $135.00 | $555.00 | $133.76 |
| 198 | Remove SM RD SN sup&AM (644-7073) | EACH | 148 | $150.00 | $135.00 | $135.00 | $150.00 | $133.40 |
| 199 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 1 | $60.00 | $66.00 | $65.00 | $165.00 | $65.00 |
| 200 | Install LRSS (struct steel) (647-7001) | LB | 2,323.60 | $10.00 | $10.00 | $9.85 | $11.00 | $9.85 |
| 201 | Remove lrsa (647-7003) | EACH | 4 | $1,150.00 | $2,900.00 | $2,825.00 | $3,130.00 | $2,820.55 |
| 202 | Install overhead sign support(30 FT bal tee) (650-7028) | EACH | 2 | $50,000 | $57,500 | $58,000 | $64,000 | $57,469 |
| 203 | Install overhead sign support(30 FT cant)(circ tube) (650-7031) | EACH | 1 | $79,000 | $89,000 | $90,000 | $98,500 | $88,619 |
| 204 | Install overhead sign support(35 FT cant)(circ tube) (650-7040) | EACH | 3 | $115,000 | $93,000 | $95,000 | $102,200 | $92,043 |
| 205 | Install overhead sign support(70 FT BRDG)(circ tube) (650-7080) | EACH | 3 | $125,000 | $162,000 | $165,000 | $179,400 | $161,676 |
| 206 | Install overhead sign support(75 FT BRDG)(circ tube) (650-7085) | EACH | 1 | $180,000 | $167,000 | $170,000 | $184,260 | $166,063 |
| 207 | Remove overhd sign sup (650-7193) | EACH | 1 | $10,000 | $10,500 | $10,500 | $11,540 | $10,389 |
| 208 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 89 | $75.00 | $84.00 | $115.00 | $57.00 | $35.00 |
| 209 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 89 | $15.00 | $18.00 | $60.00 | $75.00 | $35.00 |
| 210 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 27 | $20.00 | $45.00 | $60.00 | $125.00 | $35.00 |
| 211 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 26 | $20.00 | $17.00 | $60.00 | $110.00 | $35.00 |
| 212 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 4 | $16.00 | $55.00 | $60.00 | $23.00 | $35.00 |
| 213 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 12 | $35.00 | $36.00 | $60.00 | $23.00 | $35.00 |
| 214 | Remove delin & object marker assms (658-7078) | EACH | 239 | $40.00 | $45.00 | $35.00 | $14.00 | $35.00 |
| 215 | Install OM LG RD sign (2-OM-type 1)Y (658-7090) | EACH | 6 | $45.00 | $70.00 | $130.00 | $1,385.00 | $35.00 |
| 216 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 1,829 | $1.40 | $3.10 | $3.00 | $4.75 | $3.00 |
| 217 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 108 | $1.50 | $3.10 | $3.00 | $4.75 | $3.00 |
| 218 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 10,736 | $0.71 | $3.10 | $3.00 | $4.75 | $3.00 |
| 219 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 918 | $5.00 | $4.10 | $4.00 | $6.21 | $4.00 |
| 220 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 148 | $11.50 | $13.25 | $13.00 | $20.20 | $13.00 |
| 221 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 15,397 | $0.70 | $3.10 | $3.00 | $4.60 | $3.00 |
| 222 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 1,337 | $0.55 | $0.95 | $0.90 | $1.40 | $0.90 |
| 223 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 288 | $4.00 | $1.55 | $1.50 | $2.40 | $1.50 |
