TxDOT contract A00062536 bid tabulation
Interchange Improvement (New Or Update), US 83 (AT to US 83/84 "Y" INTERCHANGE). Let by Texas DOT on October 8, 2025, Taylor, Abilene District. 9 bids received; low bid $72,482,832 by James Construction Group, LLC, -15% against the engineer's estimate of $84,918,829.
- Owner
- Texas DOT
- Letting
- 08 OCT 2025
- Pay items
- 243
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | James Construction Group, LLC | $72,482,832 | Low | -15% |
| 2 | Sundt Construction, Inc. | $75,599,988 | +4.0% | -11% |
| 3 | Webber, LLC | $76,238,518 | +5.0% | -10% |
| 4 | Zachry Construction Corporation | $76,964,482 | +6.0% | -9.0% |
| 5 | FNF Construction, Inc. | $76,984,994 | +6.0% | -9.0% |
| 6 | Pulice Construction, Inc. | $77,537,913 | +7.0% | -9.0% |
| 7 | J. H. Strain & Sons, Inc. | $79,191,280 | +9.0% | -7.0% |
| 8 | Mario Sinacola & Sons Excavating, Inc. | $82,273,503 | +14% | -3.0% |
| 9 | A. L. Helmcamp, Inc. | $86,326,123 | +19% | +2.0% |
Engineer's estimate: $84,918,829.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. James Construction Group, LLC | 2. Sundt Construction, Inc. | 3. Webber, LLC | 4. Zachry Construction Corporation | 5. FNF Construction, Inc. | 6. Pulice Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 190.30 | $2,500.00 | $37,500 | $39,000 | $40,062 | $36,784 | $1,000.00 | $35,000 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 5 | $65.00 | $35.43 | $125.00 | $103.20 | $475.11 | $150.00 | $118.85 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 847 | $8.09 | $50.00 | $15.49 | $14.17 | $25.00 | $43.06 | |
| 4 | Removing concrete (curb & gutter) (104-7017) | LF | 260 | $7.49 | $25.00 | $3.62 | $18.53 | $15.00 | $13.08 | |
| 5 | Remove (18"-22") TRT/untrt base & asphalt pavement (105-7018) | SY | 125,018 | $22.00 | $8.34 | $5.00 | $11.22 | $8.66 | $14.25 | $12.69 |
| 6 | Remove (0"-8") TRT/untrt base & asphalt pavement (105-7048) | SY | 5,502 | $22.00 | $5.40 | $5.00 | $6.26 | $8.35 | $5.75 | $4.86 |
| 7 | Excavation (roadway) (110-7001) | CY | 65,966.02 | $22.50 | $17.36 | $8.00 | $24.61 | $14.20 | $8.25 | $11.00 |
| 8 | Embankment (final)(DC)(type C) (132-7006) | CY | 190,921.27 | $18.00 | $28.24 | $8.00 | $30.49 | $14.08 | $11.25 | $19.00 |
| 9 | Furn & place topsoil (4") (160-7002) | SY | 251,514 | $6.00 | $1.02 | $1.00 | $1.21 | $3.48 | $0.75 | $2.00 |
| 10 | Block sodding (162-7002) | SY | 5,664 | $6.46 | $7.50 | $6.23 | $7.17 | $7.50 | $7.50 | |
| 11 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 245,850 | $1.10 | $0.17 | $0.24 | $0.13 | $0.15 | $0.15 | $0.24 |
| 12 | Broadcast seed (temporary_warm) (164-7005) | SY | 122,931 | $1.00 | $0.10 | $0.20 | $0.12 | $0.14 | $0.15 | $0.20 |
| 13 | Broadcast seed (temporary_cool) (164-7006) | SY | 122,931 | $1.00 | $0.13 | $0.20 | $0.12 | $0.14 | $0.15 | $0.20 |
| 14 | Vegetative watering (168-7001) | TGL | 8,279 | $32.50 | $36.45 | $25.00 | $16.61 | $36.83 | $70.00 | $50.85 |
| 15 | Soil ret BLKT(SL_steep_clay_long) (169-7006) | SY | 1,175 | $2.40 | $3.00 | $3.56 | $4.10 | $4.50 | $3.00 | |
| 16 | FL BS (compacted in place)(type A GR 1-2) (6") (247-7044) | SY | 160,943 | $45.00 | $17.80 | $9.20 | $1.03 | $11.42 | $14.00 | $14.00 |
| 17 | FL BS (compacted in place)(type A GR 1-2) (12") (247-7113) | SY | 61,021 | $45.00 | $25.26 | $15.00 | $17.09 | $23.01 | $27.00 | $30.00 |
| 18 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 2,414 | $400.00 | $338.05 | $340.00 | $27.09 | $366.44 | $425.00 | $350.00 |
| 19 | Lime TRT (existing material)(6") (260-7006) | SY | 203,150 | $7.00 | $5.05 | $3.25 | $1.07 | $5.34 | $3.00 | $2.00 |
| 20 | Prime coat (MC-30) (310-7004) | GAL | 55,497 | $6.00 | $4.80 | $4.85 | $0.64 | $5.61 | $6.00 | $4.80 |
| 21 | D-GR HMA type-B PG64-22 (341-7001) | TON | 47,378 | $125.00 | $130.00 | $130.00 | $8.98 | $151.91 | $135.00 | $132.00 |
| 22 | SP mixes SP-C sac-B PG70-22 (344-7021) | TON | 23,576 | $135.00 | $149.00 | $149.00 | $9.67 | $174.12 | $146.00 | $153.00 |
| 23 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 1,312 | $5.30 | $8.00 | $3.94 | $6.87 | $7.00 | $3.95 | |
| 24 | Struct excavation (400-7001) | CY | 18,475 | $50.00 | $24.16 | $3.00 | $6.05 | $13.91 | $25.00 | $15.70 |
