Jfo Services, LLC: TxDOT bid record
Jfo Services, LLC submitted 18 bids on Texas DOT contracts in the data, from 05 SEP 2025 to 06 OCT 2026, and was the low bidder on 3 of them (17%). When it was not low, its total sat a median +12% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $7,792,889
- Latest bid
- 06 OCT 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2025 | 6 | 2 | 33% |
| 2026 | 12 | 1 | 8% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Houston District | 12 | 2 | 17% |
| Beaumont District | 2 | 0 | 0% |
| Bryan District | 2 | 1 | 50% |
| Yoakum District | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Cem stabil BKFL | 400-7010 | CY | 14 | 9 (64%) | $60.05 | $200.00 |
| Barricades, signs and traffic handling | 502-7001 | MO | 18 | 7 (39%) | $2,184.84 | $5,000.00 |
| Excavation (roadway) | 110-7001 | CY | 12 | 4 (33%) | $24.36 | $20.00 |
| Temporary sediment control fence (remove) | 506-7041 | LF | 15 | 3 (20%) | $1.21 | $1.00 |
| Tack coat | 341-7082 | GAL | 8 | 3 (38%) | $9.14 | $5.00 |
| Concrete sidewalks (4") | 531-7001 | SY | 5 | 3 (60%) | $63.36 | $80.00 |
| Temporary sediment control fence (install) | 506-7039 | LF | 14 | 2 (14%) | $3.50 | $4.00 |
| Pavement surface preparation for marking (6") | 678-7002 | LF | 7 | 2 (29%) | $0.13 | $0.18 |
| Embankment (final)(OC)(type C) | 132-7005 | CY | 7 | 2 (29%) | $33.74 | $37.17 |
| Construction exits (install) (type 1) | 506-7020 | SY | 6 | 2 (33%) | $28.99 | $30.00 |
| Drilled shaft (24 in) | 416-7004 | LF | 5 | 2 (40%) | $232.93 | $245.78 |
| Reflectorized pavement marking type II (W) 6" (solid) | 666-7175 | LF | 5 | 2 (40%) | $1.11 | $0.37 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| MC2 Civil, LLC | 10 | 2 of 10 |
| Castillo Aranda LLC | 10 | 2 of 10 |
| Forde Construction Company, Inc. | 8 | 5 of 8 |
| R Construction Civil, LLC | 8 | 5 of 8 |
| Isi Contracting, Inc. | 7 | 2 of 7 |
| STX Civil | 7 | 2 of 7 |
| C. E. Barker, LTD. | 6 | 0 of 6 |
| Trevway, Inc. | 6 | 4 of 6 |
| Garret Shields Infrastructure | 5 | 3 of 5 |
| Hodges and Son Construction Company, Inc. | 5 | 1 of 5 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 06 OCT 2026 | A00134683 | Houston District | Bridge Replacement, POOL HILL RD (Pool Hill Road/CR2030 @ Brookshire Creek to .) | 4 of 9 | $2,119,280 | +8.0% |
| 03 SEP 2026 | A00191741 | Houston District | Construct Pedestrian Infrastructure, FM 3005 (SS 342 (61st Street) to Cove View Blvd) | 2 of 7 | $2,259,895 | +8.0% |
| 02 SEP 2026 | A00207409 | Yoakum District | Bridge Replacement, COUNTY ROAD 125 (at Draw to STR # AA02-49-001) | 11 of 12 | $3,493,872 | +31% |
| 06 AUG 2026 | A00192187 | Beaumont District | Bridge Replacement, CR 398 (AT LEE GULLY to EXISTING (STR#200360AA0184001)) | 2 of 6 | $1,744,267 | +4.0% |
| 05 AUG 2026 | A00209716 | Houston District | Drainage Improvements, US 290 (At Cypress Creek to .) | 5 of 7 | $1,980,373 | +39% |
| 02 JUN 2026 | A00216194 | Houston District | Construct Pedestrian Infrastructure, BROADWAY ST (At UPRR, Galveston Rd, and Harding St to .) | 1 of 7 | $4,349,108 | Low, 26% under the second |
| 06 MAY 2026 | A00209252 | Beaumont District | Regional Goods Movement Program, SH 146 (AT IH 10 to .) | 2 of 6 | $4,416,648 | +1.0% |
| 04 MAR 2026 | A00139359 | Houston District | Bicycle And Pedestrian Improvements, SL 8 (Briar Forest Drive to Briar Hill Drive) | 7 of 9 | $2,996,672 | +46% |
| 05 FEB 2026 | A00183682 | Houston District | Bridge Replacement, C MEYER RD (C Meyer Rd (CR 234) at Bee Creek to .) | 2 of 9 | $2,028,455 | +12% |
| 04 FEB 2026 | A00188781 | Houston District | Surfacing/Roadway Restoration, FM 529 (Brazos River to FM 362) | 4 of 7 | $3,915,195 | +20% |
| 04 FEB 2026 | A00134679 | Houston District | Bridge Replacement, HOPKINS RD (Hopkins Rd (CR 209) at Turkey Creek to .) | 3 of 13 | $3,064,221 | +10% |
| 07 JAN 2026 | A00205023 | Houston District | Install/Upgrade Drainage Structure(S), FM 1314 (Cooper Rose Way to SH 242) | 4 of 12 | $2,390,899 | +8.0% |
| 03 DEC 2025 | A00217521 | Houston District | Landscape Development, IH 45 (IH 10 to SL 8(S)) | 4 of 4 | $3,586,118 | +59% |
| 03 DEC 2025 | A00130819 | Yoakum District | Bridge Replacement, FM 806 (AT RATLIFF CREEK to STR#0716-03-012) | 9 of 12 | $2,136,443 | +34% |
| 05 NOV 2025 | A00135986 | Bryan District | Bridge Replacement, SH 105 (AT JACKSON CREEK to .) | 6 of 12 | $3,576,488 | +27% |
| 09 OCT 2025 | A00130008 | Houston District | Bridge Replacement, IOWA LN (Iowa Lane at Brazos River Auth Canal to .) | 1 of 7 | $1,125,735 | Low, 10% under the second |
| 05 SEP 2025 | A00207208 | Houston District | Bridge Replacement, LEE RD (Lee Road at HCFCD Ditch to .) | 2 of 6 | $1,149,648 | +12% |
| 05 SEP 2025 | A00132768 | Bryan District | Construct Pedestrian Infrastructure, BS 36J (W Commerce St. (South) to US 290) | 1 of 6 | $2,318,046 | Low, 16% under the second |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.