TxDOT contract A00192187 bid tabulation

Bridge Replacement, CR 398 (AT LEE GULLY to EXISTING (STR#200360AA0184001)). Let by Texas DOT on August 6, 2026, Chambers, Beaumont District. 6 bids received; low bid $1,675,110 by Castillo Aranda LLC, +17% against the engineer's estimate of $1,431,058.

Owner
Texas DOT
Letting
06 AUG 2026
Pay items
59
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Castillo Aranda LLC$1,675,110Low+17%
2Jfo Services, LLC$1,744,267+4.0%+22%
3Elite Contractors and Equipment LTD$1,960,695+17%+37%
4MC2 Civil, LLC$2,049,867+22%+43%
5Isi Contracting, Inc.$2,137,900+28%+49%
6Ragle Construction, Inc.$2,573,312+54%+80%
TxDOT contract A00192187: bids by rank

Engineer's estimate: $1,431,058.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Castillo Aranda LLC2. Jfo Services, LLC3. Elite Contractors and Equipment LTD4. MC2 Civil, LLC5. Isi Contracting, Inc.6. Ragle Construction, Inc.
1Preparing row (100-7002)STA4.70$5,000.00$15,000$39,000$20,000$24,500$12,000$60,000
2Remove (11") TRT/untrt base & asphalt pavement (105-7031)SY620$10.00$15.00$16.32$12.00$20.00$27.00$25.00
3Excavation (roadway) (110-7001)CY91$15.00$20.00$13.95$50.00$50.00$47.00$500.00
4Excavation (channel) (110-7002)CY822$20.00$22.00$31.62$30.00$45.00$28.00$50.00
5Embankment (final)(OC)(type C) (132-7005)CY608$35.00$25.00$23.50$30.00$25.00$55.00$75.00
6Embankment (final)(DC)(type C) (132-7006)CY510$40.00$30.00$31.05$30.00$45.00$65.00$75.00
7Furn & place topsoil (4") (160-7002)SY980$2.00$10.00$10.69$5.00$3.00$10.00$8.00
8Broadcast seed (temporary_warm) (164-7005)SY540$1.00$0.50$2.51$2.00$2.00$3.60$2.00
9Broadcast seed (temporary_cool) (164-7006)SY540$1.00$0.50$2.51$2.00$2.00$3.60$2.00
10Hydro mulch seed (permanent_rural_sandy) (164-7017)SY1,080$1.00$0.50$2.51$2.00$0.70$2.33$0.70
11Vegetative watering (168-7001)TGL5.57$200.00$90.00$2,024.96$18.00$100.00$218.00$265.00
12FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176)CY135$130.00$110.00$314.78$180.00$250.00$704.00$173.00
13Prime coat (AE-P) (310-7001)GAL139$15.00$10.00$10.69$15.00$6.00$48.50$17.20
14D-GR HMA type D PG 64-22 (exempt) (341-7064)TON101$350.00$250.00$729.37$350.00$230.00$1,004.00$400.00
15Tack coat (341-7082)GAL56$10.00$10.00$9.43$15.00$10.00$107.00$22.00
16Plane & text asphalt concrete pavement(2") (354-7019)SY215$15.00$55.00$16.32$10.00$24.00$18.00$40.00
17Cem stabil BKFL (400-7010)CY48$125.00$105.00$72.09$215.00$120.00$180.00$164.00
18Temporary special shoring (403-7001)SF400$50.00$30.00$50.30$685.00$50.00$100.00$156.00
19Prestressed concrete pil (16 in SQ) (409-7001)LF360$140.00$310.00$187.72$150.00$188.00$625.00$177.00
20Prestressed concrete pil (18 in SQ) (409-7002)LF900$125.00$310.00$165.25$180.00$210.00$265.00$146.00
21Class C concrete (abutment) (420-7012)CY18.40$1,500.00$1,350.00$2,227.07$2,000.00$3,500.00$2,700.00$1,400.00
22Class C concrete (cap) (420-7022)CY19.80$1,700.00$1,450.00$3,021.53$2,850.00$4,200.00$3,300.00$2,715.00
23Class C concrete (rail foundation) (420-7052)CY2.50$1,500.00$675.00$3,510.95$600.00$3,500.00$1,798.00$1,135.00
24Reinforced concrete slab (422-7001)SF4,420$20.00$18.50$30.58$25.00$41.00$25.00$26.00
25Approach slab (422-7013)CY41.20$800.00$650.00$747.78$800.00$1,000.00$1,186.00$642.00
26Prestressed concrete slab beam (5SB15) (425-7019)LF840$280.00$320.00$298.16$300.00$280.00$260.00$259.00