| 25 | Cem stabil BKFL (400-7010) | CY | 15,529 | $200.00 | $124.89 | $225.00 | $50.11 | $39.50 | $185.00 | $100.00 |
| 26 | Trench excavation protection (402-7001) | LF | 2,611 | $40.00 | $2.08 | $1.00 | $11.78 | $24.00 | $52.00 | $5.00 |
| 27 | Temporary special shoring (403-7001) | SF | 38,025 | $40.00 | $12.11 | $2.30 | $13.00 | $21.40 | $25.00 | $17.89 |
| 28 | Drilled shaft (18 in) (416-7002) | LF | 232 | $200.00 | $152.00 | $175.00 | $138.38 | $146.48 | $245.00 | $116.61 |
| 29 | Drilled shaft (36 in) (416-7006) | LF | 1,195 | $350.00 | $234.22 | $325.00 | $297.24 | $267.55 | $440.00 | $309.60 |
| 30 | Drilled shaft (42 in) (416-7007) | LF | 1,708 | $525.00 | $259.16 | $400.00 | $319.81 | $336.50 | $490.00 | $323.50 |
| 31 | Drilled shaft (48 in) (416-7008) | LF | 783 | $560.00 | $338.74 | $500.00 | $441.28 | $480.20 | $710.00 | $527.76 |
| 32 | Drilled shaft (54 in) (416-7009) | LF | 432 | $705.00 | $411.19 | $550.00 | $525.34 | $564.28 | $600.00 | $539.46 |
| 33 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 72 | $250.00 | $225.00 | $230.00 | $331.00 | $384.32 | $340.00 | $145.00 |
| 34 | Drilled shaft (sign mounts) (48 in) (416-7032) | LF | 43 | $936.00 | $250.00 | $975.00 | $961.00 | $1,115.83 | $980.00 | $901.32 |
| 35 | Drilled shaft (sign mounts) (54 in) (416-7033) | LF | 36 | $900.00 | $850.00 | $842.00 | $977.66 | $860.00 | $816.89 | |
| 36 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 324 | $950.00 | $950.00 | $860.00 | $850.50 | $987.52 | $870.00 | $913.71 |
| 37 | Class B concrete (flume) (420-7010) | CY | 132.90 | $825.00 | $961.86 | $1,000.00 | $1,369.38 | $945.17 | $500.00 | $625.00 |
| 38 | Class C concrete (abutment)(HPC) (420-7013) | CY | 130.20 | $2,000.00 | $1,215.44 | $1,500.00 | $2,265.30 | $1,254.71 | $3,050.00 | $1,600.00 |
| 39 | Class C concrete (cap)(HPC) (420-7023) | CY | 444.90 | $2,100.00 | $1,096.27 | $1,600.00 | $2,677.28 | $1,869.87 | $2,390.00 | $1,800.00 |
| 40 | Class C concrete (cap)(HPC)(mass) (420-7025) | CY | 254.40 | $1,925.00 | $1,339.46 | $2,000.00 | $2,759.59 | $2,068.37 | $2,790.00 | $2,000.00 |
| 41 | Class C concrete (column)(HPC) (420-7039) | CY | 218.40 | $2,000.00 | $1,330.97 | $1,500.00 | $2,455.63 | $1,609.49 | $3,100.00 | $2,000.00 |
| 42 | Class C concrete (column)(HPC)(mass) (420-7041) | CY | 492 | $1,200.00 | $1,188.81 | $1,400.00 | $1,176.18 | $1,166.76 | $1,550.00 | $2,200.00 |
| 43 | Class C concrete (footing)(HPC)(mass) (420-7047) | CY | 592.80 | $1,450.00 | $810.77 | $1,000.00 | $736.86 | $897.23 | $1,050.00 | $1,000.00 |
| 44 | Class C concrete (rail foundation)(HPC) (420-7054) | CY | 891.60 | $1,000.00 | $513.21 | $725.00 | $786.65 | $698.90 | $700.00 | $659.42 |
| 45 | Reinforced concrete slab (HPC) (422-7002) | SF | 88,764 | $30.00 | $38.00 | $30.00 | $42.11 | $31.77 | $40.00 | $27.00 |
| 46 | Approach slab (HPC) (422-7014) | CY | 179.70 | $1,000.00 | $700.90 | $725.00 | $742.09 | $754.29 | $1,450.00 | $1,000.00 |
| 47 | Retaining wall (MSE) (423-7001) | SF | 75,860 | $85.00 | $60.00 | $116.00 | $125.42 | $107.68 | $107.00 | $125.00 |
| 48 | Prestressed concrete girder (TX40) (425-7003) | LF | 2,818.88 | $275.00 | $242.03 | $250.00 | $576.36 | $254.14 | $390.00 | $250.00 |
| 49 | Prestressed concrete girder (TX62) (425-7006) | LF | 9,778.18 | $225.00 | $239.21 | $325.00 | $598.21 | $248.44 | $345.00 | $270.00 |
| 50 | Riprap (concrete)(4 in) (432-7001) | CY | 180.90 | $725.00 | $635.14 | $1,000.00 | $714.81 | $663.38 | $900.00 | $600.00 |
| 51 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 34.47 | $850.00 | $732.07 | $1,250.00 | $784.63 | $1,318.42 | $1,300.00 | $600.00 |
| 52 | Riprap (mow strip)(4 in) (432-7013) | CY | 97 | $700.00 | $662.74 | $1,000.00 | $753.16 | $866.20 | $900.00 | $500.00 |
| 53 | Riprap (mow strip)(5 in) (432-7014) | CY | 122.80 | $600.00 | $662.74 | $900.00 | $753.15 | $626.52 | $500.00 | $515.00 |
| 54 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 210 | $200.00 | $135.00 | $125.00 | $170.00 | $181.44 | $200.00 | $752.15 |
| 55 | Rirrap (stone common)(dry)(15 in) (432-7032) | CY | 17 | $135.87 | $200.00 | $172.00 | $460.40 | $205.00 | $700.93 | |