| 224 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 6,090 | $2.42 | $1.55 | $1.50 | $2.40 | $1.50 |
| 225 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 5,549 | $5.95 | $4.10 | $4.00 | $6.00 | $4.00 |
| 226 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,693 | $11.00 | $7.20 | $7.00 | $10.50 | $7.00 |
| 227 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 57 | $191.00 | $165.00 | $160.00 | $250.00 | $160.00 |
| 228 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 9 | $210.00 | $235.00 | $230.00 | $355.00 | $230.00 |
| 229 | Reflectorized pavement marking type I(W)(uturn arrow)(100MIL) (666-7051) | EACH | 4 | $195.00 | $550.00 | $540.00 | $840.00 | $540.00 |
| 230 | Reflectorized pavement marking type I(W)(lane drop arrow)(100MIL) (666-7060) | EACH | 7 | $400.00 | $490.00 | $480.00 | $745.00 | $480.00 |
| 231 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 44 | $200.00 | $205.00 | $200.00 | $310.00 | $200.00 |
| 232 | Reflectorized pavement marking type I(W)(entr gore)(100MIL) (666-7069) | EACH | 9 | $1,000.00 | $1,225.00 | $1,200.00 | $1,865.00 | $1,200.00 |
| 233 | Reflectorized pavement marking type I(W)(exit gore)(100MIL) (666-7072) | EACH | 9 | $1,500.00 | $1,100.00 | $1,000.00 | $1,555.00 | $1,000.00 |
| 234 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 415 | $6.00 | $4.10 | $4.00 | $6.25 | $4.00 |
| 235 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 15,789 | $0.25 | $0.32 | $0.30 | $0.50 | $0.30 |
| 236 | Reflectorized pavement marking type II (W) 6" (DOT) (666-7173) | LF | 1,337 | $1.50 | $0.32 | $0.30 | $0.50 | $0.30 |
| 237 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 40,145 | $0.50 | $0.32 | $0.30 | $0.50 | $0.30 |
| 238 | Reflectorized pavement marking type II (W) 8" (DOT) (666-7177) | LF | 288 | $2.25 | $0.56 | $0.55 | $0.85 | $0.55 |
| 239 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 6,090 | $0.40 | $0.56 | $0.55 | $0.85 | $0.55 |
| 240 | Reflectorized pavement marking type II (W) 12" (DOT) (666-7180) | LF | 1,463 | $2.75 | $2.05 | $2.00 | $3.15 | $2.00 |
| 241 | Reflectorized pavement marking type II (W) 12" (solid) (666-7182) | LF | 5,549 | $3.61 | $2.05 | $2.00 | $3.15 | $2.00 |
| 242 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 1,693 | $5.73 | $3.40 | $3.25 | $5.00 | $3.25 |
| 243 | Reflectorized pavement marking type II (W) (arrow) (666-7186) | EACH | 57 | $80.00 | $81.50 | $80.00 | $125.00 | $80.00 |
| 244 | Reflectorized pavement marking type II (W) (double arrow) (666-7187) | EACH | 9 | $85.00 | $107.00 | $105.00 | $160.00 | $105.00 |
| 245 | Reflectorized pavement marking type II (W) (uturn arrow) (666-7189) | EACH | 4 | $100.00 | $225.00 | $220.00 | $340.00 | $220.00 |
| 246 | Reflectorized pavement marking type II (W) (LN reduct arrow) (666-7192) | EACH | 7 | $153.00 | $214.00 | $210.00 | $325.00 | $210.00 |
| 247 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 44 | $90.00 | $102.00 | $100.00 | $155.00 | $100.00 |
