C. E. Barker, LTD.: TxDOT bid record
C. E. Barker, LTD. submitted 106 bids on Texas DOT contracts in the data, from 08 MAR 2023 to 05 FEB 2026, and was the low bidder on 7 of them (7%). When it was not low, its total sat a median +33% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $35,817,376
- Latest bid
- 05 FEB 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2023 | 5 | 0 | 0% |
| 2024 | 41 | 6 | 15% |
| 2025 | 55 | 1 | 2% |
| 2026 | 5 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Yoakum District | 30 | 3 | 10% |
| Houston District | 15 | 0 | 0% |
| Bryan District | 10 | 1 | 10% |
| Austin District | 8 | 1 | 13% |
| Waco District | 6 | 1 | 17% |
| Childress District | 5 | 1 | 20% |
| Lufkin District | 4 | 0 | 0% |
| Abilene District | 4 | 0 | 0% |
| Amarillo District | 4 | 0 | 0% |
| San Antonio District | 3 | 0 | 0% |
| Beaumont District | 3 | 0 | 0% |
| Maintenance Division District | 3 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Cem stabil BKFL | 400-7010 | CY | 80 | 22 (28%) | $182.51 | $200.00 |
| Riprap (stone protection)(18 in) | 432-7043 | CY | 51 | 14 (27%) | $192.48 | $200.00 |
| Riprap (mow strip)(4 in) | 432-7013 | CY | 43 | 14 (33%) | $771.01 | $643.00 |
| Class C concrete (abutment) | 420-7012 | CY | 57 | 11 (19%) | $1,828.06 | $1,315.00 |
| Reinforced concrete slab | 422-7001 | SF | 37 | 11 (30%) | $31.15 | $27.00 |
| Barricades, signs and traffic handling | 502-7001 | MO | 101 | 10 (10%) | $4,617.90 | $5,000.00 |
| RC pipe (CL III)(24 in) | 464-7005 | LF | 39 | 10 (26%) | $131.97 | $108.13 |
| Armor joint (sealed) | 454-7003 | LF | 30 | 10 (33%) | $118.82 | $150.00 |
| Class C concrete (cap) | 420-7022 | CY | 45 | 9 (20%) | $2,068.53 | $1,557.98 |
| Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) | 658-7019 | EACH | 56 | 8 (14%) | $40.33 | $35.00 |
| Class C concrete (column) | 420-7038 | CY | 45 | 8 (18%) | $2,236.63 | $1,600.00 |
| Temporary special shoring | 403-7001 | SF | 37 | 8 (22%) | $31.82 | $35.73 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| STX Civil | 41 | 36 of 41 |
| Hodges and Son Construction Company, Inc. | 27 | 17 of 27 |
| E-Z Bel Construction, LLC | 24 | 20 of 24 |
| Talbert Companies LLC | 20 | 13 of 20 |
| Texas Materials Group, Inc. | 19 | 11 of 19 |
| Knife River Corporation - South | 19 | 13 of 19 |
| Skyline Bridge LLC | 19 | 13 of 19 |
| R Construction Civil, LLC | 18 | 10 of 18 |
| Earth Builders, L.P. | 17 | 7 of 17 |
| Trevway, Inc. | 15 | 12 of 15 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 05 FEB 2026 | A00135345 | Austin District | Reconstruct Existing Roadway, FM 487 (COLLEGE AVENUE to SH 195 BYPASS) | 9 of 10 | $4,769,760 | +31% |
| 04 FEB 2026 | A00188551 | Amarillo District | Bridge Replacement, IRWIN RD (IRWIN RD @ EAST AMARILLO CREEK to .) | 7 of 7 | $3,171,289 | +59% |
| 04 FEB 2026 | A00134679 | Houston District | Bridge Replacement, HOPKINS RD (Hopkins Rd (CR 209) at Turkey Creek to .) | 13 of 13 | $3,985,800 | +43% |
| 04 FEB 2026 | A00101674 | Yoakum District | State Park Improvements, EPWORTH PL (MISSION LAKE ROAD to GUADALUPE DELTA WMA) | 11 of 11 | $668,078 | +95% |
