TxDOT contract A00135986 bid tabulation
Bridge Replacement, SH 105 (AT JACKSON CREEK to .). Let by Texas DOT on November 5, 2025, Washington, Bryan District. 12 bids received; low bid $2,813,308 by Larry Young Paving, Inc., -17% against the engineer's estimate of $3,399,652.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 76
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Larry Young Paving, Inc. | $2,813,308 | Low | -17% |
| 2 | Forde Construction Company, Inc. | $3,281,171 | +17% | -3.0% |
| 3 | Knife River Corporation - South | $3,346,381 | +19% | -2.0% |
| 4 | Texas Steel Industrial Placing, LLC | $3,382,848 | +20% | 0.0% |
| 5 | Texas Materials Group, Inc. | $3,383,936 | +20% | 0.0% |
| 6 | Jfo Services, LLC | $3,576,488 | +27% | +5.0% |
| 7 | E-Z Bel Construction, LLC | $3,696,844 | +31% | +9.0% |
| 8 | STX Civil | $3,743,260 | +33% | +10% |
| 9 | R Construction Civil, LLC | $3,761,877 | +34% | +11% |
| 10 | C. E. Barker, LTD. | $4,162,654 | +48% | +22% |
| 11 | Hodges and Son Construction Company, Inc. | $4,503,546 | +60% | +32% |
| 12 | Fuqua Construction Co., Inc. | $4,646,509 | +65% | +37% |
Engineer's estimate: $3,399,652.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Larry Young Paving, Inc. | 2. Forde Construction Company, Inc. | 3. Knife River Corporation - South | 4. Texas Steel Industrial Placing, LLC | 5. Texas Materials Group, Inc. | 6. Jfo Services, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 12.70 | $1,600.00 | $1,000.00 | $2,400.00 | $4,382.00 | $2,000.00 | $6,600.00 | $2,057.60 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 572 | $17.00 | $5.50 | $15.00 | $10.28 | $13.00 | $20.00 | $21.14 |
| 3 | Excavation (roadway) (110-7001) | CY | 1,566 | $30.00 | $15.00 | $16.00 | $27.00 | $20.00 | $40.00 | $13.59 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 2,543 | $30.00 | $27.00 | $43.00 | $13.00 | $30.00 | $38.00 | $25.06 |
| 5 | Furn & place topsoil (4") (160-7002) | SY | 9,348 | $2.00 | $2.00 | $2.20 | $0.94 | $4.00 | $1.30 | $2.93 |
| 6 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 9,348 | $0.60 | $0.50 | $0.55 | $0.53 | $0.53 | $0.48 | $0.76 |
| 7 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 4,674 | $0.60 | $0.50 | $0.55 | $0.53 | $0.48 | $0.48 | $0.59 |
| 8 | Hydro mulch seed (temporary_cool) (164-7022) | SY | 4,674 | $0.60 | $0.50 | $0.55 | $0.53 | $0.50 | $0.48 | $0.59 |
| 9 | Vegetative watering (168-7001) | TGL | 93.50 | $42.00 | $40.00 | $95.00 | $43.80 | $50.00 | $40.00 | $152.68 |
| 10 | FL BS (compacted in place)(type A GR 1-2) (9") (247-7350) | SY | 2,791 | $50.00 | $31.00 | $37.00 | $31.50 | $30.00 | $30.00 | $27.65 |
| 11 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 15 | $350.00 | $750.00 | $380.00 | $389.00 | $400.00 | $400.00 | $433.98 |
| 12 | Lime TRT (existing material)(7") (260-7031) | SY | 1,486 | $6.50 | $35.00 | $9.75 | $9.60 | $8.00 | $13.00 | $43.45 |
| 13 | Cement (275-7001) | TON | 15 | $350.00 | $225.00 | $279.00 | $313.00 | $300.00 | $275.00 | $223.07 |
| 14 | Cement TRT (existing material)(7") (275-7025) | SY | 1,486 | $6.50 | $5.00 | $9.75 | $4.59 | $8.00 | $6.50 | $23.63 |
| 15 | Prime coat (MC-30) (310-7004) | GAL | 558 | $7.00 | $7.75 | $6.00 | $11.75 | $12.00 | $7.00 | $7.04 |
| 16 | D-GR HMA type-C PG64-22 (level-UP) (341-7018) | TON | 11 | $400.00 | $200.00 | $550.00 | $1,609.00 | $1,200.00 | $350.00 | $704.08 |
| 17 | SP mixes SP-C PG64-22 (344-7009) | TON | 918 | $190.00 | $140.00 | $139.00 | $218.95 | $210.00 | $180.00 | $179.54 |
| 18 | SP mixes SP-C sac-A PG64-22 (344-7010) | TON | 687 | $220.00 | $150.00 | $149.00 | $212.20 | $210.00 | $190.00 | $191.28 |