| 56 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 128 | $250.00 | $138.85 | $125.00 | $175.00 | $164.72 | $215.00 | $664.67 |
| 57 | Rail (type SSTR)(HPC) (450-7025) | LF | 16,956.70 | $100.00 | $69.36 | $85.00 | $76.50 | $78.24 | $95.00 | $80.00 |
| 58 | Rail (handrail)(type F) (450-7063) | LF | 170 | $139.60 | $160.00 | $189.22 | $183.49 | $265.00 | $168.30 | |
| 59 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 423 | $230.00 | $206.63 | $235.00 | $302.29 | $281.24 | $300.00 | $459.19 |
| 60 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 237.80 | $405.00 | $209.89 | $220.00 | $262.64 | $319.80 | $950.00 | $318.40 |
| 61 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 346.10 | $500.00 | $263.19 | $250.00 | $288.93 | $364.44 | $1,100.00 | $362.40 |
| 62 | Concrete box culvert (5 FT X 2 FT) (462-7006) | LF | 559 | $1,000.00 | $317.48 | $280.00 | $336.05 | $477.55 | $600.00 | $432.00 |
| 63 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 282 | $850.00 | $419.19 | $400.00 | $434.03 | $596.10 | $1,450.00 | $558.40 |
| 64 | Concrete box culvert (6 FT X 6 FT) (462-7014) | LF | 131 | $978.61 | $475.00 | $610.09 | $774.29 | $950.00 | $709.80 | |
| 65 | Concrete box culvert (8 FT X 3 FT) (462-7020) | LF | 188 | $531.00 | $500.00 | $755.38 | $843.09 | $950.00 | $738.60 | |
| 66 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 78 | $518.66 | $250.00 | $419.20 | $419.88 | $1,150.00 | $418.40 | |
| 67 | Concrete box culvert (4 FT X 2 FT)(extend) (462-7058) | LF | 62 | $683.17 | $300.00 | $527.11 | $541.20 | $1,300.00 | $462.40 | |
| 68 | Concrete box culvert (4 FT X 3 FT)(extend) (462-7059) | LF | 52 | $1,000.00 | $810.94 | $350.00 | $641.58 | $686.76 | $1,450.00 | $490.40 |
| 69 | Concrete box culvert (5 FT X 2 FT)(extend) (462-7061) | LF | 29 | $1,000.00 | $1,254.37 | $400.00 | $623.17 | $869.45 | $1,600.00 | $632.00 |
| 70 | RC pipe (CL III)(18 in) (464-7003) | LF | 3,538.32 | $75.00 | $100.00 | $110.00 | $92.15 | $87.63 | $100.00 | $82.60 |
| 71 | RC pipe (CL III)(24 in) (464-7005) | LF | 707.70 | $100.00 | $150.00 | $130.00 | $160.67 | $135.70 | $115.00 | $100.20 |
| 72 | RC pipe (arch)(CL III)(des 1) (464-7040) | LF | 4,501.34 | $250.00 | $173.44 | $148.00 | $190.10 | $178.97 | $200.00 | $157.80 |
| 73 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 3 | $7,000.00 | $6,205.75 | $6,000.00 | $7,407.63 | $7,644.93 | $10,000 | $3,196.00 |
| 74 | Inlet (complete)(pco)(3FT)(none) (465-7013) | EACH | 6 | $7,423.72 | $6,000.00 | $7,835.19 | $9,407.70 | $8,700.00 | $4,556.00 | |
| 75 | Inlet (complete)(pco)(3FT)(left) (465-7014) | EACH | 4 | $7,182.09 | $7,500.00 | $8,339.85 | $10,139 | $9,400.00 | $5,188.00 | |
| 76 | Inlet (complete)(pco)(3FT)(right) (465-7015) | EACH | 2 | $7,423.73 | $7,500.00 | $8,340.56 | $10,432 | $9,400.00 | $5,284.00 | |
| 77 | Inlet (complete)(pco)(3FT)(both) (465-7016) | EACH | 2 | $7,423.73 | $8,500.00 | $8,839.06 | $11,209 | $10,100 | $5,640.00 | |
| 78 | Inlet (complete)(pco)(5FT)(both) (465-7024) | EACH | 3 | $7,000.00 | $8,283.15 | $10,000 | $10,700 | $13,208 | $12,500 | $7,508.00 |
| 79 | Inlet (complete)(pcu)(5FT)(both) (465-7040) | EACH | 2 | $10,500 | $8,442.13 | $10,000 | $9,980.26 | $13,425 | $11,600 | $8,124.00 |
| 80 | Inlet (complete)(PMBD)(4FT) (465-7045) | EACH | 4 | $10,000 | $6,483.18 | $9,000.00 | $9,171.45 | $10,138 | $10,500 | $6,228.00 |
| 81 | Inlet (complete)(pod)(FG)(3FTX3FT) (465-7048) | EACH | 2 | $5,000.00 | $6,447.39 | $11,000 | $11,291 | $12,307 | $13,500 | $5,288.00 |
| 82 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 24 | $8,750.00 | $6,405.81 | $5,600.00 | $6,585.62 | $8,513.61 | $8,200.00 | $4,588.00 |
| 83 | Inlet (complete)(PSL)(FG)(3FTX5FT-3FTX5FT) (465-7130) | EACH | 1 | $11,500 | $9,458.59 | $7,000.00 | $8,368.01 | $10,883 | $9,100.00 | $6,148.00 |
| 84 | Inlet (complete)(PSL)(FG)(5FTX6FT-3FTX3FT) (465-7137) | EACH | 1 | $12,000 | $9,458.59 | $9,000.00 | $10,107 | $12,902 | $11,500 | $8,720.00 |
| 85 | Inlet (comp)(type sidewalk bridge) (465-7336) | EACH | 1 | $8,023.45 | $18,000 | $37,732 | $23,390 | $37,500 | $22,520 | |
| 86 | Inlet (complete) (type MSE2) (465-7352) | EACH | 2 | $9,000.00 | $12,677 | $14,000 | $17,141 | $15,214 | $8,000.00 | $14,676 |