| 07 JAN 2026 | A00205023 | Houston District | Install/Upgrade Drainage Structure(S), FM 1314 (Cooper Rose Way to SH 242) | 9 of 12 | $2,958,415 | +33% |
| 03 DEC 2025 | A00045322 | Abilene District | Bridge Replacement, FM 604 (AT JIM NED CREEK to .) | 9 of 9 | $4,985,765 | +85% |
| 03 DEC 2025 | A00130819 | Yoakum District | Bridge Replacement, FM 806 (AT RATLIFF CREEK to STR#0716-03-012) | 12 of 12 | $2,767,700 | +73% |
| 02 DEC 2025 | A00128664 | Yoakum District | Bridge Replacement, FM 1300 (AT GOLDENROD CREEK to STR # 0420-10-010) | 10 of 10 | $4,094,738 | +54% |
| 02 DEC 2025 | A00124687 | Bryan District | Bridge Replacement, FM 2039 (AT PORTER CREEK to .) | 8 of 9 | $3,748,865 | +62% |
| 06 NOV 2025 | A00036755 | Abilene District | Bridge Replacement, COUNTY ROAD 309 (AT CLEAR FORK BRAZOS RIVER to .) | 7 of 8 | $3,244,296 | +88% |
| 06 NOV 2025 | A00184978 | Yoakum District | Bridge Replacement, CLARK SCHOOL (SPRING CREEK to STR# B001-40-002&B001-40-001 BRIGGS BLVD) | 9 of 9 | $4,173,074 | +45% |
| 05 NOV 2025 | A00133631 | Childress District | Install/Upgrade Drainage Structure(S), FM 3257 (1.44 Miles North of US 287, North to 1.88 Miles North of US 287) | 6 of 6 | $2,436,653 | +37% |
| 05 NOV 2025 | A00135986 | Bryan District | Bridge Replacement, SH 105 (AT JACKSON CREEK to .) | 10 of 12 | $4,162,654 | +48% |
| 09 OCT 2025 | A00194081 | Abilene District | Bridge Replacement, CR 314 (AT DRAW to .) | 7 of 8 | $1,229,982 | +34% |
| 09 OCT 2025 | A00185000 | Austin District | Drainage Improvements, Various (Harmon Road to Alum Creek Road) | 4 of 8 | $862,933 | +2.0% |
| 09 OCT 2025 | A00130008 | Houston District | Bridge Replacement, IOWA LN (Iowa Lane at Brazos River Auth Canal to .) | 5 of 7 | $1,344,375 | +19% |
| 08 OCT 2025 | A00186223 | Houston District | Construct Frontage Roads, SH 99 (Longenbaugh Road to FM 529) | 8 of 10 | $8,955,745 | +37% |
| 08 OCT 2025 | A00186870 | Bryan District | Bridge Replacement, FM 1580 (At Mims Creek to .) | 7 of 7 | $3,596,808 | +40% |
| 08 OCT 2025 | A00194184 | Yoakum District | Bridge Replacement, HAMMAN ST (At Cottonwood Creek to STR# B009-60-001) | 3 of 5 | $5,212,443 | +7.0% |
| 05 SEP 2025 | A00205768 | Abilene District | Bridge Replacement, FM 1835 (FM 1835 to @ DOUBLE MOUNTAIN FORK BRAZOS RIVER) | 9 of 10 | $7,449,535 | +92% |
| 05 SEP 2025 | A00207208 | Houston District | Bridge Replacement, LEE RD (Lee Road at HCFCD Ditch to .) | 5 of 6 | $1,233,817 | +20% |
| 04 SEP 2025 | A00194530 | Lufkin District | Bridge Replacement, FM 2610 (FM 2610 to At Menard Creek.) | 5 of 7 | $3,074,907 | +24% |
| 04 SEP 2025 | A00043203 | Dallas District | Bridge Replacement, N TRINITY RD (TRINITY ROAD AT COOPER CREEK to IN CITY OF DENTON) | 8 of 8 | $1,959,319 | +20% |
| 04 SEP 2025 | A00134791 | Yoakum District | Bridge Replacement, COUNTY ROAD 177 (CR 177 at BOGGY CREEK to STR# AA01-32-001) | 8 of 10 | $2,152,588 | +43% |
| 08 AUG 2025 | A00063966 | Austin District | Highway Improvement, SH 95 (SL 230 to SOUTH OF FM 535) | 1 of 6 | $18,841,535 | Low, 6.0% under the second |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.