TxDOT contract A00207208 bid tabulation
Bridge Replacement, LEE RD (Lee Road at HCFCD Ditch to .). Let by Texas DOT on September 5, 2025, Harris, Houston District. 6 bids received; low bid $1,025,684 by MC2 Civil, LLC, -20% against the engineer's estimate of $1,282,858.
- Owner
- Texas DOT
- Letting
- 05 SEP 2025
- Pay items
- 71
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | MC2 Civil, LLC | $1,025,684 | Low | -20% |
| 2 | Jfo Services, LLC | $1,149,648 | +12% | -10% |
| 3 | Trevway, Inc. | $1,173,006 | +14% | -9.0% |
| 4 | STX Civil | $1,217,543 | +19% | -5.0% |
| 5 | C. E. Barker, LTD. | $1,233,817 | +20% | -4.0% |
| 6 | Forde Construction Company, Inc. | $1,360,178 | +33% | +6.0% |
Engineer's estimate: $1,282,858.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. MC2 Civil, LLC | 2. Jfo Services, LLC | 3. Trevway, Inc. | 4. STX Civil | 5. C. E. Barker, LTD. | 6. Forde Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3.45 | $18,000 | $20,000 | $3,094.79 | $2,500.00 | $8,000.00 | $36,000 | $22,000 |
| 2 | Remove (6") TRT/untrt base & asphalt pavement (105-7026) | SY | 884 | $20.00 | $4.50 | $6.68 | $12.00 | $12.00 | $19.28 | $6.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 288 | $35.00 | $10.00 | $31.55 | $15.00 | $35.00 | $33.47 | $50.00 |
| 4 | Excavation (channel) (110-7002) | CY | 92 | $55.00 | $100.00 | $71.27 | $16.00 | $50.00 | $33.47 | $160.00 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 565 | $35.00 | $10.00 | $54.76 | $9.00 | $45.00 | $38.82 | $80.00 |
| 6 | Embankment (final)(DC)(type E)(csbe) (132-7036) | CY | 308 | $70.00 | $10.00 | $139.28 | $280.00 | $50.00 | $38.82 | $145.00 |
| 7 | Spec excavation work (hyd excavator) (158-7002) | HR | 16 | $750.00 | $500.00 | $859.46 | $100.00 | $2.50 | $224.91 | $600.00 |
| 8 | Furn & place topsoil (6") (160-7004) | SY | 274 | $10.00 | $18.00 | $30.16 | $10.00 | $6.00 | $9.10 | $30.00 |
| 9 | Block sodding (162-7002) | SY | 920 | $15.00 | $6.00 | $6.21 | $6.00 | $5.00 | $6.43 | $6.00 |
| 10 | Straw or hay mulch (162-7003) | SY | 926 | $1.00 | $1.50 | $1.04 | $2.00 | $1.25 | $0.32 | $1.05 |
| 11 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 463 | $1.00 | $1.50 | $1.30 | $1.00 | $1.25 | $0.16 | $1.05 |
| 12 | Drill seed (temporary_warm_cool) (164-7015) | SY | 463 | $1.00 | $1.50 | $1.30 | $1.77 | $1.25 | $0.19 | $1.05 |
| 13 | Fertilizer (166-7001) | ACRE | 0.20 | $2,000.00 | $4,000.00 | $3,016.17 | $2,000.00 | $2,000.00 | $963.90 | $6,800.00 |
| 14 | Vegetative watering (168-7001) | TGL | 23 | $200.00 | $50.00 | $524.55 | $100.00 | $50.00 | $112.46 | $82.00 |
| 15 | Asphalt TRT base (GR 2)(PG 64) (292-7006) | TON | 278 | $75.00 | $140.00 | $200.14 | $328.00 | $180.00 | $270.43 | $180.00 |
| 16 | Concrete pavement (CRCP) (8") (360-7002) | SY | 842 | $100.00 | $105.00 | $113.05 | $120.00 | $150.00 | $106.43 | $103.00 |
| 17 | Cem stabil BKFL (400-7010) | CY | 126 | $250.00 | $50.00 | $82.97 | $240.00 | $100.00 | $128.52 | $145.00 |
| 18 | Cement stab backfill (inlet or MH) (400-7011) | CY | 17 | $160.00 | $50.00 | $82.97 | $200.00 | $100.00 | $128.52 | $200.00 |
| 19 | Drilled shaft (24 in) (416-7004) | LF | 252 | $300.00 | $300.00 | $290.77 | $232.00 | $420.00 | $404.30 | $300.00 |
| 20 | CL F concrete (cap) (420-7071) | CY | 26.20 | $1,500.00 | $2,500.00 | $1,849.77 | $1,000.00 | $1,500.00 | $1,386.95 | $2,200.00 |