| 19 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 4,670 | $5.00 | $3.75 | $5.00 | $4.00 | $4.00 | $3.50 | $7.21 |
| 20 | Cem stabil BKFL (400-7010) | CY | 176 | $220.00 | $110.00 | $165.00 | $230.00 | $200.00 | $150.00 | $61.24 |
| 21 | Temporary special shoring (403-7001) | SF | 921 | $45.00 | $15.00 | $55.00 | $145.00 | $35.00 | $90.00 | $288.67 |
| 22 | Temporary special shoring (cofferdam) (403-7002) | SF | 1,350 | $45.00 | $50.00 | $21.00 | $99.00 | $40.00 | $5.00 | $167.86 |
| 23 | Drilled shaft (18 in) (416-7002) | LF | 100 | $150.00 | $120.00 | $263.00 | $120.25 | $275.00 | $110.00 | $84.80 |
| 24 | Drilled shaft (36 in) (416-7006) | LF | 970 | $350.00 | $340.00 | $310.00 | $306.40 | $275.00 | $340.00 | $310.70 |
| 25 | Class C concrete (abutment) (420-7012) | CY | 66.40 | $1,775.00 | $1,000.00 | $2,300.00 | $1,343.00 | $1,400.00 | $2,000.00 | $1,063.18 |
| 26 | Class C concrete (cap) (420-7022) | CY | 52.60 | $2,000.00 | $1,500.00 | $2,400.00 | $1,450.00 | $2,350.00 | $1,900.00 | $1,501.24 |
| 27 | Class C concrete (column) (420-7038) | CY | 34 | $2,000.00 | $1,600.00 | $2,300.00 | $1,155.00 | $2,500.00 | $1,600.00 | $2,477.49 |
| 28 | Reinforced concrete slab (422-7001) | SF | 10,440 | $33.00 | $28.00 | $29.00 | $32.52 | $28.00 | $39.00 | $29.44 |
| 29 | Approach slab (422-7013) | CY | 90 | $950.00 | $870.00 | $875.00 | $938.90 | $600.00 | $825.00 | $644.53 |
| 30 | Prestressed concrete girder (TX28) (425-7001) | LF | 1,249.50 | $290.00 | $270.00 | $250.00 | $255.00 | $256.00 | $245.00 | $237.18 |
| 31 | Riprap (mow strip)(4 in) (432-7013) | CY | 52 | $700.00 | $620.00 | $960.00 | $890.00 | $750.00 | $870.00 | $572.26 |
| 32 | Riprap (stone protection)(18 in) (432-7043) | CY | 801 | $170.00 | $150.00 | $239.00 | $181.50 | $200.00 | $187.00 | $196.93 |
| 33 | Rail (type T223) (450-7008) | LF | 424 | $180.00 | $150.00 | $168.00 | $172.60 | $175.00 | $175.00 | $236.63 |
| 34 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 118 | $290.00 | $180.00 | $210.00 | $289.00 | $215.00 | $240.00 | $276.97 |
| 35 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $90,000 | $51,000 | $90,000 | $58,000 | $200,000 | $95,000 | $88,011 |
| 36 | Mobilization (500-7001) | LS | 1 | $340,000 | $280,000 | $308,000 | $349,000 | $339,318 | $340,000 | $336,139 |
| 37 | Barricades, signs and traffic handling (502-7001) | MO | 11 | $5,000.00 | $3,700.00 | $4,000.00 | $5,714.00 | $4,000.00 | $5,000.00 | $5,290.48 |
| 38 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $2,800.00 | $14,000 | $12,000 | $25,000 | $9,000.00 | $16,135 |
| 39 | TMA (stationary) (505-7001) | DAY | 26 | $250.00 | $290.00 | $170.00 | $500.00 | $350.00 | $250.00 | $369.64 |
| 40 | TMA (mobile operation) (505-7003) | DAY | 20 | $500.00 | $660.00 | $170.00 | $800.00 | $1.00 | $250.00 | $546.49 |
| 41 | Rock filter dams (install) (type 2) (506-7002) | LF | 190 | $40.00 | $43.00 | $36.00 | $40.00 | $60.00 | $35.00 | $52.81 |
| 42 | Rock filter dams (remove) (506-7011) | LF | 190 | $10.00 | $12.00 | $10.00 | $10.00 | $20.00 | $10.00 | $29.34 |
| 43 | Construction exits (install) (type 1) (506-7020) | SY | 224 | $45.00 | $41.00 | $35.00 | $38.00 | $50.00 | $25.00 | $23.47 |
| 44 | Construction exits (remove) (506-7024) | SY | 224 | $16.00 | $15.00 | $12.00 | $10.00 | $20.00 | $5.00 | $11.73 |
| 45 | Temporary sediment control fence (install) (506-7039) | LF | 687 | $5.50 | $5.75 | $5.00 | $6.00 | $5.00 | $5.00 | $4.11 |
| 46 | Temporary sediment control fence (remove) (506-7041) | LF | 687 | $1.00 | $1.25 | $1.05 | $1.00 | $2.00 | $1.00 | $1.76 |
| 47 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 1,530 | $50.00 | $24.00 | $77.00 | $24.00 | $80.00 | $50.00 | $40.63 |