| 87 | Inlet (complete)(wall) (465-7373) | EACH | 4 | $8,000.00 | $18,149 | $10,000 | $15,566 | $10,270 | $9,000.00 | $14,676 |
| 88 | Inlet (complete)(type sidewalk bridge)(mod) (465-7374) | EACH | 6 | $9,857.59 | $24,000 | $39,887 | $32,271 | $40,000 | $22,520 | |
| 89 | Wingwall (FW - 0) (HW=3 FT) (466-7145) | EACH | 2 | $13,070 | $10,000 | $9,466.34 | $18,385 | $7,000.00 | $16,850 | |
| 90 | Wingwall (FW - 0) (HW=4 FT) (466-7146) | EACH | 1 | $18,000 | $15,480 | $16,000 | $19,675 | $31,960 | $14,200 | $17,555 |
| 91 | Wingwall (PW - 1) (HW=3 FT) (466-7173) | EACH | 4 | $13,000 | $13,778 | $14,000 | $10,291 | $15,310 | $11,600 | $18,650 |
| 92 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 5 | $15,000 | $14,861 | $18,000 | $19,046 | $22,385 | $17,100 | $19,750 |
| 93 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 2 | $17,500 | $20,535 | $30,000 | $21,581 | $34,802 | $25,500 | $24,650 |
| 94 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 1 | $26,867 | $44,000 | $39,116 | $49,243 | $33,500 | $25,550 | |
| 95 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 2 | $29,116 | $48,000 | $46,643 | $60,308 | $44,900 | $27,850 | |
| 96 | Set (type I)(S= 3 FT)(HW= 3 FT)(6:1)(C) (467-7042) | EACH | 2 | $20,000 | $18,367 | $6,500.00 | $12,266 | $10,890 | $11,000 | $8,550.00 |
| 97 | Set (type I)(S= 4 FT)(HW= 3 FT)(6:1)(C) (467-7069) | EACH | 2 | $20,000 | $18,564 | $7,000.00 | $12,421 | $13,219 | $11,750 | $9,365.00 |
| 98 | Set (type I)(S= 5 FT)(HW= 3 FT)(4:1)(C) (467-7096) | EACH | 1 | $10,000 | $18,760 | $11,000 | $13,625 | $18,837 | $15,000 | $11,685 |
| 99 | Set (type I)(S= 5 FT)(HW= 3 FT)(6:1)(P) (467-7098) | EACH | 6 | $18,760 | $9,000.00 | $13,518 | $9,194.35 | $14,750 | $13,555 | |
| 100 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 3 | $1,118.77 | $1,500.00 | $1,735.94 | $2,112.76 | $1,800.00 | $1,072.80 | |
| 101 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 1 | $1,250.46 | $1,500.00 | $1,888.03 | $2,302.73 | $1,900.00 | $1,072.80 | |
| 102 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 3 | $1,500.00 | $1,249.37 | $1,400.00 | $1,888.04 | $2,302.73 | $1,900.00 | $1,152.00 |
| 103 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 2 | $2,400.00 | $1,412.68 | $1,700.00 | $2,242.64 | $3,200.14 | $3,000.00 | $1,418.40 |
| 104 | Set (type II) (des 1) (RCP) (6: 1) (C) (467-7417) | EACH | 5 | $1,531.26 | $1,500.00 | $3,008.74 | $2,245.16 | $2,250.00 | $1,148.00 | |
| 105 | Set (type II) (des 1) (RCP) (6: 1) (P) (467-7418) | EACH | 128 | $3,000.00 | $1,531.26 | $1,350.00 | $3,008.74 | $2,245.17 | $1,500.00 | $1,148.00 |
| 106 | Grate and frame (bridge drain) (471-7006) | EACH | 7 | $2,500.00 | $3,441.54 | $2,500.00 | $5,129.87 | $2,245.92 | $4,500.00 | $3,885.00 |
| 107 | Clean existing culverts (480-7001) | EACH | 4 | $4,000.00 | $4,592.01 | $4,500.00 | $6,026.65 | $3,847.95 | $7,000.00 | $3,500.00 |
| 108 | Pipe (PVC) (schedule 40) (6 in) (481-7013) | LF | 348 | $125.00 | $38.16 | $200.00 | $298.20 | $207.65 | $80.00 | $185.27 |
| 109 | Removing structure (set) (496-7004) | EACH | 60 | $1,000.00 | $468.77 | $800.00 | $1,188.46 | $719.08 | $2,200.00 | $500.00 |
| 110 | Removing structure (wingwall) (496-7005) | EACH | 4 | $2,300.00 | $1,145.72 | $5,000.00 | $2,689.42 | $3,595.36 | $4,050.00 | $1,500.00 |
| 111 | Removing structure (pipe) (496-7007) | LF | 2,065.40 | $35.00 | $10.10 | $30.00 | $55.79 | $22.77 | $25.00 | $5.00 |
| 112 | Removing structure (box culvert) (496-7008) | LF | 481 | $200.00 | $65.25 | $100.00 | $66.31 | $52.42 | $75.00 | $50.00 |
| 113 | Mobilization (500-7001) | LS | 1 | $7,700,000 | $7,104,224 | $8,399,300 | $7,623,851 | $7,000,000 | $7,698,000 | $7,734,761 |
| 114 | Barricades, signs and traffic handling (502-7001) | MO | 43 | $15,000 | $24,454 | $41,000 | $94,178 | $25,496 | $25,500 | $11,089 |
| 115 | Portable changeable message sign (503-7002) | EACH | 3 | $10,000 | $17,044 | $25,000 | $25,384 | $20,724 | $23,000 | $30,000 |
| 116 | TMA (stationary) (505-7001) | DAY | 681 | $300.00 | $713.01 | $165.00 | $100.00 | $201.13 | $240.00 | $500.00 |