| 21 | Reinforced concrete slab (slab beam) (422-7007) | SF | 1,466 | $30.00 | $35.00 | $55.21 | $20.00 | $30.00 | $32.75 | $50.00 |
| 22 | Bridge sidewalk (422-7012) | SF | 328 | $90.00 | $35.00 | $31.21 | $21.00 | $60.00 | $13.66 | $64.00 |
| 23 | Approach slab (422-7013) | CY | 53 | $900.00 | $1,100.00 | $1,059.02 | $700.00 | $650.00 | $765.77 | $1,100.00 |
| 24 | Prestressed concrete slab beam (4SB15) (425-7018) | LF | 133.50 | $270.00 | $155.00 | $181.96 | $208.00 | $275.00 | $187.43 | $213.00 |
| 25 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 178 | $270.00 | $155.00 | $166.63 | $200.00 | $290.00 | $187.43 | $187.00 |
| 26 | Riprap (mow strip)(4 in) (432-7013) | CY | 5 | $730.00 | $800.00 | $1,218.53 | $500.00 | $800.00 | $720.25 | $2,000.00 |
| 27 | Riprap (stone protection)(18 in) (432-7043) | CY | 373 | $235.00 | $230.00 | $185.77 | $196.00 | $250.00 | $184.21 | $234.00 |
| 28 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 172 | $22.00 | $20.00 | $19.30 | $32.00 | $50.00 | $62.12 | $40.00 |
| 29 | Rail (type T223) (450-7008) | LF | 63 | $210.00 | $200.00 | $349.77 | $124.00 | $180.00 | $232.41 | $225.00 |
| 30 | Rail (type C223) (450-7034) | LF | 63 | $250.00 | $300.00 | $451.24 | $211.00 | $230.00 | $285.96 | $287.00 |
| 31 | Armor joint (454-7002) | LF | 57 | $165.00 | $80.00 | $183.74 | $107.00 | $175.00 | $136.55 | $132.00 |
| 32 | CMP (gal steel 24 in) (460-7005) | LF | 20 | $125.00 | $250.00 | $186.26 | $104.00 | $140.00 | $172.92 | $200.00 |
| 33 | CMP (gal steel 30 in) (460-7007) | LF | 40 | $200.00 | $260.00 | $132.16 | $73.00 | $200.00 | $180.77 | $125.00 |
| 34 | RC pipe (CL III)(24 in) (464-7005) | LF | 108 | $145.00 | $150.00 | $138.17 | $136.00 | $180.00 | $117.62 | $150.00 |
| 35 | RC pipe (CL III)(30 in) (464-7007) | LF | 136 | $155.00 | $200.00 | $166.50 | $172.00 | $300.00 | $134.88 | $155.00 |
| 36 | Manh (complete)(PRM)(48IN) (465-7002) | EACH | 3 | $7,200.00 | $8,500.00 | $6,771.75 | $9,492.00 | $5,800.00 | $8,166.38 | $9,000.00 |
| 37 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 1 | $2,500.00 | $4,500.00 | $2,130.41 | $2,777.00 | $3,000.00 | $3,882.38 | $1,600.00 |
| 38 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 2 | $4,000.00 | $4,500.00 | $2,432.02 | $3,157.00 | $3,500.00 | $4,417.88 | $1,900.00 |
| 39 | Removing structure (pipe) (496-7007) | LF | 94 | $50.00 | $75.00 | $16.36 | $10.00 | $1.00 | $85.68 | $100.00 |
| 40 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $35,000 | $40,000 | $28,780 | $70,000 | $22,500 | $35,075 | $40,000 |
| 41 | Mobilization (500-7001) | LS | 1 | $130,000 | $95,000 | $110,030 | $120,000 | $110,000 | $100,000 | $135,000 |
| 42 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $16,667 | $5,000.00 | $2,300.34 | $2,500.00 | $2,500.00 | $3,534.30 | $4,500.00 |
| 43 | Portable changeable message sign (503-7002) | EACH | 10 | $10,000 | $1,300.00 | $4,126.12 | $7,000.00 | $10,000 | $6,426.00 | $7,000.00 |
| 44 | Rock filter dams (install) (type 2) (506-7002) | LF | 95 | $50.00 | $35.00 | $42.23 | $13.00 | $70.00 | $85.68 | $57.00 |
| 45 | Rock filter dams (remove) (506-7011) | LF | 95 | $20.00 | $10.00 | $12.06 | $1.00 | $10.00 | $21.42 | $21.00 |
| 46 | Construction exits (install) (type 1) (506-7020) | SY | 78 | $50.00 | $20.00 | $26.54 | $16.00 | $40.00 | $29.99 | $70.00 |