| 248 | Reflectorized pavement marking type II (W) (entr gore) (666-7195) | EACH | 9 | $500.00 | $390.00 | $380.00 | $600.00 | $380.00 |
| 249 | Reflectorized pavement marking type II (W) (exit gore) (666-7196) | EACH | 9 | $500.00 | $490.00 | $480.00 | $530.00 | $480.00 |
| 250 | Reflectorized pavement marking type II (Y) 4" (broken) (666-7208) | LF | 2,296 | $1.50 | $0.26 | $0.25 | $0.40 | $0.25 |
| 251 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 48,059 | $0.50 | $0.32 | $0.30 | $0.50 | $0.30 |
| 252 | Reflectorized pavement marking type II (Y) 12" (solid) (666-7215) | LF | 415 | $4.00 | $2.55 | $2.50 | $4.00 | $2.50 |
| 253 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 32,464 | $1.20 | $1.55 | $1.50 | $2.35 | $1.50 |
| 254 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 28,000 | $1.20 | $1.55 | $1.50 | $2.35 | $1.50 |
| 255 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 8,794 | $2.50 | $0.95 | $0.90 | $1.40 | $0.90 |
| 256 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 7,681 | $1.80 | $0.95 | $0.90 | $1.40 | $0.90 |
| 257 | Reflectorized pavement marking type I (Y)4"(broken)(100MIL) (666-7414) | LF | 2,296 | $1.20 | $0.75 | $0.70 | $1.15 | $0.70 |
| 258 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 22,559 | $1.58 | $0.92 | $0.90 | $1.55 | $0.90 |
| 259 | Reflectorized pavement marking type I (W)12"(DOT)(100MIL) (666-7424) | LF | 1,463 | $1.50 | $4.10 | $4.00 | $6.25 | $4.00 |
| 260 | Prefabricated PM type B (W)(6")(broken)contrast (668-7012) | LF | 6,995 | $28.00 | $13.25 | $13.00 | $20.00 | $13.00 |
| 261 | Prefabricated PM type B (W)(18")(yld tri) (668-7037) | EACH | 6 | $25.00 | $255.00 | $250.00 | $390.00 | $250.00 |
| 262 | Reflectorized pavement marker type I-C (672-7002) | EACH | 60 | $5.00 | $5.10 | $5.00 | $13.00 | $5.00 |
| 263 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 20 | $5.00 | $5.10 | $5.00 | $39.00 | $5.00 |
| 264 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2,129 | $4.00 | $5.10 | $5.00 | $7.75 | $5.00 |
| 265 | Eliminating existing PM & markers (4") (677-7001) | LF | 30,929 | $0.73 | $0.32 | $0.30 | $0.50 | $0.30 |
| 266 | Eliminating existing PM & markers (6") (677-7002) | LF | 2,242 | $0.40 | $0.36 | $0.35 | $0.55 | $0.35 |
| 267 | Eliminating existing PM & markers (8") (677-7004) | LF | 8,131 | $0.60 | $0.41 | $0.40 | $0.65 | $0.40 |
| 268 | Eliminating existing PM & markers (12") (677-7006) | LF | 2,574 | $0.80 | $2.80 | $2.75 | $4.30 | $2.75 |
| 269 | Eliminating existing PM & markers (24") (677-7008) | LF | 1,748 | $2.75 | $4.10 | $4.00 | $6.21 | $4.00 |
| 270 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 26 | $80.00 | $87.00 | $85.00 | $132.00 | $85.00 |
| 271 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 16 | $100.00 | $102.00 | $100.00 | $155.00 | $100.00 |
| 272 | Eliminating existing PM & markers (uturn arrow) (677-7012) | EACH | 4 | $175.00 | $122.50 | $120.00 | $195.00 | $120.00 |
| 273 | Eliminating existing PM & markers (word) (677-7015) | EACH | 17 | $80.00 | $122.50 | $120.00 | $186.00 | $120.00 |
