TxDOT contract A00216194 bid tabulation

Construct Pedestrian Infrastructure, BROADWAY ST (At UPRR, Galveston Rd, and Harding St to .). Let by Texas DOT on June 2, 2026, Harris, Houston District. 7 bids received; low bid $4,349,108 by Jfo Services, LLC, -34% against the engineer's estimate of $6,616,380.

Owner
Texas DOT
Letting
02 JUN 2026
Pay items
95
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Jfo Services, LLC$4,349,108Low-34%
2MC2 Civil, LLC$5,490,389+26%-17%
3James Construction Group, LLC$5,997,727+38%-9.0%
4Ragle Construction, Inc.$6,087,015+40%-8.0%
5Harper Brothers Construction LLC$6,857,738+58%+4.0%
6Isi Contracting, Inc.$6,965,405+60%+5.0%
7Castillo Aranda LLC$7,404,457+70%+12%
TxDOT contract A00216194: bids by rank

Engineer's estimate: $6,616,380.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Jfo Services, LLC2. MC2 Civil, LLC3. James Construction Group, LLC4. Ragle Construction, Inc.5. Harper Brothers Construction LLC6. Isi Contracting, Inc.
1Preparing row (100-7001)ACRE2.41$260,000$17,876$135,000$10,871$241,770$70,000$30,000
2Tree protection (install) (100-7013)EACH5$300.00$1,134.53$1,500.00$1,000.00$625.00$300.00$1,175.00
3Tree protection (remove) (100-7015)EACH5$120.00$283.63$500.00$250.00$185.00$100.00$294.00
4Removing concrete (pavement) (104-7001)SY811$12.00$34.69$8.00$5.10$9.00$15.00$16.00
5Removing concrete (medians) (104-7008)SY22$18.00$116.27$20.00$23.57$45.00$24.00$124.00
6Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY14$22.00$182.71$50.00$47.15$40.00$44.00$174.00
7Removing concrete (curb) (104-7016)LF266$20.00$10.89$10.00$3.54$9.00$6.00$10.00
8Removing concrete (miscellaneous) (104-7045)EACH18$350.00$265.73$10.00$64.92$85.00$188.00$1,000.00
9Remove (0"-6") TRT/untrt base & asphalt pavement (105-7046)SY1,303$15.00$10.19$2.00$6.45$4.00$6.00$13.00
10Excavation (roadway) (110-7001)CY1,132$7.00$32.74$35.00$17.92$40.00$41.00$25.24
11Embankment (final)(OC)(type C) (132-7005)CY87$60.00$132.95$60.00$55.94$30.00$58.00$59.81
12Block sodding (162-7002)SY2,203$7.00$5.11$6.00$4.50$7.00$5.75$5.29
13Vegetative watering (168-7001)TGL111$5.00$57.66$32.00$40.00$40.00$75.00$47.00
14Lime (com or QK)(slurry) (260-7005)TON23$240.00$367.59$325.00$376.11$324.00$350.00$336.00
15Lime TRT (subgrade) (8") (260-7020)SY1,254$3.00$24.58$10.00$5.81$8.00$13.00$17.00
16Concrete pavement (CPCD) (6") (360-7016)SY17$95.00$363.89$325.00$106.90$150.00$398.00$306.00
17Concrete pavement (CPCD) (7") (360-7017)SY1,165$170.00$139.64$75.00$125.00$75.00$110.00$140.00
18Cem stabil BKFL (400-7010)CY85$148.00$42.32$70.00$62.50$60.00$90.00$138.00
19Drilled shaft (36 in) (416-7006)LF1,524$500.00$222.45$285.00$190.89$195.00$300.00$414.00
20Drilled shaft (48 in) (416-7008)LF968$363.00$385.36$500.00$345.12$350.00$549.00$655.00
21Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF36$330.00$283.63$260.00$250.00$250.00$282.00$262.00
22Class A concrete (seal) (420-7001)CY22.60$1,077.00$750.27$1,000.00$852.68$740.00$1,400.00$2,400.00
23Class A concrete (miscellaneous) (420-7002)CY1$1,000.00$1,871.97$1,200.00$2,500.00$10,000$720.00$3,740.00
24Class C concrete (cap) (420-7022)CY149.60$2,400.00$1,268.47$2,000.00$2,500.00$3,500.00$3,500.00$3,250.00
25Class C concrete (column) (420-7038)CY330.80$1,759.00$1,059.49$2,000.00$1,873.00$1,060.00$3,500.00$1,719.00
26Class C concrete (footing) (420-7044)CY160.40$2,989.00$713.57$1,200.00$1,200.00$765.00$1,500.00$1,250.00