| 117 | TMA (mobile operation) (505-7003) | DAY | 90 | $500.00 | $1,089.16 | $1,200.00 | $100.00 | $1,625.88 | $650.00 | $165.84 |
| 118 | Rock filter dams (install) (type 2) (506-7002) | LF | 808 | $50.00 | $28.00 | $45.00 | $48.64 | $56.00 | $60.00 | $44.00 |
| 119 | Rock filter dams (install) (type 3) (506-7003) | LF | 20 | $50.00 | $100.00 | $134.25 | $154.57 | $150.00 | $100.00 | |
| 120 | Rock filter dams (remove) (506-7011) | LF | 828 | $25.00 | $13.50 | $15.00 | $17.39 | $20.02 | $18.00 | $15.00 |
| 121 | Temporary sediment control fence (install) (506-7039) | LF | 5,672 | $5.00 | $3.99 | $5.00 | $4.61 | $5.31 | $6.00 | $4.99 |
| 122 | Temporary sediment control fence (remove) (506-7041) | LF | 5,672 | $2.00 | $1.00 | $1.25 | $1.14 | $1.31 | $1.00 | $1.25 |
| 123 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,033 | $8.00 | $3.75 | $6.00 | $7.50 | $8.63 | $10.00 | $6.00 |
| 124 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,033 | $2.50 | $1.00 | $1.25 | $1.14 | $1.31 | $1.00 | $1.25 |
| 125 | Constructing detours (508-7001) | SY | 21,979 | $100.00 | $80.99 | $90.00 | $121.78 | $83.75 | $110.00 | $100.00 |
| 126 | One-way traffic control (port traffic signal) (510-7003) | MO | 86 | $2,500.00 | $4,380.00 | $3,100.00 | $675.00 | $6,605.44 | $1,600.00 | $3,537.91 |
| 127 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 16,230 | $24.00 | $6.84 | $13.00 | $13.58 | $16.18 | $9.00 | $22.53 |
| 128 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 42,960 | $15.00 | $5.31 | $6.00 | $9.72 | $7.51 | $4.50 | $6.25 |
| 129 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 16,230 | $13.00 | $6.84 | $10.00 | $13.04 | $12.34 | $7.50 | $18.75 |
| 130 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 1,193.50 | $120.00 | $98.09 | $140.00 | $155.38 | $84.47 | $175.00 | $148.16 |
| 131 | Permanent CTB (single slope) (type 3) (42 ) (514-7002) | LF | 624 | $270.00 | $151.40 | $250.00 | $254.58 | $487.00 | $300.00 | $324.71 |
| 132 | Concrete curb & gutter (type I) (529-7008) | LF | 1,965.30 | $55.00 | $20.68 | $55.00 | $51.86 | $42.54 | $50.00 | $26.71 |
| 133 | Concrete curb & gutter (type II) (529-7009) | LF | 12,212.70 | $28.63 | $50.00 | $45.95 | $35.95 | $45.00 | $23.79 | |
| 134 | Concrete curb (ribbon) (529-7028) | LF | 55.40 | $50.00 | $55.70 | $50.00 | $23.00 | $79.12 | $70.00 | $33.25 |
| 135 | Intersections (concrete) (530-7001) | SY | 744 | $126.15 | $150.00 | $125.22 | $116.79 | $150.00 | $85.00 | |
| 136 | Driveways (concrete) (530-7006) | SY | 448 | $122.92 | $145.00 | $132.34 | $96.62 | $150.00 | $85.00 | |
| 137 | Driveways (ACP) (530-7010) | SY | 3,833 | $60.00 | $57.49 | $80.00 | $104.97 | $65.48 | $90.00 | $109.52 |
| 138 | Driveways (ACP and concrete) (530-7014) | SY | 1,524 | $182.92 | $120.00 | $159.05 | $149.45 | $120.00 | $60.00 | |
| 139 | Concrete sidewalks (4") (531-7001) | SY | 11,981 | $71.18 | $90.00 | $69.38 | $75.48 | $107.00 | $61.25 | |
| 140 | Curb ramps (type 7) (531-7010) | EACH | 13 | $3,009.65 | $5,500.00 | $3,119.53 | $3,988.50 | $4,000.00 | $2,825.00 | |
| 141 | Curb ramps (type 10) (531-7011) | EACH | 4 | $3,010.69 | $6,500.00 | $5,044.75 | $3,847.86 | $3,750.00 | $3,125.00 | |
| 142 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 39,764 | $0.25 | $1.00 | $0.09 | $0.59 | $0.09 | $0.15 | $0.11 |
| 143 | Concrete median (536-7001) | LF | 336 | $80.00 | $120.58 | $60.00 | $111.56 | $382.04 | $290.00 | $75.35 |
| 144 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,500 | $30.00 | $27.00 | $28.00 | $27.00 | $32.24 | $30.00 | $27.70 |
| 145 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 6 | $2,500.00 | $2,170.00 | $1,700.00 | $2,170.00 | $2,878.31 | $2,540.00 | $3,949.99 |
| 146 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,800.00 | $1,650.00 | $1,400.00 | $1,650.00 | $1,036.17 | $915.00 | $1,400.00 |
| 147 | Cable barrier system (install)(TL-4) (543-7002) | LF | 1,945 | $20.00 | $25.50 | $19.00 | $25.50 | $28.78 | $25.00 | $22.70 |
| 148 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 2 | $4,000.00 | $490.00 | $2,900.00 | $4,900.00 | $6,332.30 | $5,600.00 | $4,775.00 |
| 149 | Cable barrier (remove) (543-7037) | LF | 1,643 | $7.00 | $5.00 | $5.00 | $5.00 | $13.82 | $16.00 | $3.90 |
| 150 | Cable barrier terminal section (remove) (543-7038) | EACH | 3 | $950.00 | $900.00 | $900.00 | $900.00 | $3,453.98 | $3,100.00 | $385.00 |
| 151 | Guardrail end treatment (install) (544-7001) | EACH | 7 | $3,500.00 | $3,010.00 | $3,200.00 | $3,010.00 | $4,029.64 | $4,000.00 | $3,260.00 |
| 152 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 69 | $2,100.00 | $950.00 | $1,150.00 | $950.00 | $1,727.00 | $320.00 | $1,445.00 |
| 153 | Crash cushion attenuator (remove) (545-7004) | EACH | 33 | $1,450.00 | $750.00 | $400.00 | $750.00 | $1,151.33 | $645.00 | $810.00 |
| 154 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 7 | $28,000 | $23,780 | $25,000 | $23,780 | $42,023 | $55,000 | $32,580 |
| 155 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 33 | $12,000 | $7,200.00 | $6,900.00 | $7,200.00 | $9,325.74 | $5,000.00 | $7,600.00 |
| 156 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 8 | $360.00 | $265.00 | $270.00 | $265.00 | $316.62 | $300.00 | $230.00 |
| 157 | Mailbox install-D (TWG-post) type 2 (560-7003) | EACH | 1 | $303.00 | $310.00 | $303.00 | $402.96 | $385.00 | $270.00 | |
| 158 | HI MST IL pole (150 FT)( 80 MPH) (613-7005) | EACH | 8 | $52,250 | $62,000 | $50,000 | $46,250 | $53,701 | $46,800 | $53,765 |
| 159 | HI MST IL pole (175 FT)( 80 MPH) (613-7007) | EACH | 4 | $67,325 | $69,000 | $60,000 | $56,500 | $65,603 | $57,100 | $66,429 |
| 160 | LED HI MST IL asm (6 fixt) (type B) (614-7003) | EACH | 9 | $42,650 | $40,500 | $40,000 | $35,050 | $40,697 | $35,500 | $47,393 |
| 161 | LED HI MST IL asm (6 fixt) (type C) (614-7004) | EACH | 3 | $41,110 | $39,500 | $40,000 | $34,760 | $40,360 | $35,200 | $48,716 |
| 162 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 8,095 | $20.50 | $16.00 | $11.00 | $10.75 | $12.48 | $11.00 | $16.52 |
| 163 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 975 | $32.00 | $32.00 | $38.00 | $37.65 | $43.71 | $39.00 | $46.64 |
| 164 | Electrical conductor (no.8) bare (620-7007) | LF | 3,150 | $2.25 | $1.75 | $2.20 | $2.15 | $2.50 | $2.50 | $2.80 |
| 165 | Electrical conductor (no.8) insulated (620-7008) | LF | 7,150 | $3.00 | $2.00 | $2.45 | $2.42 | $2.81 | $3.00 | $3.16 |
| 166 | Electrical conductor (no.6) bare (620-7009) | LF | 5,970 | $3.50 | $2.00 | $2.75 | $2.70 | $3.13 | $3.00 | $3.29 |
| 167 | Electrical conductor (no.6) insulated (620-7010) | LF | 10,860 | $3.75 | $2.25 | $3.00 | $2.96 | $3.44 | $3.50 | $3.83 |
| 168 | Electrical conductor (no.2) insulated (620-7016) | LF | 4,670 | $4.00 | $3.00 | $4.35 | $4.30 | $4.99 | $5.00 | $6.23 |
| 169 | ITS GND box type 2 (603636)W/apron (623-7038) | EACH | 3 | $8,750.00 | $5,625.00 | $15,500 | $15,050 | $17,475 | $17,000 | $7,755.14 |
| 170 | Ground box type A (122311)W/apron (624-7002) | EACH | 36 | $2,250.00 | $1,400.00 | $2,500.00 | $2,260.00 | $2,624.10 | $3,700.00 | $2,513.67 |
| 171 | Remove ground box (624-7013) | EACH | 6 | $400.00 | $475.00 | $550.00 | $538.00 | $624.68 | $700.00 | $807.90 |
| 172 | Remove electrical services (628-7002) | EACH | 2 | $1,000.00 | $950.00 | $825.00 | $807.00 | $937.02 | $1,000.00 | $1,386.90 |
| 173 | Elc SRV type A 240/480 060(SS)SS(E)SP(O) (628-7057) | EACH | 4 | $17,000 | $9,500.00 | $16,000 | $15,050 | $17,475 | $15,500 | $13,809 |
| 174 | Elc SRV type D 120/240 100(NS)SS(N)SP(O) (628-7259) | EACH | 3 | $5,075.00 | $7,300.00 | $15,000 | $13,975 | $16,227 | $14,500 | $9,968.74 |
| 175 | Aluminum signs (type G) (636-7002) | SF | 936 | $30.00 | $40.00 | $35.00 | $33.45 | $38.84 | $35.00 | $30.25 |
| 176 | Aluminum signs (type O) (636-7003) | SF | 418.50 | $60.00 | $40.00 | $33.00 | $32.15 | $37.33 | $35.00 | $37.64 |
| 177 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 46 | $1,000.00 | $775.00 | $700.00 | $1,028.00 | $892.28 | $1,100.00 | $695.00 |
| 178 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 13 | $1,000.00 | $850.00 | $815.00 | $1,196.00 | $978.63 | $1,300.00 | $740.00 |
| 179 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 22 | $1,000.00 | $850.00 | $900.00 | $1,189.00 | $1,036.19 | $1,300.00 | $970.00 |
| 180 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 4 | $1,100.00 | $975.00 | $1,050.00 | $1,520.00 | $1,237.68 | $1,600.00 | $1,235.00 |
| 181 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 6 | $1,100.00 | $1,050.00 | $1,225.00 | $1,489.00 | $1,439.16 | $1,600.00 | $1,135.00 |
| 182 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,150.00 | $1,150.00 | $1,795.00 | $1,381.60 | $1,900.00 | $1,215.00 | |
| 183 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 2 | $2,500.00 | $2,700.00 | $2,400.00 | $4,463.00 | $5,182.02 | $4,600.00 | $2,135.00 |
| 184 | In bridge MNT clearance sign assembly(type S) (644-7062) | EACH | 2 | $3,000.00 | $3,000.00 | $2,450.00 | $4,463.00 | $5,182.02 | $4,600.00 | $2,190.00 |
| 185 | Remove SM RD SN sup&AM (644-7073) | EACH | 93 | $120.00 | $125.00 | $125.00 | $343.00 | $398.26 | $450.00 | $95.00 |
| 186 | Install LRSS (struct steel) (647-7001) | LB | 7,062.90 | $6.50 | $12.00 | $8.30 | $6.65 | $7.72 | $7.00 | $6.35 |
| 187 | Install overhead sign support(30 FT bal tee) (650-7028) | EACH | 3 | $86,500 | $46,200 | $90,000 | $85,850 | $99,681 | $87,000 | $46,243 |
| 188 | Install overhead sign support(30 FT cant) (650-7032) | EACH | 1 | $40,500 | $52,000 | $50,845 | $59,037 | $52,000 | $44,131 | |
| 189 | Install overhead sign support(35 FT cant) (650-7038) | EACH | 1 | $41,350 | $60,000 | $58,570 | $68,215 | $60,000 | $47,418 | |
| 190 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 16 | $50.00 | $90.00 | $86.00 | $90.00 | $46.05 | $60.00 | $44.75 |
| 191 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 13 | $50.00 | $90.00 | $86.00 | $90.00 | $46.05 | $60.00 | $44.75 |
| 192 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 34,886 | $0.75 | $0.76 | $0.75 | $0.86 | $1.00 | $0.75 | |
| 193 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 41,360 | $0.75 | $0.76 | $0.75 | $0.86 | $1.00 | $0.75 | |
| 194 | Work zone pavement marking removing (reflectorized) type II-C-R (662-7053) | EACH | 639 | $6.00 | $6.50 | $6.62 | $6.50 | $7.48 | $8.00 | $6.50 |
| 195 | Work zone pavement marking removing (W)4"(broken) (662-7061) | LF | 12,775 | $2.00 | $1.35 | $1.37 | $1.35 | $1.55 | $1.50 | $1.35 |
| 196 | Work zone pavement marking removing (W)4"(DOT) (662-7062) | LF | 785 | $2.00 | $1.60 | $1.63 | $1.60 | $1.84 | $2.00 | $1.60 |
| 197 | Work zone pavement marking removing (W)4"(solid) (662-7064) | LF | 86,720 | $2.00 | $1.00 | $1.02 | $1.00 | $1.15 | $1.25 | $1.00 |
| 198 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 14,600 | $2.00 | $2.00 | $2.04 | $2.00 | $2.30 | $2.50 | $2.00 |
| 199 | Work zone pavement marking removing (W)12"(solid) (662-7075) | LF | 300 | $5.00 | $12.00 | $12.21 | $12.00 | $13.82 | $15.00 | $12.00 |
| 200 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 402 | $15.00 | $17.50 | $17.81 | $17.50 | $20.15 | $20.00 | $17.50 |
| 201 | Work zone pavement marking removing (W)18"(yld tri) (662-7093) | EACH | 17 | $39.00 | $65.00 | $66.15 | $65.00 | $74.83 | $85.00 | $65.00 |
| 202 | Work zone pavement marking removing (Y)4"(solid) (662-7097) | LF | 104,681 | $1.50 | $1.00 | $1.02 | $1.00 | $1.15 | $1.25 | $1.00 |
| 203 | Work zone pavement marking removing (Y)12"(solid) (662-7103) | LF | 991 | $3.00 | $12.00 | $12.21 | $12.00 | $13.82 | $16.00 | $12.00 |
| 204 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 1,050 | $1.20 | $1.00 | $1.02 | $1.00 | $1.15 | $1.25 | $1.00 |
| 205 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 10,208 | $1.50 | $1.25 | $1.27 | $1.25 | $1.44 | $1.50 | $1.25 |
| 206 | Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027) | LF | 578 | $2.50 | $2.54 | $2.50 | $2.88 | $2.75 | $2.50 | |
| 207 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 693 | $5.00 | $7.50 | $7.63 | $7.50 | $8.63 | $7.75 | $7.50 |
| 208 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 347 | $11.00 | $11.00 | $11.20 | $11.00 | $12.66 | $12.00 | $11.00 |
| 209 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 155 | $8.00 | $8.00 | $8.14 | $8.00 | $9.21 | $9.00 | $8.00 |
| 210 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 2,880 | $1.00 | $5.00 | $5.09 | $5.00 | $5.76 | $5.50 | $5.00 |
| 211 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 140 | $1.25 | $5.00 | $5.09 | $5.00 | $5.76 | $5.50 | $5.00 |