| 274 | Eliminating existing PM & markers (entr gore) (677-7016) | EACH | 6 | $1,160.00 | $715.00 | $700.00 | $1,090.00 | $700.00 |
| 275 | Eliminating existing PM & markers (exit gore) (677-7017) | EACH | 4 | $1,026.00 | $510.00 | $500.00 | $775.00 | $500.00 |
| 276 | Eliminating existing PM & markers (36")(yld tri) (677-7024) | EACH | 7 | $50.00 | $41.00 | $40.00 | $111.00 | $40.00 |
| 277 | Pavement surface preparation for marking (4") (678-7001) | LF | 2,296 | $0.50 | $0.16 | $0.15 | $0.35 | $0.15 |
| 278 | Pavement surface preparation for marking (6") (678-7002) | LF | 100,155 | $0.50 | $0.19 | $0.18 | $0.30 | $0.18 |
| 279 | Pavement surface preparation for marking (8") (678-7004) | LF | 6,378 | $0.50 | $0.21 | $0.20 | $0.30 | $0.20 |
| 280 | Pavement surface preparation for marking (10") (678-7005) | LF | 6,425 | $0.50 | $0.23 | $0.22 | $0.35 | $0.22 |
| 281 | Pavement surface preparation for marking (12") (678-7006) | LF | 7,427 | $0.50 | $1.05 | $1.00 | $1.55 | $1.00 |
| 282 | Pavement surface preparation for marking (24") (678-7008) | LF | 1,693 | $0.50 | $1.55 | $1.50 | $2.35 | $1.50 |
| 283 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 64 | $20.00 | $56.00 | $55.00 | $85.50 | $55.00 |
| 284 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 9 | $25.00 | $56.00 | $55.00 | $86.50 | $55.00 |
| 285 | Pavement surface preparation for marking (uturn arr) (678-7012) | EACH | 4 | $30.00 | $76.50 | $75.00 | $195.00 | $75.00 |
| 286 | Pavement surface preparation for marking (word) (678-7016) | EACH | 44 | $20.00 | $56.00 | $55.00 | $86.00 | $55.00 |
| 287 | Pavement surface preparation for marking (entr gore) (678-7017) | EACH | 9 | $120.00 | $306.00 | $300.00 | $466.00 | $300.00 |
| 288 | Pavement surface preparation for marking (exit gore) (678-7018) | EACH | 9 | $135.00 | $410.00 | $400.00 | $620.00 | $400.00 |
| 289 | Pavement surface preparation for marking (18")(yld tri) (678-7022) | EACH | 6 | $20.00 | $51.00 | $50.00 | $130.00 | $50.00 |
| 290 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 2,209 | $0.50 | $0.16 | $0.15 | $0.35 | $0.15 |
| 291 | Install highway traffic signal (system) (680-7003) | EACH | 2 | $35,000 | $53,000 | $55,000 | $58,500 | $52,683 |
| 292 | Removing traffic signals (680-7004) | EACH | 4 | $7,825.00 | $15,400 | $16,000 | $17,100 | $15,368 |
| 293 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 30 | $362.00 | $340.00 | $350.00 | $375.00 | $339.92 |
| 294 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 17 | $364.00 | $350.00 | $350.00 | $385.00 | $346.76 |
| 295 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 30 | $358.00 | $340.00 | $350.00 | $380.00 | $339.92 |
| 296 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 13 | $364.00 | $350.00 | $350.00 | $385.00 | $346.76 |
| 297 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 30 | $270.00 | $340.00 | $350.00 | $380.00 | $339.92 |
| 298 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 8 | $300.00 | $350.00 | $350.00 | $385.00 | $346.76 |
| 299 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 32 | $825.00 | $1,050.00 | $1,100.00 | $1,150.00 | $1,034.47 |
| 300 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 29 | $250.00 | $178.00 | $180.00 | $196.00 | $176.61 |
| 301 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 4 | $330.00 | $235.00 | $235.00 | $260.00 | $233.08 |
| 302 | Backplate W/ref border(5 sec)(vent)aluminum (682-7044) | EACH | 5 | $295.00 | $240.00 | $240.00 | $266.00 | $239.91 |
| 303 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 12,228 | $3.50 | $4.00 | $3.95 | $4.35 | $3.92 |
| 304 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 1,946 | $3.00 | $5.00 | $4.85 | $5.50 | $4.84 |
| 305 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 3,935 | $6.50 | $11.00 | $10.75 | $12.00 | $10.75 |
| 306 | Traffic signal CBL (type A)(18 AWG)(2 conductor) (684-7053) | LF | 9,105 | $4.00 | $2.60 | $2.55 | $2.85 | $2.55 |
| 307 | Ins traffic signal PL AM(S)1 arm(36') (686-7037) | EACH | 1 | $12,663 | $14,050 | $14,030 | $15,600 | $14,029 |
| 308 | Ins traffic signal PL AM(S)1 arm(40') (686-7041) | EACH | 1 | $12,863 | $15,000 | $14,865 | $16,500 | $14,864 |
| 309 | Ins traffic signal PL AM(S)1 arm(44') (686-7045) | EACH | 1 | $13,200 | $15,250 | $15,215 | $16,900 | $15,214 |
| 310 | Ins traffic signal PL AM(S)1 arm(48') (686-7049) | EACH | 5 | $15,220 | $15,800 | $15,720 | $17,500 | $15,717 |
| 311 | Ins traffic signal PL AM(S)1 arm(55') (686-7057) | EACH | 1 | $33,500 | $39,500 | $40,000 | $43,700 | $39,376 |
| 312 | Ins traffic signal PL AM(S)1 arm(60') (686-7061) | EACH | 1 | $43,000 | $40,100 | $45,000 | $44,500 | $40,076 |
| 313 | Ins traffic signal PL AM(S)1 arm(65') (686-7065) | EACH | 2 | $50,000 | $40,500 | $45,000 | $44,900 | $40,400 |
| 314 | Pedestrian pole assembly (687-7001) | EACH | 21 | $3,000.00 | $2,800.00 | $2,800.00 | $3,030.00 | $2,727.41 |
| 315 | Pedestrian detect push button (APS) (688-7001) | EACH | 28 | $1,150.00 | $1,200.00 | $1,200.00 | $1,320.00 | $1,181.67 |
| 316 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $4,500.00 | $4,550.00 | $4,525.00 | $5,000.00 | $4,511.52 |
| 317 | Remove radar vehicle detection system (690-7136) | EACH | 2 | $710.00 | $9,300.00 | $9,300.00 | $10,275 | $9,256.20 |
| 318 | Tip testing(drilled shaft) (4003-7001) | EACH | 18 | $6,500.00 | $9,900.00 | $9,000.00 | $3,900.00 | $9,253.85 |
| 319 | Ornamental steel structure (4075-7001) | LF | 16,703 | $126.05 | $111.00 | $105.00 | $130.00 | $140.00 |
| 320 | Install DMS (pole MTD cabinet) (6004-7001) | EACH | 3 | $30,000 | $24,000 | $25,000 | $26,500 | $23,804 |
| 321 | ITS com CBL (ethernet) (6005-7001) | LF | 80 | $2.80 | $21.50 | $21.05 | $23.50 | $21.04 |
| 322 | VIVDS prosr sys (6006-7001) | EACH | 2 | $13,150 | $5,400.00 | $5,400.00 | $5,950.00 | $5,363.51 |
| 323 | VIVDS cam assy FXD LNS (6006-7002) | EACH | 12 | $3,750.00 | $6,500.00 | $6,500.00 | $7,150.00 | $6,424.30 |
| 324 | VIVDS cabling (6006-7007) | LF | 4,458 | $2.00 | $2.75 | $2.75 | $3.00 | $2.73 |
| 325 | System integration (6009-7001) | LS | 1 | $100,000 | $177,000 | $200,000 | $197,000 | $176,000 |
| 326 | ITS pole (55 FT)(90 MPH) (6011-7001) | EACH | 3 | $35,000 | $29,100 | $35,000 | $32,205 | $29,025 |
| 327 | ITS pole MNT cab (type 2)(conf 2) (6011-7002) | EACH | 3 | $8,500.00 | $7,300.00 | $7,500.00 | $8,010.00 | $7,216.76 |
| 328 | Remove ITS pole (55 FT) (6011-7008) | EACH | 1 | $3,500.00 | $2,900.00 | $2,900.00 | $3,200.00 | $2,850.00 |
| 329 | Ground box (prepare) (6013-7006) | EACH | 22 | $1,250.00 | $850.00 | $850.00 | $925.00 | $830.23 |
| 330 | Ground box (adjust) (6013-7007) | EACH | 4 | $2,920.00 | $1,300.00 | $1,260.00 | $1,400.00 | $1,259.80 |
| 331 | Relocate ITS radio (6014-7006) | EACH | 3 | $3,650.00 | $4,200.00 | $4,200.00 | $4,560.00 | $4,109.33 |
| 332 | Installation of cellular modem (6015-7001) | EACH | 6 | $2,134.00 | $1,600.00 | $1,500.00 | $1,665.00 | $1,500.00 |
| 333 | CCTV field equip (digital) (install only) (6018-7001) | EACH | 8 | $2,000.00 | $2,300.00 | $2,250.00 | $2,500.00 | $2,250.00 |
| 334 | Remove CCTV field equipment (6018-7008) | EACH | 2 | $3,500.00 | $810.00 | $800.00 | $890.00 | $800.00 |
| 335 | Fiber optic CBL (single-mode)(12 fiber) (6027-7001) | LF | 6,900 | $5.25 | $4.00 | $3.95 | $4.50 | $3.93 |
| 336 | Fiber optic fusion splice (6027-7004) | EACH | 120 | $131.00 | $130.00 | $125.00 | $140.00 | $125.00 |
| 337 | Fiber optic patch panel (12 position) (6027-7005) | EACH | 14 | $2,700.00 | $1,550.00 | $1,550.00 | $1,710.00 | $1,538.68 |
| 338 | Fiber optic CBL(single-mode)(144 fiber) (6027-7006) | LF | 14,275 | $4.50 | $4.25 | $4.25 | $4.75 | $4.21 |
| 339 | Fiber optic patch panel (144 positions) (6027-7008) | EACH | 1 | $14,000 | $4,700.00 | $4,650.00 | $5,110.00 | $4,605.07 |
| 340 | FO splice enclosure (type 1) (6027-7009) | EACH | 7 | $2,708.00 | $2,900.00 | $2,850.00 | $3,200.00 | $2,847.51 |
| 341 | Remove fiber optic cable (6027-7018) | LF | 15,700 | $1.25 | $1.30 | $1.25 | $1.40 | $1.25 |
| 342 | WWD LED sign (6028-7002) | EACH | 34 | $1,500.00 | $5,000.00 | $5,000.00 | $5,515.00 | $4,968.72 |
| 343 | WWD solar power system (6028-7004) | EACH | 28 | $1,100.00 | $3,700.00 | $3,650.00 | $4,020.00 | $3,620.75 |
| 344 | Relocate backlit LED RDSD sign (6030-7005) | EACH | 2 | $530.00 | $1,810.00 | $1,810.00 | $2,000.00 | $1,806.50 |
| 345 | Ethernet switch (install only) (6036-7001) | EACH | 17 | $3,500.00 | $1,300.00 | $1,250.00 | $1,386.00 | $1,250.00 |
| 346 | Remove existing GND MT comm cabinet (6050-7002) | EACH | 2 | $2,859.00 | $2,900.00 | $3,000.00 | $3,200.00 | $2,890.37 |
| 347 | Remove DMS (6054-7003) | EACH | 1 | $12,887 | $6,350.00 | $6,315.00 | $7,000.00 | $6,311.40 |
| 348 | LED aesthetic light assembly (6101-7001) | EACH | 2 | $75,000 | $270,000 | $325,000 | $230,000 | $275,500 |
| 349 | Remove existing cables (power) (6106-7002) | LF | 17,580 | $0.60 | $1.30 | $1.25 | $1.40 | $1.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.