Sundt Construction, Inc.: TxDOT bid record
Sundt Construction, Inc. submitted 16 bids on Texas DOT contracts in the data, from 08 JUL 2020 to 03 JUN 2026, and was the low bidder on 5 of them (31%). When it was not low, its total sat a median +7.0% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $985,185,787
- Latest bid
- 03 JUN 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 3 | 0 | 0% |
| 2021 | 3 | 0 | 0% |
| 2022 | 2 | 1 | 50% |
| 2023 | 1 | 1 | 100% |
| 2024 | 3 | 3 | 100% |
| 2025 | 3 | 0 | 0% |
| 2026 | 1 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| El Paso District | 6 | 3 | 50% |
| Odessa District | 4 | 2 | 50% |
| San Antonio District | 2 | 0 | 0% |
| Dallas District | 2 | 0 | 0% |
| Yoakum District | 1 | 0 | 0% |
| Abilene District | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Trench excavation protection | 402-7001 | LF | 15 | 12 (80%) | $1.00 | $10.00 |
| Construction exits (remove) | 506-7024 | SY | 14 | 9 (64%) | $5.62 | $10.00 |
| Crash cushion attenuator (remove) | 545-7004 | EACH | 15 | 8 (53%) | $525.00 | $1,000.00 |
| Metal beam guard fence trans (thrie-beam) | 540-7005 | EACH | 15 | 7 (47%) | $2,100.00 | $2,140.00 |
| Downstream anchor terminal section | 540-7015 | EACH | 14 | 7 (50%) | $1,500.00 | $1,485.00 |
| Remove ground box | 624-7013 | EACH | 11 | 7 (64%) | $350.00 | $300.00 |
| Set (type II) (24 in) (RCP) (6: 1) (P) | 467-7328 | EACH | 10 | 7 (70%) | $1,875.00 | $1,900.00 |
| Guardrail end treatment (install) | 544-7001 | EACH | 16 | 6 (38%) | $3,150.00 | $3,245.00 |
| Crash cushion attenuator (move & reset) | 545-7002 | EACH | 14 | 6 (43%) | $850.00 | $1,535.40 |
| Permanent CTB (single slope) (type 1) (42 ) | 514-7001 | LF | 12 | 6 (50%) | $65.47 | $93.00 |
| Remove electrical services | 628-7002 | EACH | 11 | 6 (55%) | $1,000.00 | $602.00 |
| Excavation (roadway) | 110-7001 | CY | 16 | 5 (31%) | $10.00 | $20.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Jordan Foster Construction, LLC | 8 | 5 of 8 |
| Webber, LLC | 8 | 3 of 8 |
| Pulice Construction, Inc. | 7 | 1 of 7 |
| Zachry Construction Corporation | 5 | 3 of 5 |
| James Construction Group, LLC | 5 | 3 of 5 |
| FNF Construction, Inc. | 4 | 1 of 4 |
| J.D. Abrams, L.P. | 3 | 2 of 3 |
| Austin Bridge & Road Services, LP | 3 | 2 of 3 |
| Williams Brothers Construction Co., Inc. | 2 | 0 of 2 |
| Flatiron Constructors, Inc. | 2 | 0 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 03 JUN 2026 | A00063871 | El Paso District | Widen Road - Add Lanes, US 54 (KENWORTHY Street to FM 2529 (MCCOMBS Street)) | 4 of 4 | $86,673,637 | +25% |
| 08 OCT 2025 | A00062536 | Abilene District | Interchange Improvement (New Or Update), US 83 (AT to US 83/84 "Y" INTERCHANGE) | 2 of 9 | $75,599,988 | +4.0% |
| 05 JUN 2025 | A00011238 | San Antonio District | Widen Road - Add Lanes, US 90 (LP 1604 to 0.8 MILES W OF IH 410) | 2 of 9 | $128,454,533 | +4.0% |
| 08 JAN 2025 | A00064403 | Dallas District | Interchange Improvement, IH 35E (AT CORPORATE DRIVE to .) | 3 of 4 | $229,225,288 | +5.0% |
| 09 JUL 2024 | 07243002 | El Paso District | SH 178 Infrastructure improvements from NM/TX STATELINE to IH 10 | 1 of 2 | $243,747,771 | Low, 6.0% under the second |
| 03 MAY 2024 | 05243203 | El Paso District | IH 10 Construct new road from 0.22 MI W OF FM 1905 (ANTONIO ST) to 0.83 MI E OF SPUR 37 | 1 of 3 | $119,997,852 | Low, 3.0% under the second |
| 06 MAR 2024 | 03243201 | Odessa District | IH 20 Widen road - add lanes from EAST OF CR 1300 to EAST OF CR 1250 | 1 of 3 | $186,258,258 | Low, 4.0% under the second |
| 02 NOV 2023 | 11233201 | Odessa District | IH 20 Widen road - add lanes from EAST OF JBS PARKWAY to MIDLAND COUNTY LINE | 1 of 5 | $260,876,640 | Low, 5.0% under the second |
| 04 FEB 2022 | 02223225 | El Paso District | IH 10 Construct new road from 0.22 MI W OF FM 1905 (ANTONIO ST) to SH 20 (MESA ST) | 1 of 3 | $174,305,265 | Low, 8.0% under the second |
| 07 JAN 2022 | 01223202 | Odessa District | SH 191 Construct bridge from AT YUKON RD | 4 of 4 | $34,887,200 | +27% |
| 08 OCT 2021 | 10213201 | El Paso District | IH 10 Construct new road from 0.22 MI W OF FM 1905 (ANTONIO ST) to SH 20 (MESA ST) | 2 of 3 | $253,947,506 | +3.0% |
| 04 JUN 2021 | 06213202 | Dallas District | SH 114 Construct 0 to 6 lane grade separation over us 37 from WEST OF US 377 to EAST OF US 377 | 10 of 13 | $43,154,479 | +17% |
| 08 JAN 2021 | 01213201 | Odessa District | IH 20 Construct new interchange from AT CR 1250 | 3 of 4 | $63,112,572 | +7.0% |
| 03 SEP 2020 | 09203005 | Yoakum District | BS 71-E Construct bridge and approaches from AT COLORADO RIVER IN LA GRANGE | 6 of 11 | $15,049,206 | +10% |
| 09 JUL 2020 | 07203201 | San Antonio District | IH 10 Expand 4 to 6 ln expressway & from 4 to 4 ln fr from GRAYTOWN RD to GUADALUPE/BEXAR COUNTY LINE | 5 of 8 | $159,775,817 | +7.0% |
| 08 JUL 2020 | 07203001 | El Paso District | SL 375 Widen from 4 to 6 lanes divided from BOB HOPE DR to ZARAGOZA RD | 3 of 4 | $88,270,146 | +17% |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.