27Riprap (stone protection)(24 in) (432-7045)CY1,239$185.00$220.00$73.28$225.00$260.00$160.00$262.00
28Rail (type T223) (450-7008)LF382$150.00$140.00$143.33$180.00$200.00$170.00$123.00
29Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF50.40$180.00$130.00$421.99$250.00$210.00$209.00$220.50
30Removing structure (bridge 100 - 499 FT length) (496-7010)EACH1$50,000$55,000$32,344$50,000$50,000$50,000$305,000
31Mobilization (500-7001)LS1$131,000$100,000$173,995$160,000$200,000$150,000$250,000
32Barricades, signs and traffic handling (502-7001)MO15$5,000.00$4,000.00$2,655.30$2,000.00$5,500.00$5,700.00$15,000
33Rock filter dams (install) (type 2) (506-7002)LF30$50.00$30.00$50.30$50.00$55.00$55.00$40.53
34Rock filter dams (remove) (506-7011)LF30$20.00$5.00$37.72$20.00$12.00$27.00$12.00
35Construction exits (install) (type 1) (506-7020)SY111$37.00$35.00$31.44$40.00$30.00$27.00$17.50
36Construction exits (remove) (506-7024)SY111$15.00$5.00$12.57$10.00$15.00$11.00$15.40
37Temporary sediment control fence (install) (506-7039)LF625$6.00$5.00$3.77$4.00$5.00$2.50$4.00
38Temporary sediment control fence (remove) (506-7041)LF625$2.00$1.00$1.88$1.00$1.00$0.70$0.99
39Constructing detours (508-7001)SY286$150.00$40.00$239.73$150.00$200.00$360.00$250.00
40Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF40$80.00$70.00$154.50$50.00$145.00$52.00$150.00
41Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF80$80.00$70.00$111.83$50.00$70.00$52.00$150.00
42Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF40$25.00$20.00$49.90$25.00$30.00$52.00$30.00
43Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF80$25.00$20.00$24.95$25.00$30.00$52.00$17.00
44Metal W-beam guard fence (timber post) (540-7001)LF37.50$30.00$40.00$48.42$40.00$45.00$44.00$29.00
45Metal beam guard fence trans (thrie-beam) (540-7005)EACH3$1,500.00$1,950.00$3,332.47$2,000.00$2,000.00$2,134.00$1,450.00
46Downstream anchor terminal section (540-7015)EACH2$1,600.00$2,000.00$2,326.45$2,000.00$2,000.00$2,012.00$1,450.00
47Guardrail end treatment (install) (544-7001)EACH1$3,000.00$3,820.00$4,841.51$3,800.00$4,200.00$4,194.00$3,550.00
48Crash cushion attenuator (install)(L)(N)(TL2) (545-7005)EACH1$25,000$28,500$34,394$32,000$25,000$21,500$26,000
49Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH5$500.00$120.00$861.41$700.00$110.00$943.00$931.00
50Remove SM RD SN sup&AM (644-7073)EACH5$85.00$200.00$251.51$150.00$200.00$125.00$120.00
51Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH4$50.00$30.00$31.44$50.00$2.20$31.80$18.00
52Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH5$50.00$30.00$44.01$50.00$9.00$32.00$25.00
53Install object marker assembly (OM-3L)(TWT)GND (658-7066)EACH2$200.00$315.00$389.84$500.00$170.00$329.00$310.00
54Remove delin & object marker assms (658-7078)EACH4$50.00$50.00$125.76$50.00$50.00$37.00$35.00
55Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF1,200$2.00$5.00$1.26$5.00$3.50$1.06$1.00
56Pavement sler 6" (666-7347)LF840$1.00$3.00$0.63$1.00$0.50$0.53$0.50
57Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410)LF940$2.00$3.00$1.38$6.00$2.50$1.17$1.10
58Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422)LF420$2.00$3.00$1.38$5.00$2.50$1.17$1.10
59Pavement surface preparation for marking (6") (678-7002)LF1,360$0.50$1.00$0.13$1.00$0.50$0.11$0.10
TxDOT contract A00192187: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy