TxDOT contract A00205023 bid tabulation
Install/Upgrade Drainage Structure(S), FM 1314 (Cooper Rose Way to SH 242). Let by Texas DOT on January 7, 2026, Montgomery, Houston District. 12 bids received; low bid $2,219,724 by R Construction Civil, LLC, -20% against the engineer's estimate of $2,760,376.
- Owner
- Texas DOT
- Letting
- 07 JAN 2026
- Pay items
- 66
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | R Construction Civil, LLC | $2,219,724 | Low | -20% |
| 2 | Forde Construction Company, Inc. | $2,278,863 | +3.0% | -17% |
| 3 | Larry Young Paving, Inc. | $2,384,656 | +7.0% | -14% |
| 4 | Jfo Services, LLC | $2,390,899 | +8.0% | -13% |
| 5 | MC2 Civil, LLC | $2,395,495 | +8.0% | -13% |
| 6 | James Construction Group, LLC | $2,449,731 | +10% | -11% |
| 7 | Environmental Allies, Inc. | $2,580,321 | +16% | -7.0% |
| 8 | Roman Emperors Road, LLC | $2,681,228 | +21% | -3.0% |
| 9 | C. E. Barker, LTD. | $2,958,415 | +33% | +7.0% |
| 10 | John Reed and Company, LLC | $3,072,360 | +38% | +11% |
| 11 | Castillo Aranda LLC | $3,126,511 | +41% | +13% |
| 12 | Icon GC, LLC | $3,163,900 | +43% | +15% |
Engineer's estimate: $2,760,376.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. R Construction Civil, LLC | 2. Forde Construction Company, Inc. | 3. Larry Young Paving, Inc. | 4. Jfo Services, LLC | 5. MC2 Civil, LLC | 6. James Construction Group, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 19.31 | $10,000 | $1,500.00 | $1,800.00 | $3,500.00 | $4,534.82 | $7,000.00 | $12,430 |
| 2 | Removing concrete (medians) (104-7008) | SY | 628 | $40.00 | $10.00 | $15.00 | $16.00 | $10.18 | $15.00 | $10.50 |
| 3 | Removing concrete (curb) (104-7016) | LF | 782 | $9.00 | $7.50 | $5.00 | $5.25 | $6.36 | $15.00 | $3.57 |
| 4 | Excavation (channel) (110-7002) | CY | 2,500 | $100.00 | $18.00 | $18.00 | $22.00 | $20.42 | $22.00 | $15.04 |
| 5 | Subgr widen (DC) (112-7004) | SY | 4,405 | $12.00 | $4.00 | $7.30 | $7.25 | $14.19 | $20.00 | $4.62 |
| 6 | Embankment (final)(DC)(type A) (132-7002) | CY | 1,710 | $45.00 | $18.00 | $15.00 | $25.00 | $19.19 | $13.00 | $20.08 |
| 7 | Compost manuf topsoil (4") (161-7002) | SY | 1,111 | $3.00 | $1.00 | $2.55 | $1.25 | $1.39 | $4.00 | $1.25 |
| 8 | Block sodding (162-7002) | SY | 1,111 | $8.00 | $7.30 | $6.00 | $7.00 | $4.73 | $6.50 | $4.25 |
| 9 | Drill seed (permanent_urban_sand) (164-7011) | SY | 1,111 | $0.50 | $2.00 | $0.85 | $1.00 | $0.37 | $3.00 | $0.33 |
| 10 | Drill seed (temporary_warm_cool) (164-7015) | SY | 1,111 | $1.50 | $2.00 | $0.75 | $0.75 | $0.33 | $3.00 | $0.30 |
| 11 | Fertilizer (166-7001) | ACRE | 0.23 | $4,500.00 | $4,500.00 | $1,340.00 | $1,500.00 | $835.26 | $3,000.00 | $750.00 |
| 12 | Vegetative watering (168-7001) | TGL | 133 | $200.00 | $260.00 | $100.00 | $40.00 | $49.03 | $5.00 | $32.00 |
| 13 | Asphalt TRT base (GR 2)(PG 64) (292-7006) | TON | 2,544 | $140.00 | $145.00 | $133.00 | $137.50 | $154.46 | $130.00 | $132.00 |
| 14 | SP mixes SP-D PG70-22 (344-7051) | TON | 424 | $140.00 | $190.00 | $143.00 | $175.00 | $176.74 | $200.00 | $196.00 |
| 15 | SP mixes SP-D sac-A PG70-22 (344-7052) | TON | 1,326 | $135.00 | $190.00 | $154.00 | $183.00 | $181.64 | $150.00 | $157.00 |
| 16 | Tack coat (344-7077) | GAL | 1,557 | $7.00 | $5.50 | $4.25 | $8.00 | $4.73 | $5.50 | $7.00 |
| 17 | Planing asphalt concrete pavement(2") (354-7051) | SY | 12,055 | $2.00 | $1.65 | $3.50 | $2.50 | $1.44 | $2.75 | $2.72 |
| 18 | Cem stabil BKFL (400-7010) | CY | 8 | $300.00 | $100.00 | $250.00 | $120.00 | $54.26 | $150.00 | $1,000.00 |
| 19 | Temporary special shoring (403-7001) | SF | 603 | $35.00 | $98.00 | $90.00 | $72.00 | $133.64 | $120.00 | $16.35 |
| 20 | Drilled shaft (18 in) (416-7002) | LF | 180 | $165.00 | $280.00 | $105.00 | $110.00 | $74.85 | $95.00 | $55.38 |
| 21 | Drilled shaft (36 in) (416-7006) | LF | 720 | $300.00 | $260.00 | $320.00 | $280.00 | $228.48 | $285.00 | $209.69 |
| 22 | Class C concrete (abutment) (420-7012) | CY | 87.40 | $1,300.00 | $610.00 | $2,000.00 | $1,300.00 | $857.74 | $1,400.00 | $844.60 |
| 23 | Reinforced concrete slab (422-7001) | SF | 5,600 | $25.00 | $23.00 | $26.00 | $35.00 | $44.15 | $35.00 | $67.76 |
| 24 | Prestressed concrete girder (TX40) (425-7003) | LF | 745 | $235.00 | $200.00 | $244.00 | $290.00 | $239.58 | $205.00 | $235.36 |
| 25 | Riprap (concrete)(5 in) (432-7002) | CY | 62 | $1,000.00 | $675.00 | $855.00 | $640.00 | $694.20 | $750.00 | $476.50 |
| 26 | Riprap (concrete)(6 in) (432-7003) | CY | 105 | $625.00 | $670.00 | $785.00 | $580.00 | $271.27 | $330.00 | $472.13 |
| 27 | Riprap (mow strip)(4 in) (432-7013) | CY | 8 | $800.00 | $500.00 | $1,300.00 | $930.00 | $1,294.58 | $600.00 | $703.99 |
| 28 | Rail (type T221) (450-7004) | LF | 210 | $235.00 | $215.00 | $275.00 | $190.00 | $200.46 | $185.00 | $71.27 |
| 29 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 148 | $240.00 | $250.00 | $238.00 | $180.00 | $234.70 | $180.00 | $202.96 |
| 30 | RC pipe (CL III)(24 in) (464-7005) | LF | 85 | $150.00 | $220.00 | $135.00 | $120.00 | $157.62 | $190.00 | $126.55 |
| 31 | Inlet (complete)(type AD)(hou) (465-7314) | EACH | 2 | $7,500.00 | $7,000.00 | $8,400.00 | $7,100.00 | $6,911.72 | $6,500.00 | $5,745.67 |
| 32 | Mobilization (500-7001) | LS | 1 | $251,478 | $220,000 | $150,000 | $240,000 | $212,799 | $230,000 | $240,000 |
| 33 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $5,000.00 | $2,200.00 | $3,700.00 | $2,000.00 | $942.17 | $2,000.00 | $3,824.72 |
| 34 | TMA (stationary) (505-7001) | DAY | 120 | $225.00 | $215.00 | $320.00 | $260.00 | $185.98 | $210.00 | $390.18 |
| 35 | TMA (mobile operation) (505-7003) | DAY | 10 | $360.00 | $330.00 | $165.00 | $650.00 | $185.98 | $600.00 | $962.04 |
| 36 | Rock filter dams (install) (type 1) (506-7001) | LF | 88 | $50.00 | $45.00 | $37.00 | $45.00 | $50.11 | $125.00 | $45.00 |
| 37 | Rock filter dams (remove) (506-7011) | LF | 88 | $15.00 | $12.50 | $10.00 | $13.00 | $22.28 | $45.00 | $20.00 |
| 38 | Temporary sediment control fence (install) (506-7039) | LF | 817 | $4.00 | $5.00 | $4.80 | $5.75 | $4.46 | $4.50 | $4.00 |
| 39 | Temporary sediment control fence (remove) (506-7041) | LF | 817 | $1.50 | $1.50 | $1.10 | $1.25 | $1.11 | $2.00 | $1.00 |
| 40 | Constructing detours (508-7001) | SY | 197 | $130.00 | $175.00 | $95.00 | $72.00 | $209.78 | $120.00 | $219.10 |
| 41 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 690 | $75.00 | $75.00 | $32.00 | $45.00 | $80.53 | $40.00 | $13.16 |
| 42 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 690 | $20.00 | $3.00 | $13.00 | $8.00 | $5.92 | $7.00 | $5.94 |
| 43 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 690 | $25.00 | $5.00 | $24.00 | $18.00 | $5.68 | $20.00 | $12.29 |
| 44 | Portable concrete traffic barrier (pinning) (512-7071) | EACH | 3 | $50.00 | $520.00 | $900.00 | $500.00 | $550.86 | $900.00 | $271.86 |
| 45 | Concrete curb (dowel) (529-7014) | LF | 782 | $20.00 | $17.00 | $13.00 | $10.00 | $18.32 | $10.00 | $13.85 |
| 46 | Metal W-beam guard fence (timber post) (540-7001) | LF | 100 | $35.00 | $27.00 | $40.00 | $32.00 | $27.29 | $25.00 | $23.25 |
| 47 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $3,000.00 | $1,850.00 | $2,100.00 | $2,600.00 | $2,617.12 | $2,750.00 | $1,600.00 |
| 48 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,800.00 | $2,500.00 | $1,700.00 | $2,100.00 | $1,781.87 | $1,600.00 | $1,300.00 |
| 49 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $4,000.00 | $3,550.00 | $3,400.00 | $4,000.00 | $3,452.38 | $3,200.00 | $3,100.00 |
| 50 | Crash cushion attenuator (des source) (545-7001) | EACH | 2 | $2,000.00 | $2,600.00 | $4,000.00 | $6,100.00 | $5,289.93 | $4,900.00 | $2,500.00 |
| 51 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 2 | $2,000.00 | $2,600.00 | $4,000.00 | $5,800.00 | $5,011.52 | $4,500.00 | $2,500.00 |
| 52 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $2,000.00 | $1,050.00 | $2,600.00 | $1,600.00 | $1,392.08 | $1,300.00 | $1,000.00 |
| 53 | Install small roadside sign support and assembly tytwt(1)WP(P) (644-7059) | EACH | 4 | $2,000.00 | $475.00 | $490.00 | $590.00 | $540.13 | $500.00 | $455.48 |
| 54 | Work zone pavement marking removing (W)4"(broken) (662-7061) | LF | 280 | $0.10 | $2.50 | $2.10 | $2.50 | $2.34 | $2.20 | $2.00 |
| 55 | Work zone pavement marking removing (W)4"(solid) (662-7064) | LF | 2,500 | $0.87 | $1.50 | $1.10 | $1.25 | $1.50 | $1.50 | $1.50 |
| 56 | Work zone pavement marking removing (Y)4"(solid) (662-7097) | LF | 3,100 | $0.85 | $1.50 | $1.10 | $1.25 | $1.50 | $1.50 | $1.50 |
| 57 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 541 | $1.50 | $1.50 | $1.10 | $1.25 | $0.78 | $0.70 | $0.30 |
| 58 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 4,075 | $1.50 | $0.75 | $0.60 | $0.75 | $0.78 | $0.70 | $0.30 |
| 59 | Reflectorized pavement marking type II (W) 8" (DOT) (666-7177) | LF | 154 | $2.25 | $2.00 | $1.59 | $2.00 | $1.95 | $1.75 | $0.61 |
| 60 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 525 | $2.00 | $1.50 | $1.10 | $1.25 | $1.73 | $1.60 | $0.60 |
| 61 | Reflectorized pavement marking type II (W) (arrow) (666-7186) | EACH | 11 | $200.00 | $120.00 | $106.00 | $130.00 | $172.62 | $160.00 | $85.00 |
| 62 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 6 | $200.00 | $145.00 | $128.00 | $150.00 | $194.90 | $180.00 | $85.00 |
| 63 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 5,700 | $1.50 | $0.75 | $0.60 | $0.75 | $0.78 | $0.70 | $0.30 |
| 64 | Reflectorized pavement marker type I-C (672-7002) | EACH | 54 | $8.00 | $7.00 | $6.40 | $7.75 | $8.91 | $8.00 | $7.00 |
| 65 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 270 | $15.00 | $6.00 | $5.30 | $6.50 | $8.91 | $8.00 | $7.00 |
| 66 | Eliminating existing PM & markers (6") (677-7002) | LF | 1,928 | $0.50 | $0.75 | $0.65 | $0.75 | $0.77 | $0.70 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.