| 47 | Construction exits (remove) (506-7024) | SY | 78 | $11.00 | $10.00 | $12.06 | $1.00 | $5.00 | $10.71 | $32.00 |
| 48 | Construction perimeter fence (506-7034) | LF | 120 | $8.00 | $8.00 | $9.65 | $90.00 | $1.00 | $53.55 | $5.00 |
| 49 | Temporary sediment control fence (install) (506-7039) | LF | 517 | $6.00 | $2.10 | $2.53 | $6.00 | $1.00 | $1.93 | $5.50 |
| 50 | Temporary sediment control fence (remove) (506-7041) | LF | 517 | $2.00 | $1.00 | $1.21 | $1.00 | $1.00 | $0.64 | $2.20 |
| 51 | One-way traffic control (flagger cont) (510-7001) | HR | 400 | $60.00 | $35.00 | $39.21 | $100.00 | $40.00 | $160.65 | $85.00 |
| 52 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 40 | $60.00 | $15.00 | $141.13 | $223.00 | $80.00 | $84.07 | $60.00 |
| 53 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 40 | $60.00 | $15.00 | $138.72 | $123.00 | $80.00 | $84.07 | $60.00 |
| 54 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 40 | $20.00 | $10.00 | $60.06 | $200.00 | $40.00 | $11.25 | $60.00 |
| 55 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 40 | $20.00 | $10.00 | $60.06 | $216.00 | $40.00 | $11.25 | $60.00 |
| 56 | Concrete curb (type II) (529-7002) | LF | 726 | $45.00 | $6.00 | $8.97 | $9.00 | $40.00 | $9.91 | $14.00 |
| 57 | Driveways (concrete) (530-7006) | SY | 143 | $130.00 | $120.00 | $263.72 | $75.00 | $140.00 | $107.06 | $240.00 |
| 58 | Concrete sidewalks (6") (531-7003) | SY | 33 | $160.00 | $110.00 | $235.13 | $199.00 | $135.00 | $108.44 | $265.00 |
| 59 | Metal W-beam guard fence (timber post) (540-7001) | LF | 25 | $35.00 | $37.00 | $40.24 | $72.00 | $40.00 | $48.20 | $40.00 |
| 60 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 2 | $1,500.00 | $1,900.00 | $2,081.16 | $2,320.00 | $2,100.00 | $1,874.25 | $2,030.00 |
| 61 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,600.00 | $1,400.00 | $1,550.31 | $3,765.00 | $1,600.00 | $1,911.74 | $1,500.00 |
| 62 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,500.00 | $3,800.00 | $4,307.09 | $5,241.00 | $3,500.00 | $4,123.35 | $4,200.00 |
| 63 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 2 | $310.00 | $335.00 | $1,250.20 | $500.00 | $500.00 | $469.50 | $465.00 |
| 64 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 3 | $850.00 | $775.00 | $874.69 | $800.00 | $900.00 | $759.72 | $800.00 |
| 65 | Remove SM RD SN sup&AM (644-7073) | EACH | 3 | $160.00 | $120.00 | $132.71 | $1.00 | $150.00 | $139.23 | $132.00 |
| 66 | Install delineator assembly (D-SW)SZ 1(WFLX)GND(BI) (658-7004) | EACH | 4 | $100.00 | $85.00 | $94.10 | $6.00 | $75.00 | $91.04 | $53.00 |
| 67 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 5 | $35.00 | $26.00 | $28.96 | $6.00 | $50.00 | $37.49 | $26.00 |
| 68 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 4 | $100.00 | $75.00 | $84.45 | $25.00 | $75.00 | $91.04 | $75.00 |
| 69 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 690 | $1.50 | $1.50 | $0.66 | $4.00 | $3.00 | $1.87 | $2.00 |
| 70 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 690 | $1.50 | $1.50 | $0.66 | $4.00 | $3.00 | $1.87 | $2.00 |
| 71 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 9 | $12.00 | $20.00 | $6.03 | $50.00 | $50.00 | $32.13 | $32.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.