| 48 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 1,320 | $15.00 | $10.00 | $20.00 | $12.00 | $20.00 | $23.00 | $3.41 |
| 49 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 1,530 | $15.00 | $20.00 | $29.00 | $20.00 | $30.00 | $19.00 | $32.28 |
| 50 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 4,596 | $0.50 | $2.00 | $0.75 | $2.90 | $1.50 | $1.40 | $0.88 |
| 51 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 2,274 | $0.50 | $2.00 | $1.05 | $1.00 | $1.50 | $1.40 | $1.29 |
| 52 | Metal W-beam guard fence (timber post) (540-7001) | LF | 625 | $29.00 | $28.00 | $32.00 | $30.72 | $28.00 | $23.00 | $26.99 |
| 53 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,600.00 | $2,500.00 | $2,300.00 | $2,692.00 | $2,000.00 | $2,600.00 | $2,775.27 |
| 54 | Remove metal beam guard fence (542-7001) | LF | 381 | $3.25 | $6.00 | $3.50 | $3.40 | $3.00 | $5.00 | $5.87 |
| 55 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $3,800.00 | $3,800.00 | $3,655.00 | $3,000.00 | $3,100.00 | $3,637.77 |
| 56 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $300.00 | $300.00 | $380.00 | $360.00 | $300.00 | $250.00 | $293.37 |
| 57 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 6 | $2,000.00 | $1,300.00 | $1,750.00 | $1,694.00 | $2,000.00 | $2,000.00 | $2,170.93 |
| 58 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,400.00 | $270.00 | $925.00 | $900.00 | $2,000.00 | $1,000.00 | $1,056.13 |
| 59 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $10,000 | $8,300.00 | $9,600.00 | $8,870.00 | $10,000 | $8,500.00 | $9,857.18 |
| 60 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 5 | $750.00 | $1,000.00 | $783.00 | $761.00 | $500.00 | $690.00 | $855.79 |
| 61 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $900.00 | $1,100.00 | $908.00 | $890.00 | $725.00 | $800.00 | $928.12 |
| 62 | Remove SM RD SN sup&AM (644-7073) | EACH | 6 | $150.00 | $140.00 | $126.00 | $122.00 | $375.00 | $130.00 | $152.55 |
| 63 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $35.00 | $30.00 | $27.00 | $27.00 | $30.00 | $24.00 | $29.34 |
| 64 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 13 | $35.00 | $43.00 | $34.00 | $34.00 | $30.00 | $30.00 | $41.07 |
| 65 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 234 | $7.00 | $7.50 | $5.00 | $6.11 | $7.00 | $3.00 | $7.04 |
| 66 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 16,921 | $1.50 | $1.75 | $1.00 | $2.00 | $1.00 | $1.80 | $1.58 |
| 67 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 9,184 | $1.50 | $1.75 | $1.00 | $2.10 | $1.00 | $1.80 | $1.58 |
| 68 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 216 | $1.50 | $0.75 | $1.20 | $2.00 | $3.00 | $2.50 | $5.87 |
| 69 | Pavement sler 6" (666-7347) | LF | 500 | $1.25 | $0.25 | $0.55 | $1.00 | $0.25 | $0.50 | $0.26 |
| 70 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 5,116 | $1.00 | $1.00 | $2.00 | $2.33 | $1.00 | $1.20 | $1.03 |
| 71 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 640 | $1.50 | $1.00 | $3.75 | $2.44 | $1.00 | $1.20 | $1.03 |
| 72 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 526 | $1.50 | $1.00 | $3.75 | $2.44 | $1.00 | $1.20 | $1.03 |
| 73 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 31 | $9.00 | $7.50 | $9.25 | $11.00 | $7.00 | $6.80 | $7.04 |
| 74 | Eliminating existing PM & markers (4") (677-7001) | LF | 7,748 | $0.75 | $0.75 | $0.70 | $0.69 | $0.75 | $0.80 | $0.61 |
| 75 | Pavement surface preparation for marking (6") (678-7002) | LF | 500 | $1.25 | $0.25 | $0.10 | $0.22 | $0.25 | $0.25 | $0.12 |
| 76 | Bonding course (3007-7001) | GAL | 1,506 | $6.00 | $5.75 | $6.00 | $4.45 | $5.00 | $5.00 | $7.04 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.