Prestressed concrete girder (TX40), TxDOT 425-7003
Low bidders on TxDOT contracts carried a median of $228.00 per LF for this item, over the 24 months to 19 NOV 2026, across 25 low bids. Half of all 192 bids fell between $221.75 and $298.00.
- Owner
- Texas DOT
- Item
- 425-7003
- Unit
- LF
- Data through
- 19 NOV 2026
TxDOT prints this item as “PRESTR CONC GIRDER (TX40)”.
TxDOT has bid this work under more than one code: 4256037 on lettings from 10 JAN 2020 to 03 AUG 2023 (213 bids); 4256037001 on lettings from 06 OCT 2022 to 01 AUG 2024 (114 bids); 425-7003 on lettings from 03 DEC 2024 to 03 NOV 2026 (190 bids); 425-6037 on lettings from 07 FEB 2025 to 07 FEB 2025 (2 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 16 | 16 | $141.50 | 94 | $165.25 |
| 2021 | 17 | 17 | $154.66 | 93 | $160.62 |
| 2022 | 6 | 6 | $187.50 | 20 | $225.00 |
| 2023 | 17 | 17 | $250.00 | 46 | $258.50 |
| 2024 | 21 | 21 | $233.84 | 78 | $249.25 |
| 2025 | 12 | 12 | $231.50 | 92 | $248.88 |
| 2026 | 12 | 12 | $227.50 | 96 | $260.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Austin District | 4 | $221.88 | 36 | $249.43 |
| Dallas District | 4 | $193.38 | 21 | $234.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 397.93 to 696.50 | 6 | $267.50 |
| 714 to 1,590 | 6 | $212.50 |
| 1,789.62 to 2,578.42 | 6 | $218.38 |
| 2,818.88 to 17,486.83 | 7 | $230.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Williams Brothers Construction Co., Inc. | 14 | 13 (93%) |
| Zachry Construction Corporation | 16 | 8 (50%) |
| Webber, LLC | 41 | 7 (17%) |
| James Construction Group, LLC | 25 | 4 (16%) |
| Indus Road & Bridge, Inc. | 9 | 4 (44%) |
| Hodges and Son Construction Company, Inc. | 22 | 3 (14%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 NOV 2026 | A00184974 | Austin District | 2,333.84 | $215.77 | $318.84 | n/a | 6 | Austin Bridge & Road Services, LP | TxDOT |
| 03 SEP 2026 | A00139727 | Paris District | 472.50 | $300.00 | $296.63 | $400.00 | 8 | Longview Bridge and Road, LTD. | TxDOT |
| 05 AUG 2026 | A00190871 | Paris District | 397.93 | $245.00 | $278.00 | n/a | 8 | Hodges and Son Construction Company, Inc. | TxDOT |
| 01 JUL 2026 | A00008199 | Fort Worth District | 2,271.22 | $221.00 | $245.00 | $215.00 | 6 | Indus Road & Bridge, Inc. | TxDOT |
| 01 JUL 2026 | A00058522 | Tyler District | 1,509.60 | $230.00 | $230.00 | $200.00 | 7 | Drake Companies LLC | TxDOT |
| 03 JUN 2026 | A00063871 | El Paso District | 8,248.87 | $285.00 | $282.50 | $280.00 | 4 | Jordan Foster Construction, LLC | TxDOT |
| 02 JUN 2026 | A00200068 | Childress District | 3,482.50 | $230.00 | $240.00 | $200.00 | 9 | Skyline Bridge LLC | TxDOT |
| 07 MAY 2026 | A00183308 | Pharr District | 3,416.14 | $200.00 | $224.22 | $350.00 | 5 | Ioc Company LLC | TxDOT |
| 06 MAY 2026 | A00136586 | Corpus Christi District | 714 | $225.00 | $260.00 | $210.00 | 13 | Delgado'S Contractors, LLC | TxDOT |
| 07 APR 2026 | A00061686 | Abilene District | 400 | $290.00 | $297.50 | n/a | 6 | Skyline Bridge LLC | TxDOT |
| 04 FEB 2026 | A00045441 | Dallas District | 2,578.42 | $200.00 | $250.00 | $200.00 | 12 | Urban Infraconstruction LLC | TxDOT |
| 07 JAN 2026 | A00205023 | Houston District | 745 | $200.00 | $259.44 | $235.00 | 12 | R Construction Civil, LLC | TxDOT |
| 08 OCT 2025 | A00062536 | Abilene District | 2,818.88 | $242.03 | $250.00 | $275.00 | 9 | James Construction Group, LLC | TxDOT |
| 04 SEP 2025 | A00194530 | Lufkin District | 1,789.62 | $245.81 | $235.00 | $225.00 | 7 | THK Construction LLC | TxDOT |
| 08 AUG 2025 | A00129321 | Austin District | 596.94 | $235.00 | $280.00 | $240.00 | 11 | Dan Williams Company | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.