| 212 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 2,866 | $1.00 | $5.00 | $5.09 | $5.00 | $5.76 | $5.50 | $5.00 |
| 213 | Pavement sler 6" (666-7347) | LF | 106,991 | $1.00 | $0.25 | $0.25 | $0.25 | $0.29 | $0.25 | $0.25 |
| 214 | Pavement sler 8" (666-7348) | LF | 10,208 | $1.00 | $0.50 | $0.51 | $0.50 | $0.58 | $0.50 | $0.50 |
| 215 | Pavement sler 12" (666-7350) | LF | 1,426 | $1.50 | $4.00 | $4.07 | $4.00 | $4.61 | $4.50 | $4.00 |
| 216 | Pavement sler 24" (666-7352) | LF | 347 | $3.00 | $6.00 | $6.11 | $6.00 | $6.91 | $6.50 | $6.00 |
| 217 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 8,233 | $1.50 | $0.80 | $0.81 | $0.80 | $0.92 | $1.00 | $0.80 |
| 218 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 38,490 | $1.50 | $0.80 | $0.81 | $0.80 | $0.92 | $1.00 | $0.80 |
| 219 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 4,594 | $1.50 | $0.80 | $0.81 | $0.80 | $0.92 | $1.00 | $0.80 |
| 220 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 48,738 | $1.50 | $0.80 | $0.81 | $0.80 | $0.92 | $1.00 | $0.80 |
| 221 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 21 | $300.00 | $275.00 | $280.00 | $275.00 | $316.62 | $280.00 | $275.00 |
| 222 | Prefabricated PM type C (W)(uturn arrow) (668-7096) | EACH | 4 | $400.00 | $500.00 | $509.00 | $500.00 | $575.67 | $550.00 | $500.00 |
| 223 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 15 | $325.00 | $375.00 | $382.00 | $375.00 | $431.75 | $400.00 | $375.00 |
| 224 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 2 | $900.00 | $916.00 | $900.00 | $1,036.19 | $1,000.00 | $900.00 | |
| 225 | Reflectorized pavement marker type I-C (672-7002) | EACH | 608 | $7.00 | $6.00 | $6.11 | $6.00 | $6.91 | $7.00 | $6.00 |
| 226 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 667 | $9.00 | $6.00 | $6.11 | $6.00 | $6.91 | $7.00 | $6.00 |
| 227 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 506 | $5.00 | $6.00 | $6.11 | $6.00 | $6.91 | $7.00 | $6.00 |
| 228 | Eliminating existing PM & markers (6") (677-7002) | LF | 38,754 | $4.00 | $1.25 | $1.27 | $1.25 | $1.44 | $1.50 | $1.25 |
| 229 | Eliminating existing PM & markers (8") (677-7004) | LF | 1,672 | $1.50 | $1.35 | $1.37 | $1.35 | $1.55 | $1.75 | $1.35 |
| 230 | Eliminating existing PM & markers (24") (677-7008) | LF | 94 | $5.50 | $6.00 | $6.11 | $6.00 | $6.91 | $8.00 | $6.00 |
| 231 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 4 | $85.00 | $100.00 | $102.00 | $100.00 | $115.14 | $130.00 | $100.00 |
| 232 | Eliminating existing PM & markers (word) (677-7015) | EACH | 2 | $90.00 | $100.00 | $102.00 | $100.00 | $115.14 | $130.00 | $100.00 |
| 233 | Eliminating existing PM & markers (rumble strip) (677-7030) | LF | 17,708 | $2.00 | $0.35 | $4.25 | $0.13 | $0.01 | $0.50 | $1.53 |
| 234 | Relocate RDSD flash beacon assembly (685-7002) | EACH | 2 | $15,000 | $6,000.00 | $5,915.00 | $6,867.96 | $8,000.00 | $5,714.52 | |
| 235 | Remove luminaire pole (690-7127) | EACH | 9 | $1.00 | $1,000.00 | $550.00 | $540.00 | $627.00 | $700.00 | $842.91 |
| 236 | Bonding course (3007-7001) | GAL | 41,061 | $6.00 | $4.00 | $4.00 | $0.36 | $4.67 | $5.00 | $4.00 |
| 237 | ITS com CBL (ethernet) (6005-7001) | LF | 810 | $6.00 | $2.75 | $11.35 | $11.25 | $13.06 | $12.00 | $23.84 |
| 238 | ITS pole (50 FT) (90 MPH) (6011-7005) | EACH | 3 | $19,750 | $19,200 | $17,000 | $16,415 | $19,060 | $17,000 | $21,054 |
| 239 | ITS pole MNTD cab (type 2)(conf 1) (6011-7028) | EACH | 3 | $7,900.00 | $6,800.00 | $8,000.00 | $7,465.00 | $8,667.68 | $7,750.00 | $10,084 |
| 240 | Installation of cellular modem (6015-7001) | EACH | 3 | $2,000.00 | $850.00 | $1,800.00 | $1,780.00 | $2,066.77 | $1,800.00 | $1,014.75 |
| 241 | CCTV field equipment (digital) (6018-7002) | EACH | 3 | $5,000.00 | $9,800.00 | $12,000 | $11,340 | $13,167 | $12,000 | $9,621.89 |
| 242 | CCTV mount (pole) (6018-7003) | EACH | 3 | $1,035.00 | $450.00 | $1,500.00 | $1,420.00 | $1,648.77 | $1,500.00 | $427.76 |
| 243 | Full color matrix DMS (pole mounted) (6123-7001) | EACH | 3 | $80,000 | $13,500 | $150,000 | $142,670 | $165,655 | $150,000 | $150,560 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.