27Slab span (422-7017)CY151.80$920.00$1,107.28$1,800.00$1,190.00$2,210.00$3,500.00$2,000.00
28Riprap (concrete)(4 in) (432-7001)CY121$780.00$455.42$800.00$514.66$500.00$450.00$325.00
29Riprap (mow strip)(4 in) (432-7013)CY14$695.00$629.22$1,000.00$673.37$550.00$700.00$645.00
30STR steel (miscellaneous non-bridge) (442-7007)LB10,543$15.00$0.80$1.00$3.10$3.00$3.00$5.00
31Rail (handrail)(type F) (450-7063)LF1,978$170.00$126.81$150.00$142.66$140.00$180.00$163.00
32RC pipe (CL III)(18 in) (464-7003)LF103$79.00$114.05$115.00$106.38$85.00$250.00$169.00
33RC pipe (CL III)(24 in) (464-7005)LF35$100.00$154.49$160.00$143.11$115.00$220.00$321.00
34Inlet (complete)(PSL)(RC)(3FTX3FT) (465-7070)EACH1$5,500.00$5,632.77$3,500.00$4,565.08$5,400.00$5,500.00$3,745.00
35Inlet (complete)(type AZ)(hou) (465-7316)EACH2$6,500.00$6,767.32$5,000.00$5,971.82$7,000.00$6,900.00$5,251.00
36Manh (complete)(type A)(hou) (465-7320)EACH2$5,950.00$8,724.38$6,500.00$7,196.00$6,500.00$7,700.00$7,560.00
37Pipe (miscellaneous) (6 in) (481-7037)LF652$120.00$27.62$30.00$58.81$59.00$44.00$87.00
38Removing structure (inlet) (496-7002)EACH1$800.00$2,391.56$1,200.00$1,598.34$600.00$1,100.00$906.00
39Removing structure (building) (496-7033)EACH1$75,000$85,090$80,000$13,801$45,000$12,000$250,000
40Mobilization (500-7001)LS1$600,000$430,074$540,000$598,000$600,000$490,000$600,000
41Barricades, signs and traffic handling (502-7001)MO4$12,000$1,429.51$15,000$35,000$95,000$15,000$18,000
42Portable changeable message sign (503-7002)EACH3$15,080$5,218.83$10,000$5,630.35$5,000.00$2,200.00$5,550.00
43TMA (stationary) (505-7001)DAY101$200.00$224.66$250.00$162.11$300.00$192.00$472.00
44Rock filter dams (install) (type 2) (506-7002)LF40$35.00$51.06$40.00$45.00$45.00$20.00$53.00
45Rock filter dams (remove) (506-7011)LF40$20.00$22.69$10.00$20.00$20.00$20.00$23.50
46Construction exits (install) (type 1) (506-7020)SY333$20.00$51.06$35.00$45.00$45.00$28.00$52.88
47Construction exits (remove) (506-7024)SY333$8.00$22.69$5.00$20.00$20.00$10.00$23.50
48Temporary sediment control fence (install) (506-7039)LF1,084$10.00$5.11$3.00$4.50$4.50$2.00$5.29
49Temporary SDMT cont fence (inlet protection) (506-7040)LF10$8.00$17.02$50.00$15.00$15.00$5.00$17.63
50Temporary sediment control fence (remove) (506-7041)LF1,094$8.00$1.13$0.25$1.00$1.00$1.00$1.18
51Biodegradable erosion control logs (install) (6") (506-7042)LF705$3.00$9.08$10.00$8.00$8.00$6.00$9.40
52Biodegradable erosion control logs (remove) (506-7046)LF705$3.00$2.27$0.25$2.00$2.00$2.00$2.35
53Constructing detours (508-7001)SY33$88.00$120.33$250.00$216.16$165.00$85.00$465.00
54Concrete curb (type II) (529-7002)LF482$37.00$16.38$7.00$30.13$13.00$17.00$13.00
55Concrete curb & gutter (type I) (529-7008)LF219$40.00$24.21$21.00$34.42$32.00$19.00$24.00
56Concrete curb & gutter (type II) (529-7009)LF121$30.00$37.62$32.00$36.02$32.00$34.00$44.00
57Concrete curb (doweled) (529-7012)LF429$35.00$17.11$19.00$33.07$18.00$20.00$28.00
58Concrete sidewalks (4") (531-7001)SY154$70.00$59.15$90.00$76.49$60.00$110.00$126.00
59Curb ramps (type 7) (531-7020)SY18$383.00$164.70$300.00$399.77$210.00$250.00$4,000.00
60Concrete median (536-7002)SY39$160.00$72.70$95.00$172.05$80.00$110.00$233.00
61Right of way markers (538-7001)EACH3$413.00$1,134.53$25.00$1,400.00$550.00$900.00$470.00
62Chain link fence (install) (6') (550-7001)LF1,706$40.00$43.11$50.00$38.00$48.00$6.83$24.00
63Chain link fence (install) (8') (550-7005)LF174$1.00$55.59$70.00$49.00$49.00$17.00$33.00
64Chain link fence (remove) (550-7007)LF2,091$7.00$12.48$1.00$11.00$11.00$5.00$3.53
65Remove RD IL asm (shoe-base) (610-7007)EACH3$918.00$567.26$500.00$500.00$898.57$899.60$737.00
66In RD IL (U/P) (type 1) (150W EQ) LED (610-7014)EACH2$2,000.00$1,304.71$1,200.00$1,150.00$1,150.00$2,068.00$1,438.00
67In RD IL (type SA) 20B-4 (150W EQ) LED (610-7018)EACH2$5,000.00$5,105.38$4,500.00$4,500.00$4,500.00$7,119.29$6,396.00
68Conduit (PVC) (schedule 40) (2") (618-7030)LF835$6.00$13.61$12.00$12.00$12.00$15.00$18.57
69Conduit (PVC) (schedule 40) (2") (bore) (618-7031)LF40$25.00$28.36$25.00$25.00$25.00$24.00$29.03
70Conduit (RM) (1") (618-7072)LF1,430$18.00$36.31$32.00$32.00$32.00$22.00$29.55
71Electrical conductor (no.8) bare (620-7007)LF2,305$1.75$2.50$2.20$2.20$2.20$2.50$2.09
72Electrical conductor (no.8) insulated (620-7008)LF7,740$2.00$2.84$2.50$2.50$2.50$2.66$2.14
73Ground box type A (122311)W/apron (624-7002)EACH6$1,500.00$1,361.43$1,200.00$1,200.00$1,200.00$1,045.00$1,355.00
74Elc SRV type A 120/240 060(NS)SS(E)TP(O) (628-7011)EACH1$11,500$8,055.15$8,000.00$7,100.00$7,100.00$10,900$9,712.00
75Aluminum signs (type A) (636-7001)SF8$46.00$100.84$35.00$35.00$35.00$152.92$36.61
76Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009)EACH2$1,000.00$849.19$1,100.00$1,023.00$1,023.00$978.69$1,070.00
77Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH2$650.00$730.10$800.00$780.00$780.00$1,200.00$815.85
78Remove SM RD SN sup&AM (644-7073)EACH2$103.00$147.49$120.00$120.00$120.00$1,200.00$125.51
79Install OM SM RD sign (1-OM-PW)Y (658-7317)EACH3$50.00$25.52$27.00$27.00$35.00$1,300.00$28.24
80Install OM LG RD sign (3-OM-PW)Y (658-7322)EACH1$50.00$25.53$30.00$250.00$35.00$2,200.00$261.49
81Reflectorized pavement marking type II (W) 4" (solid) (666-7171)LF608$0.80$4.47$2.00$2.00$3.50$9.50$2.09
82Eliminating existing PM & markers (4") (677-7001)LF37$3.30$128.78$5.00$5.00$2.50$10.00$5.23
83Remove luminaire pole (690-7127)EACH1$1,000.00$567.26$500.00$1,000.00$750.00$2,375.00$1,543.00
84Cleaning / sweeping (handwork) (738-7105)SY555$8.00$2.49$8.30$2.90$1.50$50.00$0.83
85Tree removal (18" - 24" diameter) (752-7007)EACH1$122.00$1,701.79$1,400.00$746.46$1,200.00$2,100.00$4,070.00
86Tree removal (30" - 36" diameter) (752-7009)EACH2$249.00$1,701.79$2,600.00$1,244.51$3,000.00$2,800.00$2,043.00
87Install pref pedestrian steel truss BRG span (4004-7006)LF224$2,747.00$2,093.48$625.00$1,000.00$2,125.00$700.00$2,250.00
88Pedestrian shade canopy (4015-7001)LF9,134$22.00$9.31$45.00$116.96$31.00$85.00$52.00
89Install bridge identification numbers (4019-7001)EACH1$560.00$2,269.06$500.00$1,000.00$250.00$2,000.00$588.00
90Precast prest concrete hollow-core slab (4074-7001)SF8,604$22.00$40.59$32.00$39.87$70.00$42.00$40.00
91Steel fence (remove) (5007-7001)LF20$100.00$36.28$10.00$20.00$20.00$40.00$3.53
92Steel fence (install) (5007-7002)LF20$100.00$142.47$20.00$150.00$120.00$180.00$47.00
93PVC coated non-scalable fence panels (5087-7001)SF17,186$5.00$8.51$11.00$25.90$2.00$10.00$23.00
94Bridge mounted illumination (6165-7002)EACH29$2,300.00$1,230.97$1,100.00$1,085.00$1,085.00$1,178.00$1,400.00
95Parking lot illumination (6165-7003)EACH4$5,750.00$3,573.77$3,200.00$3,150.00$3,150.00$5,036.00$4,113.00
TxDOT contract A00216194: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 2, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy